Troy Industrial Development Authority
Regular MeetingTroy, NY · September 15, 2017
Minutes
Troy
Industrial Development Authority
September 15, 2017
10:00 AM
Meeting Minutes
Present: Kevin O’Bryan, Steve Strichman, Paul Carroll, Susan Farrell, Hon. Dean Bodnar and
Lou Anthony
Absent: Tina Urzan, Brian Carroll and Hon. Robert Doherty
Also in attendance: Justin Miller, Deanna DalPos, James Lozano, Mary Ellen Flores and Denee
Zeigler.
The Chairman called the meeting to order at 10:00 a.m.
I. Minutes
The board reviewed the minutes from the July 21, 2017 board meeting.
Paul Carroll made a motion to approve the July 21, 2017 meeting
minutes.
Lou Anthony seconded the motion, motion carried.
II. Staffing Agreement between the IDA and the City
Mr. Strichman advised we will discuss the staffing agreement at next month’s meeting.
The board asked what the amount was last year. Mr. Strichman advised $100,000.
III. Fee Sharing service between LDC and IDA
Mr. Strichman noted that this item will also be discussed next month as the details need
to be worked out and a policy can be set up. The board had a general discussion about
the agreement and noted that it will not apply to every project.
IV. Auditor RFP
Mr. Strichman noted that we will be re-issuing the RFP for auditor services. He added
that last year we sent a request out for the current year only due to the BST acquiring
CFO for Hire. The request that will be sent out will be for a three year contract.
V. Executive Directors report
701 River Street - Mr. Strichman advised that the project is progressing. He added that
they are working to acquire some properties surrounding the building. The board asked
if the PILOT agreement has closed. Mr. Miller advised the project has been fully
approved and the closing will be set up once the construction financing is in place.
Bow Tie Cinemas – Mr. Strichman advised that this project is currently being reviewed.
1
Salt Pile – Mr. Strichman advised that he was approached about assisting with a grant to
relocate the salt pile. He advised that there will be more details on this going forward.
433 River Street – Mr. Strichman advised that we will be meeting with First Columbia
regarding the job numbers that were submitted with the approved PILOT. Mr. Miller
explained that the extension of their previous PILOT included stipulation if they went
below the full time employee number. He added that there may be some other changes
that will be needed. Mr. Strichman advised that there will be more discussed next month
515 River Street - Mr. Strichman advised that the project located at 515 River Street is
underway. Mr. Miller advised that the PILOT for that project has not closed, but the
sales tax emption portion has.
Project Pipeline - Mr. Strichman advised that there are three potential projects coming
up; DeFazio’s in Little Italy, Bow Tie Cinemas and 669 River Street.
VI. Financials
Ms. Flores advised that the balance sheet shows no significant changes. She advised
there is a difference in the receivable number due to PILOT payments being received.
She added that those funds will be passed on to the City.
Ms. Flores advised a loss for the month in the amount of $4,400; due to IDA paying
school taxes for the Mlock parcel.
Paul Carroll made a motion to accept the financials as presented.
Hon. Dean Bodnar seconded the motion, motion carried.
Adjournment to CRC portion of the meeting at 10:10 a.m.
Lou Anthony made a motion to adjourn to the IDA portion of the
meeting to convene as the CRC.
Paul Carroll seconded the motion, motion carried.
Hon. Dean Bodnar made a motion to re-convene the IDA portion of the
meeting at 10:15 a.m.
VII. Old Business
No new business to discuss.
VIII. New Business
Mr. Strichman advised that next meeting we will have a discussion on the budget.
IX. Adjournment
With no other items to discuss, the IDA portion of the meeting was adjourned at 10:20
a.m. The chairman noted that the next meeting date may be moved to October 27th.
Lou Anthony made a motion to adjourn the IDA meeting.
Paul Carroll seconded the motion, motion carried.
2
Agenda
Chairman
Troy
Kevin O’Bryan
Industrial Development
Authority
Vice-Chair
Brian Carroll
BOARD OF DIRECTORS MEETING
Executive Director September 15, 2017
10:00 a.m.
Steven Strichman
Planning Department Conference
Board Members
Room
Hon. Dean Bodnar
Mr. Paul Carroll
Hon. Robert Doherty
AGENDA
Louis Anthony
Tina Urzan
Adam Hotaling
Susan Farrell
I. Approval of Minutes from the July 14, 2017 board meeting.
II. City Staffing Agreement 2017
III. IDA and LDC Economic Development Services Agreement
IV. Auditor RFP
V. Executive Director Report
VI. Financials
VII. Old Business
VIII. New Business
IX. Adjournment
City Hall – 433 River Street, Suite 5001, Troy, New York 12180
Phone: 518.279.7166
Troy
Industrial Development Authority
July 14, 2017
10:00 AM
Meeting Minutes
Present: Kevin O’Bryan, Tina Urzan, Steve Strichman, Brian Carroll, Hon. Robert
Doherty, Paul Carroll, Susan Farrell, Hon. Dean Bodnar and Lou Anthony
Absent: Adam Hotaling
Also in attendance: Robert Ryan, Joe Masher, Kate Jarosh, Larry Novik, Sharon
Martin, Cheryl Kennedy, Ken Crowe, John Fetscher, Darrell Camp, Asa Stackel, Patti
O’Brien, Deanna DalPos, Mary Ellen Flores and Denee Zeigler.
