Mayor & Common Council Meetings
Regular MeetingWestminster, MD · August 11, 2025
Agenda
AGENDA
CITY OF WESTMINSTER
Mayor and Common Council Meeting
Monday, August 11, 2025, at 7:00 pm
City Hall, 1838 Emerald Hill Lane, Westminster, MD 21157
City YouTube Channel Link
1. CALL TO ORDER
2. PRESENTATION
A) Update on 250th Anniversary – City of Westminster Historic District Commission
3. STATEMENT FOR THE RECORD – CLOSED MEETING OF MONDAY, JULY 28, 2025:
In accordance with the General Provisions Article, Section 3-306(c)(2) of the Annotated Code of
Maryland, and without objection it is noted that the minutes of tonight’s meeting reflect that Common
Council met in a Closed Meeting on Monday, July 28, 2025, at 6:02 p.m. pursuant to General
Provision Art., Section 3-305 (b)(10) to discuss public security, if the public body determines that
public discussion would constitute a risk to the public or to public security, including: (i) the
deployment of fire and police services and staff; and (ii) the development and implementation of
emergency plans.
Motion –Dayhoff/Gilbert
Vote to Close Meeting:
Yes No Abstain Absent
Mr. Chiavacci
Mr. Dayhoff Yes
Ms. Gilbert Yes
Mr. Hoff
Mr. Pecoraro Yes
Mayor Becker
Note for the Record: Council President Chiavacci and Councilmember Hoff were absent.
Other attendees: City Clerk Barber, Director of Human Resources Brown, Director of Housing
Services Brown, Director of Community Planning and Development Depo, City Administrator
Imhulse, Chief of Police Ledwell, Director of Technology Services Moore, Director of Finance
Rodgers, and Sgt. Laser. The Common Council took no official action during the meeting. The
Closed Meeting adjourned at 6:55 p.m.
4. APPROVAL OF MINUTES
A) Mayor and Common Council Meeting Minutes of July 28, 2025
B) Mayor and Common Council Closed Meeting Minutes of July 28, 2025
5. CONSENT CALENDAR
A) Approval to Waive the Competitive Procurement for Good Cause, under the City of
Westminster Code Chapter 36 “Procurement and Contracts’ Section 36-4 Specific Regulations
and Authorize the Purchase of a 2026 Ford from Apple Ford in the Total Amount of
$84,998.30
B) Approval of Sole Source Agreement with Funk & Bolton P.A.
C) Approval of GHD Change Order No. 9 with GHD for Additional Construction Management,
Inspection, and Testing Services for Westminster ENR Project in the Amount of $100,000
D) Approval of GHD Change Order No. 19 with GHD for Additional Construction Phase
Engineering Services for Westminster ENR Project in the Amount of $30,000
6. REPORT FROM THE MAYOR
7. REPORTS FROM COMMITTEES
A) Arts Council
B) Economic and Community Development Committee
C) Finance Committee
D) Personnel Committee
E) Public Safety Committee
F) Public Works Committee
G) Recreation and Parks Committee
H) Technology Committee
I) Intergovernmental Relations Committee
8. COUNCIL COMMENTS AND DISCUSSION
9. ORDINANCE AND RESOLUTIONS
A) Adoption of Ordinance 2025-08 an Ordinance of the Mayor and Common Council of
Westminster, Amending Chapter A175, “Fees”, Article I, “Utility Fees”, Section A175-1, “Utility
Fees, Charges and Costs Adopted; Utility Fee Schedule Established”, of the City Code, to
Increase the Fees for Water Meters to Reflect Increases in the City’s Costs Since the Last Fee
Adjustment. – City Administrator Imhulse
10. UNFINISHED BUSINESS
11. NEW BUSINESS
12. DEPARTMENTAL REPORTS
13. CITIZEN COMMENTS
14. ADJOURNMENT
MINUTES
CITY OF WESTMINSTER
Mayor and Common Council Meeting
Monday, July 28, 2025, at 6:00 p.m.
City Hall, 1838 Emerald Hill Lane, Westminster, MD 21157
YouTube Channel Link
CALL TO ORDER
Elected Officials Present: Mayor Becker, Councilmember Dayhoff, Councilmember Gilbert, and
Council President Pro Tem Pecoraro. Councilmember Hoff was absent.
Staff Present: City Clerk Barber, Director of Human Resources Brown, Director of Housing Services
Brown, Director of Community Planning and Development Depo, City Administrator Imhulse, Chief of
Police Ledwell, Director of Technology Services Moore, and Director of Finance Rodgers.
CLOSED MEEITNG
A motion was made by Councilmember Dayhoff and seconded by Councilmember Gilbert to adjourn
into a Closed Meeting on Monday, July 28, 2025, in accordance with the General Provisions Article of
the Annotated Code of Maryland, §3-305 (b)(10) to discuss public security, if the public body determines
that public discussion would constitute a risk to the public or to public security, including: (i) the
deployment of fire and police services and staff; and (ii) the development and implementation of
emergency plans.
