The meeting was called to order at 4:00 p.m. by Chair Meaders in the City Council Chambers at
West Valley City Hall 3600 Constitution Boulevard, West Valley City, UT 84119, and using
Zoom at https://zoom.us/j/95328405803.
WEST VALLEY CITY PLANNING COMMISSION MEMBERS
David McEwen, Clover Meaders, Brent Fuller, Mathew Lovato, Darrick Porter, Martell
Winters, Cindy Wood, and Harold Woodruff
ABSENT
Darrick Porter
WEST VALLEY CITY PLANNING DIVISION STAFF
Steve Pastorik, Steve Lehman, Jody Knapp, and Kirsten Hunt
WEST VALLEY CITY LEGAL DEPARTMENT
Brandon Hill
AUDIENCE
There were 6 people in the audience.
SMI-5-2021
Crewe 2 Lot Subdivision
3588 South 5450 West
R-1-8 Zone
2 Lots
.42 Acres
BACKGROUND
Mr. Mark Garza is requesting minor subdivision approval for the Crewe 2 Lot Subdivision. The
subject property currently has an existing dwelling that will be removed in lieu of two new single-
family dwellings. The property is bordered on the north, east and south by existing residential
uses along 5450 West and the Erin Hills PUD to the west.
STAFF/AGENCY CONCERNS:
Fire Department:
Existing Fire Hydrant on 5450 will suffice for this project.
Granger Hunter Improvement District:
Project will need to run availability for water, sewer and fire protection.
Subject to design and review inspections.
Utility Agencies:
Subject to all standard easement locations.
Public Works:
Authorization required of ditch/water users for any abandonment, relocation,
piping or any other modifications to existing ditches or irrigation structures.
Will require a delay agreement for improvements along 5450 West. A discussion
will be had with the City Council to determine the vision and improvements for this
street. The delay agreement is subject to change.
Revisions to the plat required.
Will need to coordinate subdivision name with County Auditor's Office.
Soils report is required.
Building Inspections:
Follow recommendations outlined in the soils report.
ISSUES:
The applicant is the developer of the Erin Hills PUD to the west and the owner of the lots
proposed in this application. The subdivision will consist of 2 lots on .42 acres. Although
zoned R-1-8, both lots are approximately 9,250 square feet. During the rezoning process
of the Erin Hills PUD to the west, the developer requested an exception to the frontage for
these two lots. An exception was granted by the Planning Commission that each lot would
be approved with 66 feet of frontage.
In addition to the frontage allowance, the developer is able to build homes in this
subdivision in accordance with Section 7-11-214 of the City Code. This section allows for
new homes to be built with a minimum square footage of 1400 square feet for a ramble and
1600 square feet for a two story. In addition, each home is allowed to be built with a 2-car
garage in accordance with this provision.
Access to the subdivision will be gained from 5450 West. At the present time, this street
is dedicated and improved with asphalt only. Although there are a few sections with curb,
gutter and sidewalk, the majority of this street is void of those improvements. Staff has
discussed the long-term vision of this right-of-way with the City Engineering Division.
The Public Works Department is planning on a discussion with the City Council to
determine if formal improvements should be required along this road. For the present time,
the City will require a delay agreement for such improvements, but that could change based
on the discussion with the City Council. For this application, we are moving forward with
a delay agreement.
As no new single-family development has occurred near this property in quite some time,
staff is unsure of any groundwater impacts. As part of the subdivision process, a soils
report will need to be submitted. The report will need to address soil characteristics and
ground water if any. This report will be reviewed by the City Engineering Division and
Building Official.
Property to the north and south is zoned R-1-8 and will not require any special fencing.
Property to the west, as already mentioned, is part of the Erin Hills PUD. They will be
installing a 6-foot pre-cast masonry wall along their east boundary - west side of this
subdivision.
As mentioned earlier, an existing single-family dwelling is currently located on the
property.
A staff understands this home was used for a training exercise by the West Valley City
Police Department. The home has broken windows and could be seen as an attraction for
unwelcome activity. It is staff’s opinion that this home be demolished as soon as possible
to prevent problems that occur with abandoned buildings.