The Chairman called the meeting to order at 10:00 a.m.
I. Minutes
D
The board reviewed the minutes from the June 16, 2017 board meeting.
Hon. Bob Doherty made a motion to approve the June 16,
R
2017 meeting minutes.
Tina Urzan seconded the motion, motion carried.
II.
T
Initial Project Resolution – Bow Tie Cinemas Project, BTP Monument Square, LLC
AF
Mr. Strichman spoke to the board about the Bow Tie cinema projects that are
located in Schenectady and Saratoga. He advised that they have been great
generators of business for those areas; sales tax, local businesses, etc. He
added that currently there is a major leakage of movie theater/entertainment
revenue going to surrounding areas. Mr. Strichman advised that the building is
about 45,000 square feet and they have had some discussion on a PILOT
structure, but nothing specific at this time, although, it will likely go out 25 years.
Mr. Strichman introduced Larry Novik and Kate Jarosh from Bonacio Construction
and Joe Masher from Bow Tie Cinemas.
Mr. Novik advised that most of the board and public are probably familiar with
the project at this point, so he will go over the project briefly and then take time
to answer questions. He explained that they will be here for the planning
workshop next week and are on the agenda for the end of the month. Mr. Novik
advised that Bow Tie Cinemas is taking a large risk in this project and we
appreciate this board’s time as well as the city’s. Mr. Novik explained that he
was involved personally in the effort to bring Bow Tie to Saratoga Springs and he
can attest to the change that can happen in a downtown due to a project like
this. He added that the theaters act as a magnet that brings people to the
downtown and the surrounding benefits by local establishments.
Mr. Masher advised that they are looking to construct a new building that will
contain 11 screening rooms with seat counts ranging from 200 to down to 75.
1
He noted that they will be luxury seats; meaning electric reclining chairs and full
food and beverage options. He added that the theaters are priced competitively
with other theaters in the country. Mr. Masher advised they are doing their first
luxury concept in Norwalk, Connecticut, but is excited to bring this concept to his
hometown of Troy, NY. Mr. Masher advised that luxury concept generally
increases attendance, especially if it is the first one in the region. He advised
that they are trying to take in everyone’s design considerations and does not
want to create a box building. Mr. Masher presented a rendering of their initial
concept. He advised they hope to create an area where cars can pull in and
drop people off as well as creating an access point to the river and a parking
area. Mr. Masher advised that there will be a balcony area where people can sit
and enjoy the view or their dinner before the show. He advised that they are
also keeping an eye on the parking situation.
The chairman advised we will take questions and comments on the Bow Tie
cinema part of the project and then will discuss the American Theater project.
Tina Urzan asked for clarification on the number of screens and seats. Mr.
Masher advised that it will be 11 screens and approximately 1300 seats in all;
each auditorium will have a different amount of seats. He advised that the seats
will be the same in all auditoriums; only the number will vary. Ms. Urzan asked
about how this seating is different than what we have seen in this area. Mr.
D
Masher advised that they will have generous spacing between them, will be
electric recliners and have a swing up tray. He added that they will be built on
platforms, they are not a traditional stadium seating. Ms. Urzan asked if there
will be traditional concessions. He advised yes and will include more dinner type
R
of options. Ms. Urzan asked about the ticket prices. Mr. Masher advised that
they ticket prices will be comparable to other theaters in the area. Ms. Urzan
asked about the number of full time employees. Mr. Masher advised that they
will have 8 full time management employees and about 50-75 part time
T
employees between the two buildings. Ms. DalPos asked about the plan for
AF
Front Street. Mr. Novik advised that they will be working with the planning
board on that later this month as well as historic review. Mr. Novik did explain
that the intent is that Front Street will carry through underneath their building.
Ms. DalPos asked if the building will include space for retail. Mr. Novik advised
no retail space included in this design. Brian Carroll asked if there are any
anticipated changes in cost that may come up during the planning process. Mr.
Novik advised no, not to his knowledge. He added that if the planning board
were to request a major change to the building design, then the costs may
change. (See attached Resolution 07/17 #1)
Brian Carroll made a motion to approve the Initial Project
Resolution for Bow Tie Cinemas Project, BTP Monument Square,
LLC.
Paul Carroll seconded the motion.
Ayes 7 Nays 1 Absent 1, motion carried.
III. Initial Project Resolution – Dauchy/River Triangle, LLC – American Cinema
Redevelopment Project
Mr. Novik spoke to the board about the historic theater located on River Street
that they purchased several years ago. He advised that when the Bow Tie
project started, there was also some interest in redeveloping the smaller theater.
Mr. Masher advised that he has always been interested in the American Theater
2
and would like to see it used specifically for independent films. Mr. Bodnar
asked about the structure of the building which has been vacant for quite a
while. Mr. Novik advised that this building is in great shape, adding that a new
roof was put on shortly before it closed which has helped to keep it from the
elements. Mr. Bodnar asked if they are confident in being able to restore this
building. Mr. Masher advised that there is not much work that is needed to the
inside and only some minor façade work is needed. Mr. Novik agreed and added
that the marquee that was taken down before they purchased it was not the
original. He noted that they will be in further discussions to see how much
historic renovations will take place. Ms. Urzan asked about the risk of this
project. Mr. Masher advised that he is confident that the downtown will respond
well to these projects. He did note that Troy has not had a movie theater in
quite some time and it is a much different place than it was even ten years ago.
