Board of Public Works
Regular MeetingWaupun, WI · September 10, 2024
Minutes
Minutes - City of Waupun
Board of Public Works
Tuesday, September 10, 2024 – City Council Chambers
CALL TO ORDER
Chairperson Mike Matoushek calls the meeting to order at 4:30pm
ROLL CALL:
Alderpersons: Peter Kaczmarki, Kambria Ledesma (online), Mike Matoushek
Citizens: Dale Heeringa, Andrew Sullivan, Dave Rens, Gregg Zonnefeld
Ex-Officio: DPW Director Jeff Daane, City Administer Kathy Schlieve
Others Present: Kris Dressler, Cedar Corporation (online)
Discussion on future meetings and gatherings involving the Board of Public Works. The next
regularly scheduled meeting is October 8, 2024, 4:30 pm, City Council Chambers.
Motion Zonnefeld, second Sullivan to approve minutes from August 19, 2024 Board of Public
Works meeting as presented. Carried unanimously.
Motion Sullivan, second Heeringa to approve fall yard waste pickup dates for October 7 to
November 11, 2024, weather permitting. Carried unanimously.
Motion Zonnefeld, second Rens to approve the museum tuckpointing bid for B and B Quality
Building Restoration, the lowest qualified bidder, in an amount of $102,792. Daane notes that the
Historical Society is not interested in the alternate which was to construct a sign base. Sullivan
questions difference between this contractor and next lowest bid (~$50,000). Kris Dressler
confirms that B and B Quality Building Restoration is a WI contractor where others are out of state
and notes that the other contractors are union contractors. Motion carries unanimously.
Motion Heeringa, second Sullivan to approve the low bid for asphalt paving S West Street (W.
Lincoln to Visser Avenue) in the amount of $42,866.25 from Kartechner Brothers LLC as
presented. Work is offset by a Local Road Improvement Program grant, which will provide a 50%
reimbursement. Carried unanimously.
Discuss ordinance amendment of Ch. 7.03(3)(4)(5) Sidewalk Construction and Repair. Daane
notes that the current ordinance needs to be updated to reflect current ADA standards. Draft
ordinance is presented. Daane explains that we are working with a new contractor for our
sidewalk program that provides grinding services vs. full replacement and that will stretch our
dollars further. Ordinance changes are needed to specify materials to be used during a repair
and to reduce the standard from 1 inch to ½ inch gap to meet ADA standards. Motion Rens,
second Sullivan to recommend draft ordinance to the Common Council to City of Waupun
Ordinance Chapter 7 Section 7.03 Sidewalk Construction and Repair to meet current ADA and
maintenance standards.
Motion Sullivan, second Rens to adjourn meeting at 4:52 pm. Carried unanimously.
Agenda
AGENDA
CITY OF WAUPUN BOARD OF PUBLIC WORKS
MEETING
Waupun City Hall – 201 E. Main Street, Waupun WI
Tuesday, September 10, 2024 at 4:30 PM
The City of Waupun Board of Public Works and Facilities Committee will meet in-person, virtually and
teleconference. Instructions to join the meeting are provided below:
Virtual: https://us02web.zoom.us/j/81987138114
Meeting ID: 819 8713 8114
Phone: 312 626 6799 US (Chicago)
CALL TO ORDER
ROLL CALL
PERSONS WISHING TO ADDRESS THE BOARD OF PUBLIC WORKS--State name, address, and subject of comments.
(2 Minutes)
No Public Participation after this point.
FUTURE MEETINGS AND GATHERING INVOLVING THE BOARD OF PUBLIC WORKS
CONSIDERATION - ACTION
1. Approve Minutes from August 19, 2024 Board of Public Works Meeting
2. Approve Fall Yard Waste Pickup Dates
3. Approve Heritage Museum Restoration REBID
4. Approve Asphalt Paving Contract for S West Street (W. Lincoln St to Visser Ave)
5. Amend Ch. 7.03(3)(4)(5) Sidewalk Construction and Repair
ADJOURNMENT
Upon reasonable notice, efforts will be made to accommodate disabled individuals through appropriate aids and
services. For additional information, contact the City Clerk at 920-324-7915.