VOTE
AYES: Councilmember Dayhoff, Councilmember Gilbert, and Council Pro Tem Pecoraro.
NAYS: None.
Note for the Record: The Mayor and Common Council went into a Closed Meeting at 6:02 p.m.
Note for the Record: The Mayor and Common Council returned in Open Session from the Closed
Meeting at 6:55 p.m.
Council President Chiavacci and City Attorney Whitworth arrived at 7:00 p.m.
PLEDGE OF ALLEGIANCE AND MOMENT OF SILENCE
Council President Chiavacci led the Pledge of Allegiance and a moment of silence.
PUBLIC HEARINGS
Annexation Resolution No. 25-06 (Annexation No. 87)
Mayor Becker conducted a public hearing beginning at 7:04 p.m., regarding Annexation 87, 1012
BWMD LLC Petition for Annexation: Annexation Resolution No. 25-06; Petition for Annexation to
Enlarging the Corporate Boundaries of the City of Westminster by Annexing into the City Certain
Property Containing ± 1.2 acres, Contiguous and Adjoining to the City’s Existing Corporate Boundaries,
Consisting of Real Property Located at 1012 Baltimore Boulevard, Westminster, Maryland 21157, Also
Identified as Tax Account Number 07-029748, Map 0046, Grid 0016, Parcel 0616. Mayor Becker noted
that the Public Hearing had been published in the Carroll County Times, meeting all applicable
requirements. Director of Community Planning and Development Depo at the direction of Mayor Becker
provided the staff report on the item. There was no one wishing to address the Common Council during
the hearing.
1
With no further comments, Mayor Becker closed the public hearing at 7:08 p.m.
Ordinance No. 2025-01, Automobile Uses Text Amendment
Mayor Becker conducted a public hearing beginning at 7:08 p.m., regarding Ordinance No. 2025-01,
Automobile Uses Text Amendment, an Ordinance of the Mayor and Common Council of Westminster,
Amending Chapter 164, “Zoning and Subdivision of Land”, of the Code of the City of Westminster, §
164-3 “Definitions and Word Usage” to add the definitions of “Automobile Detailing Shop”, “Automobile
Repair and Service Shop, Major”, “Automobile Repair and Service Shop, Minor”, and “Automobile
Sales”, and to replace the term “Service Station” with “Automobile Service Station”; to amend §164-121
“On-Premises Business Signs” and Article XX “Special Provisions,” § 164-149 “Automobile Service
Stations,” as well as the permitted uses and/or special exception uses in the Mixed Use Infill Zone(§
164-39.2), B Business Zone (§ 164-41 and § 164-42), D-B Downtown Business Zone, (§ 164-45.8 and
§ 164-45.9), (I-R Restricted Industrial Zone, (§ 164-54), I-G General Industrial Zone, (§ 164-61 and §
164-62), N-C Neighborhood Commercial Zone (§ 164-64.2), P-I Planned Industrial Zone (§ 164-66 and
§ 164-75) and PRSC Planned Regional Shopping Center Zone (§ 164-100 and § 164-101), to reflect
the newly defined uses. Mayor Becker noted that the Public Hearing had been published in the Carroll
County Times, meeting all applicable requirements. Director of Community Planning and Development
Depo at the direction of Mayor Becker provided the staff report on the item. The following spoke and
addressed the Common Council during the hearing:
Attorney Kelly Shaffer Miller, with Shaffer, Miller, & Hurff, LLP, 73 East Main Street, addressed the
Common Council representing Carroll Commerce Center, and stated her points of concern along with
her suggested amendments to the proposed legislation (Ordinance 2025-01).
Mr. Brian Ditto, Carroll Commerce Center, 69-715 Corporate Center Drive, stated his points of concern
to the proposed legislation (Ordinance 2025-01).
With no further comments, Mayor Becker closed the public hearing at 7:42 p.m.
APPROVAL OF MINUTES
A motion was made by Councilmember Dayhoff and seconded by Councilmember Gilbert to approve
the Mayor and Common Council Meeting Minutes of July 14, 2025, the Mayor and the Common Council
Work Session Meeting Minutes of July 14, 2025. There was no discussion.
VOTE
AYES: Councilmember Dayhoff, Councilmember Gilbert, and Councilmember Pecoraro.
NAYS: None.
CONSENT CALENDAR
A motion was made by Councilmember Pecoraro and seconded by Councilmember Gilber to approve
the Consent Calendar, which consisted of the following: Approval of Departmental Operating Report –
June 2025; approval of Change Order # 3 to Guyer Brothers Inc., for the Pump Station 6 Collection
System (I&I) in the amount of $50,286.50; and approval to waive the Competitive Procurement for Good
Cause, under the City of Westminster Code Chapter 36 “Procurement and Contracts” Subsection 36-4
Specific Regulations and to authorize the purchase of a Trackless Infrared Asphalt Heater with
Generator from US Municipal Supply LLC., in the total amount of $43,627.62.
VOTE
AYES: Councilmember Dayhoff, Councilmember Gilbert, and Councilmember Pecoraro.
