Public Works Committee
Regular MeetingTumwater, WA · November 7, 2024
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
NOVEMBER 7, 2024 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmember Michael Althauser.
Excused: Councilmember Angela Jefferson.
Staff: City Administrator Lisa Parks, Assistant City Attorney David
Abbott, Finance Director Troy Niemeyer, Transportation & Engineering
Director Brandon Hicks, Water Resources and Sustainability Director
Dan Smith, Engineering Services Manager Bill Lindauer, Capital Projects
Manager Don Carney, Water Resources Program Manager Patrick
Soderberg, Construction Engineer Colby Fletcher, Community
Engagement Specialist Marnie McGrath, and Administrative Assistants
Bonnie Hale and Kelly Quiroz.
Others: Meredith Greer, Greer Environmental Consulting.
APPROVAL OF
MINUTES: PUBLIC
WORKS
COMMITTEE -
OCTOBER 3, 2024 &
OCTOBER 17, 2024:
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
approve the minutes of October 3, 2024 and October 17, 2024 as
published. A voice vote approved the motion.
INTERAGENCY Director Smith reported the project provides balance to the electric grid.
AGREEMENT WITH The system battery stores solar power for use when needed, reduces
WASHINGTON electricity bills and emissions, and provides resiliency during power
DEPARTMENT OF outages. The project supports the City’s Strategic Priorities and Goals for
COMMERCE FOR 2023-2024 to continue to update and advance priorities within the Climate
TUMWATER FIRE Action Plan and the Thurston Climate Mitigation Plan.
STATIONS
SOLAR + STORAGE Existing solar power installed on City facilities provide less than 7% of
FEASIBILITY: total operating electric needs. Staff continues to add to the system. One
planned project is the City Hall and Library solar power project to add
power and backup to provide energy during power outages and to
accommodate needs during power fluctuations. Staff is seeking sources
of grant funding for the entire project cost of $14 million. Today, the
City’s backup power is supplied by a generator providing approximately
20 hours of backup power.
The Library serves as the City’s only heating and cooling shelter with no
current backup power at that location. The project provides additional
resiliency power of 22 hours at a capital cost of $1.4 million. As the
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
NOVEMBER 7, 2024 Page 2
project is a higher priority than City Hall’s project, staff continues to seek
grants to initiate project construction. The project would provide a 69%
reduction in emissions.
The projects would cover energy demands during the summer reducing
the City’s electricity bills. Grant funding would likely cover 70% of both
project costs. With the new direct pay program implemented, 30% of the
cost would be provided through the IRA Direct Pay Program.
The proposed solar–storage feasibility is partially funded by $50,000 with
no City match requirements through Washington’s Climate Commitment
Act. Both City fire stations would be included in the solar project. Staff
is working with Olympia Community Solar. The request is a
recommendation to the City Council to approve the Department of
Commerce Agreement for the grants. Staff requests the committee place
the Interagency Agreement with Washington Department of Commerce
for Tumwater Fire Stations Solar and Storage Feasibility on the
November 19, 2024, City Council Consent Calendar with a
recommendation to approve and authorize the Mayor to sign.
Chair Swarthout noted that in addition to the project, the City’s
electrification of its fleet is projected to reduce gasoline consumption by
more than 70% by 2030.
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
place the Interagency Agreement with Washington Department of
Commerce for Tumwater Fire Stations Solar and Storage Feasibility
on the November 19, 2024, City Council Consent Calendar with a
recommendation to approve and authorize the Mayor to sign. A
voice vote approved the motion.
GRANT FROM THE Meridith Greer, Greer Environmental Consulting, presented the proposal.
DEPT OF ECOLOGY Last June, the committee was briefed on a grant agreement update from
FOR THE GOLF the Department of Ecology for the golf course stormwater retrofit project.
COURSE The project has since been implemented with 60% design completed. The
STORMWATER proposed grant agreement and amendment updates some clerical errors by
RETROFIT the Department of Ecology. Changes include the start date for the project
PROJECT backdated to the original date as it had been inadvertently changed during
AMENDMENT 2: the first amendment increasing the timeline of the project. The second
change pertains to the grant system within the Department of Ecology that
caused the cancellation of several amendments. Project scope and costs
remain the same.