Minutes - City of Waupun
Board of Public Works
Monday, August 11, 2024 – City Council Chambers
CALL TO ORDER
Vice Chairman Peter Kaczmarki calls the meeting to order at 4:30pm
ROLL CALL:
Alderpersons: Peter Kaczmarki, Kambria Ledesma
Citizens: Dale Heeringa, Andrew Sullivan, Dave Rens
Ex-Officio: DPW Director Jeff Daane, Mayor Rohn Bishop, City Administer Kathy
Schlieve
Citizens: Eric Homan, Dan Holtz
Excused Absences: Mike Matoushek, Gregg Zonnefeld
FUTURE MEETINGS AND GATHERING INVOLVING THE BOARD OF PUBLIC
WORKS
1. Next Regularly Scheduled Meeting is September 10, 2024, 4:30 pm
CONSIDERATION - ACTION
2. Approve Minutes from July 9, 2024 Board of Public Works Meeting – Rens motion to
approve as presented, Sullivan seconded. Motion passes unanimously.
3. Authorize Replacement of Damaged Flatbed 39-06 with New Vehicle – Mayor Bishop
makes a statement regarding his strong opinion that the truck should be purchased from
Homan. Rens brought up the insurance pay out and Schlieve answered regarding.
Heeringa makes a motion to accept the bid of $54,128.44 from Homan, seconded by
Rens. Motion passes unanimously.
4. Approve Rebid for City Hall Reroof of Existing Ballasted Roofs with EPDM Adhered
Roof System (Roof Areas: East, West and North, 201 E Main Street) – Daane presents,
there is a $10,000 savings in this rebid with an opportunity for more savings if the
insulation is in good condition. Ledesma moves to approve the low bid, seconded by
Sullivan. Motion passes unanimously.
5. Emergency Declaration City Garage - Daane presents, the roof is in bad shape
following the May hail storm. Rens moved to approve the resolution for a Public
Emergency Declaration for the City Garage Roof Damaged during the May 2024
Hailstorm as presented. Heeringa seconded. Motion passes unanimously.
6. Recommend Public Works Garage Emergency Roof Replacement Bid to Council for
Approval – Daane and Schlieve present. Rens moves to recommend to the Council
approval of the Emergency Roof Repair and Gutter Replacement Bid for the Waupun
Public Works Garage as presented. Ledesma seconded. Motion passes unanimously.
Sullivan moves to adjourn, Heeringa seconded. Motion passes unanimously.
ADJOURNMENT
Respectfully submitted,
Kambria Ledesma, Interim Secretary
City of Waupun
AGENDA SUMMARY SHEET
MEETING DATE: 9/10/24 TITLE: Approve Fall Yard Waste Pickup Dates
AGENDA SECTION: CONSIDERATION-ACTION
PRESENTER: Jeff Daane, Public Works Director
DEPARTMENT GOAL(S) SUPPORTED (if applicable) FISCAL IMPACT
Public Infrastructure N/A
ISSUE SUMMARY:
We need to confirm fall yard waste pickup dates for 2024. We are looking at October 7 through November 11, weather
permitting. All yard waste must be at the curb by 7am on November 11.
STAFF RECOMMENDATION:
Approve dates as outlined
ATTACHMENTS:
RECOMMENDED MOTION:
Motion to approve fall yard waste pickup dates October 7 through November 11, weather permitting
AGENDA SUMMARY SHEET
MEETING DATE: 9/10/24 TITLE: Approve Heritage Museum Restoration REBID
AGENDA SECTION: CONSIDERATION-ACTION
PRESENTER: Jeff Daane, Public Works Director
DEPARTMENT GOAL(S) SUPPORTED (if applicable) FISCAL IMPACT
Public Infrastructure Base bid $102,792.00 plus alternate $106,592.00
ISSUE SUMMARY:
The Museum has water infiltrating the building in different areas. This is due to the mortar joints deteriorating. The project
was bid earlier this summer with a low bid at that time coming in just over $194,000. The bid spec was changed to repair
some of the old stone versus just replacing all of them, this was the largest cost difference in the new low bid.
B and B Quality Building Restoration was the low bid initially and is once again the lowest qualified bidder in this round of
rebidding.
STAFF RECOMMENDATION:
Approve the low bid from B and B Quality Building Restoration
ATTACHMENTS:
Bid analysis/bid tab
RECOMMENDED MOTION:
Motion to approve the museum tuckpointing bid for B and B Quality Building Restoration, the lowest qualified bidder,
in an amount that includes the base bid plus alternate for a total expenditure of $106,592.
BID ANALYSIS
Community Infrastructure • Architecture • Environmental Services
Client City of Waupun Project No. W6218-012
Project Heritage Museum Restoration REBID Date 09.04.2024
Prepared By K. Dressler
The City of Waupun (hereinafter referred to as the OWNER) has received bids on the third day of
September 2024 for the Heritage Museum Restoration REBID, (hereinafter referred to as the Project);
and
Cedar Corporation (hereinafter referred to as ENGINEER) has been retained by the OWNER to prepare
bid tabulations, analyze bid results and consult with the OWNER on the award of contracts.
