Troy Local Development Corporation
Regular MeetingTroy, NY · November 15, 2024
Minutes
Regular Board Meeting
Minutes
November 15, 2024
9:00 a.m.
BOARD MEMBERS PRESENT: Randy Coburn, Seamus Donnelly and Jeff Betts
ABSENT: Andy Ross and Hon. Tom Casey
ALSO IN ATTENDANCE: Justin Miller, Esq., Matt Jones, Deanna Dal Pos and Denee Zeigler
The regular board meeting was called to order at 9:13 a.m.
I. Minutes
The board did not have a quorum of board members present and will review the
September 20, 2024 minutes at the next meeting.
II. Executive Director’s Report
Geothermal – There was a question that had come up regarding the use of the
space under the staircase at 274 River Street and previous DOS funding. Mr. Coburn
advised that the issue will be resolved once we have the lease language. Mr. Miller
added that with the shift of location to monument square, we are pushing back the
due date. He advised we are also waiting on some of the final designs from CHA.
There will be no need to resend all the SEQRA documents to interested parties. The
change is not considered material. Mr. Miller outlined the leases that will be needed
with the city. The change of location from the Atrium to Monument Square will end up
being a better fit in the end.
King Fuels Site – The clean up is going well and it is good to be able to have city
crews assist with debris clean up. Mr. Kreshik talked about the next steps of the
remediation at the site. He explained this is where they will be removing the
contamination and replacing those areas with a mixed material. Mr. Betts asked if
there was anything of note that occurred during phase I. Mr. Kreshik advised that
there were a lot of footings and concrete that they removed from the site. The site
will be in good shape for new development once remediated. Mr. Betts added that
this is the largest cleanup of this kind in Troy.
III. New Business
No new business to discuss.
IV. Old Business
1
Geothermal – already discussed as part of the executive directors’ report
King Fuels Site – Mr. Kreshik explained there is an invoice from the city related to
cleanup of debris which was dumped on the site. Mr. Donnelly explained that the
invoice is for $4,450.07 labor/cost of disposal for tires.
Motion to approve the expenditure of $4,450.07 to the City of Troy DPW for
debris removal – Seamus Donnelly
Second – Jeff Betts
Approved
Community Business Improvement Grants – Mrs. Zeigler gave an update to the
board on current and completed projects. There is approximately $190,000 available
that can be used towards applicants that missed the final round of application
reviews. Mr. Coburn asked if there is a timeframe for the uncommitted funds to be
spent. Mr. Donnelly advised yes; they must be spent by the end of 2026. Mr.
Donnelly noted the success of this grant program. Ms. Dal Pos asked if it was
possible to use this program to target properties that need repairs. Mr. Betts advised
he spread the word on this program, and it really comes down to the property owner
to apply.
V. Financials
Mr. Jones went over the statement of financial position noting that as of October 31,
2024 our total assets stand at $3,960,496. He advised $474,503 in cash with
$1,419,791 in liabilities, leaving a fund balance of $2,540,405. No significant
changes to the statement of financial position.
Mr. Jones went over the statement of activity for the month of October, noting a
surplus of $38,788. The most significant source of revenue was from admin fees and
the largest expense comes from professional services.
Mr. Jones went over the budget for 2025. Updates were made to reflect the National
Grid income, rental income and the one outstanding loan. Mr. Jones noted upcoming
changes with the HUD Loan ending in 2026. He also noted that the loan from the
CRC is still open. The board noted they will discuss repayment in future meetings.
The board was not ready to adopt the budget without the full board being able to
review it.
Motion to approve the financials and table the budget until next meeting –
Seamus Donnelly
Seconded – Jeff Betts
Approved
VI. Adjournment
With no other items to discuss, the regular board meeting was adjourned at 9:53
a.m.
Motion to adjourn the regular board meeting at 9:53 a.m. – Randy Coburn
Seconded – Jeff Betts
Approved
2
Agenda
Chair Board Members
Jeff Betts Randy Coburn
Hon. Tom Casey
Vice-Chair
Andy Ross Executive Director
Seamus Donnelly
Board of Directors Meeting
City Hall
Planning Dept. Conference Room
433 River Street, Suite 5001
Troy, NY 12180
NOVEMBER 15, 2024
9:00 a.m.
AGENDA
I. Approval of Minutes September 20, 2024 Board Meeting.
II. Executive Directors Report
III. New Business
IV. Old Business
1. Geothermal Project Update
2. King Fuels Remediation Update
3. Community Business Improvement Grant
V. Financials and 2025 Draft Budget Presentation
VI. Adjournment
Regular Board Meeting
Minutes
September 20, 2024
9:00 a.m.
BOARD MEMBERS PRESENT: Andy Ross, Seamus Donnelly and Hon. Tom Casey
ABSENT: Jeff Betts and Randy Coburn
ALSO IN ATTENDANCE: Justin Miller, Esq., Matt Jones, Max Freed, Deanna Dal Pos, Tara
D
Rainstrom and Denee Zeigler
The regular board meeting was called to order at 9:14 a.m.
I. Minutes
R
The board did not have a quorum of board members present and will review the
minutes at the next meeting.
