I. Pledge of Allegiance
II. Attendance: Dave Franz, Larry Jones, Sharon Walker, Mary Grabianoski, Cindy Madrick, and Chris Lake
attended in person.
III. Approval of the March 21, 2022, Plan Commission Meeting Minutes – Approved.
IV. Continuance Requests
Docket Address of
Name Item to be Considered
Number Project
Petitioner requested a Continuance to the May 16, 2022, Plan
Commission Meeting.
The Club at Approved to continue to the May 16, 2022, Meeting
Holliday Farms / 6 in Favor
10571 Pete Dye
2022-15-RP Replat of HF 0 Opposed
Ridge, Zionsville
Section 2, Lot
Petition for the Approval of a Replat of Holliday Farms, Section
F28
Two, Lot F28 to reduce the platted front setback line in the
Holliday Farms (PUD) Planned Unit Development Zoning
District.
V. Continued Business
Docket Address of
Name Item to be Considered
Number Project
None at this time.
VI.New Business
April 19, 2022
Docket Petitioner/ Address of
Item to be Considered
Number Project Name Project
Approved as presented.
6 in Favor
Zionsville 11500-12065 N. 0 Opposed
2022-24-MPR Redevelopment Michigan Rd, Adoption of Plan Commission Order regarding
Commission Zionsville establishment of Economic Development Area / approval of
Declaratory Resolution and Economic Development Plan
(EDP) for the Michigan Road Economic Development Area.
Approved as presented, and subject to resolution of
outstanding review items identified by the Engineering
Review Memo in Exhibit 5 of the Staff Report; and subject to
approval of the two requested Development Standards
Zionsville Variances by the Board of Zoning Appeals.
Presbyterian 4775 W. 116th 6 in Favor
2022-13-DP
Church / Street, Zionsville 0 Opposed
Food Pantry
Petition for Development Plan Approval of a 5,600+/-
square foot building to serve as a food pantry in the (Urban
B-O) Urban Office Business District and within the Urban
(MRO) Michigan Road Overlay Zoning District.
Approved as presented.
6 in Favor
Tim Lai /
75 N. Main Street, 0 Opposed
2022-16-DPA COhatch
Modification Zionsville Petition for the Modification of the Development Plan
regarding building elevations in the (VBD)Village Business
Zoning District.
VII. Other Matters to be considered
Docket Address of
Name Item to be Considered
Number Project
Discussion: 2022 Filing Schedule
Please note that a quorum of the Zionsville Town Council may be in attendance at the meeting.
Respectfully Submitted: Wayne DeLong, AICP, CPM
Director of Community & Economic Development
Town of Zionsville
April 19, 2022
Zionsville Plan Commission
April 18, 2022
In Attendance: David Franz, Larry Jones, Sharon Walker, Mary Grabianowski, Cindy Madrick,
Chris Lake
Staff attending: Attorney Bob Clutter, Wayne DeLong, Roger Kilmer
A quorum is present.
Franz Call to order the Zionsville Plan Commission meeting of Monday, April 18,
2022. Please start with the Pledge of Allegiance.
All Pledge of Allegiance.
Franz Roger or Wayne – who’s taking roll?
DeLong I’ll take care of that.
Franz Wayne, all right.
DeLong Mr. Franz?
Franz Present.
DeLong Mrs. Grabianowski?
Grabianowski Present.
DeLong Mr. Jones?
Jones Present.
DeLong Mrs. Walker?
Walker Present.
DeLong Mr. Lake?
Lake Present.
DeLong Mrs. Madrick?
Madrick Present.
Franz All six members are present. In your packet is a set of minutes from the March
21, 2022 Plan Commission meeting. Are there any comments, additions,
deletions to those minutes? If there are none, is there a motion to approve?
Grabianowski So moved.
Franz Is there a second?
Lake Second.
Page 1 of 17
Zionsville Plan Commission
April 18, 2022
Franz All in favor signify by aye.
All Aye.
Franz Opposed by nay.
[No response]
Motion carries 6-0 those are approved. At this point in time, is there anybody
online who would be, want to be recognized in the minutes? No one? All right.
Franz Um, Zelonis – what’s her first name?
Grabianowski Sally.
Lake Sally.
Franz Sally Zelonis? Okay. Um, all right. We have a continuance request Docket
Number 2022-15-RP, The Club at Holliday Farms/Replat of Holliday Farms
Section 2, Lot F28, 10571 Pete Dye Ridge, Zionsville, Petition for the Approval
of a Replat of Holliday Farms, Section 2, Lot F28 to reduce the platted front
setback line in the Holliday Farms (PUD) Planned Unit Development Zoning
District. Is there anybody present or this just a request from them – Wayne?
Roger?
Kilmer I was under the impression someone was going to be online but –
Franz Okay. There she is.
DeLong No, this is Heather James – next matter.
Franz Oh next matter, okay.
Clutter RDC attorney.
Franz Okay. My mistake. Um –
Kilmer It appears no one is online. I thought there was going to be someone online to
represent.
Franz Okay. All right.
Kilmer They have submitted a, a request for this continuance.
