Hearing Examiner
Regular MeetingTumwater, WA · June 8, 2022
Minutes
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 1
CONVENE: 7:00 p.m.
CASE NUMBER: TUM-21-1887 and TUM-21-1889
DESCRIPTION OF The Applicant is requesting preliminary plat and planned unit
PROPOSAL: development (PUD) approvals to subdivide 10.43 acres into 41 single-
family lots, one storm drainage/open space tract, one tree/open space
tract, one wetland/open space tract, one tract for future BLA, and two
private road tracts.
PROJECT NAME: Kirsop Crossing Division 3 Preliminary Plat and Preliminary Planned
Unit Development (TUM-21-1887 and TUM-21-1889)
APPLICANT: Evergreen Heights LLC
1868 State Avenue NE,
Olympia, WA 98506
PROJECT Hatton Godat Pantier
PROPONENT/ Jeff Pantier, PLS
REPRESENTATIVE: 3910 Martin Way East Suite B,
Olympia, WA 98506
PUBLIC HEARING: Hearing Examiner Andrew Reeves with Sound Law Center convened
the public hearing at 7:00 p.m. to consider the Applicant’s request for
preliminary plat and planned unit development approvals to subdivide
10.43 acres into 41 single-family lots, one storm drainage/open space
tract, one tree/open space tract, one wetland/open space tract, one tract
for future BLA, and two private road tracts for property located at
6139 Kirsop Road SW, Tumwater, WA 98512.
Examiner Reeves reported the purpose of the hearing is to collect
evidence in the form of exhibits and testimony to determine whether
the proposal complies with the City’s Comprehensive Plan, zoning
ordinances, Critical Areas Ordinances, and the specific requirements
for approval of a planned unit development and preliminary plat under
Tumwater Municipal Code (TMC).
Examiner Reeves reported that prior to the public hearing he received
and reviewed the following 15 exhibits:
1. Staff Report
2. Plat Map
3. Vicinity Map
4. MDNS w/attachments
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 2
5. Public Hearing Notice
6. Applications & Narrative
7. Notice of Application Exhibit
8. Zoning Map Exhibit
9. Public Notice Certification
10. Notice of Application Comments
11. Concurrency Ruling
12. SEPA Comments
13. Forestry Plan
14. Critical Areas Report
15. Gopher Report
Examiner Reeves admitted the following exhibits into the record
during the public hearing:
16. Preliminary Civil Plans (9 Sheets), dated November 2021 17
17. City of Tumwater Water and Sewer Availability Letter, dated
December 10, 2021
18. Preliminary Drainage Report, Jared Crews, EIT, dated
November 15, 2021
19. Winter Groundwater Monitoring Report, Insight Geologic,
Inc., dated April 5, 2021
20. Supplemental Soil Evaluation Report, Insight Geologic, Inc.,
dated October 7, 2020 21
21. Thurston County Hearing Examiner Decision (No. PLAT/PUD
2003103430), dated April 13, 2005
22. Kirsop Crossing Final Plat Map (4 Sheets), recorded July 27,
2018
23. Correction to Staff Report Memorandum, dated June 10, 2022
Examiner Reeves reported all testimony will be under oath or
affirmation because should the decision should be appealed, the audio
recording of the hearing, admitted exhibits, and the decision would
serve as the foundation for an appeal. The order of testimony begins
with the City of Tumwater providing an overview of the proposal and
any recommendations, testimony by the Applicant to present any
additional information, testimony from the public, and closing
arguments by the City of Tumwater and the Applicant.
CITY TESTIMONY: Examiner Reeves administered the oath to Tumwater Permit Manager
Tami Merriman.
Manager Merriman reported the Applicant is requesting preliminary
plat and planned unit development approvals to subdivide 10.43 acres
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 3
into 41 single-family lots, one storm drainage/open space tract, one
tree/open space tract, one wetland/open space tract, one tract for future
BLA, and two private road tracts. The property is located at 6139
Kirsop Road SW, Tumwater, WA 98512, Section 05, Township 17N,
Range 2W, Parcel # 79900002400. The property is zoned Single
Family Low Density Residential.
