Public Works Committee
Regular MeetingWeston, WI · September 13, 2021
Minutes
Village of Weston, Wisconsin
PUBLIC WORKS & UTILITY COMMITTEE MEETING
Monday, September 13, 2021 at 4:30 p.m.
AGENGA ITEMS
1. Meeting called to order by Public Works & Utility Committee Chair Zeyghami
at 4:30 p.m.
2. Welcome, introductions and acknowledgement of guests.
Lauren White in audience.
3. Roll Call by Recording Swenson:
Hooshang Zeyghami {C} Present
Tom Hubbard Present
Roy Mumper Present
Luis Lopes Serrao Excused
Nate Fiene Arrived later
4. Approval of 8/09/21 Public Works & Utility Committee Minutes.
M/S/P Hubbard/Mumper - Approve 8/9/21 Public Works Meeting minutes.
Yes Vote: 3 No Vote: 0 Abstain: 0 Not Voting: 1 Result: Pass
Hooshang Zeyghami {C} Yes
Tom Hubbard Yes
Roy Mumper Yes
Luis Lopes Serrao ------
Nate Fiene ------
PUBLIC COMMENTS
Join Zoom Meeting by Computer (audio only meeting to make comments):
https://zoom.us/j/5445915099
Join Zoom Meeting by Phone (audio only meeting to make comments):
+1 312 626 6799
Meeting ID: 544 591 5099
ACKNOWLEDGE WORK PRODUCT TRANSMITTALS
None.
ITEMS REFERRED TO COMMITTEE BY VILLAGE BOARD
None.
RESOLUTIONS/ORDINANCES
5. Resolution 2021-024: Zinser St Utility Extension – Final Resolution
Wodalski noted the final resolution is to levy special assessments for the water
and sewer infrastructure which was extended south of Weston Ave to serve
Crane Meadows Golf Course. Final assessment rates on final project cost and
the numbers are listed on attachment. System is in operation, but no one is
connected yet.
M/S/P Mumper/Hubbard - Approve final resolution for Zinser St Utility Extension.
Yes Vote: 4 No Vote: 0 Abstain: 0 Not Voting: 1 Result: Pass
Hooshang Zeyghami {C} Yes
Tom Hubbard Yes
Roy Mumper Yes
Luis Lopes Serrao ------
Nate Fiene Yes
STAFF REPORTS
6. CIP Update
Wodalski noted the final resolution for the Weston School East Neighborhood
Project should be complete in the next two months. Crestwood Acres is
proceeding on schedule. Project should be wrapped up by middle October.
Birch St project will get revised set of drawings. Public meeting possibly be held
10/7 with property owners. The Municipal Center footings and frost walls are
being poured, the precast panels should start being erected by the middle of
October. Mi-Tech is working on the easements for the Cedar Creek interceptor
access road. Ryan St/Apache project is going to be delayed. The contractor is
having issues getting pipe delivered, they have enough for the river boring to be
done but the rest will likely wait until next spring. The contractor will be asking
for a time extension but not a budget increase. Tanya Tricia lift station is
expected to start the week of October 18th. The PSC has given the Village
official notice on wells 7 & 8 that a complete application was received, they have
120 days to review.
7. Street Operations Update
Raczkowski mentioned the Ross Ave bridge patches grew so we have more deck
repair happening. On the south side of the deck full depth repairs were needed
instead of just partial depth. This coming week they may be able to get the edge
poured. Likely there will be a couple weeks with the signals yet. American Asphalt
will be working on the westbound lanes on Barbican Ave this coming week. They
will then flip to the eastbound lanes once the westbound lanes are complete.
Village staff over excavated the eastbound lanes on Westview Blvd. The
subgrade was poor and there was no breaker underneath the 7 ½ inch slab, there
was black dirt underneath. North side of that road has fabric breaker and base.
Our staff worked on the pedestrian trail with similar results of having to remove
black dirt and install gravel. Wodalski noted a new employee, Trevor Janikowski,
started this week.