He advised that the city is vibrant and full of activity these days and a movie
theater would be a great addition. Mr. Novik added that they have also noted a
nice momentum curve; a long term vision is needed in order to see the potential.
He noted that a large company such as Bow Tie has seen the potential also and
is willing to take a chance in Troy. Mr. Masher explained that Bow Tie cinemas
have a great history of successful management. He advised that they have put
theaters in places with high crime rates and the presence of the theater helped
to turn the area around. The board had a general discussion of the success of
D
the Bow Tie project in Schenectady. Mr. Doherty wanted to note that
throughout this whole process, Bow Tie Cinemas and Bonacio Construction have
been very professional and feels this will continue through to the project. He
added that through several public meetings, there was discussion about
R
connecting this space to the very important Hudson River. Mr. Novik spoke
about the design of the building and how they want the site to connect to the
riverfront. He explained that the one of their buildings is located next to the
riverfront park staircase that was put in a few years ago. Mr. Novik found that
T
people do not congregate at the railing on the top deck enjoying the view of the
AF
river, rather, people use the staircase all of the time as a connection to another
space. He advised that the idea of an open hole to the river is not as compelling
as an active space with the energy of people coming and going, connecting them
to other areas of the city.
Brian Carrol asked if there have been anything in the discussions with the
planning board that would significantly change the cost of this project. Mr. Novik
advised no, the size of this project will not change. Brian Carroll asked for
clarification on a piece of information he read about the fact that the American
Theater project will be done in conjunction with 1 Monument Sq and that both
projects would not move forward without assistance. Mr. Masher explained that
the statement regarding the projects being done in conjunction comes from the
idea that they would not be as successful with the smaller American Theater
project if the larger one at 1 Monument Square was not going to happen. Mr.
Novik added that Bonacio Construction has been struggling to find an alternate
use for the American Theater site for any other use for quite some time. He
advised that when Bow Tie expressed an interest, they realized it was a great
opportunity to keep it as a theater. Brian Carroll asked if the American Theater
project doesn’t go through, will 1 Monument Square still happen. Mr. Novik
explained that it would be a shame to not move the project forward; there may
not be another opportunity like this. Mr. Strichman outlined that next steps in
the process and explained they should be back to us in September. (See
attached Resolution 07/17 #2)
3
Lou Anthony made the motion to approve the Initial Project
Resolution for Dauchy/River Triangle, LLC – American Cinema
Redevelopment Project.
Bob Carroll seconded the motion, motion carried.
IV. Executive Directors report
701 River Street - Mr. Strichman advised that the project has submitted their
application to the planning commission for July.
515 River Street – Mr. Strichman advised no updates on this project, but will
reach out again and advise the board of any updates.
V. Financials
Ms. Flores advised that the balance sheet shows $817,000 in assets versus
$817,000 in equity; no change.
Ms. Flores advised not much change with the operating statement either. She
advised that there is a loss of $18,000 for the month which is made up of
D
professional services.
Brian Carroll made a motion to accept the financials as
presented.
VI.
R
Tina Urzan seconded the motion, motion carried.
Old Business
T
No new business to discuss.
AF
VII. New Business
The chairman advised that we will not have a meeting in August.
VIII. Adjournment
With no other items to discuss, the IDA portion of the meeting was adjourned at
10:38 a.m. Next meeting will be September 15th.
Tina Urzan made a motion to adjourn the IDA meeting.
Brian Carroll seconded the motion, motion carried.
4
INITIAL PROJECT RESOLUTION
(Bow Tie Cinemas Project, BTP Monument Square, LLC)
A regular meeting of the Troy Industrial Development Authority (the “Authority”) was
convened on July 14, 2017 at 10:00 a.m., local time, at 433 River Street, 5th Floor, Troy, New
York 12180.
The meeting was called to order by the Chairman and, upon roll being called, the
following members of the Authority were:
MEMBER PRESENT ABSENT
Kevin O’Bryan X
Brian Carroll X
Hon. Dean Bodnar X
D
Hon. Robert Doherty
Louis Anthony
Paul Carroll
X
X
X
Adam Hotaling
Susan Farrell
Tina Urzan R X
X
X
T
The following persons were ALSO PRESENT: Robert Ryan, Joe Masher, Kate Jarosh,
Larry Novik, Sharon Martin, Cheryl Kennedy, Ken Crowe, John Fetscher, Darrell Camp, Asa
AF
Stackel, Patti O’Brien, Deanna DalPos, Mary Ellen Flores and Denee Zeigler.
After the meeting had been duly called to order, the Chairman announced that among the
purposes of the meeting was to consider and take action on certain matters pertaining to a
proposed project for the benefit of BTP Monument Square, LLC.