STAFF ALTERNATIVES:
A. Grant preliminary approval for the Crewe 2 Lot Subdivision subject to the following
conditions:
1. That compliance be made with Granger Hunter Improvement District regarding
water line extensions, sewer connections and fire protection.
2. That the subdivision name be approved by Salt Lake County.
3. That the developer follow recommendations outlined in the soils report.
4. That the developer resolve all staff and agency concerns.
5. That a delay agreement be provided for future installation of improvements along
5450 West.
6. That the existing single-family dwelling be demolished as soon as possible.
B. Continuance to allow the developer an opportunity to address issues raised during the
public hearing.
Discussion: Steve Lehman presented the application. He mentioned that the existing
development agreement includes square footage requirements for the homes.
Steve said that the developer would most likely add basements to the structures
where the square footage requirement increases significantly without a basement.
Steve explained that the developer would need to work with the building official
regarding a groundwater investigation to ensure that basements can be built on the
subject property.
Steve noted that the Public Works Department will have a conversation with the
City Council to see if they will want improvements on 5450 West or not. Steve
said this would help to determine what would happen with the delay agreement.
Mark Garza, the applicant, said that Steve covered everything in his report, and he
is aware of the requirements. He stated that he does not see any issues with
complying with all of the conditions.
Motion: Commissioner Winters motioned to approve SMI-5-2021 subject to the six staff
alternatives.
Commissioner McEwen seconded the motion.
Vote: Commissioner Fuller Yes
Commissioner McEwen Yes
Commissioner Lovato Yes
Commissioner Woodruff Yes
Commissioner Wood Yes
Commissioner Winters Yes
Chairperson Meaders Yes
Unanimously – SMI-5-2021 – Approved.
PUD-3-2021
Cottages at Pearce Farm PUD
6765 West 3500 South
RM Zone
65 Units
10 Acres
6.5 Units/Acre
BACKGROUND
Mr. Greg Larsen is requesting preliminary approval for a residential community to be known as
the Cottages at Pearce Farm. The subject property was rezoned in May 2021 from the A zone to
the RM zone. The subject property is bordered on the east by existing single-family zoning, the
south by property zoned agriculture, the west by 6800 West and the north by 3500 South
STAFF/AGENCY COMMENTS:
Public Works Department:
Authorization required of ditch/water users for any abandonment, relocation, piping or any
other modifications to existing ditches or irrigation structures.
Contact Salt Lake County Auditor’s Office for approval of street names and subdivision
names.
Dedication and improvements required along 3500 South and 6800 West as described in
the development agreement.
Ensure that grade difference at property lines are minimalized.
Revisions to plat required.
Flood control, drainage, and other issues associated with 6800 West be coordinated with
Public Works.
Utility Companies:
Standard Utility Easements required.
Granger Hunter Improvement District:
Project is subject to all requirements and design standards of the water district.
Fire Department:
Proposed fire hydrant locations need to be shown on subdivision plat.
Project shall meet all provisions of Fire Code relating to this type of development.
Building Division:
Soils report will be required.
ISSUES:
Project Overview:
The Cottages at Pearce Farm is a residential community for senior living which will consist
of 65 units on 10 acres. This equates to an overall density of 6.5 units per acre. A club
house is also proposed for the site and will be located toward the center of the project.
Residential units will be one story in height. Based on the development agreement, 25%
of all units will have a bonus room above the garage. The developer is proposing units
with a minimum size of 1500 square feet. All units will have a two-car garage of
approximately 400 square feet and a drive space in front of the garage for parking.
Building architecture is virtually the same that was shown to the Planning Commission
during the rezone application but has been refined. Materials will be stone/masonry
products and fiber cement. All units will have a private patio that is accessible from the
dining/living room area within the dwelling. The developer is proposing
craftsman/bungalow architecture with each having multiple elevations. The developer has
also proposed multiple colors schemes to be used throughout the project to add variety.
As mentioned previously, all units will have a 2-car garage with parking in front of the
garage. In addition to the garage and driveway spaces, the developer is providing guest
parking in and through the project as well. At the present time, the site plan is showing a
total of 273 parking spaces which equates to 4.2 spaces per unit.
