A regular meeting of the Board of Public Utilities Commissioners, City of Tulare,
was held on Thursday, June 2, 2016, at 3:00 p.m., in the Tulare Public Library &
Council Chambers.
BOARD MEMBERS PRESENT: Lee Brehm, Philip Smith, Edward Henry, Dick
Johnson
BOARD MEMBERS ABSENT: Mark Watte
STAFF PRESENT: Don Dorman, Paul Melikian, Joe Carlini, Michael Miller, Trisha
Whitfield, Steve Bonville, Nick Bartsch, Benjamin Siegel, Tim Doyle, Shonna Oneal
I. CALL TO ORDER REGULAR SESSION:
President Brehm called the regular session to order at 3:00 p.m.
II. PLEDGE OF ALLEGIANCE:
President Brehm led the Pledge of Allegiance.
III. CITIZEN’S REQUEST OR COMMENTS: This is the time for citizens to comment on
items within the jurisdiction of the Board. The Board cannot legally discuss or take
official action on citizen comments that are introduced tonight. Each speaker will be
allowed three minutes, with a maximum time of 10 minutes per item, unless
otherwise extended by the Board.
There were no citizen comments presented.
IV. COMMUNICATIONS:
There were no items for this section on the agenda.
V. CONSENT CALENDAR:
It was moved by Vice President Smith, seconded by Board Member Johnson
and unanimously carried that the items on the consent calendar be approved as
presented with the exception of items 3 and 5.
(1) Approve minutes of the May 19, 2016 regular/special meeting(s).
(2) Accept the April Investment Report.
Page 2978
(3) Accept the Public Works Project Dashboard. Board Member Henry pulled
this item for clarification on projects WT0020 and SD0015. Field Services
Manager Trisha Whitfield and City Manager Don Dorman provided responses
thereto. Following discussion, it was moved by Board Member Henry, seconded
by Vice President Smith and carried 4-0 (Board Member Watte absent) to accept
the item as presented.
(4) Adopt Resolution 16-09 authorizing the surplus of four (4) City vehicles.
(5) Authorize the City Manager to enter into a Suitability and Sale Agreement
between the City of Tulare and Samuel Gonzalez requiring property
suitability testing at 333 South I Street, Tulare, California, APN #175-185-
008-000, for a proposed new City well site, and upon determination of
suitability, authorize the City Manager to execute all necessary escrow
related documents, including applicable deeds to purchase said property in
the amount of $30,000. Board Member Henry pulled this item for clarification
regarding the assessed property value versus the purchase price. General
Services Director Steve Bonville provided a response thereto. Following
discussion, it was moved by Vice President Smith, seconded by Board Member
Johnson and carried 4-0 (Board Member Watte absent) to approve the item as
presented.
(6) Approve revisions to the Hydrological Enterprise Program (HEP) Business
Plan that incorporates a new section pertaining to Water Meters.
VI. GENERAL BUSINESS:
(1) Approve scope changes to project WT0020 Well Rehabilitation Project;
award and authorize the City Manager to execute a contract on Well #31
Rehabilitation project to Valley Pump & Dairy Systems of Tulare, California
in the amount of $51,122.00; and authorize the City Manager or Public
Works Director to approve contract change orders in amounts up to 10%
($5,112.20) of the contract award. Field Services Manager Trisha Whitfield
provided a report for the Board’s review and consideration. The Board raised
questions and staff provided responses thereto. Charles Ritchie of Tulare
inquired about the benefits the rehabilitation will provide. Water and Wastewater
Collections Utility Manager Tim Doyle provided a response thereto. Following a
brief discussion, it was moved by Vice President Smith, seconded by Board
Member Henry and carried 4-0 (Board Member Watte absent) to approve the
item as presented.
(2) Approve new conservation target of 20% and accept water conservation
report for April 2016. Management Analyst Benjamin Siegel provided a report
for the Board’s review and consideration. Public Works Director Joe Carlini
provided additional details regarding the new conservation target. Following
discussion, it was moved by Vice Present Smith, seconded by Board Member
Page 2979
Johnson and carried 4-0 (Board Member Watte absent) to approve the item as
presented.
It was the consensus of the Board to direct staff to bring back a proposed project
identifying two different options for metering the Matheny Tract water connection.
VII. ITEMS OF BOARD INTERESTS:
Items of Board interest were discussed among the Board and staff.
VIII. ADJOURN REGULAR MEETING:
President Brehm adjourned the regular meeting at 3:43 p.m.
__________________________________
President of the Board of Public Utilities
Commissioners of the City of Tulare
ATTEST:
__________________________
Secretary of the Board of
Public Utilities Commissioners
Get email alerts for Tulare
A daily email when new agendas and minutes are posted.