Public Works, Sewer and Water
Regular MeetingVerona, WI · July 14, 2025
Minutes
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: Monday July 14, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order Meeting called to order by Beth Tucker Long at 5:38 pm
2. Roll Call Beth Tucker Long, Chris Weiss also present Bryan Manning, Public works Director,
Michael Trotter, Assistant Public works Director, Carla Fischer, City Engineer AECOM.
3. Public Comment. None
4 Approval of the Minutes: June 23, 2025. Moved by Beth Tucker Long and seconded by Chris Weiss to
approve the minutes with corrections. Motion passed 2-0
5 Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde Brothers pay
request #10 Moved by Chris Weiss and seconded by Beth Tucker Long to approve project #2022-109
North Booster Station- Rohde Brothers pay request #10 in the contract sum not to exceed $18,000.00
Motion passed 2-0
6 Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde Brothers
change order request #2 Moved by Beth Tucker Long and seconded by Chris Weiss to approve
Project #2022-109 North Booster Station-Rohde Brothers Inc. change order request in the sum not to
exceed 6,414.00 Motion passed 2-0
7 Discussion and Possible Action: Project 2022-110 Well #6 Reconstruction and Liner Installation
Water Well Solutions. Moved by Chris Weiss and Seconded by Beth Tucker Long to approve Water
Well Solutions Project 2022-110 Well #6 Reconstruction and Liner Installation, for Lamna Flo pipe
replacement for a total sum not to exceed $62,304.00 Motion passed 2-0
8 Discussion and Possible Action: Well #6 Electric Pump Motor inspection and rebuild.
Moved by Chris Weiss and Seconded by Beth Tucker Long to approve additional cost to EMS (Electric
Motor Service) to rebuild Well #6 Well Motor for a total sum not to exceed $15,000.00
Motion passed 2-0
9 Discussion and Possible Action: Well #6 Chemical Pumps and Blower Replacement.
Moved by Chris Weiss and Seconded by Beth Tucker Long to approve cost to replace and install new
Pumps and Blower to William Reid for total sum not to exceed $20,055.00 Motion passed 2-0
10 Discussion and Possible Action: Well #6 Con Lyte Nitro Analyzer for Chemical Nitrate Testing
Moved by Beth Tucker Long and Seconded by Chris Weiss to approve purchase of a Con Lyte Nitro
Nitrate Analyzer for Well #6 from Midwest Meter for a total sum not to exceed $11,667.00 Motion
passed 2-0
11 Staff Report:
12 Adjourn Moved by Beth Tucker Long and Seconded by Chris Weiss to adjourn at 6:23 pm
Motion passed 2-0
Beth Tucker Long - Chairperson
POSTED: July10, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
Agenda
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: Monday July 14, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order
2. Roll Call
3. Public Comment.
4. Approval of the Minutes: June 23, 2025.
5. Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde Brothers pay
request #10
6. Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde Brothers
change order request #2
7. Discussion and Possible Action: Project 2022-110 Well #6 Reconstruction and Liner Installation
Water Well Solutions.
8. Discussion and Possible Action: Well #6 Electric Pump Motor inspection and rebuild.
9. Discussion and Possible Action: Well #6 Chemical Pumps and Blower Replacement.
10. Discussion and Possible Action: Well #6 Con Lyte Nitro Analyzer for Chemical Nitrate Testing
11. Staff Report:
12. Adjourn
Beth Tucker Long - Chairperson
POSTED: July10, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: Monday June 23, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order Meeting called to order by Beth Tucker Long at 5:21 pm
2. Roll Call Beth Tucker Long, Chris Weiss
3. Public Comment. None
4. Approval of the Minutes: June 11, 2025. Moved by Chris Weiss and seconded by
Beth Tucker Long to approve the minute. Motion passed 2-0
5. Discussion and Possible Action: Recommend approval of Project 2025-102
Pavement Surface Treatment Fahrner Asphalt. Moved by Chris Weiss and
seconded by Beth Tucker Long to approve Project 2025-102 Asphalt Pavement
Service Treatment to Fahrner Asphalt sealers LLC in the contract sum not to
exceed $106,491.00 Motion passed 2-0
6. Discussion and Possible Action: Recommend approval of Project 2025-110 Well 4
Rehabilitation Water Well Solutions Inc. Moved by Beth Tucker Long and
seconded by Chris Weiss to approve Project 2025-110 Well 4 Rehabilitation
Water Well Solutions Inc in the contract sum not to exceed $160,684.00
Motion passed 2-0
7. Discussion: Project Update 2022-107 Military Ridge State Trail Paving and Bridge
Design.