On motion duly made by Brian Carroll and seconded by Paul Carroll, the following
resolution was placed before the members of the Troy Industrial Development Authority:
Member Aye Nay Abstain Absent
Kevin O’Bryan X
Brian Carroll X
Hon. Dean Bodnar X
Hon. Robert Doherty X
Louis Anthony X
Paul Carroll X
Adam Hotaling X
Susan Farrell X
Tina Urzan X
Page 1 of 5
Resolution No. 07/17 #1
RESOLUTION OF THE TROY INDUSTRIAL DEVELOPMENT AUTHORITY
(THE “AUTHORITY”) (i) ACCEPTING THE APPLICATION OF BTP
MONUMENT SQUARE, LLC (THE “COMPANY”) IN CONNECTION WITH
A CERTAIN PROJECT (AS MORE FULLY DEFINED BELOW); (ii)
AUTHORIZING THE SCHEDULING, NOTICE AND CONDUCT OF A
PUBLIC HEARING WITH RESPECT TO THE PROJECT; AND (iii)
DESCRIBING THE FORMS OF FINANCIAL ASSISTANCE BEING
CONTEMPLATED BY THE AUTHORITY WITH RESPECT TO THE
PROJECT
WHEREAS, by Title 11 of Article 8 of the Public Authorities Law of the State of New
York, as amended, and Chapter 759 of the Laws of 1967 of the State of New York, as amended
D
(hereinafter collectively called the “Act”), the TROY INDUSTRIAL DEVELOPMENT
AUTHORITY (hereinafter called the “Authority”) was created with the authority and power to
own, lease and sell property for the purpose of, among other things, acquiring, constructing and
equipping industrial, manufacturing and commercial facilities as authorized by the Act; and
R
WHEREAS, BTP MONUMENT SQUARE, LLC, for itself and/or on behalf of an
entity to be formed ( collectively, the “Company”), has requested the Authority’s assistance with
T
a certain project (the “Project”) consisting of (i) the acquisition by the Authority of a leasehold
interest in approximately 1.57 acres of real property located at One Monument Square, Troy,
AF
New York 12180 (the “Land”, being more particularly identified as TMID Nos. 101.53-1-1,
101.45-5-4.1, 101.45-5-5 and 100.60-1-2) and the existing site and infrastructure improvements
located thereon (the “Existing Improvements”), (ii) the planning, design, engineering,
construction, and improvement of the Land and Existing Improvements into approximately
43,000 square feet of retail space consisting of an 8-10 screen multiplex movie theater, along
with parking improvements for approximately 100-130 vehicles, exterior access and egress
improvements, curbage, utility and related exterior improvements (collectively, the
“Improvements”), (iii) the acquisition and installation by the Company in and around the Land,
Existing Improvements and Improvements of certain items of equipment and other tangible
personal property necessary and incidental in connection with the Company’s development of
the Project in and around the Land, Existing Improvements and Improvements (the “Equipment”,
and collectively with the Land, the Existing Improvements and the Improvements, the
“Facility”); and (iv) the lease of the Facility to the Company and
WHEREAS, pursuant to the Act, the Authority desires to adopt a resolution describing
the Project and the Financial Assistance (as hereinafter defined) that the Authority is
contemplating with respect to the Project; and
WHEREAS, it is contemplated that the Authority will (i) accept the Application
submitted by the Company; (ii) approve the scheduling, notice and conduct of a Public Hearing
Page 2 of 5
with respect to the Project; and (iii) approve the negotiation, but not the execution or delivery, of
certain documents in furtherance of the Project, as more fully described below.
NOW, THEREFORE, BE IT RESOLVED BY THE MEMBERS OF THE TROY
INDUSTRIAL DEVELOPMENT AUTHORITY AS FOLLOWS:
Section 1. The Company has presented an application in a form acceptable to the
Authority. Based upon the representations made by the Company to the Authority in the
Company’s application and in related correspondence, the Authority hereby finds and determines
that:
(A) By virtue of the Act, the Authority has been vested with all powers necessary and
convenient to carry out and effectuate the purposes and provisions of the Act and to exercise all
powers granted to it under the Act; and
(B) The Authority has the authority to take the actions contemplated herein under the
Act; and
(C)
D The action to be taken by the Authority will induce the Company to develop the
Project, and otherwise furthering the purposes of the Authority as set forth in the Act; and
(D)
R
The Project will not result in the removal of a commercial, industrial, or
manufacturing plant of the Company or any other proposed occupant of the Project from one
area of the State of New York (the “State”) to another area of the State or result in the
T
abandonment of one or more plants or facilities of the Company or any other proposed occupant
of the Project located within the State; and the Authority hereby finds that, based on the
AF
Company’s application, to the extent occupants are relocating from one plant or facility to
another, the Project is reasonably necessary to discourage the Project occupants from removing
such other plant or facility to a location outside the State and/or is reasonably necessary to
preserve the competitive position of the Project occupants in their respective industries; and
Section 2. The proposed Financial Assistance being contemplated by the Authority
includes (i) a sales and use tax exemption for materials, supplies and rentals acquired or procured
in furtherance of the Project by the Company as agent of the Authority; (ii) mortgage recording
tax exemption(s) in connection with secured financings undertaken by the Company in
furtherance of the Project; and (iii) an abatement or exemption from real property taxes levied
against the Land and Facility pursuant to a PILOT Agreement to be negotiated.