Public notice for the application reflecting that the application was
submitted and deemed complete was mailed to property owners within
300 feet of the subject property, affected agencies, posted on-site, and
published in The Olympian newspaper on January 3, 2022. The City
of Tumwater Community Development Department reviewed a SEPA
Environmental Checklist and other information submitted by the
applicant and issued a Mitigated Determination of Non-significance
(MDNS) on February 18, 2022. The SEPA MDNS was mailed to
property owners within 300 feet of the site, affected agencies, post on-
site, and published in The Olympian newspaper on February 18, 2022.
Public notification of the Hearing Examiner public hearing was mailed
to property owners located within 300 feet of the subject property and
various agencies, posted on-site, and published in The Olympian
newspaper on May 27, 2022, in conformance with Tumwater
Municipal Code (TMC) 14.06.
The site is relatively flat, and mostly pasture with some trees. A
wetland is located in the northwest corner. An existing manufactured
home and miscellaneous outbuildings are located on the property and
will be demolished to construct a single-family residential subdivision.
The site is surrounded by residentially zoned property. The properties
to the north and northeast are zoned Residential/Sensitive Resource.
The parcel to the south is zoned Multi-Family Medium Density
Residential and was developed as Kirsop Crossing Div I. The parcels
to the west are zoned Single Family Low Density. The area is
developed with older residential uses. A large wetland complex exists
to the northeast, as well as to the southeast of the site.
Improvements will include grading for public roads and lot pads,
construction of approximately 540 lineal feet of frontage
improvements on Kirsop Road SW and Kirsop Extension Road, and at
the intersection of Kirsop Road SW & Kirsop Extension Road SW.
Other improvements include the extension of City water and sewer
utilities to serve the project, storm water systems to treat and
detain/retain storm water generated from new pollution generating
impervious surfaces, street lighting, and extension of private utilities.
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 4
Manager Merriman noted that the Staff Report incorrectly references
Patio Drive rather than Patio Street, which is a public street and not a
private street as depicted in the Staff Report on page 2. The proposal
includes the continuation of Lanai Street SW through the subdivision
to Kirsop Road SW, as well as a public street connection to Patio
Street to the south.
Water and sewer will be provided by the City of Tumwater, electricity,
and natural gas by Puget Sound Energy, telephone and cable by
Comcast and CenturyLink, and garbage collection by Pacific Disposal.
All utilities on the site will be underground pursuant to Tumwater
Municipal Code (TMC) 17.12.200.
The Application was reviewed against plans within the City. Staff
found that the project is consistent with the following plans, which is
documented within the Staff Report:
• Tumwater Comprehensive Plan
• Parks and Recreation Plan
• Tumwater Transportation Plan
• Thurston Regional Trail Plan
• Sustainable Development Plan for the Thurston Region
The findings are documented within the Staff Report.
Title 14 of the Washington State Growth Management Act (GMA)
requires public notice. As noted earlier, the Notice of Application was
issued and the City received comments from several individuals and a
local tribe. The Squaxin Island Tribe requested a Cultural Resource
Survey, which was completed. Several property owners provided
comments reflecting concerns about increased traffic, vehicle speed,
existing conditions on Kirsop Road, as well as increased development
in the area of existing farms near environmental areas. The Staff
Report includes findings addressing all those concerns. The project
was reviewed by the City’s Transportation Manager, who issued a
concurrency determination. The applicant is required to provide
frontage improvements and off-site improvements to include
improving the intersection of Kirsop Road and Kirsop Extension Road.
Additionally, the Applicant must include internal connections to other
streets and mitigate for vehicle trips that are disbursed to the Tumwater
Boulevard interchange.
One of the concerns addressed the poor condition of Kirsop Road.
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 5
When the property was annexed to the City, Kirsop Road was in poor
condition. The City is responsible for the maintenance of Kirsop Road
and not the Applicant. Another concern centered on additional traffic
generating more vehicles speeding on roads. Unfortunately, the
situation is prevalent in many rural areas when development occurs.
Residents observing speeding vehicles beyond the posted speed limit
should contact the Tumwater Police Department.