Director Smith requested the committee place Amendment 2 of the
Department of Ecology Grant for the Golf Course Stormwater Retrofit
project on the City Council Consent Calendar on November 19, 2024 with
a recommendation to approve and authorize the Mayor to sign.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
NOVEMBER 7, 2024 Page 3
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
place Amendment 2 of the Department of Ecology Grant for the Golf
Course Stormwater Retrofit Project on the City Council Consent
Calendar on November 19, 2024 with a recommendation to approve
and authorize the Mayor to sign. A voice vote approved the motion.
ACCEPTANCE OF Construction Engineer Fletcher said the project consisted of pedestrian
WORK WITH crossings at Barnes Boulevard, Custer Way, and Capitol Boulevard near
SOUND PACIFIC the Kentucky Fried Chicken restaurant and ADA improvements to
CONSTRUCTION sidewalks in residential areas.
FOR THE 2022
PEDESTRIAN The Barnes Boulevard and Ridgeview Loop crosswalk improvements
IMPROVEMENTS were completed at the request of Tumwater School District. The school
PROJECT: district and the City executed an agreement to install the pedestrian
crossing. The pedestrian crossing is solar operated. The second
pedestrian crossing was on Capitol Boulevard. That crossing is a
signalized pedestrian crossing across a multi-lane street. The crossing
was prioritized because of its location. The Custer Way and Capitol
Boulevard pedestrian crossing is a signalized crossing that was included
and removed from a prior project because of the lack of funding.
Sidewalk improvements corrected numerous deficiencies identified by
staff. Many residential streets were included with improvements to
sidewalks, driveway entrances, and ADA accessibility. Photographs of
several of the improvements were shared with the committee.
The project scope spanned 30 working days with construction initiated on
September 6, 2022 with substantial and physical completion issued on
July 10, 2023. The project included electrical components, which delayed
the project because of procurement delays. Funding for the project was
from the Transportation Capital Facilities Plan, Tumwater Transportation
Benefit District, Tumwater School District, and the City of Tumwater.
The contract was awarded to Sound Pacific Construction for $493,337.00
with a final contract total of $497,877.97.
Chair Swarthout asked whether the proposed action releases payment to
the contractor for work completed in 2023. Engineer Fletcher advised
that the contractor has been compensated. The action is final acceptance
of work.
Staff requests the committee recommend the City Council accept the 2022
Pedestrian Improvements project as complete and authorize the release of
the performance bond as soon as the laws of the state of Washington
allow and place it on the November 19, 2024, City Council Consent
Calendar.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
NOVEMBER 7, 2024 Page 4
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
recommend the City Council accept the 2022 Pedestrian
Improvements project as complete and authorize the release of the
performance bond as soon as the laws of the state of Washington
allow and place it on the November 19, 2024, City Council Consent
Calendar. A voice vote approved the motion.
ACCEPTANCE OF Engineer Fletcher displayed a City map depicting the scope of work on
WORK WITH MILES the 2023 Pavement Maintenance project of pavement improvements
RESOURCES FOR throughout the City, replacement of paved markings, crack sealing, plastic
THE 2023 pavement marking replacements, and ADA sidewalk improvements.
PAVEMENT
MAINTENANCE The scope of work was based on site investigations and roadway
PROJECT: pavement ratings. Roadways included arterials, collectors, and residential
streets. The project paved seven new lane miles of asphalt roads,
completed 55,000 square yards of pavement grinding to accommodate
new asphalt, completed 15 tons of roadway crack sealing, completed
4,700 square yards of pavement reinforcement interlays, completed 5,700
yards of pavement and subgrade subbase repair, installed four bio-
infiltration galleries, installed 16,000 new raised pavement markers,
installed 500 square yards of new concrete sidewalk with 17 new ADA
ramps, and completed 137 miles of new pavement lines.
Engineer Fletcher shared construction photographs of the grinding and
inlays and some of the auxiliary components for stormwater management.
The project commenced on June 20, 2023 and was completed on October
12, 2023. Final completion of the project was on March 1, 2024 due to
procurement delays for some electrical components. Funding was
provided by the Tumwater Transportation Benefit District. The
Engineer’s estimate was $3,907,963.96. Miles Resources offered the
lowest bid of $3,857,000.00 with the final contract totaling $4,171,958.00.