No Action Taken
8. Staff Report:
9. Adjourn
Beth Tucker Long - Chairperson
POSTED: June 19, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on
or not on the agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410
Investment Court, Verona, WI, 53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting,
please contact the City Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be
made to accommodate your request. Notice is hereby given that a majority of the City Council may be present at the
meeting of the Public Works, Sewer & Water Committee to gather information about a subject over which they have
decision-making responsibility. The City Council and any other standing committees will not take formal action at this
meeting.
Meeting Date: July 14, 2025
PW/S&W Committee Memo
Public Works/Sewer & Water Committee
Listed below is an explanation of the items on the Public Works/Sewer & Water Committee
agenda.
Item (5) Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde
Brothers pay request #10
Pay request for painting per contract.
Recommended Motion: Recommend approval of Project #2022-109 North Booster Station-
Rohde Brothers pay request #10 in the contract sum not to exceed $18,000.00
Item (6) Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde
Change order request #2
This change order incorporates the costs incurred to the Contractor for the work including the air
compressor control panel relocation, tracing of control circuits, cable/wire identification, temp controls
for the air compressor control panel after initial shut down, and removal and reinstallation of the panel.
Also includes new conduit for getting controls to the RTU cabinet.
Recommended Motion: Recommend approval of Project #2022-109 North Booster Station-
Rohde Brothers Inc. change order request in the sum not to exceed $6,414.00
Item (7) Discussion and Possible Action: Project 2022-110 Well #6 Reconstruction and Liner
Installation Water Well Solutions.
Water Well Solutions was hired in Feb. 2025 to reconstruct the well and install a liner for a contract
amount of $378,500.00 Upon inspection, the Lamna Flo pipe was found to be brittle and damaged. It is
used to prevent the well from pumping sand and equalizes the suction column in the well.
Replace 20 Sections $62,304.00
Recommended Motion: Recommend approval to Water Well Solutions Project 2022-110 Well
#6 Reconstruction and Liner Installation, for Lamna Flo pipe replacement for a total sum not to
exceed $62,304.00
Item (8) Discussion and Possible Action: Well #6 Electric Pump Motor inspection and rebuild.
The 300 HP Well Motor was sent in to be inspected and serviced.by Electric Motor Service. The original
estimate to be rebuilt was $10,000.00 Upon inspection they found the bearing housing was cracked.
Additional cost of $5,000 with new housing. $15,000.00
Recommended Motion: Recommend approval of additional cost to EMS (Electric Motor
Service) to rebuild Well #6 Well Motor for a total sum not to exceed $15,000.00.
Page 1 / 2
Meeting Date: July 14, 2025
PW/S&W Committee Memo
Item (9) Discussion and Possible Action: Well #6 Chemical Pumps and Blower Replacement
Well 6 chemical pumps both Fluoride and Chloride need replacing because of parts missing, dried out,
wrong type and size. Price includes a replacement chemical blower to blow off gas fumes and prevent
further corrosion due to a failing blower. Cost to replace and install new Pumps and Blower $20,055.00
William Reid
Recommended Motion: Recommend approval of cost to replace and install new Pumps and Blower
to William Reid for total sum not to exceed $20,055.00
Item (10) Discussion and Possible Action: Well #6 Con Lyte Nitro Analyzer for Chemical
Nitrate Testing
Con Lyte Nitro analyzer is a for Nitrate testing. This unit will actively test nitrate levels and give daily
feedback and results to our remote office through SCADA. This is essential to maintaining and testing
Nitrate levels for DNR compliance. $11,667.00
Recommended Motion: Recommend approval to purchase a Con Lyte Nitro Nitrate Analyzer for
Well #6 from Midwest Meter for a total sum not to exceed $11,667.00
.
Total additional amount needed to complete Well #6 rehabilitation $109,026.00
Page 2 / 2
Owner: City of Verona, Wisconsin
Project: North Pump Station and Electrical System Updates
Project No.: 2022-109.1 Contract: 2022-109.1
Contractor: Rohde Brothers, Inc.