The ENGINEER hereby consults as follows:
1. Bids were received from three bidders. Base bids ranged from a low of $102,792.00 to a high of
$172,113.00. A summary of the bid tabulation is attached.
2. Based upon ENGINEER's analysis of the bids received on the above PROJECT, the responsive low
bidder is:
B&B Quality Building Restoration of WI LLC
2456 Highway MM
Fitchburg, WI 53575
Base Bid Amount: $102,792.00
Alternate Bid Amount: $ 3,800.00
Total Bid Amount: $106,592.00
3. It is understood that by this analysis, that the ENGINEER does not guarantee the Contractor's
performance which is covered by the Contractor's bond, but it is a statement by the ENGINEER
that the ENGINEER has no information which would lead the ENGINEER to believe that the
Contractor does not have the necessary equipment and personnel to complete the PROJECT in
compliance with the drawings and specifications within reasonable tolerances generally accepted
in the trade.
4. It is further understood that this analysis is not a representation that the ENGINEER has reviewed
the proposal for possible legal irregularities which should be a function of the OWNER'S legal
counsel, and at the option of the OWNER.
5. It is further understood that in the event that OWNER feels that the Contract should be awarded
on some basis other than price, the OWNER should defer further action on this PROJECT until a
thorough legal review can be made by OWNER'S legal counsel.
Page 1 of 1
Cedarburg • Green Bay • Madison • Menomonie
Bid Tab
Heritage Museum Restoration REBID
City of Waupun
Dodge County, WI
September 3, 2024
B&B Quality Bldg Rest Berglund Construction Building Restoration
Line Fitchburg, WI Chicago, IL Roseville, MN
Item Item Description Unit Qty Unit Price Extension Unit Price Extension Unit Price Extension
Base Bid
1 Re‐Pointing Masonry SF 1200 $36.00 $43,200.00 $25.00 $30,000.00 $41.00 $49,200.00
2 Cut Stone Replacement SF 20 $400.00 $8,000.00 $650.00 $13,000.00 $633.00 $12,660.00
3 Limestone Replacement SF 25 $400.00 $10,000.00 $560.00 $14,000.00 $838.00 $20,950.00
4 Fill Crack in Cut Stone LF 5 $165.00 $825.00 $300.00 $1,500.00 $872.00 $4,360.00
5 Fill Chipped Cut Stone SF 5 $125.00 $625.00 $700.00 $3,500.00 $977.00 $4,885.00
6 Masonry Cleaning SF 4500 $1.00 $4,500.00 $4.00 $18,000.00 $1.00 $4,500.00
7 Roof Flashing LF 90 $49.00 $4,410.00 $80.00 $7,200.00 $153.00 $13,770.00
8 Concrete Stair with Landing EA 1 $8,500.00 $8,500.00 $31,720.00 $31,720.00 $20,160.00 $20,160.00
9 Concrete Foundation LF 16 $700.00 $11,200.00 $580.00 $9,280.00 $1,198.00 $19,168.00
10 Railing LF 18 $550.00 $9,900.00 $1,400.00 $25,200.00 $718.00 $12,924.00
11 Sidewalk Replacement SF 32 $51.00 $1,632.00 $50.00 $1,600.00 $298.00 $9,536.00
Base Bid Total $102,792.00 $155,000.00 $172,113.00
Alternate
12 Concrete Slab SF 32 $25.00 $800.00 $75.00 $2,400.00 $120.00 $3,840.00
13 Concrete Foundation EA 2 $1,500.00 $3,000.00 $1,300.00 $2,600.00 $2,800.00 $5,600.00
Alternate Total $3,800.00 $5,000.00 $9,440.00
Base Bid + Alternate $106,592.00 $160,000.00 $181,553.00
Page 1 of 1
AGENDA SUMMARY SHEET
MEETING DATE: 9/10/24 TITLE: Approve Asphalt Paving Contract for S West
Street (W. Lincoln St to Visser Ave)
AGENDA SECTION: CONSIDERATION-ACTION
PRESENTER: Jeff Daane, Public Works Director
DEPARTMENT GOAL(S) SUPPORTED (if applicable) FISCAL IMPACT
Total project $42,866.25 Wisconsin Local Roads and
Public Infrastructure Improvement Program will offset 50% of the project
costs
ISSUE SUMMARY:
On September 4th the City held a bid opening for mill and overlay of S. West St. We received and opened two bids. One
from Kartechner Brothers LLC and the other from Northeast Asphalt.