II.
T
Executive Director’s Report
AF
Nothing at this time, but reports will resume next meeting.
III. New Business
No new business to discuss.
IV. Old Business
Geothermal Update – Mr. Miller updated the board about the geothermal project.
He noted that the city council authorized serving as lead agency for SEQRA and lead
agency letters have been sent out. The next steps will be to hold a public hearing
related to the leases for parkland, area under staircase and a portion of the Atrium.
All these items should be wrapped up in late October. Mr. Miller noted we are all
working towards January approval for the PSC.
King Fuels Site – Mr. Miller noted that phase I was completed and will be
surrendering the south portion of the site. They will be moving into the next phase
after a light cleanup is done with the help of the city.
Community Business Improvement Grants –
670 Pawling Ave - Mrs. Zeiger spoke on behalf of the 670 Pawling Ave project
where the applicant is looking to access $3,500 that was not used from her total
1
approval of $50,000. The addition of a grooming station was part of the original
scope of work but the timing of when it was going to be completed came into
question. After speaking to a business consultant, the applicant was advised to
complete the grooming center as part of the project. Board approval is needed to
allow a second disbursement to this applicant.
Motion to approve an additional disbursement of $3,500 for the project located
at 670 Pawling Ave – Seamus Donnelly
Second – Hon. Tom Casey
Approved
1813 Fifth Ave – Ms. Rainstrom spoke about her original project that is now
considered completed. She is extremely grateful for the grant funds which have
allowed her to hold new events such as micro weddings. She advised that because
of it being an old building an issue came up with the roof which created an issue with
the work recently completed. It’s a costly and complicated project that was going to
be addressed after this work was completed, however, the weather has shown it
needs to be worked on now to prevent further damage to the building. The original
grant amount requested was $33,659. She is asking for an additional amount of
$16,341 to bring it to the max grant amount of $50,000.
Motion to approve an additional $16,341 for additional work needed for 1813
D
Fifth Avenue. – Seamus Donnelly
Second – Hon. Tom Casey
Approved
R
Staffing – Mr. Miller advised there was an amount of $15,000 that was originally set
aside for the executive director position. There is now more program and activity
which calls for some additional staffing. He advised the amount will now be divided
between four individuals: Executive Director $5,000, Deputy Executive Director
T
$4,000, Project Manager $3,000 and Acting Secretary $3,000. Mr. Miller noted that
there is a separate agreement for each position.
AF
Motion to approve the staffing agreement and stipend in the amount of $4,000
for Randy Coburn as Deputy Executive Director – Seamus Donnelly
Second – Hon. Tom Casey
Approved
Motion to approve the staffing agreement and stipend in the amount of $3,000
for Andrew Kreshik as Project Manager – Seamus Donnelly
Second – Hon. Tom Casey
Approved
Motion to approve the staffing agreement and stipend in the amount of $3,000
for Denee Zeigler as Acting Secretary – Seamus Donnelly
Second – Hon. Tom Casey
Approved
Motion to approve the staffing agreement and stipend in the amount of $5,000
for Seamus Donnelly as Executive Director – Hon. Tom Casey
Second – Andy Ross
Abstained – Seamus Donnelly
Approved
2
V. Financials
Mr. Jones went over the statement of financial position noting that as of August 31,
2024 our total assets stand at $3,827,620. He advised $364,508 in cash with
$1,408,482 in liabilities, leaving a fund balance of $2,419,238. No significant
changes to the statement of financial position.
Mr. Jones went over the statement of activity for the month of August, noting a
surplus of $1,148.08. The most significant source of revenue was from the National
Grid license fee and the largest expense comes from accounting fees.
Mr. Jones went over the budget for 2025. He noted that there will need to be some
additional work on a few of the National Grid items, the loan from the CRC and the
geothermal project. Mr. Miller noted we can discuss these details before the next
meeting to work on getting it finalized for October.
Motion to approve the financials as presented – Seamus Donnelly
Seconded – Hon. Tom Casey
Approved
VI. Adjournment
D
With no other items to discuss, the regular board meeting was adjourned at 9:40
a.m.
Motion to adjourn the regular board meeting at 9:40 a.m. – Seamus
Donnelly
R
Seconded – Hon. Tom Casey
Approved
T
AF
3
Carmella R. Mantello Seamus P. Donnelly
Mayor Deputy Mayor
Joseph F. Mazzariello Office of General Services Phone: (518) 279-7161
City Hall Fax: (518) 270-4546
Commissioner of General Services
Joe.mazzariello@troyny.gov
433 River Street
Troy, New York 12180
October 24, 2024 Invoice No. 1
To: Troy Local Development Corporation
From: Troy City Hall
Subject: Invoice for Clean up at King Fuels Site; National Grid remediation license obligation
12 overtime labor hours 6 employees - $2,801.15
2 regular labor hours 3 employees - $131.92.
Total labor rate - $2,933.07
Tire removal fee – 233 tires x $6 each $1,398.00
Tires with rims removal 17 . $7 each $119.00
Total tire removal fee- $1,517.00
Invoice Total - $4,450.07