W5745 Woodchuck Ln
Plymouth, WI 53073
Estimate Prepared By: Brian Marquardt
Name
Project Manager
Title
4/20/2025
Date
SUMMARY
ORIGINAL CONTRACT AMOUNT 581,100.00
APPROVED CONTRACT REVISION AS OF 3,503.00
ADJUSTED CONTRACT AMOUNT 584,603.00
REQUEST THIS ESTIMATE
TOTAL COMPLETED TO DATE 580,603.00
PREVIOUS REQUESTS FOR PAYMENT 562,603.00
TOTAL EARNED THIS REQUEST 18,000.00
RETAINAGE 0% 0.00
CURRENT PAYMENT DUE 18,000.00
AECOM
Name
July 3rd, 2025
Date
City of Verona
Name
Date
Owner's approval
Date
REQUEST FOR PAYMENT
PROJECT NAME: Verona North Pump Station DATE: 4/20/2025
ADDRESS: 7049 Cross Country Road, Verona, WI 53593
CONTRACT FOR: HVAC, Plumbing, Mechanical
Project 24025 Contract # 2022-109.1 Invoice #
REQUEST NUMBER: 10 PERIOD FROM: 4/1/2025 TO: 4/30/2025
ORIGINAL CONTRACT AMOUNT 581,100.00
APPROVED CONTRACT REVISION AS OF 3,503.00
ADJUSTED CONTRACT AMOUNT 584,603.00
TOTAL COMPLETED TO DATE 580,603.00
PREVIOUS REQUESTS FOR PAYMENT 562,603.00
TOTAL EARNED THIS REQUEST 18,000.00
RETAINAGE 0% 0.00
CURRENT PAYMENT DUE 18,000.00
SUBCONTRACTOR Rohde Brothers, Inc.
SIGNED: Brian Marquardt
TITLE: Project Manager
W5745 WOODCHUCK LANE • P.O. BOX 409 • PLYMOUTH, WI 53073-0409
PHONE: (920) 893-5905 • FAX: (920) 893-5908 • EMAIL: rohde@rohdebros.com
PROJECT: Verona North Pump Station
SUBCONTRACTOR: ROHDE BROTHERS INC.
APPLICATION DATE: 4/20/2025
PAYMENT APPLICATION NUMBER: 10
SUBCONTRACTOR SCHEDULE OF VALUES
TOTAL COMPLETED &
WORK COMPLETED
STORED TO DATE
ITEM SCHEDULED PREVIOUS MATL RETAINAGE BALANCE
DESCRIPTION OF WORK
NO. VALUE APPLICATION THIS STORED 5% TO FINISH
(B) %
(A) (C) (D) APPLICATION THIS (I) (J)
(G) (H)
(E) Request
(F)
1 Job Supervision $20,000.00 18,000.00 18,000.00 90.00% 900.00 2,000.00
2 Submittals $10,000.00 10,000.00 10,000.00 100.00% 500.00 0.00
3 O&M's $5,000.00 4,000.00 4,000.00 80.00% 100.00 1,000.00
4 Project Closeouts $5,000.00 4,000.00 4,000.00 80.00% 100.00 1,000.00
5 Permits & Bonds $5,200.00 5,200.00 5,200.00 100.00% 260.00 0.00
6 Mobilization $1,000.00 1,000.00 1,000.00 100.00% 50.00 0.00
7 Demobilization $1,000.00 1,000.00 1,000.00 100.00% 50.00 0.00
Procurement
8 Process Pipe, Fittings, & Valves $67,000.00 67,000.00 67,000.00 100.00% 3,350.00 0.00
9 Hangers $5,000.00 5,000.00 5,000.00 100.00% 250.00 0.00
10 LW Allen/Altronex
11 43 21 00 Large Booster Pumps $75,000.00 75,000.00 75,000.00 100.00% 3,750.00 0.00
12 43 21 00 Small Jokcey Pump $25,000.00 25,000.00 25,000.00 100.00% 1,250.00 0.00
14 40 61 14 Instrumentation & Controls $9,766.00 9,766.00 9,766.00 100.00% 1,250.00 0.00
15 40 71 13 Inline Magnetic Flow Meter $10,000.00 10,000.00 10,000.00 100.00% 500.00 0.00
17 Motor Control Center $147,595.00 147,595.00 147,595.00 100.00% 1,280.08 0.00
18 North Booster Station Well-4 RTU Modifications $44,719.00 44,719.00 44,719.00 100.00% 0.00 0.00
Labor Installation
19 Measure & Planning $15,000.00 15,000.00 15,000.00 100.00% 700.00 0.00
20 Deliveries $3,000.00 3,000.00 3,000.00 100.00% 0.00 0.00
21 Piping Labor $15,000.00 15,000.00 15,000.00 100.00% 325.00 0.00
22 Equipment Setting $15,000.00 15,000.00 15,000.00 100.00% 0.00 0.00
23 Demolition $5,000.00 5,000.00 5,000.00 100.00% 0.00 0.00
24 Startup/Commissioning $3,000.00 3,000.00 3,000.00 100.00% 0.00 0.00
0.00
Page 2 of 3
P:\2024\24025 Verona North Pump Station\Correspondence\Billing\Verona North Pump Station Pay App Master[SOV] 4/18/2025 2:38 PM