NAYS: None.
2
REPORT FROM THE MAYOR
Mayor Becker noted that on Tuesday, July 15, 2025, she spent some time with Mr. Robin Summerfield
from Senator Chris Van Hollen’s Office and Ms. Delanie Blubaugh from Senator Alsobrooks’s Office
with a walking tour around the City of Westminster.
REPORTS FROM COMMITTEES
Council President Chiavacci, on behalf of the Public Safety Committee, reported that during the week
of July 14-18, 2005, Sgt. Dellospedale and Officer Hara participated in the annual Camp Cops Youth
Outreach event. Council President Chiavacci also noted that on July 24, 2025, Lt. Rife was recognized
by our local High’s Store with their Hometown Hero Award as a community partner who exemplifies
exceptional service and dedication for his unwavering commitment to making a positive impact in our
community. Council President Chiavacci closed his report by noting that on July 25, 2025, Detective
Hinds received the designation of Police Officer First Class or “PFC” for successfully completing the
probationary period at the Westminster Police Department (WPD) and for performing in a manner that
supports the agency’s mission.
COUNCIL COMMENTS AND DISCUSSION
Councilmember Dayhoff noted his attendance at the Westminster Pride Festival held on Saturday, July
26, 2025, held at City Park in Westminster.
BIDS
Approval of Award to EARN Contractors Inc., for Exterior Painting at the Cranberry Water
Treatment Plant in the amount of $ 82,100.00.
A motion was made by Councilmember Pecoraro and seconded by Councilmember Dayhoff to approve
the award of bid to EARN Contractors Inc., for the exterior painting at the Cranberry Water Treatment
Plant in the amount of $ 82,100.00. City Administrator Imhulse provided the staff report on the item.
There was no discussion.
VOTE
AYES: Councilmember Dayhoff, Councilmember Gilbert, and Councilmember Pecoraro.
NAYS: None.
ORDINANCE AND RESOLUTIONS
Adoption of Annexation Resolution No. 25-07, an Annexation Plan for Annexation 87 for Certain
Property Containing ± 1.2 acres, Contiguous and Adjoining to the City’s Existing Corporate
Boundaries, Consisting of Real Property Located at 1012 Baltimore Boulevard, Westminster,
Maryland 21157, Consisting of Real Property Identified as Tax Account Number 07-029748, Map
0046, Grid 0016, Parcel 0616, which Property is the Subject of a Petition for Annexation
Submitted by the Owners of the Subject Property to the Mayor and Common Council of
Westminster
A motion was made by Councilmember Gilbert and seconded by Councilmember Dayhoff to adopt
Annexation Resolution No. 25-07, an Annexation Plan for Annexation 87 for Certain Property
Containing ± 1.2 acres, Contiguous and Adjoining to the City’s Existing Corporate Boundaries,
Consisting of Real Property Located at 1012 Baltimore Boulevard, Westminster, Maryland 21157,
Consisting of Real Property Identified as Tax Account Number 07-029748, Map 0046, Grid 0016, Parcel
0616, which Property is the Subject of a Petition for Annexation Submitted by the Owners of the Subject
Property to the Mayor and Common Council of Westminster. Director of Community Planning and
Development Depo provided the staff report on the item. There was no discussion.
3
VOTE
AYES: Councilmember Dayhoff, Councilmember Gilbert, and Councilmember Pecoraro.
NAYS: None.
Adoption of Annexation Resolution No. 25-06 (Annexation 87), Enlarging the Corporate
Boundaries of the City of Westminster by Annexing into the City Certain Property Containing ±
1.2 Acres, Contiguous and Adjoining to the City’s Existing Corporate Boundaries, Consisting of
Real Property Located at 1012 Baltimore Boulevard, Westminster, Maryland 21157, Also
Identified as Tax Account Number 07-029748, Map 0046, Grid 0016, Parcel 0616
A motion was made by Councilmember Dayhoff and seconded by Councilmember Pecoraro to adopt
Annexation Resolution No. 25-06 (Annexation 87), enlarging the corporate boundaries of the City of
Westminster by annexing into the City certain property containing ± 1.2 acres, contiguous and adjoining
to the City’s existing corporate boundaries, consisting of real property located at 1012 Baltimore
Boulevard, Westminster, Maryland 21157, also identified as Tax Account Number 07-029748, Map
0046, Grid 0016, Parcel 0616. Director of Community Planning and Development Depo provided the
staff report on the item. There was no discussion.
VOTE
AYES: Councilmember Dayhoff, Councilmember Gilbert, and Councilmember Pecoraro.
NAYS: None.
UNFINISHED BUSINESS
There was no unfinished business to be discussed by the Mayor and Common Council.
NEW BUSINESS
There was no new business to be discussed by the Mayor and Common Council.
DEPARTMENTAL REPORTS
Department of Public Works
City Administrator Imhulse provided an update on the ongoing night road paving in the City.
Technology Services
Director Moore noted several projects the department has been handling.
