Development Review Board Panel A
Regular MeetingWilsonville, OR · May 11, 2026
Minutes
Development Review Board Panel A
Regular Meeting Minutes
May 11, 2026
Wilsonville City Hall & Remote Video Conferencing
https://www.ci.wilsonville.or.us/meetings/pc
Approved
CALL TO ORDER - ROLL CALL June 8, 2026
Chair Galloway called the meeting to order at 6:30 pm.
Present: Alice Galloway, Jordan Herron, Janis Sanford
Excused: Megan Chuinard, Mitch Cooper
Staff Present: Kimberly Rybold, Amanda Guile-Hinman, Hannah Tuia, Alie Cloo, Amy Maag,
Miranda Bateschell, Chris Myers, and Shelley White
CHAIR'S REMARKS
The Conduct of Hearing and Statement of Public Notice were read into the record.
CITIZEN INPUT
There was none.
CONSENT AGENDA
1. Approval of minutes of the February 9, 2026 DRB Panel A meeting
Jordan Herron moved to approve the February 9, 2026 DRB Panel A meeting minutes as
presented. Janis Sanford seconded the motion, which passed 3 to 0. (Ayes: Herron, Sanford,
Galloway)
PUBLIC HEARING
2. Resolution No. 443. iONNA Electric Vehicle Charging Station. The applicant is
requesting approval of a Stage 1 Preliminary Plan, Stage 2 Final Plan, Site Design Review,
and Class 3 Sign Permit for an electric vehicle (EV) charging station with 16 EV charging
stalls and an amenities building housing restrooms and vending machines.
Case Files:
DB25-0004 iONNA Electric Vehicle Charging Station
-Stage 1 Preliminary Plan (STG125-0002)
-Stage 2 Final Plan (STG225-0003)
-Site Design Review (SDR25-0004)
-Class 3 Sign Permit (SIGN25-0009)
Development Review Board – Panel A Meeting Minutes Page 1
May 11, 2026
The following exhibit was entered into the record:
• Exhibit B6: One, printed page dated May 11, 2026 showing two emails confirming the
change in the subject site’s ownership to Seth Cutler, iONNA, LLC.
Chair Galloway called the public hearing to order at 6:38 p.m. and read the conduct of hearing
format into the record. All Board members declared for the record that they had visited the
site. No board member, however, declared a conflict of interest, bias, or conclusion from a site
visit. No board member participation was challenged by any member of the audience.
Associate Planner Tuia announced that the criteria applicable to the application were stated
starting on page 2 of the Staff report, which was entered into the record. Copies of the report
were made available to the side of the room and on the City’s website.
Associate Planner Tuia presented the Staff report via PowerPoint, briefly noting the site's
location and reviewing the requested applications as follows:
• Proper noticing procedures were followed for the application with notice mailed to all
property owners within 250 ft of the subject property. Notice was also published in the
newspaper, on the City's website, and placed on the subject site. One public comment was
received. (Exhibit D1)
• The four requests before the Board were objective in nature, as they involved verification of
compliance with Code standards. None were discretionary in nature.
• Planned Development Stage 1. The subject site was currently vacant, did not have an
existing master plan or any previous approvals, and was zoned Planned Development
Industrial (PDI).
• The Stage 1 Preliminary Plan proposed a new EV charging station and an amenity
building with an overall development and layout consistent with the PDI Zone. The PDI
Zone allows for limited, service commercial use, which the subject use fell under.
• Service commercial under 5,000 sq ft was permitted in PDI. The charging area, charging
units, and the amenity combined totaled approximately 3,650 sq ft, falling under the
threshold. As such, the development proposal was an eligible use in the PDI Zone.
• Planned Development Stage 2. In the Stage 2 Final Plan, the Applicant proposed installing
16 EV charging stalls, which are partially covered by two canopies. Additionally, the 260 sq
ft amenities building would house restrooms and vending machines, with the vending
machines in a recessed portion of the building. Picnic tables and a pet relief area would be
located outside.
• Proposed site improvements met or exceeded City standards for parking, circulation
areas, pedestrian connections, landscaping, utilities, and other site features.
• Site Design Review. The Applicant used appropriate professional services to design
structures on site using quality materials. The new amenity building was attractively
designed utilizing Hardie plank siding.
• The recessed area with the vending machines would be located under the snack
dispenser sign. Restrooms would be located behind separate doors. (Slide 7)
Development Review Board – Panel A Meeting Minutes Page 2
May 11, 2026
• The Applicant’s proposed landscaping was professionally designed by a landscape
architect and exceeded the area requirements, incorporating a variety of plant materials
and demonstrating appropriate attention to landscaping.
• Class 3 Sign Permit. The Applicant proposed two building signs, one “iONNA” sign and one
sign above the snack dispenser. Additionally, two, smaller “iONNA” signs were proposed on
each of the canopies. All proposed signs were compliant with Code requirements, including
size, placement, materials, etc.