Other topics related to this project:
Access:
Access to the subdivision will be gained from 3500 South and from 6800 West. The
developer will be coordinating access and improvements along 3500 South with UDOT.
A main entrance will be gained from this access and will have a landscaped median as you
pull into the development. In addition, signage identifying the project will also be located
at this point.
A second access point will be gained from 6800 West. According to the development
agreement, the developer will be piping the center running ditch, burying the power lines,
installing curb, gutter and sidewalk along the east side of 6800 West and installing 24-feet
of pavement on the east side of the street. The improvements along this right-of-way will
extend out to 3500 South.
The project itself has a looped street system which will satisfy the fire department for
access and maneuverability. The right-of-way width for the internal street will be 26 feet
of asphalt. A sidewalk is located along the interior portion of the private road with various
crossings. Per City policy, gutters are not allowed to be counted towards the asphalt width.
Staff will coordinate this with the City Engineering Division and developer.
Building Setbacks:
Setbacks for this project are illustrated on the site plan. According to the RM zoning
standards, the perimeter setbacks are required to be 20 feet. According to the site plan,
setbacks along the perimeter of the development range in size from 20-30 feet. As the site
continues to be reviewed and refined, setbacks may change, but a minimum of 20 feet is
required. For those units that may have a loft and are taller than 25 feet, which is unlikely,
but possible, an additional setback would be required for those buildings if located along
the perimeter boundary of the subdivision.
Site Amenities:
The developer is proposing a number of amenities for this project. At the present time, the
applicant is proposing a club house of approximately 2,800 square feet with a kitchen,
fitness center and gathering area, and either a pool or pickleball court will be constructed.
A walking path around the perimeter of the development is also proposed. Although not
an amenity listed in the development agreement, each unit will have a private courtyard or
patio space with access from the dwelling as well.
Fencing:
During the rezoning process, the developer agreed to install a 6-foot masonry wall as you
enter the project and vinyl siding around the remaining sides. The design of the wall and
fence has yet to be selected but will be evaluated during the final plat application.
Grading:
The site slopes downward from south to north a vertical distance of 25 feet. Although the
site looks relatively flat, there is a good amount of slope over a distance of 700 feet.
Although the slope is gradual, staff does have some concern that adjacent properties are
not impacted by any grade differential at property line. To help lessen this problem, the
developer will be installing a retaining wall along the south boundary of the subdivision.
The engineering division will review the existing grade and proposed grading plan to
ensure that water runoff will not be a problem for adjacent properties. Staff understands
that some elevation change is to be expected for drainage and sewer requirements, but
staff’s expectation is that the site will have a similar grade as it does today when finished.
Measures shall be taken to eliminate significant grade differences at any property line and
fill shall be limited to help with this potential problem.
Landscaping:
While landscaping is generally addressed at the final plat stage, staff would like to mention
a few things at this point in the review process. The overall open space requirement is
50%. During the rezone, the developer received a reduction in the open space requirement
to 48%. Staff will work with the developer to define what is needed for the project
landscaping as this moves through the subdivision process. A landscaping and irrigation
plan will need to be submitted prior to final plat review.
As part of this project, a main entry will be gained from 3500 South. The developer plans
on landscaping this area with a median and landscaping on both sides of the entry. A
monument sign will be located in this area. Staff will work with the applicant to provide a
landscape plan for all areas of the project including the entrance to the subdivision.
Lighting:
The project site will require streetlights along 3500 South and 6800 West consistent with
current City lighting standards. Internal lighting will also be required. The developer can
choose to use similar lighting, but on a smaller scale, or choose a different light to fit the
project. The developer is still deciding how to light the sidewalk areas and open space
areas within the project. An overall lighting plan will be provided during the final plat
application.
Garbage Collection:
The development has been designed with a good street pattern. The developer will need
to coordinate with a waste management company for the collection of garbage. Due to the
length of some drive courts, residents may need to place their garbage cans along the
private street for this purpose.
