Planning Board
Regular MeetingTaunton, MA · March 2, 2023
Minutes
*************************************************************************************
TAUNTON PLANNING BOARD MINUTES
Meeting held at 15 Summer Street, City Hall, in the Chester R. Martin Municipal Council
Chambers
*************************************************************************************
DATE: March 2, 2023
BOARD MEMBERS: Anthony Abreau, Chairman Michael Monteiro
Bob Campbell John Reardon
Manuel Spencer, Clerk Dennis I. Ackerman, Vice Chairman
Brian Carr
ADVISORS: Kevin Scanlon, City Planner
Michael Patneaude, City Engineer
__________________________________________________________________________
Roll Call: Campbell, Reardon, Spencer, Monteiro, Carr, Ackerman and Abreau present. Meeting opens at
5:33 PM
Manny made motion to approve minutes of Feb. 2, 2023 seconded by Mike. All in favor.
Executive Session with Law Dept. relative to pending litigation
Motion made and seconded to go into executive session on pending litigation: 5:34 PM
Roll call vote; Ackerman, Reardon, Campbell, Spencer, Monteiro, Carr, and Abreau….Yes
The Board came out of Executive Session at 6:15 Chairman Abreau stated one vote was taken in Executive
Session.
Public Meeting - A Site Plan Review - Hart Street property I.D. Map 94, Lot 215- for the
construction of a 7,000 sq. ft. 2-story marijuana cultivation and retail facility with associated site
access, drainage, parking and utilities, submitted by Tanios Barbour on behalf of San Holdings, LLC
Brian Dunn, Tracey Duarte, Jacques Barbour, Tanios Barbour, Jeff Bandini, McMcahon Traffic, Atty. Daniel
deAbreau, and Adam Glassman, Architect were invited into the enclosure. Dept. comments were read into
the record from DIRB, Eng., Commission for Individuals with Disabilities, and Water. Tracey stated the
submitted updated plans addressing all DIRB & City Engineer’s comments. She shows new plans and
explains project. The site is 1.1/2 acres on the south side of Hart Street and there are some wetlands
delineated on plans. There is a very steep incline and there is a 5-10 slope toward wetlands and 2 to 1 slope
for grading. The site is fully wooded and they are proposing a 2 story 3,500 (total 7,000 sq. ft.) building
There will be retail on first floor and the traffic will be counterclockwise per the DIRB. The dumpster will
be on a pad, they have 26 parking spaces and the drainage basin is in back. They will need to add fill to the
site for grading and the water will flow to water quality system to hold a 100 year storm. The site will tie
into Hart ST. for sewer and old Hart St. for water. They spoke with Mike Arruda and he indicated an 8 inch
pipe will be ok. (in his letter he indicated 12”) They will connect to the 20 foot wide easement. They are
seeking waivers as shown on plans (50% reduction of landscaping on side from 25 feet to 12.5 feet,, to allow
the required plantings be reduced to 50% and waive the requirement that all parking lots consisting of 10 or
more parking spaces shall provide 200 sq. ft. of interior landscaping.) They added the site distance to the
plans. They have 490 feet on both sides and City Engineer wanted the site distance from 235 Hart S. but it
was on plans and there is no issue. Tony asked how wide the driveway will be and it was answered 24 feet
wide with one way circulation per the DIRB. Tony asked where is the snow removal ? Tracey pointed out it’s
1
on the western side of the property. Bob asked about rip rap? Tracey answers there is good sand. The
ground water was between 60 inches and 102 inches (about 2 ½ - 3 ½ feet down) Bob asked how do you
get access to basin? There will be a gate on the fence around basin. Tracey pointed out the rip rap detail
has always been on the plans. Bob asked if they are proposing any sign? Tracey answers yes the sign is on
revised plans. The sign will be at street. Mike asked about 50% landscaping buffer? Tracey explains there is
existing vegetation and there will be a retaining wall. The retaining wall is 246 feet long and its maximum
height is 17 feet. Brian Dunn states it’s similar to that at Greco Ford on Rte. 44. Bob asked if the guardrail
is all wood or will it have any steel. He suggests adding steel cable to it. Manny asked what waivers are
they requesting? Tracey answers 50% reduction of landscaping on side from 25 feet to 12.5 feet,, to allow
the required plantings be reduced to 5% and waive the requirement that all parking lots consisting of 10 or
more parking spaces shall provide 200 sq. ft. of interior landscaping. Public Input: No one in favor or
opposed. Jeff stated the site distance at the intersection exceed the required 85% .
