Planning Commission Meeting
Regular MeetingWest Valley City, UT · September 26, 2012
Minutes
WEST VALLEY CITY
PLANNING COMMISSION
MINUTES
September 26, 2012
The meeting was called to order at 4:03 p.m. by Chairman Phil Conder at 3600
Constitution Boulevard, West Valley City, Utah
WEST VALLEY CITY PLANNING COMMISSION MEMBERS
Harold Woodruff, Brent Fuller, Jack Matheson, Terri Mills, Phil Conder,
Joe Garcia, and Barbara Thomas
ABSENT
Imaan Bilic
WEST VALLEY CITY PLANNING DIVISION STAFF
Steve Pastorik, Steve Lehman, and Nichole Camac
AUDIENCE
Approximately one (1) people were in the audience
West Valley City Planning Commission
September 26, 2012
Page 2
SUBDIVISION APPLICATIONS
PUD-2-2012
Truong Townhome Subdivision
1600 West 3860 South
RM Zone
76 Units
6.54 Acres
11.6 Units/Acre
BACKGROUND
Mr. Russ Platt, representing the property owner, is requesting preliminary approval for a
residential development to be known as the Truong Townhomes. The subject property
was recently rezoned from the C-2, C-3, R-1-8 and M zones to the RM zone. The
subject property is bordered on the north by light industrial uses and the Gates at
Kingspointe Condominiums, the east and south by residential uses and the west by
commercial properties.
STAFF/AGENCY COMMENTS:
Public Works Department:
• Authorization required of ditch/water users for any abandonment, relocation,
piping or any other modifications to existing ditches or irrigation structures.
• Contact Salt Lake County Auditor’s Office for approval of street names and
subdivision names.
• Existing and any new street improvements along 3860 South shall be installed in
accordance with plan and profiles approved by the Engineering Division.
• Concerns regarding the connection of the private street off of the cul-de-sac.
Modify access to connect with the cul-de-sac at a right angle.
• Revisions to plat required.
• Flood control issues to be coordinated with Public Works and UDOT.
Utility Companies:
• Standard Utility Easements required.
Granger Hunter Improvement District:
• Project is subject to all GHID requirements and design standards.
Fire Department:
West Valley City Planning Commission
September 26, 2012
Page 3
• Proposed fire hydrant locations need to be shown on subdivision plat.
• Project shall meet all provisions of Fire Code relating to this type of development.
• Second access required from the east and along the north side of City park.
Building Division:
• Will require a soils report.
ISSUES:
Project Overview:
The Truong Townhomes will be a residential community consisting of 76 units on
6.54 acres. This equates to an overall density of 11.6 units per acre. As part of
the rezoning process, the developer and City negotiated a development agreement
that will be made part of this application.
Proposed townhomes will be a combination of 2 and 3 story units. The 2 story
units will have 3 bedrooms and will comprise 1,400 square feet. The 3 story units
will have 4 bedrooms and will be approximately 1,750 square feet in size. Each
unit will have a two car garage accessed from the rear of the building allowing the
front of the townhome to face a common green.
The elevations consist of architectural enhancements placed along different planes
to create visual depth. This will result in a more attractive building. Steep roof
pitches and second floor balconies will add to this concept. The rear elevation has
been designed with boxed windows, raised roof sections and building relief to
help eliminate the stark look that often accompanies the rear elevation of large
buildings. Brick will also be used along the rear elevation to help enhance these
elevations. Staff has evaluated this project in regards to the multiple family
design standards. In almost all instances, this project meets with the standards
outlined in the ordinance. There are however, a few areas that the developer will
need to work on. To ensure that these changes have been incorporated into the
elevations, final working drawings will be required prior to final plat submittal.
Side elevations are typical for this type of development. Although these
elevations have multiple windows, including boxed windows, staff has suggested
that additional relief be incorporated on the elevations facing 3860 South. In
addition, the developer is willing to add a second color to garage doors, windows
in garage doors, and different patterns in the door to enhance the visual
appearance as you drive down 3860 South.
West Valley City Planning Commission
September 26, 2012
Page 4
Building materials will consist of brick, stucco and hardi-plank. The developer is
suggesting that two color schemes be used for this project. The colored variations
will need to be substantial enough so that one color does not dominate the project.