STAFF RECOMMENDATION:
Approve the low bid from Kartchener Brothers LLC
ATTACHMENTS:
Bid Tab
RECOMMENDED MOTION:
Motion to approve the low bid in the amount of $42,866.25 from Kartechner Brothers LLC as presented.
CITY OF WAUPUN
BID TAB
Asphalt Paving Contract
S. West St. (W. Lincoln St. to Visser Ave.)
Wednesday, September 4, 2024
Kartechner Brothers LLC
N11829 County Rd I
Waupun WI 53963
Item No Item Description Approx S.Y. Mill Price Surface Price Total Price
2" Profile Mill
2" Blacktop Sufrace (4LT 58‐28s)
1 S. West St. (W. Lincoln St. to Visser Ave) 4899 $ 0.95 $ 7.80 $ 42,866.25
Total Item #1 $ 42,866.25
Northeast Asphalt
20 Camelot Dr.
Fond Du Lac WI 54935
Item No Item Description Approx S.Y. Mill Price Surface Price Total Price
1 2" Profile Mill
2" Blacktop Sufrace (4LT 58‐28s)
S. West St. (W. Lincoln St. to Visser Ave) 4899 $ 1.40 $ 9.00 $ 50,949.60
Total Item #1 $ 50,949.60
AGENDA SUMMARY SHEET
MEETING DATE: 9/24/2024 TITLE: Amend Ch. 7.03(3)(4)(5) Sidewalk Construction
and Repair
AGENDA SECTION: CONSIDERATION-ACTION
PRESENTER: Jeff Daane, Director Public Works
DEPARTMENT GOAL(S) SUPPORTED (if applicable) FISCAL IMPACT
SUMMARY:
Attached is the City’s current ordinance 7.03 Sidewalk Construction and Repair. ADA and maintenance standards have
changed and the ordinance is recommended for updates.
STAFF RECOMMENDATION:
Discussion
ATTACHMENTS:
Preliminary Ordinance 7.03 Sidewalk Construction and Repair with Proposed Revisions
RECOMMENDED MOTION:
Motion to recommend updates to the Common Council to City of Waupun Ordinance Chapter 7 Section 7.03 Sidewalk
Construction and Repair to meet current ADA and maintenance standards.
7.03 SIDEWALK CONSTRUCTION AND REPAIR. Formatted: Heading 1
(1) DEFINITIONS. The following terms have the meanings indicated:
Crack. A fissure within a sidewalk square.
Defective Sidewalk or Square. A sidewalk square meeting the criteria for replacement in subsection (4)
below.
Joint. A cleavage created for expansion purposes which separates 2 or more sidewalk squares.
Sidewalk. A public sidewalk within the street right-of-way.
Sidewalk Square. That portion of a sidewalk bordered by joints and the sidewalk edge.
Spalling. A chipped or splintered condition of a sidewalk square.
(2) WISCONSIN STATUTES. Section 66.615, Wis. Stats., is incorporated herein by reference.
(3) DELEGATION OF AUTHORITY; SIDEWALK INSPECTORS. The City Engineer shall have the authority of the Board
of Public Works as provided for in §66.615, Wis. Stats., and he they shall designate one or more subordinates
as sidewalk inspectors who shall have the duty of inspecting the sidewalks within the City and ordering or
arranging for the replacement and or repair of defective sidewalks.
(4) CRITERIA FOR DETERMINING NECESSITY OF REPLACEMENT OR REPAIR when applicable. Sidewalk squares
which meet the following criteria shall be considered defective, unsafe and insufficient and in need of
replacement or repair:
(a) There is a difference in height equal to or greater than one-half inch in the elevation of adjacent
sidewalk squares.
(b) There is a crack equal to or greater than one-half inch in width.
(c) There is a difference in height equal to or greater than one-half inch in the elevation of adjacent
sections of a crack or a crack with width greater than one-half inch for 3 inches or longer
(d) There is depression greater than one-half inch within a sidewalk square.
(e) There is spalling which has resulted in a depression greater than one-half inch.
(f) There is a noticeable change or distortion in the constant grade resulting from the heaving or
settlement of 2 or more sidewalk squares, where this creates a difference in height of one inch or
more.
(g) There has been a temporary sidewalk repair.
(5) TEMPORARY SIDEWALK REPAIR. No sidewalk square shall be ordered or arranged to be repaired by way of
crack fillers, asphalt wedges, surface treatments or the like by a sidewalk inspector, except as a temporary
measure pending replacement and or repair. Sidewalk squares which, upon inspection, are noted to have
been temporarily repaired shall be ordered or arranged to be replaced. However, wherever the only defect is
a difference in elevation due to settlement or having, it shall be permissible to remedy the defect by
adjusting the square.
