Public Works Committee
Regular MeetingTumwater, WA · March 21, 2024
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
March 21, 2024 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmembers Michael Althauser and Angela
Jefferson.
Staff: City Administrator Lisa Parks, City Attorney Karen Kirkpatrick,
Finance Director Troy Niemeyer, Transportation and Engineering Director
Brandon Hicks, Assistant Transportation and Engineering Director Mary
Heather Ames, Engineering Services Manager Bill Lindauer,
Communications Manager Ann Cook, Construction Engineer Colby Fletcher,
and Administrative Assistant Cathy Nielsen.
APPROVAL OF
MINUTES: PUBLIC
WORKS
COMMITTEE,
FEBRUARY 22, 2024:
MOTION: Councilmember Jefferson moved, seconded by Councilmember
Althauser, to approve the minutes of February 22, 2024, as published. A
voice vote approved the motion unanimously.
INTERSTATE 5 / Manager Lindauer updated members on the status of the Interstate 5/Trosper
TROSPER ROAD / Road/Capitol Boulevard Reconfiguration Project.
CAPITOL
BOULEVARD Manager Lindauer shared an exhibit reflecting the project limits. All
RECONFIGURATION infrastructure (water, sewer, storm, underground utilities and overhead
PROJECT UPDATE: utilities) located within the project area will be restored and all overhead
utilities will be undergrounded within the project limits. The reconstruction
of Lee Street includes a pavement overlay and minor storm drainage
improvements. The project includes a new road from Lee Street to Trosper
Road serving as 6th Avenue. A new roundabout is included on 6th Avenue
serving northbound on and off freeway ramps to include realignment of
existing ramps. On Trosper Road, a new roundabout will be constructed as
well as a roundabout at the Capitol Boulevard and Trosper Road intersection
with full improvements along Trosper Road within the project area. The road
off Trosper Road connecting to Linda Street is a new addition with other
improvements on Linda Street.
Since January 2023, the project has been in construction. All undergrounding
components of the project are completed. Approximately 1,560 feet of new
sanitary sewer was installed along Capitol Boulevard. Approximately 3,250
feet of water lines were replaced along with replacement of the storm drainage
system to incorporate water quality and quantity control for portions of the
project of approximately 4,020 feet. The joint utility trench for conversion of
overhead utility lines to underground (Puget Sound Energy, Comcast, and
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
March 21, 2024 Page 2
other providers) spanned approximately 1,550 feet. Except for final
connections, most utility work has been completed.
The Sixth Avenue connector was completed. The connector road connects
Lee Street to Trosper Road. The 6th Avenue and northbound I-5 ramp
roundabout is substantially completed and fully functional. The Trosper Road
and the 6th Avenue roundabout was completed along with a small component
of the northbound on ramp on the north side of Capitol Boulevard. State
northbound on and off ramps are fully functional. Much work was completed
on Linda Street and the Trosper Road extension with the exception of final
paving to complete those portions of the project. The Lee Street
reconstruction component was completed as well the stormwater pond. In the
last 15 months, the contractor has been busy and completed many of the
project elements required to move the project forward.
Manager Lindauer shared photographs of the project components. One photo
was the new roundabout at Trosper Road and 6th Avenue. The roundabout
was difficult to construct because of changes in grade. The roundabout central
island has been completed along with the sidewalks. Beacons were installed
for pedestrians. The roundabout at 6th Avenue and the I-5 northbound ramps
also encountered changes in grade between the new roundabout and existing
ramps. The change in grade required construction staging with the contractor
applying different solutions to solve the problem. Subsequently, the
roundabout was constructed in two segments to resolve the grade issue.
Councilmember Althauser noted that the grade of the roundabout for the I-5
northbound ramps appear to enable driving onto the roundabout. He asked
whether that feature was selected to enable access by emergency vehicles as
other roundabouts lack the same feature. Manager Lindauer explained that the
roundabout includes a larger truck apron. Typically, cars do not drive on the
asphalt truck apron because it is designed to accommodate trucks exiting or
entering the freeway.