Final colors for this project will be reviewed by the Planning Commission during
the first phase of the project.
As mentioned previously, all townhome units will have a two car garage for
parking. The 3 story units will have a driveway while the 2 story units will not.
For this reason guest spaces are provided. The total number of spaces required is
145 where 248 are provided in garages and driveways. In addition, 24 guest
spaces are provided for units where driveways are not planned.
Setbacks are illustrated on the site plan and are proposed to be 20 feet from the
public right-of-way. The side setback for the middle units along the south
property line will be 10 feet. Staff has expressed concern regarding the proposed
distance between buildings. The distance measured on the plat is approximately 7
feet. The developer has agreed to remove 4 units in these areas which increases
this space to approximately 24 feet. These units will be relocated to the eastern
portion of the development site.
During the study session, a question was raised regarding the distance between
buildings facing the common green. This distance varies between 30 and 35 feet.
Staff has asked the applicant to provide a rendering to better illustrate this. We
hope to have this for the regular meeting. This area is not intended to be used for
recreational space as other spaces will be provided throughout the project. This
space will contain covered porches and an interconnecting sidewalk system.
Other matters related to this project:
Access:
Access to the subdivision will be gained from 3860 South. All streets intersecting
3860 South will be private. The preliminary plat shows a street width of 26 feet.
It is anticipated that asphalt with a concrete curb will be used for the construction
of these roads.
The developer will also dedicate and install the remaining portion of Grasmere
Lane located to the east of the City Park. This road was initially installed as part
of the Grasmere Acres Subdivision. However, only the east portion of this road
was constructed as the developer did not own the west portion.
During the rezone process, residents in the area expressed concern about the
completion of this road as it would then provide a through connection with
residents in the Kingspointe Subdivision to the north. These roads have always
been planned for this connection. With the development of this property, the time
for that connection is now. The construction of this road will likely take place
when the eastern portion of this project develops.
West Valley City Planning Commission
September 26, 2012
Page 5
During the review of this plat, the Public Works Department expressed concern
over the connection of the cul-de-sac and the street providing access to the east
portion of the development. The turning movements at this connecting point
would be unsafe. As a result, the developer will be required to locate this street
further to the south thus providing a true 90 degree turn off of the cul-de-sac.
Staff has discussed this with the developer and modifications will be made to the
plat.
At the present time, the only access to this property is from 3860 South. The Fire
Department will require that a second point of access be provided for this
development. The Fire Department requires a second point of access when more
than 100 multiple family units are proposed. The Gates at Kingspointe to the
north has 84 units. Since this project consists of 76 units, the second access will
be required. The access road does not need to be a full access, but can be gated.
The developer will need to coordinate the installation of this road along with
provisions for the gate during the review of the second phase. Coordination will
also need to take place with the Parks Department as this access will be positioned
along the north side of the City Park.
The east portion of this project has a turnaround for the Fire Department. The
width of this turnaround will need to be 20 feet. As a result of this requirement,
the developer may end up eliminating the two end units. As mentioned
previously, the overall site will undergo slight revisions due to engineering issues
and staff recommendations regarding open space. These revisions may or may
not allow the density to remain at 76 units. The development requirements of
each project will ultimately determine the final density.
Garbage Collection:
The development has been designed with a U shaped street pattern. This will
allow all residents to have their own garbage can. Dumpsters will not be needed
in this project. The developer will need to coordinate garbage collection with a
private agency for collection.
Landscaping:
While landscaping is generally addressed at the final plat stage, staff would like to
mention a few things at this point in the review process. The overall open space
will need to comprise an area equal to 50% of the project site. The useable open
space will need to comprise 15% of the project site. Per the development
agreement, the portion of land to be dedicated as a City Park will be included in
the overall calculation of open space.
Enhanced landscaping will be installed along the east, west and north sides of the
warehouse building. This will help screen the building from residential uses. The
plans for this landscaping will be reviewed during the final plat process.
Enhanced landscaping will also be needed along 3860 South to help buffer the
residential units along this frontage.
West Valley City Planning Commission
September 26, 2012
Page 6
The project does include areas for storm water detention. Staff has expressed
concern that if these areas are too deep, the space will not count toward the
useable space calculation. Suggestions have been made to feather these detention
basins out over the whole project thus lessening the depth of these basins. This
matter will be more thoroughly addressed as engineering reviews take place.