• Ownership update. After publication of the Staff report, Staff was informed that the site’s
ownership had changed to iONNA, LLC. New Exhibit B6 confirmed the change in ownership,
updating the Staff report. The amendments were read into the record as follows (Slides 9 &
10, Exhibit A2):
(Note: deleted language struck through, additional language in bold, italic text)
• On the Staff report cover page to state, “David Wales, Barber Street Wildcat, LLC Seth
Cutler iONNA, LLC.”
• On Page 14, update the Initiating Application Finding to state, “The application has a
signature of David Wales, an authorized signer for the property owner at the time of
application, Barber Street Wildcat, LLC. Exhibit B6 provides confirmation that the
current property owner is iONNA, LLC.”
• On Page 15, amend Finding A6 to state, “The property affected by the revised Stage 1
Preliminary Plan is was under the sole ownership of Barber Street Wildcat, LLC. at the
time of application and the application has been signed by David Wales, authorized to
sign on behalf of Barber Street Wildcat, LLC. Exhibit B6 provides confirmation that the
current property owner is iONNA, LLC.”
• On Page 17, amend Finding B2 to state, “The subject parcels were under the ownership
of the Barber Street Wildcat, LLC. at the time of application, for whom an authorized
signer, David Wales signed the application. Exhibit B6 provides confirmation that the
current property owner is iONNA, LLC.”
Janis Sanford asked if the original application needed to be updated due to the change in
ownership.
Ms. Tuia replied that because the application was correct when submitted, it did not need to be
updated. Exhibit B6 confirmed that the current property owner was aware of the application on
the property, and they intended to proceed.
Chair Galloway called for the Applicant’s presentation.
Andres Villacres, Site Development Manager, iONNA, LLC, stated the Applicant was very
excited about the project and planned to expand quickly throughout the United States and
eventually North America.
• Wilsonville was a key location, as the subject site was located right off I-5. iONNA, LLC was
aggressively building a Level 3 DC fast-charging network, which included the subject site in
Wilsonville.
Development Review Board – Panel A Meeting Minutes Page 3
May 11, 2026
• A Level 3 charger could charge a vehicle from 0 to 80 percent in approximately 30 minutes
with a full charge in an hour. iONNA provides a high-quality charging experience, especially
for flagship-level sites like the subject site with restrooms, vending machines, and canopy
covers that enable users to relax in a comfortable, safe, well-lit environment while their cars
were charging.
• He thanked Ms. Tuia for her assistance and offered to answer any questions from Board
members.
Chair Galloway stated she was thrilled with the project as she owned an electric car and the
facility would be convenient. She asked what types of chargers would be available and for what
types of vehicles, and about the hours of operation.
Mr. Villacres replied that the United States had two nationwide standards, CCS and MACS, or the
Tesla charger. Of the nine chargers, six would be dual-port CCS chargers in twelve bays, and three
would be dual-port MACS chargers for Teslas in six bays. The sites ran fairly independently and
would be open 24 hours a day, 7 days a week (24/7).
Chair Galloway asked where the pet relief area would be in relation to the charging bays and
restrooms.
Mr. Andres explained that the pet relief area would be located in the northwest corner of the
property, west of the northern row of chargers.
Jordan Herron stated the facility was thoughtfully designed and he liked the project.
Chair Galloway called for public testimony regarding the application.
Staff noted an attendee on Zoom, who had submitted testimony via email, was inadvertently
removed from the meeting and they were seeing if he could call in to give his testimony.
Jordan Herron moved to take a five-minute recess. The motion was seconded by Janis
Sanford and passed 3 to 0. (Ayes: Herron, Sanford, Galloway)
Chair Galloway reconvened the meeting at 7:01 pm.
Mike Sharpe, Wilsonville, Oregon asked if there would be attendants at the station, and how
often the bathrooms and pet areas would be cleaned.
Mr. Villacres replied the site would be unmanned, but would have 24/7 security cameras,
reviewed by humans, and numbers onsite to call in case of emergency. For cleaning, iONNA
partnered with local and national janitorial firms. Initially, cleanings would be done daily and
then adjusted to perhaps, every other day. The maintenance team would keep the pet relief
areas tidy as well.
Development Review Board – Panel A Meeting Minutes Page 4
May 11, 2026
Eric Schaffner, Portland, encouraged the Board to approve the resolution. He had followed
iONNA closely since the business began and its projects of building high-quality EV charging
sites nationwide. He had visited three of iONNA’s active locations near Salem, and in
Vancouver, Washington, and Colorado, and all were uniformly clean, safe, attractive, and
reliably functional. He believed the proposed location, which he had also visited, was an
excellent choice that would be appreciated by both local EV owners and those transiting
through the area.
Chair Galloway confirmed there was no other public testimony and called for the Applicant's
rebuttal.
Mr. Villacres thanked the members of the public for their support, noting that iONNA
appreciated public feedback, even if opposed, as that was how iONNA improved itself.
Janis Sanford asked about the timeline for completion.
Mr. Villacres replied that after approval, receiving the building permit would take
approximately 60 to 90 days, and constructing the facility would take about 8 to 12 weeks. As
long as the permitting went smoothly, the Applicant expected the project to open by the end of
the year.
Chair Galloway asked if the Applicant had a marketing plan to inform people about the new
charging facility.
