Airport Advisory Board
Regular MeetingWauchula, FL · January 13, 2025
Minutes
On January 13, 2025 the City of Wauchula Airport Advisory Board met for its regular meeting at
1:30 p.m. in the Commission Chambers, Suite 105 of Historic City Hall located at 225 East Main
Street, Wauchula, Florida.
Board members present: Ward Grimes
Steve Johnson
Michael Gillispie, Chairman
Mike Burch
Staff members present: John Eason, Deputy City Manager
Stephanie Camacho, City Clerk
Gillispie declared a quorum and called the meeting to order.
Approval of the Agenda
Johnson motioned to approve the agenda, seconded by Burch. All were in favor. Motion carried.
Election of Chair and Vice Chair
Johnson motioned to elect Michael Gillispie as Chairman, seconded by Burch.
Gillispie accepted the position. With no discussion, Eason called for all in favor. All responded aye.
For those opposed, no response. Motion carried.
Gillispie motioned to elect Michael Burch as Vice Chairman, seconded by Johnson.
Burch accepted the position. With no discussion, Eason called for all in favor. All responded aye.
For those opposed, no response. Motion carried.
Appointment of New Board Member – Mike Landskroner
Johnson motioned to approve the appointment, seconded by Burch. All were in favor. Motion
carried.
Approval of the Minutes for August 5, 2024
Johnson motioned to approve the minutes, seconded by Burch. All were in favor. Motion carried.
Russ Holliday – AVCON
Holliday provided updates on the following projects. Further details are attached to these minutes.
Terminal Building and T-Hangar Update - Russ Holliday
RW 36 Feasibility Study Update – Russ Holliday
RW 36 Extension Update – Russ Holliday
Hangar Repairs from Hurricane’s Ian and Milton – Russ Holliday and Ward Grimes
Public Comment
No one was present for public comment.
With no further business to discuss, Gillispie adjourned the meeting at 2:09 p.m.
Michael Gillispie, Chairman Stephanie Camacho, City Clerk
CITY OF WAUCHULA MUNICIPAL STAFF PROJECT REPORT
Jan 13, 2025
CITY COMMISSION CHAMBERS, SUITE 105
225 EAST MAIN STREET, WAUCHULA, FLORIDA
Advisory Board Members City Administration
Michael Gillispie, Chair City Manager Olivia Minshew
Mike Wilkinson, Vice-Chair
Deputy City Manager John Eason
Ward Grimes
Assistant City Manager\Finance Director –
Stephen Johnson Sandee Braxton
Mike Burch City Clerk Stephanie Camacho
AGENDA
Invocation
Pledge of Allegiance
Call to Order – Please silence cell phones
Roll Call – Secretary/Clerk
Declaration of Quorum
Approval of Agenda
Approval of Minutes: June 1, 2024
I. Taxiway A Rehab Construction update – Project is Completed, and all documentation delivered
to Airport and FAA.
II. DB T-Hangars, Pilot’s Lounge Remodel, and Hangar Repairs
A. T-Hangars: AVCON has received the sealed land survey. The geotechnical team has
completed their field work, and the team expects a geotechnical engineering report
to be submitted soon. The survey has been uploaded to JACIP. The geotechnical
report has been delivered and uploaded to JACIP and delivered to the City. The next
step is to begin the preliminary construction plans design process. The intent is to
try to synchronize the project with the other two building projects so that they might
be bid together to save costs based on economies of scale. This project is in 30%
AVCON staff report2405200T001_AVCONReport_CHNAAB_Mtg_2024-11-04.docx
design stage. The Team is trying to synchronize the design with the ongoing Hangar
rehabilitation project, so that the projects can be bid together to save costs. Once
the repair project plans are approved by the adjustor, this project will be designed.
The project has started preliminary design in order to synchronize with the Hurricane
Ian repairs. Update: The project will need to be decoupled from the Hangar Repair
project based on input from the Insurance Carriers. Work in progress 30% startup
design.
B. Pilot’s Lounge Remodel: This project has been deferred to a later year due to
inadequate funding.
