City Council
Regular MeetingZanesville, OH · March 10, 2025
Agenda
Ordinance 2025-26
Attachment A
City of Zanesville, Ohio
Leisure Farms Construction Administration and Inspection Services ATTACHMENT A
Phase by
Week Esti ODOT
Months Description Category WK HR Total Hrs Rates Sub-Total Total Notes
2 0.5 0 Pre-Construction Services (14 cal days) Construction Manager 2 6 12 105.00 1,260.00 1,260.00 Preconstircition Services
Arrange and Administrate Pre-construction Conference
6 1.5 Earthwork (42 cal days) 30 Work Days Project Inspector 6 40 240 85.00 20,400.00 Full Time Inspection
126 Work Days or 25 weeks of work deducting weekends and holidays Project Inspector OT 6 10 60 127.00 7,620.00
Construction Engineer 6 6 36 105.00 3,780.00 31,800.00 Cooodination of Field Changes, Project Management
Shop drawing reviews, submittal Reviews
4 1.5 Storm Sewer (42 cal days) 30 Work Days Project Inspector 4 40 160 85.00 13,600.00 Full Time Inspection
126 Work Days or 25 weeks of work deducting weekends and holidays Project Inspector OT 4 10 40 127.00 5,080.00
Construction Engineer 4 6 24 105.00 2,520.00 21,200.00 Cooodination of Field Changes, Project Management
Shop drawing reviews, submittal Reviews
6 1.5 Sanitary Sewer (42 cal days) 30 Work Days Project Inspector 6 40 240 85.00 20,400.00 Full Time Inspection
126 Work Days or 25 weeks of work deducting weekends and holidays Project Inspector OT 6 10 60 127.00 7,620.00
Construction Engineer 6 6 36 105.00 3,780.00 31,800.00 Cooodination of Field Changes, Project Management
Shop drawing reviews, submittal Reviews
6 1.5 Waterline (42 cal days) 30 Work Days Project Inspector 4 40 160 85.00 13,600.00 Full Time Inspection
126 Work Days or 25 weeks of work deducting weekends and holidays Project Inspector OT 4 10 40 127.00 5,080.00
Construction Engineer 4 6 24 105.00 2,520.00 21,200.00 Cooodination of Field Changes, Project Management
Shop drawing reviews, submittal Reviews
4 1.5 Roadway Work (42 cal days) 30 Work Days Project Inspector 4 40 160 85.00 13,600.00 Full Time Inspection
126 Work Days or 25 weeks of work deducting weekends and holidays Project Inspector OT 4 10 40 127.00 5,080.00
Construction Engineer 4 6 24 105.00 2,520.00 21,200.00 Cooodination of Field Changes, Project Management
Shop drawing reviews, submittal Reviews
2 1.5 Post Construction Services (42 cal days) 30 Work Days Project Inspector 2 8 16 85.00 1,360.00
126 Work Days or 25 weeks of work deducting weekends and holidays Project Inspector OT 2 0 0 127.00 0.00
Construction Engineer 2 6 12 105.00 1,260.00 2,620.00
Leasure Farms Construction Administration, Inspection and Materials Testing Fee
Hours Rate Total
Project Inspector 976 85.00 $82,960.00
Project Inspector OT 240 127.00 $30,480.00
Construction Engineer 168 105.00 $17,640.00
Sub Total $131,080.00
9500 Midwest Avenue Resource/Task Unit Rate Total
Garfield Heights, Ohio 44125 Reimbursable 1 500.00 $500.00
1 17,000.00 $17,000.00
Mark Pace QCI Estimated Total = $148,580.00
1/20/2025
1190961.85
#REF!
Get email alerts for Zanesville