8. Utility Operations Update
Swenson noted staff is working with AECOM on the SCADA scope of work. The
Kerry Well had a bad sample. We had Municipal Well and Pump come in for a re
chlorination of the well and had to be on Rothschild water for about a week.
Moving forward we’ll need to look at more frequent cleaning of that well. Wells did
have few repairs to chemical feed lines completed. Large meters were inspected
and calibrated. There will be twelve hydrants replaced yet this fall, 9 are digless so
no excavation is needed. Sewer jetting was completed last month. Staff has been
televising sanitary sewer in the “annexed area” of Rothschild and there appears to
be areas in need of lining. Eleven well permits were issues. Staff is working on an
emergency response plan. Clark Dietz is working with staff on a sewer lining
project on the Cedar Creek Interceptor from Meadow Rock to Shorey on Camp
Phillips. There are also several meter pits that are below ground and we want to
bring them above ground.
POLICY DISCUSSIONS AND RECOMMENDATIONS
9. Ross Ave and Kramer Lane Agreement with Town of Weston
Wodalski said in 2019 we worked with the Town of Weston to reconstruct Ross
Ave between Powers St heading east to Machmueller Park. Discussions fell
apart and a grant was not applied for in 2019. The Town did put a grant to
repave part of Ross Ave which was entirely in the Village. The Town Board has
changed and they have approached us about partnering on this road again.
The project would also include installing water mains and sanitary sewer
extensions. There should also be a multi-use path along the project route as
well. Wodalski met with Town Chairman Olson and Olson would like us to apply
for funding. It was noted the DOT Multimodal grant program when it comes out
this fall would be a good grant to try and get. The cost for the roadway portion
of the project would be based on a 46/54 percentage based on how much
frontage each community has along the route. A roundabout at the Kramer and
Ross Ave intersection would be included in the project scope. That would be
50/50 split.
M/S/P Hubbard/Mumper – Approve Ross Ave agreement with
Town of Weston to include a walking and multi-use path.
Yes Vote: 4 No Vote: 0 Abstain: 0 Not Voting: 1 Result: Pass
Hooshang Zeyghami {C} Yes
Tom Hubbard Yes
Roy Mumper Yes
Luis Lopes Serrao -----
Nate Fiene Yes
10. Scada System Design Contract
Scada System dates back 20 years. The underlying controls are not up to
current standards. The upgrade will bring it up to standard and upgrade any
electrical. It will take care of the infrastructure. AECOM is one of the specialists
for wastewater system, wells, lift stations. Two of the 13 lift stations are on the
Scada Systems. All utility guys have iPads that they can control some of the
items. The design includes investigating and redesign at all the locations, so it
is not just designing new. Mumper asked if the design contract was
competitively bid. Wodalski said it was not, as AECOM is doing the design for
Wells 7 and 8 which they will have to have a SCADA system for and it made
sense to have them then do the other locations. The system will be expandable
if we add the next well. We want an open system so we could modify or
maintain it moving forward.
M/S/P Mumper/Fiene – Recommend approving the contract with AECOM as
well as removing or redlining anything that doesn’t need to be mentioned in the
contract.
Yes Vote: 4 No Vote: 0 Abstain: 0 Not Voting: 1 Result: Pass
Hooshang Zeyghami {C} Yes
Tom Hubbard Yes
Roy Mumper Yes
Luis Lopes Serrao -----
Nate Fiene Yes
11. Ross Ave and CR-X/Camp Phillips Intersection Recommendation
Wodalski stated the recommendation was to install a roundabout at the
intersection of Ross Ave and CR-X/Camp Phillips due to the truck volume that
goes through there. With the village owning the northeast corner it can be
shifted to the east so it doesn’t affect private property on the south. A
roundabout improves the long-term safety of the intersection. Marathon County
indicated they would prefer to apply for a grant for the funding of the project and
they would be the lead agency. We would look at continuing with design
currently and then likely apply for grants with the intention to reconstruct the
intersection in 2024 or 2025 project. The design costs are proposed to be split
50/50 with the County.