(a) Crack filling will be allowed only using High Performance, self-leveling one-part Polyurethane sealant as
preventive maintenance. .
(6) PROCEDURE; SIDEWALK REPLACEMENT AND PAYMENT OF COSTS. The procedure for sidewalk replacement
and for the payment of the cost shall be governed by §66.615, Wis. Stats.
Created: 2024-04-24 15:47:57 [EST]
(Supp. No. 19)
Page 1 of 3
(7) NONCOMPLIANCE. Sidewalks replaced by the City contractor or City forces shall be subject to an
administrative fee as established annually by the Common Council on the Fee Schedule per tax parcel in
addition to the replacement cost.
(8) NEW SIDEWALKS.
(a) Owners of business or commercial real estate abutting any public street in the City shall construct and
perpetually maintain sidewalks prior to the time of opening for business.
(b) Owners of residential real estate abutting any public street in the City shall construct and perpetually
maintain sidewalks in the manner following:
1. Sidewalks shall be constructed at such time as directed by the Board of Public Work. Owners shall
be prohibited from constructing sidewalks absent such direction from the Board.
2. Where the Board of Public Works has directed that residential sidewalks be constructed, the
Board is authorized to grant temporary exemptions to owners where the Board determines that
special or unusual situations make the construction of sidewalks impossible or impractical and an
alternate means of sidewalk is available or unnecessary. All such exemptions shall be for a term
of one year, unless the Board otherwise directs at the time of granting the exemption, however,
in no event shall such exemption be granted on a permanent basis.
(9) SIDEWALK CONSTRUCTION. These specifications shall apply to the construction and restoration of sidewalks
installed for improvement of pedestrian facilities. All sidewalks installed on public property shall be
constructed in accordance with the following provisions:
(a) All sidewalks shall be constructed with Class A Concrete, unless other materials are approved by the
City Engineer, the Director of Public Works, or Board of Public Works.
(b) All sidewalks shall have a minimum width as outlined in the Table in §7.13, unless otherwise provided
by the Board of Public Works.
(c) The elevation of the sidewalk, as measured at the outside edge (edge nearest to the private property)
shall be no less than 2% or no more than 5% above the top of the adjacent curb. The transverse slope
of the sidewalk shall be not less than one-quarter inch per foot or more than one inch per foot, sloping
toward the public street.
(d) All sidewalks shall have a concrete thickness of 4 inches over a 4-inch gravel base, except at driveways
where sidewalk shall be constructed of concrete 6 inches thick over a 4-inch gravel base.
(e) Commercially prepared concrete (ready-mix) shall conform substantially to the Standard Specifications
for Road and Bridge Construction as prepared by the Wisconsin Department of Transportation, Division
of Highways, except that concrete shall contain not less than 6 bags of cement per cubic yard.
(f) The foundation for the sidewalks shall be thoroughly tamped or otherwise compacted to prevent
settlement and be moistened before placing the concrete. The concrete shall be consolidated and
spaded sufficiently to bring the mortar to the surface and prevent honeycombing. Before the mortar
has set, the surface shall be struck off and floated with a wooden or magnesium float, steel troweled
and brushed.
(g) Transverse joints shall be constructed at right angles to the centerline of the sidewalk, either by sawing
or grooving, at approximately 4-foot intervals. One half-inch transverse expansion joint filler shall be
installed at each property line. The edges of the sidewalk shall be rounded with an edger having a ¼-
inch radius. Concrete shall not be placed on frozen ground and shall be protected against freezing for a
period of 72 hours after placement. The concrete shall be cured for a minimum of three days using
impervious plastic or paper, wet fabric or liquid impervious membrane.
Created: 2024-04-24 15:47:57 [EST]
(Supp. No. 19)
Page 2 of 3
(h) All sidewalks shall generally be located as outlined in the Table in §7.13 unless it is necessary to be
further from the property line to match the location of sidewalks on either or both sides of the
property involved.
(10) PENALTY. Any person who shall fail to replace or repair defective, sidewalks within 45 days after being so
ordered as provided herein shall be subject to a penalty as provided in §18.04 of this Municipal Code. A
separate offense shall be deemed committed on each day in which a violation of this section occurs or
continues. This section shall not preclude the City from replacing or repairing defective sidewalks as provided
in §66.615, Wis. Stats.
(Ord. No. 23-09, § 4, 11-28-2023)
Created: 2024-04-24 15:47:57 [EST]
(Supp. No. 19)
Page 3 of 3