STAFF ALTERNATIVES:
A. Grant preliminary approval for the Cottages at Pearce Farm PUD subject to the following
conditions:
1. That the developer resolve all staff and agency concerns.
2. That the Planned Unit Development be subject to the development agreement
reviewed and approved during the rezoning process.
3. That 3500 South and 6800 West be dedicated and improved according to plan and
profiles approved by the Public Works Department.
4. That the developer provide an overall landscape plan to be reviewed during the first
phase of the final plat process. Said landscaping plan shall provide measures to
ensure water conservation techniques will be used in accordance with City
ordinances.
5. That all requirements of the West Valley City Fire Department be satisfied
regarding access and fire protection.
6. That the developer resolve any issues regarding irrigation ditches and irrigation
water that may be in use.
7. That compliance be made with Granger Hunter Improvement District regarding
water line extensions, connections, water rights and fire protection.
8. That the subdivision name and street names be approved by the Salt Lake County
Auditor’s Office.
9. That building setbacks and height be in accordance with the site plan reviewed by
the Planning Commission. Slight modifications to those setbacks may be made if
necessary, as determined by subsequent site plan review, but a minimum setback
of 20 feet is required along the perimeter. If buildings exceed 25 feet in height, the
buildings shall be setback per City ordinance.
10. That specialty lighting be provided throughout the entire development. Said
lighting will be reviewed during the final plat.
11. That the project site contain 48% open space.
12. That a soils report be submitted prior to final plat submittal.
13. That the grading and drainage plan be reviewed by the City Engineering Division.
Measures shall be taken to eliminate significant grade differences at any property
line and fill shall be limited to help with the same.
B. Continuation, in order for the developer to address issues raised during the public hearing.
Discussion: Steve Lehman presented the application. Steve stated that the development
agreement states either a pool or pickleball court is a required amenity, and the
applicant is still thinking about which would be the best addition. Steve explained
that the topography of the subject property would require a modification to the
proposed walking path; however, the trail will still be an added amenity.
Greg Larson, the applicant, said that Steve did a great job with his presentation,
and he has enjoyed working with him. Mr. Larson said that he would answer any
questions that the Commission may have. There were no questions for Mr.
Larson.
Angela, an adjacent homeowner, addressed the Commission. She wanted to know
what type of fence was being proposed because she was worried about possible
noise disturbance. Steve explained that the entrance to the subject property would
have a masonry wall on either side so, that wall will be between the subject
property and her home. Angela asked Steve how close the wall would be to her
house. Steve said the wall would be on the property line. Angela asked if the
fence would be six feet in height. Steve explained that the wall would be three
feet at the front of the access, for twenty feet, to ensure that cars exiting or
entering the site can see pedestrians walking and then rise to six feet. He stated
the rest of the fencing would be a six-foot vinal fence.
Motion: Commissioner Woodruff motioned to approve PUD-3-2021 subject to the thirteen
staff alternatives.
Commissioner Fuller seconded the motion.
Vote: Commissioner Fuller Yes
Commissioner McEwen Yes
Commissioner Lovato Yes
Commissioner Woodruff Yes
Commissioner Wood Yes
Commissioner Winters Yes
Chairperson Meaders Yes
Unanimously – PUD-3-2021 – Approved.
CA-7-21
Malone Powersports Expansion
1331 West 3300 South
M Zone (2.14 Acres total/Exp .86 Acres)
The applicant, Malone Powersports, is requesting a conditional use for expansion of a
recreational vehicle facility at 1331 West 3300 South. This property is zoned M, Manufacturing.
The West Valley City General Plan designates this area as General Commercial. The
surrounding zone is C-2 to the north and east and M to the west and south. The surrounding uses
include Jones Heating to the north, Questar Gas and GHID facilities to the east and south, and an
additional Malone Powersports facility to the west.
This property is located within the Jordan River Overlay Zone (JROZ). The use is considered
“Motorized Outdoor Recreation Equipment” and is currently prohibited in this overlay zone.
However, per 7-14-203, existing businesses may continue and can expand with approval by the
Planning Commission.