M/S/P Fiene/Mumper – Motion to recommend roundabout at intersection of
Ross Avenue and Camp Phillips to Board of Trustees.
Yes Vote: 4 No Vote: 0 Abstain: 0 Not Voting: 1 Result: Pass
Hooshang Zeyghami {C} Yes
Tom Hubbard Yes
Roy Mumper Yes
Luis Lopes Serrao -----
Nate Fiene Yes
12. Tanya/Tricia Lift Station Easement
Wodalski noted the goal was to relocate the station on existing right of way.
After looking at several alternatives it didn’t seem to be possible to not impact
private property. Staff then discussed an easement with the adjacent resident.
The necessary easement requires 331 square feet. The land is currently
assessed at $2 per square foot. The property owner’s request was $3 a square
foot, difference is $300 total on the project. The easement would allow us to
have a generator at that station so backup power is available during storms.
This appeared to be the most economical way to reconstruct the lift station.
M/S/P Mumper/Hubbard – Recommendation to purchase easement for $1,000.
Yes Vote: 4 No Vote: 0 Abstain: 0 Not Voting: 1 Result: Pass
Hooshang Zeyghami {C} Yes
Tom Hubbard Yes
Roy Mumper Yes
Luis Lopes Serrao -----
Nate Fiene Yes
13. Shorey Ave Utility Connection and Sewer Extension Agreement
Swenson indicated the utilities were contacted by a person looking to build a
house along Shorey Ave, east of Cedar Park St. There is water main fronting
those properties. The adjacent property to the west is 2112 Shorey Ave and
they do have sewer and water service on the North side of Shorey. The sewer
would need to be extended 230 ft to the east for this other resident. In 2009 an
agreement was made with the then owners of 2112 Shorey stating once sewer
is available in front of their property, they would be forced to connect to the new
main and abandon the long lateral.
Staff is looking to see how best to handle the agreement in place and how
Village would team with Mr. Gumz to get the sewer extended to the property he
is interested in. Mr. Gumz wants to know what his shared options would be.
Staff estimates the cost would be $30,000-35,000 total. We as staff will need to
come back with proposal.
M/S/P Fiene/Mumper – Motion to defer until further information is obtained.
Yes Vote: 4 No Vote: 0 Abstain: 0 Not Voting: 1 Result: Pass
Hooshang Zeyghami {C} Yes
Tom Hubbard Yes
Roy Mumper Yes
Luis Lopes Serrao -----
Nate Fiene Yes
14.2022-2026 CIP Project Discussion
The goal is next month to have a final version adopted so we can utilize the
revised CIP for grant applications. Wodalski went over the changes that were
made since last month’s meeting which rearranged the County Road X/Ross
Ave intersection and then some equipment was rearranged as well. These
were highlighted in red text on the attachment.
FUTURE ITEMS
15. Next meeting date(s):
a. Monday, October 11, 2021 @ 4:30 p.m. Regular Meeting
b. Monday, November 8, 2021 @ 4:30 p.m. Regular Meeting
c. Monday, December 13, 2021 @ 4:30 p.m. Regular Meeting
d. Monday, January 10, 2022 @ 4:30 p.m. Regular Meeting
16.Topics for future meetings
None.
17.Remarks from Administrator
We are going to work with our attorney to come up with a standard form of
agreement for engineering contracts so we don’t have to have the attorney review
every contract moving forward.
18. Remarks from Staff
None.
24. Remarks from Committee members.
None.
25. Announcements.
None.
ADJOURNMENT:
M/S/P Fiene/Hubbard – Motion to adjourn at 5:45 pm
Yes Vote: 4 No Vote: 0 Abstain: 0 Not Voting: 1 Result: Pass
Hooshang Zeyghami {C} Yes
Tom Hubbard Yes
Roy Mumper Yes
Luis Lopes Serrao -----
Nate Fiene Yes
Get email alerts for Weston
A daily email when new agendas and minutes are posted.