Mike made motion to approve Site Plan Review with dept. comments and including waivers, seconded
by Manny.
Condition #1) That the plans dated February 6, 2023 revised on March 1, 2023 shall govern with the following
additional conditions;
Condition #2) Lighting shall not illuminate any portion of abutting properties
Condition #3) The site shall be kept clean and clear of debris
Condition #4) Two sets of as-builts shall be submitted upon occupancy for all work on site and shall include
design engineer and land surveyor certification notes stating the development has been built according to the
approved plans. Plans will show all construction of buildings, utilities, grades, setbacks etc
Condition #5) Two sets of updated plans shall be provided that conforms to this decision prior to Building
permit
Condition #6) Compliance with a Conservation Commission Order of Conditions SE 73-3036 for this project.
Condition #7) Filling shall follow the Mass DOT compaction testing guidelines with reports provided for the
file
Condition #8) A stamped structural design is required for the retaining wall
Condition #9) The drainage pipe shall be a min of 12 inch in diameter and a manhole shall be added before the
water quality structure
Condition #10) The hidden driveway sign shall be relocated to the west of this entrance
Condition #11) Dumpsters shall be kept closed at all times, be located on a concrete pad, be emptied regularly
and be enclosed in a fenced area with a 6ft stockade fence or equivalent
Condition #12) Traffic circulation onsite shall be one way counterclockwise and signed and striped accordingly
Condition #13) Waste disposal containment area shall be shown on the plan
2
Condition #14) Show the sign on the plan
Condition #15) The water main shall be extended with a 8 inch main from where it ends at 235 Hart Street to
the proposed property
Condition #16) A landscape plan conforming to section 440-702 for interior and perimeter landscaping shall be
provided. A reduction of side yard landscaping to 12.5’ and reduction of plantings to 50% and interior
landscaped islands as shown on plans.
Condition #17) Proposed guardrails to be re-enforced with steel cable.
Condition #18) The ISO sign for handicapped parking needs to be provided.
Notes;
Note 1) DPW permits are required including city licensed contractor, road opening and trench permits. Plans
shall be submitted to DPW for water services, fire service line, gate valves and curb stops
Note 2) DPW specifications shall apply including backflow devices, pressure testing, materials, installation,
inspection and approval and prior notice is required before any city water work is to be performed and
inspections are required prior to backfilling
Vote: 7 In Favor
Anthony Abreau YES
Dennis Ackerman YES
Robert Campbell YES
John Reardon YES
Manuel Spencer Jr YES
Michael Monteiro YES
Brian Carr YES
Public Hearing - 515 Middleboro Avenue (Property .I .D. 96-135 & 96-134) - A Special Permit/Site
Plan Review from Section 440 Attachment #2 of the Zoning Ordinance to allow a 3,320 s. f. auto repair
shop with auto sales (58 vehicles) with an updated parking layout for customers, sales, and repair
storage spaces and the installation of a drainage system in the Business District, property owned by
Lillian Amaro submitted by Amaro Family Auto.
Request to continue to next month.
Motion made and second to grant continuance to April 6, 2023
Vote: Ackerman, Spencer, Abreau, Carr, Monteiro, Reardon, Campbell…Yes.
Meeting adjourned at 6:44 PM