C. Hangar Repairs: AVCON has developed a base scope and fee for design/build of
repair of existing hangars damaged by Hurricane Ian. The Airport has reached out to
FAA for BIL funding to supplement the insurance claim to make the necessary
repairs. At this time several communications have been received from FAA and they
are weighing the eligibility of this funding request using BIL funds. A pre-application
was submitted for BIL funds on October 18 to FAA requesting funds. Based on input
from the insurance company the scope/fee for the design work is being reviewed,
and will be provided to staff for review as soon as possible. After several rounds of
review by the insurance company’s adjustors, they have approved the scope and fee
for AVCON and structural repair experts to perform the design plans\permitting.
The City and AVCON have signed the agreement, and the subconsultants are being
signed up currently. The next step is for the subconsultants’ to schedule their field
laser scan survey. The Structural Engineer is on site tomorrow with AVCON’s
structural engineer performing their field review of the hangar buildings. Update:
The structural engineer has completed the draft drawings to approximately 95%
level. Staff have forwarded to the insurance company representatives for review
and comment, to implement for the 100% drawings stage. Project is ahead of
schedule. Update: The structural engineers are reviewing a request from FEMA
regarding justification of costs, and update of estimated costs of repairs, based on
the final plans. Our PEMB consultant is also reviewing. This effort is in support of
the Airport staff request for additional construction funds. The plans have been
provided to the insurance company representatives for review. Laser scans delivered
to the Insurance Reps. Support files are needed to view the scan files with RECAP
and those have been requested from the subconsultant. Insurance company has
authorized bidding of the project once the T-Hangar plans and specs are completed,
and after Hurricane Milton assessments are completed. Update: The support files
were transmitted to the Insurance company representatives as requested. This
project will need to be decoupled from the T-Hangar project as the Insurance reps
have asked the Team to start bidding procedures. The Team is working on the front
end documents to bid the project based on the plans. Update: A meeting was held
with the insurance carriers, AVCON, and the Airport/City staff to determine a
solution to the complexity of the damages sustained to the hangar buildings by two
separate storms. The result of the meeting was for McLarens to provide a Hurricane
AVCON staff report2405200T001_AVCONReport_CHNAAB_Mtg_2024-11-04.docx
Milton damage assessment with photographs to add to the plans and specifications.
Once those are received, AVCON will incorporate in the bid documents and forward
to all parties for review. It is anticipated that the project will be broken down by
each hangar, and possibly separated by storm, into separate bid schedules/line
items for bidding and construction tracking purposes. The project will then be
publicly bid in order to increase competition and get the best prices. After bids are
received, analyzed, and a bidder recommended, the two companies will work
together behind the scenes to establish which repairs will be funded by which
agency.
D.
Schedule:
1. 4/2 - on -site survey
2. 3 to 4 weeks to develop point cloud scan and convert to REVIT model
3. 4-30 Provide completed REVIT model to ADS
4. 5-1 to 5-3 ADS to study model in order to focus on areas needing direct
observation
5. 5-7 to 5-8 ADS to make site investigation
6. Estimate first part of June for completion of docs.
7. Permitting 30 days – July – Plans currently under review by Insurance
Company and FEMA – COMPLETED.
8. Bidding 30 days - Feb - Mar
III. RW 36 Extension Update
A. Justification and Environmental Study: Peter Green of FAA has agreed to a second
meeting to review the proposed outline. AVCON has completed the draft pre-
planning document and delivered it to the City and FDOT for review. The next step is
for FAA to review after the coordination meeting is held, which will be used to make
any adjustments. The second meeting was held with Peter Green of FAA, with the
outline received well. The issue of the RPZ was brought up and responded to.
AVCON submitted the draft EA report based on the outline. AVCON submitted the
environmental engineer’s report from the design phase, as well as the proposed
scope for the planning phase to fill any gaps in the scopes, to FAA. All reports are
under review by FAA. Peter Green has left the ADO at the time of this writing to go
to the Southern Region in Atlanta. So this study may be passed on to a new
reviewer. Update: The project team has met with the new FAA review Amy Reed,
and FDOT to orient her to the project. In addition the team met internally
afterwards to discuss the additional work needed to complete the historical artifacts,
and other sections of the study. In addition, the issue of the avigation easements
and how to process that with the land owner was discussed this week. The project
team explored the possibility of dual extensions to relieve the aviation easement
requirement due to the overhanging RPZ. The FDOT PTGA is for only two years, and
will expire in March of 2025. Therefore we anticipate an extension request for at
least 6 months to one year will be needed. Anticipated completion of the EA is
AVCON staff report2405200T001_AVCONReport_CHNAAB_Mtg_2024-11-04.docx
December 2025. Update: The project team continues to meet weekly on the project.