This property was originally approved for redevelopment and expansion for Highland Golf in
2019 (C-15-19). This approval included demolition of an existing building on site and
construction of a new building that is currently being built. The 3500 South Streetscape is also
being updated to comply with City Code. The rear portion of the site was to remain gravel for
golf cart storage. At this time Malone Powersports would like to expand further and improve the
south portion of the lot as well. This area will be hard surfaced and used for inventory storage.
Upon approval of the use expansion there will also be some updated plan submittals required.
There will be some modifications to the overall grading and drainage for the site. The internal
design of the building was also modified to remove the second story mezzanine so updated
building plans will be required. The site landscaping has been increased from 9% to 14% (5%
min is required) so updated landscaping plans will also be reviewed.
There is currently a multi-tenant pole sign on the property that was used for Highland Golf and
Plaza Cycle. Both of these uses no longer occupy the site and this is now a single tenant user so
the pole sign will be removed.
There is a canal on the west side of this site that will remain, and no internal connection shall be
provided between this lot and the adjacent Malone Powersports lots. Any unimproved areas shall
be maintained free of weeds.
Staff Alternatives:
Approval, subject to the resolution of any concerns raised at the public hearing as well as the
following:
1. The existing business, Malone Powersports, may expand per the approved plans.
2. An updated landscaping plan must be submitted with a minimum of 5% of
landscaping on site. This includes the 3500 South streetscape improvements set
forth in 7-10.
3. The back storage area must be hard surfaced and maintained free of weeds.
4. There shall be no storage or use on unimproved areas.
5. All customer and employee parking and maneuvering areas must be hard
surfaced.
6. All fencing shall be maintained, and only approved fencing materials shall be
used.
7. Signage shall meet the standards set forth in Title 11 of the WVC Municipal
Code.
8. Any dumpsters provided on site must meet the requirements set forth in 7-2-118.
9. Must meet the requirements of all affected departments and agencies.
10. Subject to review upon valid complaint.
Continuance, to allow for the resolutions of any issues raised at the public hearing.
Discussion: Jody Knapp presented the application. Cal Johnson, the Civil Engineer for this
project, said that they have decided to pave the back of the building as opposed to
adding gravel. Mr. Johnson did not have anything else to add and said he would
answer any questions.
Motion: Commissioner Lovato motioned to approve CA-7-2021 subject to the ten staff
alternatives.
Commissioner Fuller seconded the motion.
Vote: Commissioner Fuller Yes
Commissioner McEwen Yes
Commissioner Lovato Yes
Commissioner Woodruff Yes
Commissioner Wood Yes
Commissioner Winters Yes
Chairperson Meaders Yes
Unanimously – CA-7-2021 – Approved.
C-18-2021
Kim Plaza
1778-1816 West 3600 South
C-2 Zone (1.23 Acres)
The applicant, Greg Steffensen Architect, is requesting conditional use approval for a retail
shopping center building at 1778-1816 West 3600 South. This property is zoned C-2, General
Commercial, and the West Valley City General Plan designates this area as General Commercial.
The adjacent property to the north is zoned A, Agricultural and C2, General Commercial with
the remaining areas C-2. The surrounding uses include auto service and single unit residential
development to the north with similar office/retail uses to the west (Kim Heang Market), a Sonic
restaurant to the east, State Trailer Supply and Ray Hour Chiropractor to the south.
This site is Lots 14-16 of the Plaza 3600 Business Park which was approved by the Planning
Commission in 1998 (C-26-98). Access to the site is gained off of 3600 South, which is a private
road. The original approval specified that each development must be reviewed as a separate
conditional use before the Planning Commission since the tenants were not known at the time of
the overall approval, furthermore this particular use is also listed as a conditional use in the C-2
zone.
The proposed development for the site is a 7-unit multi-tenant building with a mix of retail and
restaurant uses. The proposed building will be approximately 47,465 sq. ft. There shall be no
outside storage. The parking for the site has been calculated for the proposed mix of uses,
including two potential restaurant tenants. The tenant mix and parking counts shall be monitored
as the units are developed to maintain the required parking.