Section 3. The Chairman, Vice Chairman, and/or Executive Director/Chief Executive
Officer of the Authority are hereby authorized, on behalf of the Authority, to schedule, notice
and conduct a public hearing in compliance with the Act and negotiate (but not execute or
deliver) the terms of (A) an Agent and Financial Assistance and Project Agreement (the “Agent
Agreement”), (B) a Lease Agreement, pursuant to which the Company leases the Project to the
Authority (or, a Deed of conveyance to the Authority whereby the Authority will acquire fee title
to the Land and Project), (C) a related Leaseback Agreement, pursuant to which the Authority
leases its interest in the Project back to the Company, (D) a PILOT Agreement, pursuant to
Page 3 of 5
which the Company agrees to make certain payments in-lieu-of real property taxes, and (E)
related documents thereto; provided (i) the rental payments under the Leaseback Agreement
include payments of all costs incurred by the Authority arising out of or related to the Project and
indemnification of the Authority by the Company for actions taken by the Company and/or
claims arising out of or related to the Project and (ii) the terms of the PILOT Agreement are
consistent with the Authority’s Uniform Tax Exemption Policy or the procedures for deviation
have been complied with.
Section 4. The officers, employees and agents of the Authority are hereby authorized
and directed for and in the name and on behalf of the Authority to do all acts and things required
and to execute and deliver all such certificates, instruments and documents, to pay all such fees,
charges and expenses and to do all such further acts and things as may be necessary or, in the
opinion of the officer, employee or agent acting, desirable and proper to effect the purposes of
the foregoing resolutions and to cause compliance by the Authority with all of the terms,
covenants and provisions of the documents executed for and on behalf of the Authority.
Section 5. These Resolutions shall take effect immediately.
D
R
T
AF
Page 4 of 5
T
AF
R
D
INITIAL PROJECT RESOLUTION
(Dauchy/River Triangle, LLC – American Cinema Redevelopment Project)
A regular meeting of the Troy Industrial Development Authority (the “Authority”) was
convened on July 14, 2017 at 10:00 a.m., local time, at 433 River Street, 5th Floor, Troy, New
York 12180.
The meeting was called to order by the Vice Chairman and, upon roll being called, the
following members of the Authority were:
MEMBER PRESENT ABSENT
Kevin O’Bryan X
Brian Carroll X
Hon. Dean Bodnar X
Hon. Robert Doherty X
D
Louis Anthony
Paul Carroll
Adam Hotaling
X
X
X
Susan Farrell
Tina Urzan
R X
X
The following persons were ALSO PRESENT: Robert Ryan, Joe Masher, Kate Jarosh,
T
Larry Novik, Sharon Martin, Cheryl Kennedy, Ken Crowe, John Fetscher, Darrell Camp, Asa
Stackel, Patti O’Brien, Deanna DalPos, Mary Ellen Flores and Denee Zeigler.
AF
After the meeting had been duly called to order, the Chairman announced that among the
purposes of the meeting was to consider and take action on certain matters pertaining to a
proposed project for the benefit of Dauchy/River Triangle, LLC.
On motion duly made by Lou Anthony and seconded by Hon. Bob Doherty, the
following resolution was placed before the members of the Troy Industrial Development
Authority:
Member Aye Nay Abstain Absent
Kevin O’Bryan X
Brian Carroll X
Hon. Dean Bodnar X
Hon. Robert Doherty X
Louis Anthony X
Paul Carroll X
Adam Hotaling X
Susan Farrell X
Tina Urzan X
Page 1 of 5
Resolution No. 07/17 #2
RESOLUTION OF THE TROY INDUSTRIAL DEVELOPMENT AUTHORITY
(THE “AUTHORITY”) (i) ACCEPTING THE APPLICATION OF
DAUCHY/RIVER TRIANGLE, LLC (THE “COMPANY”) IN CONNECTION
WITH A CERTAIN PROJECT (AS MORE FULLY DEFINED BELOW); (ii)
AUTHORIZING THE SCHEDULING, NOTICE AND CONDUCT OF A
PUBLIC HEARING WITH RESPECT TO THE PROJECT; AND (iii)
DESCRIBING THE FORMS OF FINANCIAL ASSISTANCE BEING
CONTEMPLATED BY THE AUTHORITY WITH RESPECT TO THE
PROJECT
WHEREAS, by Title 11 of Article 8 of the Public Authorities Law of the State of New
D
York, as amended, and Chapter 759 of the Laws of 1967 of the State of New York, as amended
(hereinafter collectively called the “Act”), the TROY INDUSTRIAL DEVELOPMENT
AUTHORITY (hereinafter called the “Authority”) was created with the authority and power to
own, lease and sell property for the purpose of, among other things, acquiring, constructing and
R
equipping industrial, manufacturing and commercial facilities as authorized by the Act; and
WHEREAS, DAUCHY/RIVER TRIANGLE, LLC, for itself and/or on behalf of an
T
entity to be formed ( collectively, the “Company”), has requested the Authority’s assistance with
a certain project (the “Project”) consisting of (i) the acquisition by the Authority of a leasehold
AF
interest in approximately .17 acres of real property located at 285-289 River Street, Troy, New
York 12180 (the “Land”, being more particularly identified as TMID No. 101.45-5-3) and the
existing building structure located thereon consisting principally of a multi-story former movie
theater (the “Existing Improvements”), (ii) the planning, design, engineering, construction,
reconstruction, rehabilitation and improvement of the Land and Existing Improvements into an
modern movie theater, the upgrade and improvement of commercials space, exterior access and
egress improvements, mechanical, roof, window, utility and HVAC improvements, and parking,
curbage, signage and related exterior improvements (collectively, the “Improvements”), (iii) the
acquisition and installation by the Company in and around the Land, Existing Improvements and
Improvements of certain items of equipment and other tangible personal property necessary and
incidental in connection with the Company’s development of the Project in and around the Land,
Existing Improvements and Improvements (the “Equipment”, and collectively with the Land, the
Existing Improvements and the Improvements, the “Facility”); and (iv) the lease of the Facility
to the Company and
WHEREAS, pursuant to the Act, the Authority desires to adopt a resolution describing
the Project and the Financial Assistance (as hereinafter defined) that the Authority is
contemplating with respect to the Project; and
Page 2 of 5
WHEREAS, it is contemplated that the Authority will (i) accept the Application
submitted by the Company; (ii) approve the scheduling, notice and conduct of a Public Hearing
with respect to the Project; and (iii) approve the negotiation, but not the execution or delivery, of
certain documents in furtherance of the Project, as more fully described below.