Entry Feature:
Although not discussed at this point, staff is recommending that an entry feature
or features be installed along 3860 South as part of this project. As noted in the
past, the City’s Police Department has stated that projects which have an
identifiable entry marker will help deter crime.
Fencing:
The developer has indicated that a 3-rail fence will be installed along 3860 South.
Fencing along the south boundary and along a portion of the west boundary is
under discussion. Staff recommends that a new fence be installed along these
areas. Fence type will need to be discussed during the final plat process. As part
of the development agreement, a 6-8 foot masonry wall will be installed along the
east, west and north sides of the warehouse property.
Lighting:
It is anticipated that street lights will need to be installed along 3860 South. The
project site warrants additional lighting along the private roads and throughout the
open spaces. Staff will recommend that a lighting plan be submitted at final plat.
Soils Report:
Although basements are not planned for this project, a soils report will be
required. The developer will need to coordinate findings of the soils report with
the Building Division and Engineering Division regarding the construction of
housing and street improvements.
Grading:
The property is relatively flat except the portion that will eventually be dedicated
to the City for a new park. The developer anticipates taking earth material from
the west side to the east side in order to raise the grade of the park. Bringing fill
to this area of the property not only benefits the park, but the area immediately to
the west of the unfinished Grasmere Lane. All grading and drainage issues will
need to be coordinated with the Public Works Department.
Tree Survey:
There are a number of mature trees on the east side of the development site.
Those that line the south boundary were likely installed as part of the LDS Church
site plan. There are additional trees that line the east boundary as well. Some of
these will be removed for the construction of Grasmere Lane. However, trees
located in the southeastern area of the property adjacent to lot 8 of the Grasmere
Acres Subdivision should be preserved. Not only would these trees benefit the
City Park, but they will provide a buffer for the resident to the east. Typically, a
West Valley City Planning Commission
September 26, 2012
Page 7
tree survey is done as part of the subdivision process. Staff will require that the
developer’s engineer illustrate these trees on the preliminary plat.
STAFF ALTERNATIVES:
A. Grant preliminary approval for the Truong Townhome Subdivision subject to the
following conditions:
1. That the developer resolve all staff and agency concerns.
2. That the Planned Unit Development be subject to the multiple family
design standards outlined in the City ordinance, and the development
agreement negotiated during the rezoning process.
3. That a soils report be prepared prior to the final plat review of the first
phase.
4. That the developer provide an overall landscape plan to be reviewed
during the first phase of the final plat process. Said landscaping plan shall
provide measures to ensure water conservation techniques will be used in
accordance with City ordinances.
5. That all requirements of the West Valley City Fire Department be satisfied
including the hammerhead turnaround, and secondary access.
6. That the developer resolve any issues regarding irrigation ditches and
irrigation water that may be in use.
7. That compliance be made with Granger Hunter Improvement District, i.e.,
water line extensions, connections, water rights and fire protection.
8. That the subdivision name and street names be approved by the Salt Lake
County Auditor’s Office.
9. That proposed building setbacks be in accordance with the site plan
reviewed by the Planning Commission dated September 26, 2012. Based
on discussions in this report, certain buildings will be modified to meet the
required setbacks along 3860 South.
10. That specialty lighting be provided throughout the entire development. In
addition, the developer will need to coordinate street lighting on 3860
South with the City Engineering Division. Said lighting will be reviewed
during the final plat.
11. That access off of the cul-de-sac be redesigned per the City Traffic
Engineer. Also, any existing improvements along 3860 South that are
damaged, or may become damaged through construction be replaced.
West Valley City Planning Commission
September 26, 2012
Page 8
12. That the developer coordinate storm water issues with both the City
Engineering Office and UDOT.
13. That all conditions noted above be completed prior to the first phase being
submitted for final plat review.
14. That a tree survey be completed. The area of focus shall be on the eastern
portion of the proposed subdivision.
B. Continuation, in order for the developer to address issues raised during the public
hearing.
Applicant:
Russell Platt
1759 E 4620 S
Discussion: Steve Lehman presented the application. Barbara Thomas asked if
there is only one entrance into the entire subdivision from 3860 South. Steve
replied that there will be several private streets leading into the neighborhood. Joe
Garcia asked if there will be trees planted to allow privacy within the
neighborhood. Steve replied that there will be courtyards to allow for outdoor
seating and added that there will be vegetation throughout the common areas as
well. Terri Mills asked if the units being moved will affect the usable open space.