Several other comments addressed whether the existing road could
carry heavy equipment and construction vehicles. The City exempts
construction vehicles at the time of construction. Staff proposes
including a condition requiring construction equipment and heavy
equipment to use 70th Avenue from the south to access the subject
property.
Other comments speak to the surrounding rural area home to various
wildlife species. One of the tenants of the GMA is to require specific
densities within the City, which protects lands outside the City for
agriculture and preservation of rural lands. As the property is located
within City limits requiring development at urban densities, some
property surrounding the subject property is considered rural sensitive
area with wetlands that serve to protect against heavy development in
the surrounding area.
Additional comments spoke to the importance of protecting trees on
the subject property as much as possible. The Applicant provided a
Tree Forestry Plan. Because of construction requirements for
infrastructure, the developer was able to retain trees in the area around
the wetland totaling approximately 35 trees. However, retention of the
trees by the developer did not meet the City’s minimum retention of 12
trees per acre. The City requires mitigation for tree replacement at a
ratio of 3:1 comprised of 270 new trees planted on the site. The
existing trees will provide habitat for birds and other wildlife. A
neighboring property owner also requested play areas for children.
The application provides for a tot lot and play area on Tract C, which
meets both the neighbor’s request and the City’s minimum
requirement for open space. Another concern by neighbors was an
existing wetland and whether the City reviewed the wetland to ensure
it would not flood onto the site. The Wetland Report is detailed and
speaks to the functions of the wetland. The wetland is fed by a stream
located further north. The proposed development is located outside of
the wetland system and outside of any riparian buffers. The likelihood
of flooding is negligible possible as prior flooding occurring in the
area was located to the east in lower lying areas.
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 6
The City issued a MDNS in February 2022 to include a Transportation
Concurrency ruling by the City’s Transportation Manager. The ruling
indicated the Applicant meets concurrency by completing frontage
improvements, off-site improvements at the intersection, connections
to the adjoining subdivision, and mitigation for trips to Tumwater
Boulevard. No appeals were filed for the MDNS; however, the City
received some comments. The Olympic Region Clean Air Authority
requires an asbestos survey for demolition of existing structures, which
is included as a Condition of Approval. The Squaxin Island Tribe
requested a Cultural Resource Survey. The survey has been
completed. The Department of Ecology provided comments on solid
waste, toxic clean up, and requirements for a construction stormwater
permit. Another citizen was concerned about the existing condition of
Kirsop Road and heavy equipment traffic, and assurance that the sewer
line would be extended. Staff provided information to the citizen. As
noted earlier, the condition of Kirsop Road is the City’s responsibility
and heavy equipment traffic is requested to access the development
site through 70th Avenue during construction. The sewer line will be
extended.
The environmental review included tree protection requirements in
Title 16 of the Tumwater Municipal Code. The Applicant is required
to retain trees. The Applicant is able to retain 35 trees of the 157
required trees. The Applicant is mitigating the difference by
replanting trees at a 3:1 ratio resulting in 270 new trees planted on the
site. The Wetlands critical Areas Report confirmed a wetland on the
site as a Category IV wetland, which requires a 150-foot buffer. The
Applicant has satisfied the requirement by providing a much greater
buffer. The Applicant provided a pocket gopher study concluding no
gopher mounds were observed on the property. The Culture Resource
Study recommends compliance with a Standard Inadvertent Discovery
Plan which is also required by the City. The Department of
Archeology & Historic Preservation concurred with the City’s
recommendation.
The property is zoned Single Family Residential Low Density
allowing a density of four dwelling units per acre and a maximum of
six dwelling units per acre. The Single Family Residential Low
Density zone allows up to seven dwelling units; however, any density
over six dwelling units requires a transfer of development rights. The
Applicant has not requested an increase in density and the subdivision
as proposed meets the density requirement of six dwelling units per
acre.
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 7
The zoning district requires a minimum lot size of 3,200 square feet
and a minimum lot width of 50 feet, except for alley load lots requiring
a minimum of 40 feet. Lots adjacent to the wetland or wetland buffer
are encouraged to be as large as possible. The maximum building
height is 35 feet. Front yard setbacks are 10 feet and side setbacks are
5 feet with the rear yard setback of 20 feet. The minimum open space
requirement is 10% of the total land area. The plat meets the
requirements through a request for a planned unit development (PUD)
zoning overlay. The PUD overlay is to encourage development by
enabling flexibility in zoning requirements. The Applicant submitted a
PUD Application to seek relief from the minimum lot widths and to
enable private streets within the single family zoning district. Nine of
the 41 lots are less than the minimum required 50 feet when not
adjacent to an alley. The plat includes two private streets.