The building will be constructed out of masonry block with a mixture of metal panels, wood
veneer, concrete panels, stucco and metal architectural awnings. The building design must
comply with the Commercial Design Standards. The north side of the building will be partially
visible to the public due to the location of the adjacent residential buildings and a stub street
(Shafer Lane) so staff recommends that the visible portions also comply with the secondary
façade requirements in the Commercial Design Standards.
The landscaping on site must meet the 15% minimum area as required in the C-2 Zone. The
landscape plan indicates 15% has been provided. The landscaping/setbacks along the frontage of
this parcel were approved as part of the original overall shopping center landscaping concept.
This includes a minimum setback for the building of 40’ from the property line, which is the
center of the private road, as well as a 7-foot landscaped setback for the parking to provide an
area for street trees that were originally planted when the roadway was improved. The site will
also have a 5’ strip of landscaping adjacent to the parking lot on the east and west sides and a 10’
wide landscaped area to the north. These areas must all include 50% live plant material and trees.
Since the property is partially adjacent to residential a 6’ tall solid masonry wall is required.
There is an existing unfinished masonry block wall that will be painted/refinished to match the
building. A similar masonry enclosure will also be constructed around the dumpster located on
the site.
A lighting plan has been provided. Staff will work with the applicant to ensure that the site
complies with the standards set forth in the West Valley City Code including the light levels
adjacent to residential uses. The applicant has indicated that the wall mounted lighting on the
north side of the building are security lights so they will not be on at all times and there will be
shields installed to direct the light away from the adjacent property.
Only wall signage is proposed for this site. All signage shall comply with the West Valley City
Sign Ordinance, to include no more than 15% signage on the front building face, and 5% on the
remaining sides, and no more than 50% of the window area shall be covered in signs. A building
permit must be issued for all signage. Ground signage has not been proposed at this time.
Staff Alternatives:
Approval of the conditional use for a shopping center subject to compliance with all of the
City’s zoning ordinances and the following:
1. The landscaping must be completed per the approved site plan and in accordance with
applicable standards in the West Valley City Municipal Code including but not limited to
a minimum 40’ front building setback measured from the front property line and a 7’
wide landscaped area along 3600 West with trees per C-26-98.
2. The building must be designed in accordance with the Commercial Design Standards
which shall include secondary façade treatments on the visible portions of the north side
of the building.
3. There must be adequate parking on site for the proposed tenant mix.
4. A 6’ masonry wall shall be required along all residential zone boundaries. The wall shall
not be unfinished concrete block and must be painted or finished to match the adjacent
building.
5. The dumpster location shall be at least 20’ from any residential boundary and completely
secured with a 6’ tall masonry enclosure.
6. All lighting shall be designed per Title 7 and not negatively impact adjacent residential
uses.
7. All signage must comply with the West Valley City Sign Ordinance.
8. Must meet requirements of all affected departments and agencies and is subject to review
upon valid complaint.
Continuance for reasons determined in the meeting.
Discussion: Jody Knapp presented the application. Jody stated that the north side of the
building adjacent to the residential property would be the secondary façade and
will need to meet those requirements. She said they are proposing to keep as
many of the existing trees as possible, and if they remove any trees, they will
replace them. Jody stated that the security lights on the outside of the building
would not be on all the time, and they would have a shield to direct the light
down, away from the adjacent residential properties.
Commissioner Fuller pointed out that there is a piece of property between the
subject property and Sonic. He asked Jody if she knew of any potential uses for
that lot. Jody said that she believes that Sonic owns the property, and she isn’t
aware of any plans. She said that code enforcement worked to clean it up and
keep it free of parking.
Motion: Commissioner McEwen motioned to approve C-18-2021 subject to the eight staff
alternatives.
Commissioner Winters seconded the motion.
Vote: Commissioner Fuller Yes
Commissioner McEwen Yes
Commissioner Lovato Yes
Commissioner Woodruff Yes
Commissioner Wood Yes
Commissioner Winters Yes
Chairperson Meaders Yes
Unanimously – C-18-2021 – Approved.
PLANNING COMMISSION BUSINESS
Approval of Minutes from July 21, 2021 Study Meeting
Approval of Minutes from July 28, 2021 Regular Meeting
Discussion: Chair Meaders asked to have her name replaced with Commissioner McEwen for
who called the meeting to order on the July 28, 2021 Regular Meeting Minutes.