Subcontractors 0.00
25 Controls/Power Wiring (Pieper Electric) $68,283.00 68,283.00 68,283.00 100.00% 0.00 0.00
26 Painting (Omni Glass & Paint) $25,537.00 7,537.00 18,000.00 25,537.00 100.00% 0.00 0.00
Change Orders
27 CO 1 - Moving piping $3,503.00 3,503.00 3,503.00 100.00% 0.00 0.00
Totals $584,603.00 562,603.00 18,000.00 0.00 580,603.00 99.32% 14,615.08 4,000.00
Page 3 of 3
P:\2024\24025 Verona North Pump Station\Correspondence\Billing\Verona North Pump Station Pay App Master[SOV] 4/18/2025 2:38 PM
CHANGE ORDER (EJCDC C-941)
Change Order
No. 02
Date of Issuance: June 10, 2025 Effective Date: June 10, 2025
Project: North Booster Pump Station Owner: City of Verona, WI Owner's Contract No.: 2022-109.1
and Electrical Upgrades
Contract: North Booster Pump Station and Electrical Upgrades Date of Contract: December 12th, 2023
Contractor: Rohde Brothers, Inc. Engineer's Project No.: 60698041
The Contract Documents are modified as follows upon execution of this Change Order:
Description: This change order incorporates the costs incurred to the Contractor for the work including the air compressor
control panel relocation, tracing of control circuits, cable/wire identification, temp controls for the air compressor control
panel after initial shut down, and removal and reinstallation of the panel. Also includes new conduit for getting controls to
the RTU cabinet.
Attachments: Rohde Brothers, Inc. Change Order Proposal and Cost Breakdown and Pieper Power Change Order Summary
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price: Original Contract Times: Working days Calendar days
Substantial completion (days or date): March 26, 2025
$ 581,100.00 Ready for final payment (days or date): July 04, 2025
[Increase] [Decrease] from previously approved [Increase] [Decrease] from previously approved Change Orders
Change Orders No. - to No. 1: No. - to No. -:
Substantial completion (days): - 0 days
$ 3,503.00 Ready for final payment (days): - 0 days
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial completion (days or date): - -
$ 584,603.00 Ready for final payment (days or date): - -
[Increase] [Decrease] of this Change Order: [Increase] [Decrease] of this Change Order:
Substantial completion (days or date): - 0 days
$ 6,414.00 Ready for final payment (days or date): - 0 days
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial completion (days or date): March 26, 2025
$ 591,017.00 Ready for final payment (days or date): July 04, 2025
RECOMMENDED: ACCEPTED: ACCEPTED:
By By: By:
Engineer (Authorized Signature) Owner (Authorized Signature) Contractor (Authorized
Date: June 10th, 2025 Date: Signature)
Date:
EJCDC C-941 Change Order
Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.
00 63 00-1 of 00 63 00-2
Verona North Booster Pump Station and Electrical Upgrades Change Order 02
Proposal Proposal#: 20572 W5745 Woodchuck Lane
AECOM Date: 06-Jun-25 P.O. Box 409
Plymouth, WI 53073-0409
Attn: Zach Topel Department Totals
Phone: (920) 893-5905
7049 Cross Country Rd. Pipe Fitting $6,414.00 Fax: (920) 893-5908
Verona, WI 53593
We hereby propose to furnish all material and labor necessary to complete work as described below, in a good and
workmanlike manner, for the sum of: $6,414
Six Thousand Four Hundred Fourteen Dollars
Description
See attached CO scope of work and breakdown from Pieper Power.