Staff recommends approval of the PUD. The preliminary plat with
conditions conform with the subdivision regulations, the
Comprehensive Plan and zoning ordinance, wetland ordinance,
planning and development standards of the City. Adequate provisions
have been included for public health, safety, and general welfare.
Staff recommends approval of the Preliminary Plat and Planned Unit
Development with 37 conditions.
Manager Merriman reported the list of conditions include a
requirement for grading, water, sewer, fire coverage, storm, streets,
and other development requirements. The conditions include specific
requirements for heavy equipment to use 70th Avenue for access to the
property during construction, it includes specific requirements to work
with ORCA to obtain the asbestos permit and City demolition permit,
requires well and septic abandonment pursuant to state and county
regulations, and includes specific tree requirements. She noted one
proposed correction to Condition 10 and a clarification to two other
conditions. The reference in Condition 10 of “Kirsop Road” should be
changed to reflect “Lanai Street.” Within Condition 34, information
on the maximum lot coverage for impervious surface of 60% should be
amended to reflect that with the PUD an increase in lot coverage up to
25% is allowed.
Examiner Reeves asked whether that correction is reflective of lot
coverage that could increase to 85%. Manager Merriman advised that
the maximum lot coverage would be 75% but she would need to
review the code to confirm the total coverage. Examiner Reeves
suggested the Applicant could provide additional clarification.
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 8
Manager Merriman cited a change to Condition 38 reflecting that the
Citywide Design Guidelines allow garages to occupy up to 65% of the
façade as opposed to 50% as stated in the condition.
Examiner Reeves said the Staff Report specifies a tract for future
BLA. He asked whether the acronym refers to a boundary line
adjustment. Manager Merriman responded that she assumed there was
a discrepancy between owner fence lines and actual property
boundaries. Including a notation for a future BLA would address that
issue.
Examiner Reeves asked whether the Comprehensive Plan or the
Zoning Code have been amended in any way since the application was
deemed complete that would impact the proposal. Manager Merriman
said no changes have occurred that would affect the proposal.
APPLICANT Examiner Reeves administered the oath to Chris Carlson representing
TESTIMONY: Hatton Godat Pantier.
Mr. Carlson introduced Jeff Pantier, a professional land surveyor and
the Applicant, Rob Rice with Rob Rice Homes.
Mr. Carlson thanked Manager Merriman for the thorough staff report.
With respect to Condition 34, the PUD code allows a 25% increase in
lot coverage, which equates to 25% of 60% or 15% additional
coverage for maximum lot coverage of 75%. Examiner Reeves
thanked Mr. Carlson for the clarification.
Mr. Carlson noted that in Condition 39 for impact fees, the Applicant
requests an amendment to the condition acknowledging that there are
two existing residences on the site (mobile homes) and the City’s
Impact Fee Ordinance allows for a credit of impact fees for those
existing uses. Essentially, the condition should specify a credit for two
traffic impact fees, two park impact fees, and two school district
impact fees.
Examiner Reeves administered the oath to Jeff Pantier.
Mr. Pantier addressed the question surrounding the notation of “BLA.”
The proposed plat design represents a culmination of up to five
different concepts that have been in review with the City resulting in
the proposed design including the configuration of the four-way
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 9
intersection. Both the City and the Applicant expended much work on
the process. Rob Rice is the developer of the project. Mr. Rice is also
the builder/developer for an adjacent project located to the south of the
property. Essentially, the proposal is a continuation of a development
currently constructing homes. In terms of compatibility, both
developments are essentially the same.
In terms of potential flooding, the lots are all elevated. The lowest lot
in the development is elevated seven feet above the wetland. The
wetland elevation of 160 feet is lower than the pad elevation of 167 for
the lowest lot in the subdivision.