Mr. Villacres stated he would have to consult with the iONNA marketing team for a definitive
answer, but he understood that as the site neared completion, the marketing team would
reach out to the City to see about a ribbon-cutting or other events since this was one of
iONNA’s flagship-tier sites.
Chair Galloway confirmed there were no additional questions or discussion and closed the
public hearing at 7:08 pm.
Janis Sanford moved to adopt the Staff report with the addition of Exhibit B6, and the
amendments as read into the record by Staff. Jordan Herron seconded the motion, which
passed 3 to 0. (Ayes: Herron, Sanford, Galloway)
Jordan Herron moved to adopt Resolution No. 443, including the amended and adopted Staff
report. Janis Sanford seconded the motion, which passed 3 to 0. (Ayes: Herron, Sanford,
Galloway)
Chair Galloway read the rules of appeal into the record.
Development Review Board – Panel A Meeting Minutes Page 5
May 11, 2026
BOARD MEMBER COMMUNICATIONS
3. Results of the February 23, 2026 DRB Panel B meeting
4. Results of the April 27, 2026 DRB Panel B meeting
5. Recent City Council Action Minutes
STAFF COMMUNICATIONS
6. Frog Pond East and South Training
Senior Planner Rybold and Planning Director Bateschell noted the training was being provided
in anticipation of upcoming Frog Pond applications, including a public hearing scheduled for
May 28, 2026. DRB Panel B was also provided the training last month as both DRB panels would
be convened for the May meeting. Staff presented the Frog Pond East and South Training via
PowerPoint, describing the background and key differences between the Frog Pond East and
South Master Plan and its implementing Development Code and what the Boards had seen with
Frog Pond West.
Staff responded to Board questions by clarifying accessible housing requirements, urban form
standards, expected development patterns based on parcel size and ownership, cottage cluster
concepts, planned Stafford Road and Frog Pond East commercial area improvements,
anticipated park ownership and maintenance responsibilities, and the potential for future
waiver training.
ADJOURNMENT
The meeting was adjourned at 7:54 p.m.
Development Review Board – Panel A Meeting Minutes Page 6
May 11, 2026
Agenda
DEVELOPMENT REVIEW BOARD PANEL A AGENDA
May 11, 2026 at 6:30 PM
Wilsonville City Hall & Remote Video Conferencing
PARTICIPANTS MAY ATTEND THE MEETING AT:
City Hall, 29799 SW Town Center Loop East, Wilsonville, Oregon
Zoom: https://us02web.zoom.us/j/85843043229
TO PROVIDE PUBLIC TESTIMONY:
Individuals must submit a testimony card online:
https://www.wilsonvilleoregon.gov/DRB-SpeakerCard
and email testimony regarding Resolution No. 443
to Hanna Tuia, Associate Planner at
htuia@wilsonvilleoregon.gov
by 2:00 PM on May 11, 2026.
CALL TO ORDER
CHAIR'S REMARKS
ROLL CALL
Megan Chuinard Mitch Cooper
Alice Galloway Jordan Herron
Janis Sanford
CITIZEN INPUT
This is an opportunity for visitors to address the Development Review Board on items not on the
agenda. Staff and the Board will make every effort to respond to questions raised during citizens input
before tonight's meeting ends or as quickly as possible thereafter.
CONSENT AGENDA
1. Approval of minutes of the February 9, 2026 DRB Panel A meeting
PUBLIC HEARINGS
2. Resolution No. 443. iONNA Electric Vehicle Charging Station. The applicant is requesting
approval of a Stage 1 Preliminary Plan, Stage 2 Final Plan, Site Design Review, and Class 3 Sign
Permit for an electric vehicle (EV) charging station with 16 EV charging stalls and an amenities
building housing restrooms and vending machines.
Case Files:
Development Review Board Panel A Page 1 of 2
May 11, 2026
DB25-0004 iONNA Electric Vehicle Charging Station
-Stage 1 Preliminary Plan (STG125-0002)
-Stage 2 Final Plan (STG225-0003)
-Site Design Review (SDR25-0004)
-Class 3 Sign Permit (SIGN25-0009)
BOARD MEMBER COMMUNICATIONS
3. Results of the February 23, 2026 DRB Panel B meeting
4. Results of the April 27, 2026 DRB Panel B meeting
5. Recent City Council Action Minutes
STAFF COMMUNICATIONS
6. Frog Pond East and South Training
ADJOURN
The City will endeavor to provide the following services, without cost, if requested at least 48 hours prior
to the meeting by contacting the Shelley White, Planning Administrative Assistant
at drba@wilsonvilleoregon.gov or 503-682-4960: assistive listening devices (ALD), sign language
interpreter, and/or bilingual interpreter. Those who need accessibility assistance can contact the City by
phone through the Federal Information Relay Service at 1-800-877-8339 for TTY/Voice communication.
Habrá intérpretes disponibles para aquéllas personas que no hablan Inglés, previo acuerdo. Comuníquese
al 503-682-4960.
Development Review Board Panel A Page 2 of 2
May 11, 2026
Get email alerts for Wilsonville
A daily email when new agendas and minutes are posted.