According to plans and specifications as drawn by: AECOM
Project #: 24-025 Project: North Booster Station
Location of Work: Verona, WI Owner: City of Verona
Terms: Net 30 Days. Finance charge of 1-1/2% per month (Annual Percentage rate of 18%) added after 30 days after first billing date.
Respectfully Submitted,
Accepted By: Date: Brian Marquardt
Per: Brian Marquardt
Title:
ROHDE BROTHERS, INC.
This proposal when signed by you and returned to us shall constitute a valid and binding contract, which shall be governed and construed according to the laws
of the State of Wisconsin. This proposal is subject to 30 days acceptance from the date of this proposal and may be changed without notice before actual receipt
of acceptance. This proposal is based on a form of contract using the latest editions of AIA Document A201. “General Conditions of the Contract for
Construction” in conjunction with either AIA Document A101, “Standard Form of Agreement Between Owner and Contractor” of AIA Document A401,
“SUBCONTRACT Standard Form of Agreement Between Contractor and Subcontractor”, or on a time and material form of contract using the latest edition of
Rohde Brothers, Inc. “Standard Form of Construction Contract Proposal For Cost Of Work Plus A Fee”. Rohde Brothers shall also be reimbursed for all
expenses it incurs while protecting its rights in the performance of this work. This shall include any appropriate legal or administrative action that Rohde
Brothers must take to protect its interests, such as, but not limited to, attorney and accounting fees, court reporter fees, filing fees, the actual cost of effecting
service of papers or providing witnesses, and expenses incurred by Rohde Brothers itself.
CONFIDENTIAL CUSTOMER COPY
City of Verona
Breakdown of Rohde Proposal #20572
Proposal Name: North Booster Station
Subcontract Total
Pieper Power $ 6,109.00
Total Before Adjustment $ 6,109.00
Allowable Adjustment 5.0%
Total Subcontract Cost $ 6,414.45
Material Total: $ 0
Total Labor $ 0
Total Subcontractor $ 6,414
Total Change Order $ 6,414
Page: 1 of 1 Printed: 6/6/2025 10:49:12 AM by: marquardtb
CHANGE ORDER SUMMARY
JOB NAME: Verona NBPS
Rohde Brothers, INC. CHANGE ORDER NUMBER: PCO#1
W5745 Woodchuck Ln REVISION NUMER: N/A
P.O. Box 409 DATE: 6/5/2025
Plymouth, WI 53073 JOB NO: IN00006435
ATTENTION : Brian Marquardt CONTRACT NO: SC-2915
AMOUNT OF C/O: $6,109
REGARDING YOUR REQUEST FOR QUOTATION:
Air compressor control panel relocation. Tracing of control circuits, Cable/Wire Identification, temp controls for aircompressor control
panel after initial shut down, removal and reinstallation of panel. Additional new conduit for getting controls to the RTU cabinet.
SUMMARY: A. LABOR $4,886
B. MATERIALS $279
C. DJE $147
SBO: YES
SUBTOTAL $5,312
OVERHEAD & PROFIT 15.00% $797
D. SUBCONTRACTS $0
OVERHEAD & PROFIT 0.00% $0
SUBTOTAL $6,109
BOND $0
INSURANCE $0
GRAND TOTAL $6,109
ADDITIONAL CALENDAR DAYS EXTENDED TO CONTRACT COMPLETION DATE: 0
THIS AMOUNT ONLY COVERS THE DIRECT COSTS IN LABOR, MATERIALS, SUBCONTRACTS AND EQUIPMENT NECESSARY TO EXECUTE THE
CHANGED WORK DESCRIBED IN THE PROPOSAL. AT THE PRESENT TIME, WE CANNOT ASSESS OR EVALUATE THE OVERALL IMPACT OF THE
CHANGED WORK ON OUR ORIGINAL CONTRACT SCOPE OF WORK. WE THEREBY RESERVE OUR RIGHTS TO CLAIM FOR ANY INDIRECT COSTS
WHICH MAY ARISE IN THE FUTURE AS A RESULT OF DELAYS TO THE WORK, OUT OF SEQUENCE WORK, INEFFICIENCIES, EXTENDED CONTRACT
COMPLETION, LABOR AND MATERIAL ESCALATION AND/OR ACCELERATION AND EXTENDED WARRANTIES.