NOW, THEREFORE, BE IT RESOLVED BY THE MEMBERS OF THE TROY
INDUSTRIAL DEVELOPMENT AUTHORITY AS FOLLOWS:
Section 1. The Company has presented an application in a form acceptable to the
Authority. Based upon the representations made by the Company to the Authority in the
Company’s application and in related correspondence, the Authority hereby finds and determines
that:
(A) By virtue of the Act, the Authority has been vested with all powers necessary and
convenient to carry out and effectuate the purposes and provisions of the Act and to exercise all
powers granted to it under the Act; and
(B)
Act; and
(C)
D The Authority has the authority to take the actions contemplated herein under the
The action to be taken by the Authority will induce the Company to develop the
R
Project, and otherwise furthering the purposes of the Authority as set forth in the Act; and
(D) The Project will not result in the removal of a commercial, industrial, or
T
manufacturing plant of the Company or any other proposed occupant of the Project from one
area of the State of New York (the “State”) to another area of the State or result in the
AF
abandonment of one or more plants or facilities of the Company or any other proposed occupant
of the Project located within the State; and the Authority hereby finds that, based on the
Company’s application, to the extent occupants are relocating from one plant or facility to
another, the Project is reasonably necessary to discourage the Project occupants from removing
such other plant or facility to a location outside the State and/or is reasonably necessary to
preserve the competitive position of the Project occupants in their respective industries; and
Section 2. The proposed Financial Assistance being contemplated by the Authority
includes (i) a sales and use tax exemption for materials, supplies and rentals acquired or procured
in furtherance of the Project by the Company as agent of the Authority; (ii) mortgage recording
tax exemption(s) in connection with secured financings undertaken by the Company in
furtherance of the Project; and (iii) an abatement or exemption from real property taxes levied
against the Land and Facility pursuant to a PILOT Agreement to be negotiated.
Section 3. The Chairman, Vice Chairman, and/or Executive Director/Chief Executive
Officer of the Authority are hereby authorized, on behalf of the Authority, to schedule, notice
and conduct a public hearing in compliance with the Act and negotiate (but not execute or
deliver) the terms of (A) an Agent and Financial Assistance and Project Agreement (the “Agent
Agreement”), (B) a Lease Agreement, pursuant to which the Company leases the Project to the
Authority (or, a Deed of conveyance to the Authority whereby the Authority will acquire fee title
Page 3 of 5
to the Land and Project), (C) a related Leaseback Agreement, pursuant to which the Authority
leases its interest in the Project back to the Company, (D) a PILOT Agreement, pursuant to
which the Company agrees to make certain payments in-lieu-of real property taxes, and (E)
related documents thereto; provided (i) the rental payments under the Leaseback Agreement
include payments of all costs incurred by the Authority arising out of or related to the Project and
indemnification of the Authority by the Company for actions taken by the Company and/or
claims arising out of or related to the Project and (ii) the terms of the PILOT Agreement are
consistent with the Authority’s Uniform Tax Exemption Policy or the procedures for deviation
have been complied with.
Section 4. The officers, employees and agents of the Authority are hereby authorized
and directed for and in the name and on behalf of the Authority to do all acts and things required
and to execute and deliver all such certificates, instruments and documents, to pay all such fees,
charges and expenses and to do all such further acts and things as may be necessary or, in the
opinion of the officer, employee or agent acting, desirable and proper to effect the purposes of
the foregoing resolutions and to cause compliance by the Authority with all of the terms,
covenants and provisions of the documents executed for and on behalf of the Authority.
D
Section 5. These Resolutions shall take effect immediately.