Steve replied that the numbers haven’t been calculated yet but the development
must meet all requirements and added that if open space becomes a problem a few
units will have to be removed. Commissioner Mills stated that she likes the idea
of moving the units since the current layout creates a narrow alley way between
townhome buildings.
Russell Platt stated that the common space between the units allow residents the
ability to interact with one another and indicated that windows within the homes
are staggered to create privacy. Mr. Platt explained that landscaping plans are
currently being reviewed but there will likely be a mixture of deciduous and other
types of trees throughout the development. Mr. Platt stated that the City Park will
be easy to walk to for the entire development and indicated that the walkway will
be nicely landscaped as well. Mr. Platt explained that there will be a monument
sign that will name the development and denote its entrance located near the front
of the subdivision. He stated that the west side of the development will have a
masonry fence and the southern portion of the project will be chain-link with
slats. Jack Matheson asked if hardi-plank will be used for the colored portion of
the townhomes. Mr. Platt replied yes and added that there will likely be colored
shingles as well. Terri Mills asked if the reds and yellows will be muted. Mr. Platt
replied no but indicated that all colors will tie together. Commissioner Thomas
asked if each street will have a monument sign. Mr. Platt replied no and indicated
that there will be a type of column to indicate each portion of the neighborhood.
Joe Garcia stated that there are cars parking in the cul-de-sac currently and
West Valley City Planning Commission
September 26, 2012
Page 9
expressed concern with this increasing in the future. Mr. Platt replied that the
proposed development has more parking than what is required and any concerns
will be worked out as part of the traffic study.
There being no further discussion regarding this application, Chairman Conder
called for a motion.
Motion: Commissioner Garcia moved for approval subject to the 14 staff
conditions.
Commissioner Woodruff seconded the motion.
Roll call vote:
Commissioner Fuller Yes
Commissioner Garcia Yes
Commissioner Matheson Yes
Commissioner Mills Yes
Commissioner Thomas Yes
Commissioner Woodruff Yes
Chairman Conder Yes
Unanimous -PUD-2-2012- Approved
PLANNING COMISSION BUSINESS
Approval of minutes from September 12, 2012 (Regular Meeting) Approved
Approval of minutes from September 19, 2012 (Study Session) Approved
There being no further business, the meeting adjourned at 4:28 p.m.
Respectfully submitted,
_____________________________________
Nichole Camac, Administrative Assistant
Agenda
WEST VALLEY CITY PLANNING COMMISSION AGENDA
Wednesday, September 26, 2012
Planning Commission Technical Committee ..............................................................September 18, 2012 @ 8:00
a.m.
Planning Commission Study Session ..........................................................................September 19, 2012 @ 3:30
p.m.
Planning Commission Pre-Meeting.............................................................................September 26, 2012 @ 3:00
p.m.
Planning Commission Meeting ...................................................................................September 26, 2012 @ 4:00
p.m.
The Public Hearing is held in the City Council Chambers at West Valley City Hall.
3600 Constitution Boulevard, West Valley City, UT 84119
Woodruff Fuller Matheson Mills Conder __ Garcia __ Thomas __ Bilic
SUBDIVISION APPLICATIONS
PUD-2-2012 Petition by RUSSELL PLATT requesting preliminary plat approval for the Truong
Subdivision. This will be a planned community consisting of 76 lots and 3 parcels on 3.54
acres. The proposed development is located at 1600 West 3860 South and is zoned 'RM'
(residential multi-family). (Staff- Steve Lehman at 801-963-3311)
PLANNING COMMISSION BUSINESS
Approval of Minutes from September 12, 2012 (Regular Meeting)
Approval of Minutes from September 19, 2012 (Study Session)
West Valley City does not discriminate on the basis of race, color, national origin, sex, religion, age, sexual orientation or disability in employment or the provision of services. If you are planning to
attend this public meeting and, due to a disability, need assistance in understanding or participating in the meeting, please notify the City eight or more hours in advance of the meeting. We will try
to provide whatever assistance may be required. The person to contact for assistance is Nichole Camac, 963-3282.
Get email alerts for West Valley City