The tract on the north side of an existing fence reflects an
encroachment of an old fence. The Applicant is not debating the
placement of the fence and the intent is to create a tract through the
final plat process to avoid a boundary line adjustment and another land
use process. The tract will be part of the final plat document, which
could be conveyed by a deed to the adjacent property owner to
maintain harmony within the neighborhood. The area is located north
of lots 31 and 32. The proposal would create Tract D to address
encroachment by the fence and simplify the transfer of ownership of
that strip of land. The practice has been initiated several other times
on other plats.
Examiner Reeves said he understands the idea and because it is a
separate tract identified on the plat, the impacts have been addressed.
Mr. Carlson offered several exhibits for the record. The exhibits were
included within the application submitted to the City. The first
proposed exhibit is a nine-page Preliminary Civil Engineering Plan Set
completed for the project. Additionally, as previously mentioned, the
Squaxin Island Tribe requested a cultural resource assessment for the
project. Mr. Carlson requested inclusion of the report into the record.
Examiner Reeves admitted the nine-page Preliminary Civil
Engineering Plan Set as Exhibit 16 and the Cultural Resource
Assessment as Exhibit 17.
Manager Merriman advised that the City has been instructed by DAHP
and the Squaxin Island Tribe that the Cultural Resource Survey is not
open to public records and should not be part of the public record. The
survey was previously attached to the SEPA Checklist on the SEPA
Register and the City was asked to remove the survey. Essentially, to
follow the codes and RCWs regarding the cultural study, the City
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 10
requested DAHP or the Squaxin Island Tribe affirm through a written
confirmation that the survey sufficed. The letter attached as an exhibit
from the Department of Archaeology & Historic Preservation affirms
the department’s concurrence of the Cultural Resources Study and that
the recommendation to complete an Inadvertent Discovery Plan was
adequate.
Examiner Reeves said he does not believe the report would need to be
admitted as part of the record. The information in terms of exposure
of the information to public records is new to the extent that he has
observed that during the last several years, the request for a survey has
been applied to most projects throughout western Washington.
Mr. Carlson noted that the report indicated no cultural resources were
discovered. He agreed to withdraw the request to include the report as
an exhibit. Mr. Pantier supported the withdrawal as well. Examiner
Reeves noted that his decision would refer to the completion of the
survey and that DAHP affirmed the survey was completed.
Examiner Reeves asked the Applicant about other exhibits to admit.
Mr. Carlson requested admittance of the Water and Sewer Availability
Letter issued by the City’s Public Works Department attesting to the
ability and willingness to serve the plat with potable water and sewer
service for the proposed 41 lots. Examiner Reeves admitted the letter
as Exhibit 17.
Mr. Carlson advised of several more exhibits. One exhibit was
included within the application materials submitted to the City;
however, the Applicant requests adding the exhibit to the record
because of the number of comments from the community surrounding
flooding and stormwater. The Applicant prepared a Preliminary
Drainage Report for the project. The report includes the geotechnical
report prepared to inform the preliminary design of the storm drainage
system. Examiner Reeves entered the Preliminary Drainage Report as
Exhibit 18.
Mr. Carlson reported the geotechnician who prepared the geotechnical
report within the Preliminary Drainage Report also prepared a Winter
Groundwater Monitoring Report. The City’s Drainage Manual
requires winter stormwater studies. He asked for admittance of the
Winter Groundwater Monitoring Report into the record. Examiner
Reeves assigned the report as Exhibit 19.
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 11
The geotechnician also completed a Supplemental Soil Evaluation
Report. The original report included within the Preliminary Drainage
Report included only three tests pits; however, the geotechnician dug
an additional 12 testing pits with five located in the area of the tract for
the storm drainage facility. Examiner Reeves admitted the report as
Exhibit 20.