The latest submittal was last week July 30, 2024, of the Final Draft form of the
Purpose and Needs Chapter to all parties. FDOT has indicated that comments from
Management at Central Office are forthcoming for several months, but not yet
received. Team will carry on, based on recent discussions with Dawn Gallon of
FDOT. The team is getting pricing from the extension surveyor for the Avigation
easement metes and bounds survey required for the extended Runway Protection
Zone (RPZ). The purpose and Need have been delivered to the Airport and the FAA
(Amy Reed) for review. Update: The purpose and need chapter comments have been
received and implemented and sent back to FAA. FAA has authorized the Team to
proceed with the Alternatives and Special Studies phases of the Environmental
Assessment. FDOT Central Office has reviewed and approved the Justification and
kicked it down to the Management in District #1 for review and approval. A meeting
has been scheduled for the 5th of November with FAA to review the next steps. The
Additional Avigation Easement Survey field work has been completed. The survey
deliverable is expected in a couple of weeks. Update : FDOT advised via email on
November 18, 2024 that the document titled “Wauchula Municipal Airport (CHN)
Runway 36 Extension Justification Study followed the methodology recommended in
the FAA AC 150/5325-4B, Runway Length Requirements for Airport Design. Once the
airport has reached the 500 operations of the Aircraft Design Group II, the project
will meet the justification for FDOT funding. Subject to the availability of
appropriated funds, the Department may participate in all the capital cost of the
project at that time. The airport sponsor may begin the project with pre-construction
studies, design, and construction using the funding allocated by the legislature and
with other sponsor resources. At the time the project meets the justification criteria,
FDOT will make a final determination regarding the project and funding percentages
pursuant to Chapter 332, FS: Airports and Other Air Navigation Facilities.” Following
the meeting with the FAA on November 5, 2024 a subsequent meeting was held with
FAA on December 9, 2024 to approaches for the special purpose studies, specifically
the Biological Assessment (BA) and the Cultural Resource Assessment Survey (CRAS).
During that time, FAA informed AVCON that the Caracara study as part of the BA
would need to commence with US Fish and Wildlife approval no later than January
10, 2025 or the project would be delayed until the next season (one year). At that
time, AVCON’s subconsultant, Young Bear Environmental, began coordination with
FAA to prepare a scope amendment for the required species surveys. Final scope and
fee was received by Young Bear on December 30, 2024. Additional fees for the subs
and AVCON are $100.000 and the survey period for the BA is approximately months.
AVCON will request approval to proceed with the survey and request an extension.
B. Young Bear Fee for $89,500.00
Amendment 1
Archeological Consultants Inc. Fee $3,000.00
AVCON staff report2405200T001_AVCONReport_CHNAAB_Mtg_2024-11-04.docx
Subtotal Subconsultants: $92,500.00
AVCON Fee $7,500.00
TOTAL $100,000.00
Specific Purpose Species
Surveys
Amendment 1: $ 89,500.00
CRCA: $ 45,000.00
E BLRA: $ 20,000.00
SE AMKE: $ 5,000.00
FL SACR $ 5,000.00
Gopher Tortoise: $ 2,000.00
BA Report: $ 12,500.00
C. Civil Design Plans: The preliminary schematic plans are currently being worked on (
pre-30% design). The geotechnical and environmental studies are being generated
by the subconsultant experts, and their draft reports have been requested, but not
received to date. We have requested the reports again and will update the City and
FDOT with those reports when received. The team has received the environmental
Threatened and Endangered species report from the biologist. The only impacts will
be the small impact to the existing wetland by Taxiway Alpha extension. The next
step is for the design team to continue to work on the schematic design plans as the
environmental study is developed in parallel. Update: The design team will carry on
with the 30% design plans based on recent developments with the EA study and
present staff with a new schedule for design which will be on a parallel track with
the EA. It is anticipated that the design will be completed well ahead of the EA
approval, so the team is trying to pace this effort accordingly. Update: FDOT
confirmed that the team should carry on with the design of the runway extension
but pace the effort along with the EA as much as possible, but slightly ahead so that
the project can be bid out with fresh pricing and start construction as soon as
possible in conjunction with the EA approval. According to Airport Staff and FDOT
representatives the second installment has been authorized and should be issued to
the Airport this cycle. The 30% design stage plans are being working on and several
AVCON staff report2405200T001_AVCONReport_CHNAAB_Mtg_2024-11-04.docx
progress plots have been delivered to the Airport staff. The rough grading plans are
completed, and the PAPI unit location calculations have been completed and
incorporated into the plans. The Construct Safety and Phasing Plans are nearly
completed and will be filed along with the 7460-1 filing at the 60% design stage.