Community Planning and Development
Director of Community Planning and Development reported the following:
On July 17, 2025, the Planning and Zoning Commission:
• Held a public hearing for Annexation Resolution 25-06, approving Annexation 87 and
Annexation Plan for Annexation 87. The Commission forwarded Annexation Resolution 25-06
to the Mayor and Common Council with a favorable recommendation, as introduced; The Board
of Zoning Appeals July 1, 2025, meeting was cancelled as there were no applications to come
before the Board.
• Held a public hearing for Ordinance No. 2025-01, Automobile Uses Text Amendment. The
Commission forwarded Ordinance No. 2025-01 to the Mayor and Common Council with a
favorable recommendation, as amended.
• Approved Sign Permit 1988, for David Ross Orthodontics at 255 Baltimore Boulevard allowing
a sign that is greater than 64 square feet and up to but not exceeding 125 square feet.
• Heard a presentation regarding the Carroll County Water Resource Element.
4
On August 5, 2025, the Board of Zoning Appeals is scheduled to hear BZA Case No. 25-04, an
application by Modular Genius, Inc., appealing May 21, 2025, Zoning Determination ZDET 25-04 made
by the Zoning Administrator concerning outdoor storage as a permitted use in the Meadow Branch
Industrial Park on Lot 2C.
Finance
Director of Finance Rodger provided a status update on the preliminary work of the FY25 Audit.
Westminster Police Department (WPD)
Chief of Police Ledwell provided updates on the work of the department.
CITIZEN COMMENTS
Ms. Lyndi McNulty, 195 West Main Street, addressed the Common Council with praise of the newly
renovated Wakefield Valley Park Pavilion and Event Center noting that it will be a great venue for the
City of Westminster.
ADJOURNMENT
Council President Chiavacci announced that the next meeting of the Mayor and Common Council would
be held on Monday, August 11, 2025, at 7:00 p.m. He adjourned the meeting at 8:07 p.m.
Respectfully Submitted,
Douglass A. Barber, MMC
City Clerk
Full audio version is available on www.westminstermd.gov
Adopted by the City of Westminster Common Council on _____________________________.
5
Purchase of a Replacement Ford Pickup Truck
To: Mayor and Common Council
From: Cory Stouffer, Superintendent of the Utility Maintenance Department
Date: July 22, 2025
Re: Approval to Waiver of Competitive Procurement for Good Cause, under the City of Westminster
Code Chapter 36 “Procurement and Contracts” § 36-4 Specific Regulations and Authorize the
Purchase of a 2026 Ford Pickup truck from Apple Ford, in the total amount of $84,998.30
Background
The City’s adopted FY26 capital budget allocates funding for the replacement of trucks and equipment.
This proposed purchase is for a replacement pickup truck.
The requested vehicle is available via an existing contract between Baltimore County (#0004504) and
Apple Ford, located at 8800 Stanford Blvd. Columbia MD. Westminster’s procurement code allows the
City to piggyback on this competitively awarded contract.
The vehicle being purchased is a 2026 replacement pickup truck from Ford. Further information is
provided in the attached specification sheet. The cost of the unit is $84,998.30 inclusive of all selected
options.
Project Funding
The FY26 budget for this project is $85,000.00.
Recommendation
Staff recommends that the Mayor and Common Council waive the Competitive Procurement for Good
Cause, under the City of Westminster Code Chapter 36, “Procurement and Contracts” § 36-4 Specific
Regulations, and to authorize the purchase of a 2026 Ford pickup truck from Apple Ford, in the total
amount of $84,998.30
Attachment
• Quotes, Specification Sheet for a 2026 Ford pickup
cc: Sara Imhulse, City Administrator
FY26 CIP Budget – Purchase of Replacement Pickup Truck
for Utility Maintenance Department
Department
To: Mayor and Common Council
From: Theresa M. Rodgers, Director of Finance
Date: August 11, 2025
Re: Funding for Pickup Truck for Utility Maintenance Department
Background
As part of the FY26 Capital Improvement Plan (CIP), the Mayor and Common Council authorized $85,000.00
for a replacement pickup truck for the Utility Maintenance Department. The funding source for the purchase
is 50% sewer fund reserves and 50% water fund reserves.
Apple Ford has provided a quote for a 2026 Ford F-350 for 84,998.30. If this purchase is approved by the
Mayor and Common Council, it will be fully appropriated in the FY26 CIP.
cc: Sara Imhulse, City Administrator
Fleet/Government Sales
8800 Stanford Blvd. Columbia, MD 21045
07/22/25
Westminster
Quote for 2026 Ford F-350 Extended Cab 4x4 8FT Chassis riding the Baltimore County Contract #0004504.