Staff identified several roads as part of the project. Based on good
pricing, several change orders added more streets to the contract because
of the availability of funds.
Staff requests the committee recommend the City Council accept the 2023
Pavement Maintenance project as complete and authorize the release of
the performance bond as soon as the laws of the state of Washington
allow and place it on the November 19, 2024, City Council Consent
Calendar.
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
recommend the City Council accept the 2023 Pavement Maintenance
project as complete and authorize the release of the performance
bond as soon as the laws of the state of Washington allow and place it
on the November 19, 2024, City Council Consent Calendar. A voice
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
NOVEMBER 7, 2024 Page 5
vote approved the motion.
AUTHORITY TO Capital Projects Manager Carney reported the project began in November
SOLICIT BIDS AND 2021 with the execution of the service provider agreement with BBS
RECOMMEND Engineering and its subconsultants, Northwest Hydraulic Consultants and
AWARD FOR THE Aqua Terra Cultural Resource Consultants. Project design was completed
PERCIVAL CREEK in June 2024 as a draft and forwarded to the Washington State
FISH BARRIER Department of Transportation for review and response. Staff anticipates
REMOVAL receiving a response by November 24, 2024.
PROJECT:
The project removes and replaces a fish barrier culvert conveying Percival
Creek under Sapp Road. The culvert is an undersized five-foot diameter
concrete culvert to be replaced with a 60 feet long by 19 feet wide by 8.5
feet high box culvert. Other improvements include adding instream large
woody debris and streambed material, roadway reconstruction, and
additional multimodal facilities for the Percival Creek crossing.
Manager Carney shared photographs of the existing culvert, a five-foot
diameter concrete culvert not conducive to fish passage. Stream
improvements include re-grading 140 feet of stream bank, plantings of
willows in the lower area, and shrubs and trees in the upland area. Road
improvements include 11-foot wide lanes with six-foot bike lanes and a
five-foot sidewalk connecting to an existing sidewalk. Because of the
complexity of existing conditions, much of the work includes deep
excavation in a segment of the road that is not wide enough to divert
traffic around the work zone. The project has a narrow construction
timeline because of work windows for fish protection. A full road closure
and detour will be necessary to complete the work expeditiously and for
the safety of construction personnel, City staff, and the traveling public.
The roadway up to the culvert excavation will remain open to local traffic.
Staff plans to notify the public by placing reader boards one week prior to
the project start time to advise the public of the road closure. Following
commencement of the project, construction signs will be installed for the
detour route. Staff will notify schools, fire, and property owners.
The Engineer’s estimate for construction is in the range of $2,000,000 to
$2,500,000. The City received $100,000 for right-of-way acquisition
from PROTECT fund to accommodate the new larger culvert, another $2
million from the PROTECT fund for construction, and a $257,550 grant
from the Washington State Recreation and Conservation Office for
culvert replacement.
Staff is scheduled to release the project bid in November/December 2024
and award the project in January 2025. The contractor will design the box
culvert with reviews of the design by the City and the state. Fabrication
of the new culvert is anticipated to occur in spring 2025. Construction is
anticipated to occur in June/July 2025 and end in September 2025 over a
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
NOVEMBER 7, 2024 Page 6
70-day work window. The road is scheduled to reopen in September
2025.
Staff requests the committee authorize staff to solicit bids for the Percival
Creek Fish Barrier Removal project, recommend City Council award and
authorize the Mayor to sign a Public Works Contract with the lowest
responsible bidder, and recommend City Council authorize the closure
and detour of Sapp Road SW from Crosby Boulevard SW to RW Johnson
Road SW for the duration of the project. The roadway will be open to
local traffic only.
Councilmember Althauser asked whether the road is scheduled for closure
during the 70-day construction period. Manager Carney advised that staff
recommends the closure during the duration of the project.
Councilmember Althauser asked whether any additional Council action is
required prior to the project commencing. Manager Carney advised that
the request is to approve moving forward with the project by authorizing
the release of the bid, awarding the contract, and initiating the project with
a road closure.