Update: The second installment of $4.55 M has been received from FDOT, and
accepted by the City, for the design and construction of the Runway Extension
project. The 60% and 75% design stage plans have been completed and delivered to
the Airport for review. The project is about a month ahead of schedule. See updated
schedule below based on current progress. The majority of the current design effort
is on the storm-water modeling calculations, and permit application and report in
anticipation of submittal to the SFWMD.
Proposed Schedule:
1. 30% 60% QC Submittal – Internal - NOV 8TH
2. 30% 60% Submittal – Civil \ Electrical – NOV 15TH To Owner
3. 60% 75%QC Submittal – Internal – JAN 17TH – Submitted December 24, 2024
- Completed
4. 60% 75% Submittal - Civil \ Electrical – JAN 24TH – Submitted December 24,
2024 - Completed
5. 90% QC Submittal – Internal – FEB 28TH
6. 90% Submittal - Civil \ Electrical – MAR 7TH
7. 100% QC Submittal – Internal – APR 4TH
8. 100% Submittal - Civil \ Electrical – APR 11TH
Additional fees have been incurred to comply with permit requirements including the Avigation
Easement Surveys, additional topographic and wetland surveys in the amounts detailed below.
Additional Wetland Flagging - Young Bear Environmental (YBE) $ 2,000.00
Additional Topographic Survey - GF Young Surveying, Inc. (GFY) $ 21,500.00
Avigation Easement Surveys - GF Young Surveying, Inc. (GFY) $ 8,600.00
Total Additional Sub-Consultant Services $ 32,100.00
IV. New Two-Tank Fuel Farm Project + Generator Set – A federal pre-application was formulated
and submitted to FAA for the design of two new fuel tanks, truck turn-around, waste oil tank,
and truck containment. FDOT was copied for programming in FY 2025. Update: Federal pre-
applications were updated to include an Emergency Standby Engine Generator Set in order to
capture expiring 2022 BIL AIG funds at the request of the Airport and FAA. The project qualified
for a Categorical Exclusion, and therefore will not require a separate environmental assessment
by the FAA.
V. AMPU – The Airport Master Plan Update will be deferred to another near-term outer year.
Update: JACIP was updated to push the AMPU out to at least 2026 due to ongoing project
commitments.
AVCON staff report2405200T001_AVCONReport_CHNAAB_Mtg_2024-11-04.docx
ATTACHMENTS:
A. Link to latest Runway 36 plans:
Wauchula
Copy + paste the link into your Windows Explorer or Internet browser URL
https://av-sma.avconinc.com
Domain:
av.cfe
Login:
Wauchula
Password:
2OpenFTP@Wauchula
AVCON staff report2405200T001_AVCONReport_CHNAAB_Mtg_2024-11-04.docx
Agenda
WAUCHULA MUNICIPAL AIRPORT ADVISORY BOARD MEETING AGENDA
MONDAY, JANUARY 13th, 2025 AT 1:30 P.M.
CITY COMMISSION CHAMBERS, SUITE 105
225 EAST MAIN STREET, WAUCHULA, FLORIDA
Advisory Board Members City Administration
Michael Gillispie, Chair City Manager Olivia Minshew
Ward Grimes
Deputy City Manager John Eason
Stephen Johnson
Michael Burch
City Clerk Stephanie Camacho
Invocation
Pledge of Allegiance
Call to Order – Please silence cell phones
Roll Call – Secretary/Clerk
Declaration of Quorum
Approval of Agenda
Election of Chair and Vice Chair
Appointment of New Board Member – Mike Landskroner
Approval of Minutes: August 5th, 2024
Terminal Building and T-Hangar Update – Russ Holliday
RW 36 Feasibility Study Update – Russ Holliday
RW 36 Extension Update – Russ Holliday
Hangar Repairs from Hurricane’s Ian and Milton – Russ Holliday and Ward Grimes
Adjourn