Vehicle 2026 Ford F-350 Extended Cab 4x4 8FT Chassis $57,626.30
** 610A-XL TRIM ***
Power Locks, Doors, Windows, Bluetooth, Backup Camera,
Power Mirrors
99A 6.8L V8 Gas Engine
44G 10 Speed Auto Trans
X3E 3.73 E-Locking Rear
18B Platform Running Boards
473 Snowplow Prep Package
52B Trailer Brake Controller
66S Upfitter Switches
86M Dual Batteries
153 Front Tag Bracket
IBQ Intercon Body Quote $28,372.00
SL Spray In Bed Liner $1,350.00
BCCD Baltimore County Contract Discount ($1,350.00)
GPC Ford Price Concession ($1,000.00)
Color Oxford White
Interior 40/20/40 Vinal
Delivery Days 200 Days ARO
Net Price Per Unit: $84,998.30
Please contact me with any questions, changes, or to finalize your order. I look forward to hearing from
you. You can reach me at 443-539-1223 or by e-mail at: Jskipper@AppleFord.com.
Thank you,
Justin Skipper
Approval of Sole Source Agreement with Funk & Bolton P.A.
To: Mayor and Common Council
From: Sara Imhulse, City Administrator
Date: August 4, 2025
Re: Approval of Sole Source Agreement with Funk & Bolton P.A.
Background
The City has contracted with Funk & Bolton P.A. to provide government-relations services at the State
level since FY23. This relationship has proven fruitful, and staff is recommending the continuation of this
service.
The FY25 contract expired in June. Funk & Bolton P.A. has suggested a fixed monthly fee arrangement
of $4,583.33 for 12 months of service, for a total contract amount of $54,999.96.
Recommendation
Staff recommends the Common Council to approve a Sole Source contract with Funk & Bolton P.A. in the
amount of $54,999.96 for
government relations services.
Consent Calendar – GHD Change Order #9
To: Mayor and Common Council
From: Vance Summerhill
Date: August 6, 2025
Re: Approval of Change Order #9 with GHD in the amount of $100,000 for additional construction
management, inspection, and testing services for Westminster ENR project.
Background
The original ENR project scope with GHD for construction management outlined a substantial completion date
of 6-26-22 (1,266 days) and a final completion date of 9-24-22 (1,356 days). Unfortunately, the contractor,
HRI, has delayed the project significantly. A reasonable estimate is that the contractor, HRI, is still several
months away from reaching Substantial and Final completion.
The City has exhausted funds from Change Order #8 in the contract with GHD because of this delay from HRI.
Change Order #8 was based on HRI’s anticipated Substantial completion date of December 14,2024 and Final
completion date of March 10, 2025. Therefore, it is necessary to adjust the contract and increase funding for
additional construction management, inspection, and testing services. If those dates are further delayed, the
City may need to consider another change order.
Project Funding
Funds have been exceeded for this project and will require a budget amendment in the future. The budget
amendment will reallocate funds likely from sewer fund reserves. Additionally, we have notified HRI that we
intend to pursue liquidated damages.
Recommendation
Staff recommend that the Mayor and Common Council approve Change Order #8 with GHD in the amount of
$100,000 for additional construction management, inspection, and testing services for Westminster ENR
project.
Attachment
• Proposed Change Order #9 and associated supporting documentation.
cc: Sara Imhulse, City Administrator
Theresa Rodgers, Director of Finance
FY26 CIP Budget – ENR Project, GHD CO #9
To: Mayor and Common Council
From: Theresa M. Rodgers, Director of Finance
Date: August 11, 2025
Re: Funding for ENR Project, GHD Change Order (CO) #9 for Additional Construction Management,
Inspection and Testing Services
Background
As part of the FY26 Capital Improvement Plan (CIP), the Mayor and Common Council authorized funds to
complete the WWTP ENR project. The completion of the project will be delayed longer than anticipated,
resulting in GHD CO #9 for $100,000.00 for additional construction management, inspection, and testing
services. This CO was not anticipated during the CIP budget process and will therefore require a FY26 budget
amendment if the CO is approved by the Mayor and Common Council. The funding source for GHD CO #9 will
be sewer fund reserves.
cc: Sara Imhulse, City Administrator
CHANGE ORDER
Change Order No. ______9__________________ Date: ______8/4/2025________
Agreement Date: ___December 20, 2018____________________________
Contractor For: ___Construction Management, Inspection and Testing Services for
Westminster WWTP ENR and Biosolids Upgrade Contract No. ____S-08-04_____________
Owner: Mayor and Common Council of Westminster_________________________________
You are hereby instructed, subject to the provision of the above named contract, to make
the following changes:
and to add/subtract to the contract, in accordance with the contract, the sum of _one hundred
twenty thousand ________________ Dollars ($_100,000______).
Amount of original contract $_3,957,752________ Total Additions $__3,332,676___________
Total Deductions $_________________ Total Revised Contract $__7,290,428__________
The Contract Time will be (increased) (decreased) by _____90_____ calendar days.
The date for completion of work will be continuous until the end of the construction contract.