Motion: Commissioner Fuller moved to approve the minutes for July 21, 2021 and July
28, 2021 subject to the correction by Chair Meaders.
Commissioner Lovato seconded the motion
Vote: Commissioner McEwen Yes
Commissioner Lovato Yes
Commissioner Fuller Yes
Commissioner Woodruff Yes
Commissioner Wood Yes
Commissioner Winters Yes
Chairperson Meaders Yes
Unanimous – Minutes from July 21, 2021 and July 28, 2021 – Approved
There being no further business, the meeting adjourned at 4:36 p.m.
Respectfully submitted,
Kirsten Hunt, Administrative Assistant
Agenda
WEST VALLEY CITY PLANNING COMMISSION AGENDA
9/8/2021 at 4:00 p.m.
The Public Hearing will be held in person in the City Council Chambers at West Valley City Hall 3600 Constitution
Boulevard, West Valley City, UT 84119, and electronically via Zoom at:
https://zoom.us/j/95328405803.
A Study Session will be held a week prior to the Public Hearing on Wednesday at 3:30 p.m. and a Planning Commission Pre-
Meeting will be held the day of the Public Hearing at 3:30 p.m.
Preliminary application information will be available here by 6:00 pm on Monday, August 30, 2021. Staff analyses, as well as
any final application materials, will be available by 12:00 pm on Tuesday, September 7, 2021.
Testimonies for or against the proposed applications can be provided to the Planning Commission during the public hearing or
in writing prior to the hearing. If you wish to submit written comments, please be advised that this should be provided to the
Planning Staff member assigned to the application at least seven (7) days prior to the meeting to enable the Planning
Commission to properly consider the comments.
___Fuller ___Lovato ___McEwen ___Meaders ___Porter ___Winters ___Wood ___Woodruff
SUBDIVISION APPLICATIONS
SMI-5-2021 Petition by MARK GARZA is requesting preliminary approval for the Crewe 2 Lot Subdivision.
The subdivision will consist of 2 lots on .42 acres. The subdivision is located at approximately 3588
South 5450 West and is zoned R-1-8 (Single Unit Dwelling Residential, minimum lot size 8,000 square
feet). (Staff – Steve Lehman at 801-963-3311 or steve.lehman@wvc-ut.gov)
PUD-3-2021 Petition by GREG LARSEN is requesting preliminary approval for the Cottages at Pearce Farm
PUD. The subdivision will consist of 65 units on 10 acres. The subdivision is located at approximately
6765 West 3500 South and is zoned RM (Multiple Unit Dwelling Residential). (Staff – Steve Lehman
at 801-963-3311 or steve.lehman@wvc-ut.gov)
CONDITIONAL USE APPLICATIONS
CA-7-2021 Petition by ROYAL SOLUTIONS, LLC requesting a conditional use amendment for an expansion
at Highland Golf. The property is located at 1331 W. 3300 S. on .86 acres and is zoned M
(Manufacturing). (Staff – Jody Knapp at 801-963-3497 or jody.knapp@wvc-ut.gov)
C-18-2021 Petition by GREG STEFFENSEN, ARCHITECT requesting a conditional use for a shopping center.
The property is located at 1778-1816 W. 3600 S. on 1.23 acres and is zoned C2 (General Commercial).
(Staff – Jody Knapp at 801-963-3497 or jody.knapp@wvc-ut.gov)
PLANNING COMMISSION BUSINESS
Approval of Minutes from July 21, 2021 Study Meeting
Approval of Minutes from July 28, 2021 Regular Meeting
West Valley City does not discriminate on the basis of race, color, national origin, sex, religion, age, sexual orientation or disability in employment or the provision of services. If you are planning to
attend this public meeting and, due to a disability, need assistance in understanding or participating in the meeting, please notify the City eight or more hours in advance of the meeting. We will try
to provide whatever assistance may be required. The person to contact for assistance is Kirsten Hunt, 801-963-3282.
Get email alerts for West Valley City
A daily email when new agendas and minutes are posted.