1. The meeting was called to order by Mr. Touchett at 5:07pm.
2. Roll Call: Present: Evan Touchett, Mara Helmke, Rye Kimmett. Also present: Theran Jacobson, Director of Public
Works; Carla Fischer, AECOM.
3. MOVED by Touchett, seconded by Helmke, to approve the minutes of the June 13, 2022, meeting of the Public
Works/Sewer and Water Committee. Motion carried 3-0.
4. DISCUSSION regarding generator at Well 2. No action taken.
Jacobson noted the following: Well 2 has been offline for a scheduled rehabilitation. Well 2 previously had a
direct drive natural gas powered generator which is believed to have been part of the initial construction in
1959. As part of the rehabilitation process the generator was removed and the age of the backup generation
was evident and parts unavailable to reinstall. Communication occurred with the contractors working on the
well rehab and vendors to determine the best course of action for backup power at this site. Quotes were
received and staff recommends the all-inclusive quote from Pieper Power to have all work completed by one
entity in the estimate amount of $139,713
5. DISCUSSION regarding mixer at Country View pumping station. No action taken.
Jacobson noted the following: A mixer at the country view lift station is recommended by City and Madison
Metropolitan Sewerage District (MMSD) staff. MMSD monitors, operates, and maintains the two City owned
sanitary pumping stations. Grease accumulation creates challenges in the wet well during low flow times when
it solidifies which creates a mat on the surface. The grease mat inadvertently creates false alarms and staff
responses. Grease trap efficiency is approximately 85% therefore grease accumulation will always be present
and needs to be managed and the agreed upon approach is the mixer. The quote for the mixer is estimated at
$64,616 but is being verified with revised numbers.
6. DISCUSSION regarding rain barrel rebate. Touchett noted he would like to encourage rain barrel usage and
proposed a rebate of $30 per barrel and kit. Kimmett stated she thinks the rebate should be capped at four per
household. Committee thinks the City should cap all total rebates at $5,000/year. Committee thinks rebate
application should include receipts, photo of rain barrels installed, and should be submitted to the City within
three weeks of installation. City Staff is advised to create a proposed policy for committee review. No action
taken.
7. MOVED by Touchett, seconded by Helmke, to adjourn at 5:35pm. Motion carried 3-0.
Note: These minutes were prepared by Theran Jacobson, Director of Public Works. These minutes are based
on the notes of the recorder and are subject to change at a subsequent meeting.