ATTEST:
BY:___GHD Inc.___________________
ACCEPTED:
DATE: ____8/4/2025_______________
The Mayor and
Common Council of Westminster
Owner ACCEPTED:
By: _______________________
Dr. Mona Becker, Mayor __ ______
Contractor
Date: ________________________
________________________
Address
16701 Melford Boulevard, Suite 221
Bowie, Maryland 20715
United States
www.ghd.com
Our ref: 8614921
August 04, 2025
Mr. Mike Matov
City Of Westminster
Department of Planning and Public Works
45 W Main Street
Westminster MD 2157
Amendment No. 9 - Additional Construction Management, Inspection and Materials Testing Services
Westminster WWTP ENR and Biosolids Upgrade
Dear Mr. Matov
GHD is pleased to submit this proposal for additional services associated with the Westminster WWTP ENR
and Biosolids Upgrade Project. The following is a detailed description of the proposed scope of services and
estimates that are anticipated for the remaining duration of the contract:
1. Construction Management and Inspection
GHD’s original scope of work for construction management and inspection services was executed in an
agreement dated 12/20/18 titled “Construction Management, Inspection and Testing Services for Westminster
WWTP ENR and Biosolids Upgrade”. The original construction contract was 1,266 days (6/26/22) to
Substantial Completion and 1,356 days (9/24/22) to Final Completion. These services were extended several
times by the City to account for delays in completing the project.
In May 2025, the City executed Amendment No. 8 to extend GHD’s construction management/inspection
services beyond April 2025 with the expectation that the $120,000 budget would be sufficient to completion of
the project. The Contractor has not achieved Substantial Completion to date and are expected to be on-site for
a minimum of the next 3 months. Since the budget associated with Amendment No. 8 was fully exhausted
during the month of July, an additional amendment is necessary to extend CM/I services.
As with Amendment No. 8 construction management and inspection services will be billed on an hourly and
expense basis in accordance with the table below. While we cannot estimate with accuracy the total cost of the
future services necessary to support the City for the remaining portions of the project, GHD’s reasonable
estimate of what may be required is $100,000. The actual effort may be more or less than this, but GHD will
invoice the City based on actual effort with the bill rates included in this proposal below. These bill rates are
reflective of the new fiscal year starting in July. Should actual effort exceed this projection, for reasons such as
further delay by the General Contractor, then an additional amendment in the future may be necessary. In
summary, GHD recommends basing Amendment No. 9 for an additional budget allotment for a value of
$100,000.
The Power of Commitment
GHD
Labor Category Base Rate
Principal $270.00
Construction Manager $245.00
Senior Electrical Engineer $245.00
Senior Process Engineer $260.00
Structural Engineer $225.00
Sr Project Manager $225.00
Project Manager $210.00
Architect $185.00
Electrical Engineer $175.00
Process Engineer $165.00
Staff Engineer $150.00
CAD Manager $150.00
Designer $110.00
Admin Assistant $95.00
Intern/Co-op $80.00
Sr RPR $155.00
RPR $120.00
Costs
GHD proposes to complete the remaining scope of work on an hourly and expense basis. The additional
budget requested is estimated as follows:
1. Additional Construction Management and Inspection $ 100,000
TOTAL CHANGE ORDER VALUE $ 100,000
Please advise if the City would like to further discuss.
Regards
Vincent Maillard
Principal
+1 240 206-6826
vincent.maillard@ghd.com
8614921 | Amendment No. 9 - Additional Construction Management, Inspection and Materials Testing Services Westminster WWTP ENR and Biosolids Upgrade
2
Consent Calendar – GHD Change Order #19
To: Mayor and Common Council
From: Vance Summerhill
Date: August 6, 2025
Re: Approval of Change Order 19 with GHD in the amount of $30,000 for additional construction phase
engineering services for Westminster ENR project.
Background
The original ENR project scope with GHD for engineering outlined a substantial completion date of 6-26-22
(1,266 days) and a final completion date of 9-24-22 (1,356 days). Unfortunately, the contractor, HRI, has delayed
the project significantly. A reasonable estimate is that the contractor, HRI, is still several months away from
reaching Substantial and Final completion.
The City has exhausted funds from Change Order #18 in the contract with GHD because of this delay from HRI.
Change Order #18 was based on HRI’s anticipated Substantial completion date of December 14,2024 and Final
completion date of March 10, 2025. Therefore, it is necessary to adjust the contract and increase funding for
additional construction phase engineering services. Should the project be further delayed past, the City may
need to consider another change order.
Project Funding
Funds have been exceeded for this project and will require a budget amendment in the future. The budget
amendment will reallocate funds likely from sewer fund reserves. Additionally, we have notified HRI that we
intend to pursue liquidated damages.
Recommendation
Staff recommends that the Mayor and Common Council approve Change Order 19 with GHD in the amount of
$30,000 for additional construction phase engineering services for Westminster ENR project.