Mr. Carlson cited several comment letters that spoke to the condition
of Kirsop Road and the lack of sidewalks. The Applicant is requesting
submittal of information related to the Kirsop Crossing Plat, which
was approved prior to the area being annexed to the City. To meet the
requirements of safe walking to schools, the Thurston County Hearing
Examiner included a finding and condition for the Kirsop Crossing
Plat project to include the addition of a school bus waiting area off
Kirsop Road adjacent to the subject project at the request of the
Tumwater School District. Mr. Carlson requested admission of the
Thurston County Hearing Examiner’s decision to include the condition
to reflect that the condition for safe walking to schools has been
satisfied. The proposed project is directly connected via sidewalk,
Patio Street, and Kirsop Road, which satisfies the safe walking to
schools condition with the connection of sidewalks to the bus waiting
area located to the south. Examiner Reeves admitted the Hearing
Examiner decision as Exhibit 21.
Mr. Carlson reported the final exhibit for admittance is the recorded
plat for Kirsop Crossing (project located to the south) reflecting the
location of the bus waiting area. Examiner Reeves admitted the
information as Exhibit 22.
In response to the request to include the credit of two residences for
impact fees, Manager Merriman affirmed the City’s fee ordinance
includes provisions for credit for existing structures. The Applicant
will receive credit for the existing two residential units.
Examiner Reeves recommended producing another exhibit (23) to
ensure the recording of changes and clarifications requested by
Manager Merriman. Mr. Pantier asked Manager Merriman to revise
the condition for review by Mr. Carlson for review prior to forwarding
the information to Examiner Reeves.
PUBLIC Examiner Reeves administered the oath to Jessie Solomon.
TESTIMONY:
Jesse Solomon reported he is working with Examiner Reeves to serve
as a future hearing examiner.
TUMWATER HEARING EXAMINER PUBLIC HEARING
MINUTES OF VIRTUAL MEETING
June 8, 2022 Page 12
Mr. Solomon noted that Tract D on the plat map reflects the fence line
located within the Applicant’s property. He asked whether that
interpretation of the location of the fence was accurate. Mr. Pantier
affirmed the fence is located within the Applicant’s property. Mr.
Solomon asked about the owner of the fence and the responsible party
for constructing the fence. Mr. Pantier said the intent and what was
attested during testimony was that the Applicant plans to concede the
fence to the adjacent property owner.
Examiner Reeves summarized the plan for clarifying the conditions
and the additional exhibits (16-22) to include in the record to be
provided by the Applicant to City staff and changes to the conditions
as Exhibit 23. Based on testimony and the staff report by the City
staff, he does not envision any issue for rendering a decision approving
the proposal with recommended conditions.
ADJOURNMENT: With there being no further business, Examiner Reeves adjourned
the public hearing at 7:54 p.m.
Prepared by Valerie L. Gow, President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
HEARING EXAMINER
MEETING AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Sunset Room, 555
Israel Rd. SW, Tumwater, WA 98501
Wednesday, June 08, 2022
7:00 PM
The Tumwater Hearing Examiner is an appointed official of the City, and rules upon land use and zoning
matters. Within 10 business days of the conclusion of the hearing, the Examiner shall render a decision,
including findings and conclusions. Questions on the operation and procedures of the Hearing Examiner
may be directed to the Community Development Department at 360-754-4180.
1. Call to Order
2. Public Hearing
a. Kirsop Crossing Division 3 Preliminary Plat and Preliminary Planned Unit Development (TUM-
21-1887 and TUM-21-1889)
3. Adjourn
Remote Meeting Information
The public hearing will be held both virtually via Zoom and in person at Tumwater City Hall.
Attend in Person
Tumwater City Hall, Sunset Room, 555 Israel Rd. SW, Tumwater, WA 98501.
Watch Online
Go to http://www.zoom.us/join, and enter the Webinar ID: 885 9076 5178 Passcode 799517
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID: 885 9076 5178 Passcode 799517
The City of Tumwater Hearing Examiner will hear testimony from interested parties via computer audio
or by telephone by registering in advance to provide comment.
Public Comment – Register in advance for this webinar:
https://us02web.zoom.us/webinar/register/WN_HYeJc4qHScuxg6leV_suDw
After registering, you will receive a confirmation email containing information about joining the webinar.
Written comments may be submitted to City of Tumwater, Community Development Department, 555
Israel Road SW, Tumwater, WA 98501, or by email at tmerriman@ci.tumwater.wa.us or by fax at (360)
754-4138, and must be received by 6:00 p.m. on June 8, 2022.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.