Public Works Committee
Regular MeetingTumwater, WA · July 21, 2022
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
July 21, 2022 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmembers Michael Althauser and
Charlie Schneider.
Staff: Transportation and Engineering Director Brandon Hicks,
Engineering Services Manager Bill Lindauer, Department Assistant
II Mallory Coleman, Community Engagement Specialist Marnie
McGrath and Administrative Assistant Cathy Nielsen.
INTERSTATE 5/ TROSPER Manager Lindauer briefed members on proposal to accept completion
ROAD/ CAPITOL of work on the Interstate 5/Trosper Road/Capitol Boulevard
BOULEVARD Reconfiguration Demolition project. The demolition project was a
RECONFIGURATION – component of the larger project and administered separately to
BUILDING DEMOLITION; prepare for the future roundabout project.
ACCEPTANCE OF WORK:
Manager Lindauer displayed a vicinity map depicting the two project
locations. The contract covered buildings located at 5301 Capitol
Boulevard and 348 Lee Street. A major scope of the project was
completion of the hazardous material assessment. Some abatement
was necessary as part of the project. A consultant completed the
abatement work. Staff developed the construction documents, plans,
specifications, and estimate. The project demolished three existing
structures in preparation for the roundabout project. The first
building impacted the new roundabout at Trosper Road and Capitol
Boulevard intersection. Removal of the building was necessary to
add a new sidewalk and roadway. The second site was purchased by
the City to accommodate new construction of a new 6th Avenue
roadway.
Manager Lindauer shared photographs of various stages of the
demolition of the buildings. The site on Lee Street included two 2-
story buildings with a carport between the buildings. The hazardous
material assessment identified the presence of asbestos and other
hazardous materials, which required abatement prior to demolition of
the building. Demolition of the site was quick and easy.
Manager Lindauer reported the project was designed, managed, and
inspected by Transportation and Engineering staff and funded
through the Transportation Capital Facilities Plan. The City
contracted with Skycorp, LTD for $191,600. The final contract
payment was $175,240.52. The reduced cost was due to less material
handling than forecasted for the project.
Councilmember Schneider inquired about the outcome of the plan to
salvage some materials from the building located on Capitol
Boulevard. Manager Lindauer reported the staff worked with other
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
July 21, 2022 Page 2
City departments to salvage furnishings and other items within the
building. The contractor was able to salvage and recycle building
materials to the extent possible.
Chair Swarthout reviewed the proposed action requested by staff.
CONSENSUS: The Public Works Committee unanimously recommended the
City Council accept the Interstate 5/Trosper Road/Capitol
Reconfiguration – Building Demolition project as complete and
authorize the release of the performance bond as soon as the laws
of the state of Washington allow.
INTERSTATE 5/ TROSPER Manager Lindauer reported the agreement with the Washington State
ROAD/CAPITOL/ Department of Transportation (WSDOT) is an intra-agency
BOULEVARD agreement outlining requirements by WSDOT for completion of
RECONFIGURATION; work on the Interstate 5/Trosper Road/Capitol Boulevard
WASHINGTON STATE Reconfiguration project. The agreement applies only to work
DEPARTMENT OF completed within the WSDOT right-of-way. The agreement provides
TRANSPORTATION permission from WSDOT for the construction of the improvements
(WSDOT) within properties controlled by WSDOT. The agreement includes
CONSTRUCTION general construction administration requirements, a section on project
AGREEMENT: special provisions exclusive to the project, and a mechanism of
payment for any WSDOT inspectors who might be required to
inspect work or materials. Compensation is based on time and
materials.
Manager Lindauer shared photographs of and described the affected
project sites covered by the agreement.
Councilmember Althauser asked about the status of the overall
project timeline and when the public can anticipate some traffic
disruption in and around the project site. Manager Lindauer
explained that staff is preparing to release bids with one component
of the project under coordination with WSDOT. Following
completion of the item with WSDOT, the City will release bids. The
bidding process involves a one-month period. The current schedule
calls for construction operations to begin in mid-September and
continue for the next 18 months. Initial work this year and early next
year is utility work that will disrupt traffic significantly as the work is
performed below ground. As the project progresses, sidewalk, curb,
and paving will follow next summer through the end of the year.
Councilmember Althauser recommended the committee receive
periodic updates on the status of construction progress because the
project is complex, challenging, and a major improvement of interest
to the public. The Council is often asked about the status of
construction projects occurring in the City. Utilizing the committee’s
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
July 21, 2022 Page 3
meetings serves as an effective conduit to provide periodic updates
on the status of the project.
Chair Swarthout reviewed the proposed action for consideration by
the committee.
MOTION: Chair Swarthout moved, seconded by Councilmember Althauser,
to recommend the City Council approve and authorize the
Mayor to sign the WSDOT Construction Agreement, in
substantially similar form as approved by the City Attorney, to
complete transportation improvements within WSDOT right-of-
way as part of the Interstate 5/Trosper Road/Capitol Boulevard
Reconfiguration Project. A voice vote unanimously approved the
motion.
OTHER BUSINESS: Chair Swarthout inquired about the status of the street striping
project. Director Hicks advised that staff is currently soliciting bids
for the project. The project is anticipated to start by the end of
August.
ADJOURNMENT: With there being no further business, Chair Swarthout
adjourned the meeting at 8:19 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, July 21, 2022
8:00 AM
1. Call to Order
2. Roll Call
3. Interstate 5 / Trosper Road / Capitol Boulevard Reconfiguration – Building Demolition; Acceptance
of Work (Bill Lindauer)
4. Interstate 5 / Trosper Road / Capitol Boulevard Reconfiguration; Washington State Department of
Transportation (WSDOT) Construction Agreement (Bill Lindauer)
5. Additional Items
6. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/85319710964?pwd=c2RPL2ZHdU1hRDQ0UkpWNTNCTVA0Zz09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 853 1971 0964 and Passcode
124663.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.
Get email alerts for Tumwater
A daily email when new agendas and minutes are posted.