Director Hicks added that the committee would be asked to review and
recommend the award of the construction contract to the City Council
prior to commencement of the project.
Councilmember Althauser recommended including the proposed action as
a Council Consideration rather than an item on the Consent Calendar as
the road closure will be disruptive to the public. A discussion by the
Council would help to increase transparency of the project to the public.
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
approve release of bids for the Percival Creek Fish Barrier Removal
project, recommend City Council award and authorize the Mayor to
sign a Public Works Contract with the lowest responsible bidder, and
recommend City Council authorize the closure and detour of Sapp
Road SW from Crosby Blvd SW to RW Johnson Rd SW for the
duration of the project at a future City Council Consideration item.
A voice vote approved the motion.
OLD HWY 99 & 79TH Manager Carney reported the design project converts the intersection at
AVENUE 79th Avenue and Old Highway 99 to a roundabout from a stop-controlled
ROUNDABOUT intersection. The project includes some frontage improvements of curb,
SCHEDULE 74 gutter, road widening, and sidewalks along the properties designated as
UNDERGROUND the City’s future Operations and Maintenance facility and Trails End
CONVERSION Park. The project carries forward the City’s goal of undergrounding all
DESIGN utilities. Schedule 74 for underground conversion is required for the
AGREEMENT WITH project.
PUGET SOUND
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
NOVEMBER 7, 2024 Page 7
ENERGY: The project would underground approximately 3,400 feet of overhead
power lines along City-owned parcels along 79th Avenue, at the
intersection of 79th Avenue SE and Trails End Drive SE, and along
portions of Old Highway 99 within the project limits.
Puget Sound Energy (PSE) will provide the City with a scope of work, a
design for the underground system, construction plans, operating rights,
work schedule, and a construction cost estimate.
The cost of the design is estimated at $140,000 with a split of 60%
($84,000) to PSE and 40% to the City ($56,000). The next phase is the
construction agreement. PSE will provide the design for all underground
facilities, supply conduits, transformers, install electrical systems,
coordinate and complete change orders, complete surge connections,
remove all overhead utilities including poles, and provide project
inspection services. The City’s responsibility is to construct the
improvements and install surface transformers.
Staff requests the committee recommend the City Council approve and
authorize the Mayor to sign the Puget Sound Energy (PSE) Schedule 74
Underground Conversion Design Agreement to design the utility
underground conversion for the Old Highway 99 and 79th Avenue
Roundabout project and place it on the November 19, 2024, City Council
Consent Calendar.
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
recommend the City Council approve and authorize the Mayor to
sign the Puget Sound Energy (PSE) Schedule 74 Underground
Conversion Design Agreement to design the utility underground
conversion for the Old Highway 99 and 79th Avenue Roundabout
project and place it on the November 19, 2024, City Council Consent
Calendar. A voice vote approved the motion.
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 8:50 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
MEETING AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, November 07, 2024
8:00 AM
1. Call to Order
2. Roll Call
3. Approval of Minutes: Public Works Committee - October 3, 2024 & October 17, 2024
4. Interagency Agreement with Washington Department of Commerce for Tumwater Fire Stations
Solar + Storage Feasibility (Water Resources & Sustainability Department)
5. Grant from the Dept of Ecology for the Golf Course Stormwater Retrofit Project Amendment 2
(Water Resources & Sustainability Department)
6. Acceptance of Work with Sound Pacific Construction for the 2022 Pedestrian Improvements
Project (Transportation & Engineering Department)
7. Acceptance of Work with Miles Resources for the 2023 Pavement Maintenance project
(Transportation & Engineering Department)
8. Authority to Solicit Bids and Recommend Award for the Percival Creek Fish Barrier Removal
project (Transportation & Engineering Department)
9. Old Hwy 99 & 79th Ave Roundabout Schedule 74 Underground Conversion Design Agreement with
Puget Sound Energy (Transportation & Engineering Department)
10. Additional Items
11. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/83405340160?pwd=JDqMMaoW6Rwt6r0JE5rax4gzW9e7PD.1
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 834 0534 0160 and Passcode
503889.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4129 or email ADACoordinator@ci.tumwater.wa.us.
Get email alerts for Tumwater
A daily email when new agendas and minutes are posted.