R
T
AF
Page 4 of 5
T
AF
R
D
AUTHORIZING RESOLUTION
(Ratifying Administrative Fee Policy)
A regular meeting of the Troy Industrial Development Authority was convened on
September 15, 2017, at 10:00 a.m. at 433 River Street, Troy, New York 12180
The meeting was called to order by the Chairman, with the following members being:
PRESENT:
ABSENT:
THE FOLLOWING PERSONS WERE ALSO PRESENT:
On motion duly made and seconded, the following resolution was placed before the
members of the Troy Industrial Development Authority:
Resolution No. 2017 -
RESOLUTION OF THE TROY INDUSTRIAL DEVELOPMENT AUTHORITY
RATIFYING ADMINISTRATIVE FEE POLICY AND PROCEDURES
WHEREAS, by Title 11 of Article 8 of the Public Authorities Law of the State of New
York, as amended, and Chapter 759 of the Laws of 1967 of the State of New York, as amended
(hereinafter collectively called the “Act”), the TROY INDUSTRIAL DEVELOPMENT
AUTHORITY (hereinafter called “Authority”) was created with the authority and power to
own, lease and sell property for the purpose of, among other things, acquiring, constructing and
equipping industrial, manufacturing and commercial facilities as authorized by the Act; and
WHEREAS, pursuant to Chapter 563 of the Laws of 2015, the Authority approved by
resolution dated May 20, 2016 the following administrative policies and forms: (i) an updated
Application for Financial Assistance (the “Application”); (ii) an updated Project Recapture and
Termination Policy; (iii) a Uniform Project Evaluation Policy; and (iv) a standard form of Agent
and Financial Assistance and Project Agreement; and
WHEREAS, the Authority desires to ratify the Administrative Fee Schedule contained
within the Application and also authorize certain fee sharing with the Troy Local Development
Corporation (“TLDC”).
NOW, THEREFORE, BE IT RESOLVED BY THE MEMBERS OF THE TROY
INDUSTRIAL DEVELOPMENT AUTHORITY AS FOLLOWS:
Section 1. The Authority hereby ratifies the Administrative Fee Schedule contained
within the Application, and as set forth within Exhibit A, hereto.
Page 1
Section 2. The Authority hereby recognizes and acknowledges the role of TLDC as a
charitable, not-for-profit local development corporation and supporting organization for both the
Authority and the City of Troy, New York. In furtherance of same, TLDC undertakes certain
real estate development projects and initiatives that generate new projects for the Authority. In
recognition of TLDC’s mission and projects that support the Authority’s mission, the Authority
hereby approves the assignment of administrative fee income for projects that are generated and
led by TLDC activities. The foregoing shall include projects associated with the former King
Fuels site, 444 River Street, and any other projects that the Authority may identify from time to
time. In furtherance of the foregoing, the Authority hereby authorizes the execution and delivery
of the Administrative Fee Sharing Agreement attached hereto as Exhibit B.
Section 3. The members, officers, employees and agents of the Authority are hereby
authorized and directed for and in the name and on behalf of the Authority to do all acts and
things required and to execute and deliver all such certificates, instruments and documents, to
pay all such fees, charges and expenses and to do all such further acts and things as may be
necessary or, in the opinion of the officer, employee or agent acting, desirable and proper to
effect the purposes of the foregoing resolutions and to cause compliance by the Authority with
all of the terms, covenants and provisions of the documents executed for and on behalf of the
Authority.
Section 3. These Resolutions shall take effect immediately upon adoption.
The question of the adoption of the foregoing Resolution was duly put to a vote on roll
call, which resulted as follows:
Member Aye Nay Abstain Absent
Kevin O’Bryan
Brian Carroll
Hon. Dean Bodnar
Hon. Robert Doherty
Louis Anthony
Paul Carroll
Adam Hotaling
Susan Farrell
Tina Urzan
The Resolutions were thereupon duly adopted.
Page 2
EXHIBIT A
AUTHORITY ADMINISTRATIVE FEE SCHEDULE
Troy Industrial Development Authority (TIDA)
433 River Street, Suite 5001, Troy New York 12180
AUTHORITY ADMINISTRATIVE FEE SCHEDULE
Taxable and Tax Exempt Industrial Development Revenue Bonds
Application Fee: A non‐refundable fee of $2,500.00 and a $500.00 processing fee are
payable to the TIDA at the time the application is submitted. The
$2,500.00 fee will be credited towards the total fee at closing.
Fee: First $10,000,000: .75% of the principal amount of the bond series.
Over $10,000,000: .5% of the bond series
Annual (post‐closing) administrative fee of $1,500.00
Straight Lease Transactions (including PILOT Agreement)
Application Fee: A non‐refundable fee of $2,500.00 and a $500.00 processing fee are
payable to the TIDA at the time the application is submitted. The
$2500.00 fee will be credited towards the total fee at closing.
Fee: .75%
Annual administrative fee of $500.00
Sales Tax and/or Mortgage Recording Tax only Transactions (No PILOT
Agreement)
Application Fee: A non‐refundable fee of $2,500.00 and a $500.00 processing fee are
payable to the TIDA at the time the application is submitted. The
$2500.00 fee will be credited towards the total fee at closing.
Fee: Minimum $4,500.00 or 10% estimated exemption amount, whichever is
greater
Annual administrative fee of $500.00
Page 3
EXHIBIT B
Form of Administrative Fee Sharing Agreement
Page 4
STATE OF NEW YORK )
COUNTY OF RENSSELAER ) ss:
I, the undersigned Secretary of the Troy Industrial Development Authority, DO
HEREBY CERTIFY:
That I have compared the foregoing extract of the minutes of the meeting of the Troy
Industrial Development Authority (the “Authority”) including the resolution contained therein,
held on September 15, 2017, with the original thereof on file in my office, and that the same is a
true and correct copy of the proceedings of the Authority and of such resolution set forth therein
and of the whole of said original insofar as the same relates to the subject matters therein referred
to.