Attachment
• Proposed Change Order No. 18 and associated supporting documentation.
cc: Sara Imhulse, City Administrator
Theresa Rodgers, Director of Finance
FY26 CIP Budget – ENR Project, GHD CO #19
To: Mayor and Common Council
From: Theresa M. Rodgers, Director of Finance
Date: August 11, 2025
Re: Funding for ENR Project, GHD Change Order (CO) #19 for Additional Construction Phase Engineering
Services
Background
As part of the FY26 Capital Improvement Plan (CIP), the Mayor and Common Council authorized funds to
complete the WWTP ENR project. The completion of the project will be delayed longer than anticipated,
resulting in GHD CO #19 for $30,000.00 for additional construction phase engineering services. This CO was
not anticipated during the CIP budget process and will therefore require a FY26 budget amendment if the CO
is approved by the Mayor and Common Council. The funding source for GHD CO #19 will be sewer fund
reserves.
cc: Sara Imhulse, City Administrator
CHANGE ORDER
Change Order No. ______19__________________ Date: ______8/4/2025________
Agreement Date: ___December 20, 2018____________________________
Contractor For: ___Construction Phase Engineering Services for Westminster WWTP ENR
and Biosolids Upgrade Contract No. ____S-08-04_________________
Owner: Mayor and Common Council of Westminster_________________________________
You are hereby instructed, subject to the provision of the above named contract, to make the
following changes:
and to add/subtract to the contract, in accordance with the contract, the sum of _fifty
thousand________________________________________ Dollars ($_30,000______).
Amount of original contract $_18,719.04________ Total Additions $__7,015,442.91________
Total Deductions $_________________ Total Revised Contract $__7,034,160.95_________
The Contract Time will be (increased) (decreased) by _____90_____ calendar days.
The date for completion of work will be _continuous until the end of the construction contract__.
ATTEST:
_________________
BY:___GHD Inc.___________________
ACCEPTED:
DATE: ____8/4/2025______________
The Mayor and
Common Council of Westminster
Owner ACCEPTED:
By: _______________________
Dr. Mona Becker, Mayor __
_______________________________
Contractor
Date: ________________________
________________________
Address
16701 Melford Boulevard, Suite 221
Bowie, Maryland 20715
United States
www.ghd.com
Our ref: 8614921
August 04, 2025
Mr. Mike Matov
City Of Westminster
Department of Planning and Public Works
45 W Main Street
Westminster MD 21157
Amendment No. 19 - Additional Construction Phase Engineering Services Westminster WWTP ENR and
Biosolids Upgrade
Dear Mr. Matov
GHD’s original scope of work for construction phase engineering services was amended in November of 2018
via Amendment No. 11 to reflect the anticipated scope of work and duration of the Westminster WWTP ENR
and Biosolids Upgrade construction contract. The original construction contract was 1,266 days (6/26/22) to
Substantial Completion and 1,356 days (9/24/22) to Final Completion. These services were extended several
times by the City to account for delays in completing the project.
In May 2025, the City executed Amendment No. 18 to extend GHD’s construction engineering services beyond
April 2025 with the expectation that the $50,000 budget would be sufficient to completion of the project. The
Contractor has not achieved Substantial Completion to date and are expected to be on-site for a minimum of
the next 3 months. The budget associated with Amendment No. 18 is expected to be fully exhausted by the
end of August, so an additional amendment is necessary to extend construction engineering services.
As with Amendment No. 18 construction engineering services will be billed on an hourly and expense basis in
accordance with the table below. While we cannot estimate with accuracy the total cost of the future services
necessary to support the City for the remaining portions of the project, GHD’s reasonable estimate of what may
be required is $30,000.
The actual effort may be more or less than this, but GHD will invoice the City based on actual effort with the bill
rates included in this proposal below. These bill rates are unchanged from the previous executed amendment.
Should actual effort exceed this projection, for reasons such as further delay by the General Contractor and/or
inability to successfully complete startup and commissioning, then an additional amendment in the future may
be necessary. In summary, GHD recommends basing Amendment No. 19 for an additional budget allotment for
a value of $30,000.
The Power of Commitment
GHD
Labor Category Base Rate
Principal $270.00
Construction Manager $245.00
Senior Electrical Engineer $245.00
Senior Process Engineer $260.00
Structural Engineer $225.00
Sr Project Manager $225.00
Project Manager $210.00
Architect $185.00
Electrical Engineer $175.00
Process Engineer $165.00
Staff Engineer $150.00
CAD Manager $150.00
Designer $110.00
Admin Assistant $95.00
Intern/Co-op $80.00
Sr RPR $155.00
RPR $120.00
Please advise if the City would like to further discuss.
Regards
Vincent Maillard
Principal
+1 240 206-6826
vincent.maillard@ghd.com
8614921 | Amendment No. 19 - Additional Construction Phase Engineering Services Westminster WWTP ENR and Biosolids Upgrade 2
Ordinance No. 2025-08 - Adoption
To: Mayor and Common Council
From: Sara Imhulse, City Administrator
Meeting Date: August 7, 2025
Re: Adoption of Ordinance 2025-08, an Ordinance of the Mayor and Common
Council of Westminster, amending Chapter A175, “Fees”, Article I, “Utility Fees”,
Section A175-1, “Utility Fees, Charges and Costs Adopted; Utility Fee Schedule
Established”, of the City Code, to Increase the Fees for Water Meters to Reflect
Increases in the City’s Costs Since the Last Fee Adjustment
BACKGROUND
Fees for water meters were last reviewed and amended by Mayor and Common Council in 2008. The
current cost of the water meters exceeds the amount in the Code, which means that the City is
currently subsidizing certain water meters. Ordinance 2025-08 amends the Code to reflect current
pricing.