Manager Lindauer reported the northbound on and off ramps were closed for
10 days to accommodate removal of the existing ramps in order to grade and
build the new ramps. It speaks to the example of the benefits of a road closure
to achieve cost and time savings. The inconvenience to the public was reduced
to a specific timeframe.
Manager Lindauer shared a photo of the new stormwater pond for City right-
of-way. The pond is secured along the perimeter by a black chain link fence
with an access road to the pond for maintenance.
The Capitol Boulevard/Trosper Road roundabout is the next project to
complete. The contractor is forecasting a May/June completion date. Work
on the project has been initiated with the most complicated component,
construction of the central island, requiring some existing lane shifts to keep
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
March 21, 2024 Page 3
traffic moving through the area during construction. Approximately 90% of
the concrete work has been completed. Other pending components include
clean-up work and final work on Linda Street frontage and the Trosper Road
extension. Final asphalt paving operations along Trosper Road and Capitol
Boulevard are scheduled during the night to reduce traffic impacts over the
next several months. The final project work includes clean-up, illumination,
and landscaping. Approximately 80% of the project has been completed.
When the project was initiated in January 2023, staff anticipated completing
the project by mid-2024. Currently, the project is on schedule for completion
with substantial completion estimated in July 2024. All physical completion
of the project is projected by September 2024 followed by closeout of the
project by the end of the year.
The project bid was $12,150,150.00 with current cost estimates 6% over the
bid. Projections occurred during the course of the project to account for unit
bid pricing for overages and underages on each item. Staff evaluates costs
monthly. The 6% overage is a combination of unforeseen conditions
discovered during construction, required design changes, and other choices of
adding or adjusting specific components of the project that benefitted the City.
The projected construction is projected to be 13% to 18% over the bid at the
time of project completion.
Councilmember Althauser asked whether the City includes a contingency in
the project budget to account for any additional costs. Manager Lindauer said
the average contingency is 10% or below. If the amount is over 10%, the
Council is required to approve the overage.
Director Hicks acknowledged employees who played critical roles in the
project by both Manager Lindauer’s team and Manager Cook’s team. The
project entailed a joint effort because the City has never encountered so much
public outreach and engagement for a project. Without the assistance of
Manager Ann Cook and Specialist Marnie McGrath, it would not have been
possible for the department’s team to contact all local businesses and others
located within the project area. David Mills serving as the primary inspector
for the project has been with the City for many years and is an important link
between the City and the contractor. Colby Fletcher, a new employee,
transformed the department’s capital construction program and contributed
much experience from his prior employment with the Washington State
Department of Transportation. He was promoted to Construction Engineer
and will serve as the primary lead for all City infrastructure projects moving
forward. Credits are deserving to both Manager Lindauer’s team and Manager
Cook’s team.
Manager Lindauer said the project progressed smoothly because of the
combined efforts of the teams to include the construction team.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
March 21, 2024 Page 4
The committee acknowledged and thanked staff for their efforts on the project
to reduce impacts to local businesses and people traveling through the City.
Councilmember Jefferson suggested considering official recognition of both
demonstrated leadership and teamwork as the efforts serve as an example of
excellence.
City Administrator Parks echoed similar recognition of the teams and said
staff plans to consider a way to celebrate the teams’ excellence.
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 8:28 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
MEETING AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, March 21, 2024
8:00 AM
1. Call to Order
2. Roll Call
3. Approval of Minutes: Public Works Committee, February 22, 2024
4. Interstate 5 / Trosper Road / Capitol Boulevard Reconfiguration Project Update (Bill Lindauer)
5. Additional Items
6. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/84479673214?pwd=QnVzK1dmZTNna2g3Q09YcjR3WHgzZz09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 844 7967 3214 and Passcode
048480.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.