I FURTHER CERTIFY that all members of said Authority had due notice of said
meeting, that the meeting was in all respects duly held and that, pursuant to Article 7 of the
Public Officers Law (Open Meetings Law), said meeting was open to the general public, and that
public notice of the time and place of said meeting was duly given in accordance with Article 7.
I FURTHER CERTIFY that there was a quorum of the members of the Authority present
throughout said meeting.
I FURTHER CERTIFY that as of the date hereof, the attached resolution is in full force
and effect and has not been amended, repealed or modified.
IN WITNESS WHEREOF, I have hereunto set my hand and seal of said Authority this
__ day of ______________, 2017.
Secretary
[SEAL]
Page 5
ECONOMIC DEVELOPMENT SERVICES AGREEMENT
THIS ECONOMIC DEVELOPMENT SERVICES AGREEMENT (the
“Agreement”), dated as of September __, 2017, is entered into by and between the
TROY LOCAL DEVELOPMENT CORPORATION, a not-for-profit local
development corporation duly organized under the laws of the State of New York with
offices at 433 River Street, Troy New York 12180 (“TLDC”) and TROY INDUSTRIAL
DEVELOPMENT AUTHORITY, a public benefit corporation duly organized under
the laws of the State of New York with an address of 433 River Street, Troy New York
12180 (“TIDA”).
WITNESSETH:
WHEREAS, by Title 11 of Article 8 of the Public Authorities Law of the State of
New York, as amended, and Chapter 759 of the Laws of 1967 of the State of New York,
as amended (hereinafter collectively called the “Act”), TIDA was created with the
authority and power to own, lease and sell property for the purpose of, among other
things, acquiring, constructing and equipping industrial, manufacturing and commercial
facilities as authorized by the Act; and
WHEREAS, TLDC is a duly-established, not-for-profit local development
corporation of the State pursuant to Section 1411(h) of the Not-for-Profit Corporation
Law (“N-PCL”) and a Certificate of Reincorporation filed on April 5, 2010 (the
“Certificate”) established for the charitable and public purposes of relieving and reducing
unemployment, promoting and providing for additional and maximum employment,
bettering and maintaining job opportunities, instructing or training individuals to improve
or develop their capabilities for such jobs, by encouraging the development of, or
retention of, an industry in the community or area, and lessening the burdens of
government and acting in the public interest; and
WHEREAS, in accordance with an authorizing resolution adopted by TIDA on
September 15, 2017, TIDA and TLDC wish to memorialize the terms and conditions
pursuant to which TLDC will provide certain economic development services to TIDA in
exchange for administrative fee sharing in connection with TIDA projects; and
WHEREAS, in furtherance of the Act and N-PCL, TLDC and the TIDA desire to
enter into this Agreement pursuant to which TLDC will perform certain economic
development services for the benefit of the TIDA in connection with projects and
applications for financial assistance brought before the TIDA from time to time.
NOW, THEREFORE, for and in consideration of the promises and the mutual
covenants hereinafter contained, and other good and valuable consideration the receipt
and sufficiency of which is hereby acknowledged, the parties hereto formally covenant,
agree and bind themselves as follows:
Section 1. Economic Development Services. The TIDA hereby engages
TLDC to provide economic development services (the “Services”) that shall include:
(a) Provide strategic advice and assistance to potential projects and applicants
directly seeking TIDA financial assistance, including (i) the development and
submission of applications for financial assistance, (ii) the development and
assistance with cost-benefit analysis and presentation of applications to the
TIDA board for review and consideration, (iii) providing TIDA applicants
with assistance in presenting projects to the TIDA, affected tax jurisdictions,
zoning and planning boards, and before federal and state agencies, as
applicable;
(b) Provide grant writing and other strategic project funding application services,
including assistance with Consolidated Funding Applications (“CFA”);
(c) provide marketing and attraction services for TIDA projects, programs,
financial assistance and services;
(d) Advance acquisition and marketing of properties within the City that will
cultivate TIDA Projects.
Section 2. Compensation. In consideration for the Services, the TIDA shall
pay to TLDC all or a portion of the fees collected by the TIDA at closings for bond
financings and/or straight lease transactions that TLDC provides Services for in Sections
1(a) and 1(b), above (the “Compensation”). TLDC reserves the right on a case by case
basis to reinvest any Compensation earned hereunder back into the project being assisted
by the TIDA.
Section 3. Term; Termination. This Agreement shall be for a term of three
(3) years and automatically renew for successive one year terms thereafter. Either party
may terminate this Agreement upon six (6) months’ written notice.
Section 4. Counterparts. This Agreement may be executed in any number of
counterparts, each of which shall be deemed an original but which together shall
constitute a single instrument.
IN WITNESS WHEREOF, TLDC and the TIDA have caused this Agreement to
be executed in their respective names, all as of the date first above written.
TROY LOCAL DEVELOPMENT CORPORATION
By: _______________________________
Kevin O’Bryan, Chairman
TROY INDUSTRIAL DEVELOPMENT AUTHORITY
By: _______________________________
Steven Strichman, Executive Director
Get email alerts for Troy
A daily email when new agendas and minutes are posted.