RECOMMENDATION
Staff recommends that Mayor and Common Council adopt Ordinance 2025-08.
Sponsored by: Dr. Mona Becker, Mayor
Tony Chiavacci, Council President
ORDINANCE NO. 2025-08
AN ORDINANCE OF THE MAYOR AND COMMON COUNCIL OF WESTMINSTER,
AMENDING CHAPTER A175, “FEES,” ARTICLE I, “UTILITY FEES,”
SECTION A175-1. “ UTILITY FEES, CHARGES AND COSTS
ADOPTED; UTILITY FEE SCHEDULE ESTABLISHED,” OF THE CITY
CODE, TO INCREASE THE FEES FOR WATER METERS TO REFLECT
INCREASES IN THE CITY’S COSTS SINCE THE LAST FEE
ADJUSTMENT.
WHEREAS, pursuant to the Local Government Article (“LG”) of the Annotated Code of
Maryland, Section 5-202, the Mayor and Common Council of Westminster (“the City”) has the
authority to pass such ordinances as it deems necessary and appropriate to (1) assure the good
government of the municipality; (2) protect and preserve the municipality’s rights, property, and
privileges; (3) preserve peace and good order; (4) secure persons and property from danger and
destruction; and (5) protect the health, comfort, and convenience of the residents of the
municipality; and
WHEREAS, the authority of LG § 5-202 has been implemented through the City Charter,
which provides in part that the Common Council shall have the power to pass such ordinances as
deemed advisable to provide for the good government and peace, health and welfare of the City
and the inhabitants thereof; and
WHEREAS, pursuant to the foregoing authority, the City has enacted Chapter § A175-1,
setting forth the fees and charges for the various services and facilities provided by the City; and
WHEREAS, it has come to the attention of the Common Council that the City is incurring
increased expenses for the purchase of water meters and that those increased expenses are not
adequately captured by the fees authorized by Chapter A175 for the installation of new or
replacement water meters at premises serviced by the City’s water and sewage treatment plant,
NOW THEREFORE BE IT ORDAINED AND ENACTED BY THE MAYOR AND
COMMON COUNCIL OF WESTMINSTER,
SECTION 1. That the Code of the City of Westminster, Chapter A175, “Fees,” Article I,
“Utility Fees,” Section A175-1, “Utility fees, charges and costs adopted; Utility Fee Schedule
established,” shall be and hereby is amended as follows:
§ A175-1. Utility fees, charges and costs adopted; Utility Fee Schedule established.
The Mayor and Common Council of Westminster hereby enacts and adopts the following fees,
charges and costs relating to the utility services provided pursuant to Chapters 124 and 160 of the
Westminster City Code.
A. Chapter 124, Sewers and Sewage.
1 of 3
* * *
B. Chapter 160, Water.
Article I, Potable Water
(1) Section 160-2, Metered service: Consists of fixed quarterly charge plus water usage
charge.
* * *
(8) Section 160-11, Meters:
(a) Meter size.
Size
(inches) Fee
¾ $300 356.00
1 $355 479.00
1½ $600 852.50
2 $700 1,139.50
Greater than 2 Actual cost as determined by
Director of Public Works
SECTION 2. That this Ordinance shall take effect ten (10) days after the date of its passage
and approval, unless it is returned unsigned by the Mayor at the next meeting of The Mayor and
Common Council together with the Mayor’s reasons for withholding his signature therefrom, and is
not passed thereafter by the votes of four-fifths of the members of the Common Council, and further
provided that it is posted after adoption for not less than two weeks in some conspicuous location in
the City Hall and recorded in a book provided for that purpose.
INTRODUCED this ___ day of July, 2025.
Douglass A Barber, City Clerk
Strikethrough: Indicates language proposed to be deleted from the Code.
BOLDFACE UNDERLINED SMALL CAPITALS: Indicates language proposed to be added to the Code.
*** Asterisks: Indicates language in the Code that remains unchanged and that is not set forth in this
Ordinance.
2 of 3
ADOPTED this ____ day of August, 2025.
Douglass A. Barber, City Clerk
APPROVED this _____ day of August, 2025.
Dr. Mona Becker, Mayor
APPROVED AS TO FORM AND LEGAL
SUFFICIENCY this ___ day of _________, 2025
Ramsay M. Whitworth, Esq., City Attorney
Strikethrough: Indicates language proposed to be deleted from the Code.
BOLDFACE UNDERLINED SMALL CAPITALS: Indicates language proposed to be added to the Code.
*** Asterisks: Indicates language in the Code that remains unchanged and that is not set forth in this
Ordinance.
3 of 3
Get email alerts for Westminster
A daily email when new agendas and minutes are posted.