City Council Worksession
Regular MeetingWatertown, MN · October 26, 2021
Minutes
Watertown City Council
Work Session
Mayor Steve Washburn
Lindsay Guetzkow
Adam Pawelk
Michael Walters
Dan Schuette
10/26/2021 - Minutes
1. Call To Order And Roll Call
Mayor Steve Washburn called the Watertown City Council work session to order at 5:31 p.m. on Tuesday
October 26, 2021, in the council chambers of City Hall.
Council Members Present: Washburn, Michael Walters, Lindsay Guetzkow, and Adam Pawelk.
Staff Present: Administrative Services Director Lynn Tschudi (virtual), City Administrator Jake Foster, and
Public Utilities Superintendent Doug Kammerer.
2. New Business
2.I. 2022 Enterprise Budget & Utility Rates
Administrative Services Director Lynn Tschudi said the City conducted a utility rate study in 2017
based on future projects that would be needed in water, sewer, and stormwater systems. To pay for
future projects, the City needs to operate based on new connection rate assumptions of 17 homes per
year, increasing to 22 homes in the year 2023. Tschudi said the City has far exceeded these
assumptions in the past few years while continuing to budget revenues conservatively.
Tschudi reviewed the Water, Sewer, and Storm Water operating funds for council. Highlights of the
expenses for 2022 include:
• New meter for well #1, new chemical feed for well #3
• Additional funds for aging water meters
• Increase in employee wages due to pay equity / market study
• Team building
• Additional funds for jetting/televising
• Increase in employee wages due to pay equity / market study
• Team building
• Additional funds for jetting/televising
• Increase in utilities costs
Pawelk asked about the team building divided between water and sewer as well as general fund.
Tschudi explained that $10,000 was allocated to general fund, $5,000 to water and $5,000 to sewer
because many employees are split 70%/30% general fund, enterprise fund. Walters asked what kind
of teambuilding and council visioning is planned for 2022. Tschudi said she would like the new City
Administrator to have a decision in the process.
Pawelk asked why the engineering fees were increased in the sewer operating fund. He asked if the
wastewater treatment facility engineering fees would be tracked with the capital project. Tschudi said
the majority of the engineering fees will be capitalized with the project. Kammerer said there will be
other projects during 2022 other than the WWTF that require engineering.
Guetzkow asked about the storm water ponds and if those costs have been captured. Kammerer said
the ponds will be taken care of this year. She asked Tschudi if the wage study data has been
confirmed. Foster said the wage ranges are accurate, but where employees were placed on the scale
may not be accurate due to their experience. He would like to analyze this further and bring it to
council at a future meeting.
Tschudi reviewed the Water, Sewer, and Stormwater Utility Rates. Water is expected to increase by
1%, Sewer by 4%, and Stormwater by 5%. These rates are planned accordingly by the 2017 Utility
Rate Study. Tschudi explained that although the cost of the WWTF has increased significantly, the
City’s financial advisor suggests planning the 2022 increases around the current study. Any future
increases can be planned with a new study. Tschudi shared a comparison of a 2021 and 2022
residential utility bill. Overall increase will average around 2.75%.
Council discussed the need for updated wastewater treatment facility numbers in order to know what
the future rates will be.
2.II. General Fund Budget Update
Tschudi updated council on the General Fund Budget. She explained that the health insurance rates
increased about 4% from 2021, and property/casualty still are estimated to increase by 5%. Tschudi
said she decreased the EDP Software/Technology by $10,000 since the accounting software CIP
project was moved to 2023. Tschudi said the levy increase is now at 5.23% with an increase to the
average value home of $21.
3. Adjournment
Mayor Washburn adjourned the work session at 6:05 p.m.
309 Lewis Avenue South; P.O. Box 279, Watertown, MN 55388
__________________________________________________________
Steve
309 Lewis Avenue South; P.O. Box 279, Watertown, MN 55388
__________________________________________________________
Steve
Washburn, Mayor
ATTEST:__________________________________________
Lynn Tschudi, Admin. Services Director