OPS-14, 15, 16 This price is valid for 14 days. This form was approved:
JOB NUMBER C.O. NO. DATE REVISION
Verona NBPS IN00006435 PCO#1 5-Jun-25 N/A
A. LABOR
*SUPER INTENDENT 0 HRS @ $146.32 TOTAL $0.00
** SUPERVISOR 0 HRS @ $117.50 TOTAL $0.00
*** SAFETY 0 HRS @ $79.29 TOTAL $0.00
ELECTRICIAN 38 HRS @ $128.59 TOTAL $4,886.42
ESTIMATOR 0 HRS @ $85.00 TOTAL $0.00
ENGINEER 0 HRS @ $50.00 TOTAL $0.00
@ TOTAL $0.00
@ TOTAL $0.00
@ TOTAL $0.00
TRAVEL @ TOTAL $0.00
SUBSISTENCE @ TOTAL $0.00
PREMIUM COSTS TOTAL $0.00
LABOR TOTAL $4,886.42
B. MATERIALS
MATERIAL PER "TAKE-OFF" TOTAL $271
MISCELLANEOUS MATERIAL & WASTE 3.00% TOTAL $8
SUBTOTAL $279
FREIGHT AND HANDLING TOTAL $0
SPECIAL EXPEDITING TOTAL $0
SALES TAX 0.0% TOTAL $0
MATERIAL TOTAL $279
*SUPER INTENDENT - 6% OF TOTAL MAN HOURS
** SUPERVISOR - 12 % OF TOTAL MAN HOURS
*** SAFETY - 3 % OF TOTAL MAN HOURS
TS11A
JOB NUMBER C.O. NO. DATE REVISION
Verona NBPS IN00006435 PCO#1 5-Jun-25 N/A
C. DJE QUANTITY UNIT PRICE AMOUNT
Field Office $0.00
Telephone $0.00
Field Office Supplies $0.00
Field Office Equipment $0.00
Blueprinting $0.00
$0.00
$0.00
First Aid and Safety Supplies $0.00
$0.00
Warehousing $0.00
Storage Charges $0.00
Freight Charges $0.00
$0.00
Special Insurance $0.00
$0.00
Permit and Inspection Fees $0.00
$0.00
$0.00
Equipment and Tools 3.00% of Labor 1 $146.59 $146.59
Truck - Jobsite Van $7.50 $0.00
Truck - Pick-Up $0.00
Truck - Stake $0.00
Truck - Line $0.00
Fuel - (On Jobsite) $0.00
$0.00
Travel and Trips Expenses $0.00
Lodging Expenses $0.00
Living Allowance $0.00
Entertainment $0.00
Double Union Benefits $0.00
$0.00
Job Clean-Up $0.00
$0.00
Temp Power Consumption Charges $0.00
Utility Comp Charges - Temp Service $0.00
Utility Comp Charges - Perm Service $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTAL: $147
ESTIMATING FORM
PROJECT CODE # PAGE OF
Verona NBPS
LOCATION ARCH. OR ENG. ESTIMATE NO.
Notes: SPECIFICATION NO. SCALE DRAWING NO.
ESTIMATED BY PRICED BY REVIEWED T.S. REVIEWED DATE
6/5/2025
Labor
Description Quan. Material Unit Material Extension Labor Unit Notes
Extension
Rigid galvanized steel, 3/4" diameter 30 $6.10 $183.00 0.119 3.57
Clip, 1 hole for rigid conduit, 3/4" diameter 4 $0.43 $1.72 0.02 0.08
GRC, Standard, LB, LR or LL fittings with covers, 3/4" diameter 2 $14.45 $28.90 0.733 1.466
GRC, Standard, Ericson, 3/4" diameter 2 $10.45 $20.90 0.68 1.36
Flex Steel conduit, connectors, plain, 3/4" diameter 1 $3.44 $3.44 0.136 0.136
Pressed steel, square, 4" 1 $4.06 $4.06 0.476 0.476
Pressed steel, square 4-11/16", covers, blank 1 $3.50 $3.50 0.18 0.18
Type THWN-THHN, copper, stranded, #14 100 $0.20 $19.70 0.00733 0.733
Type THWN-THHN, copper, stranded, #12 20 $0.29 $5.70 0.00866 0.1732
Tracing and Labeling of control wires 1 20 20
Removal of Aircompressor Control Panel 1 4 4
Mounting of Aircompressor Control Panel 1 4 4
Testing and Commissioning 1 1 1
Total this page - $271 - 38 -
TS 24 Total all pages - $271 - 38 -
Get email alerts for Verona