Franz Okay. Is there any discussion to this matter? If not, is there a motion to continue
this to May 16th – is that correct? Monday, May 16th Plan Commission meeting?
Grabianowski I move that we continue it until Monday, May 16th.
Franz Is there a second?
Page 2 of 17
Zionsville Plan Commission
April 18, 2022
Walker Second.
Franz Any discussion? All in favor signify by aye.
All Aye.
Franz Opposed by nay.
[No response]
Motion is continued. Um, on to New Business. Docket Number 2022-24-MPR,
Zionsville Redevelopment Commission, 11500-12065 North Michigan Road,
Zionsville, Adoption of Plan Commission Order regarding establishment of an
Economic Development Area/approval of Declaratory Resolution and Economic
Development Plan (EDP) for the Michigan Road Economic Development Area.
Petitioner present online. Please proceed.
Lake Mr. Franz, I need to recuse myself of this matter.
Franz Okay. Thank you.
DeLong And Mr. Franz I’m happy to start with a quick introduction –
Franz Okay.
DeLong But certainly on your screen is Heather James with Ice Miller. She serves with
the Redevelopment Commission here as, as support legal for their efforts.
Certainly the matter that’s in front of you is associated in part with The Farm.
Certainly it’s a PUD project that some of you recall from 10 – nearly 10 years
ago as, as a project. Certainly here we are today talking about the creation of an
Economic Development Area which both encapsulates this property as well as
extends northerly along Michigan Road, uh, to a terminus at, uh, I believe, it’s
Greenfield Avenue and per the maps. Certainly this effort is one that you may
recall this, this process some of you may recall from prior, prior exercises – last
was 2019 with the creation of the Holliday Farms TIF area but stopping there
with that quick introduction certainly now turning to Ms. James to walk through
the technical side of, of what’s in front of you.
Franz All right. Thank you.
James Thanks Wayne. Uh, before you you have a –
Franz Heather would you introduce yourself, address please.
James My address? Sure. Hi. I’m –
Franz Name and address yeah.
James Heather James with Ice Miller, uh, bond counsel to the Town and my address is
2122 North Alabama Street in Indianapolis. Okay. So before you this evening is
an Order to consider approval of the Declaratory Resolution that was adopted by
the Redevelopment Commission on March 28th and then attached to that
Page 3 of 17
Zionsville Plan Commission
April 18, 2022
Declaratory Resolution is also an Economic Development Plan creating this new
Michigan Road Economic Development Area. So just so that you’re aware of the
process, the first step in the process was adoption of that Resolution by the
Redevelopment Commission. The second step is to come before you all for you
to consider whether or not that Resolution and the plan attached thereto conform
to the plan for development for the Town. Assuming that you feel comfortable
that it does conform, then we’d ask you to consider approval of this Order this
evening and then we would move forward with, um, a Town Council Resolution
approving your Plan Commission Order and then we would move along to
publishing a notice to have a confirmatory Resolution and a public hearing of the
Redevelopment Commission and at that point we’d go back to the Council to
adopt one more Resolution and then this Economic Development Area and the
allocation areas therein would be officially created and we would submit notice
to both the County Recorder and to the DLGF so that everybody is aware of what
we’ve done. I’m happy to answer any questions that you might have about the
process, the Order, the Resolution or the Economic Development Plan.
Franz All right. Thank you.
James Sure.
Franz Anybody have questions or comments on this matter? Wayne, I’m assuming
when this was first approved way back when this was all part of the consideration
– this was something that was going to occur?
DeLong The creation of an EDA –
Franz Yeah.
DeLong TIF for this area has always been something that’s been talked about. Certainly
the actions have taken a little longer to get here so to speak than what you
normally have seen.
Franz Okay.
Walker Was it always to go this far north as it has? Because I, I wasn’t on the Council or
the Commission then.
DeLong No. The, the original conversation was focused on the, uh, The Farm –
Walker Okay.
DeLong The 58 acres – but certainly with, you know, a lot, many things have happened
over the last 10 years and this certainly seemed like a great opportunity to
leverage the activity that’s happening through there. You, you now have TIF
districts that exist from 146th Street all the way down to Willow which is the
Holliday Farm area and then this seems like a logical extension northerly and you
ultimately would really enhance the, uh, pedestrian connectivity in other projects
that could get facilitated with, with additional public dollars more rapidly.
Franz All right.
Page 4 of 17
Zionsville Plan Commission
April 18, 2022
Jones So here’s kind of an odd question about this – because, obviously, we’ve been
kind of going round and round with some of the stuff on Holliday Farms lately
and one of the comments you made to me, Wayne, was about that with Holliday
Farms and the TIF that was set up there they really haven’t drawn any money
down on that. Correct?
DeLong That’s correct. There’s, there’s an EDA but there has been no effort to date to
work through a development agreement and ultimately results in a bond issuance.
We certainly anticipate seeing that conversation possibly come to a conclusion
this year with, uh, end-of-year bond issuance for Holliday Farms – Holliday
Farms TIF.
Jones And so what, what point does the Town get involved in the conversation that if
we’re granting all of this we can – I’ll just be direct – extract some sort of what
I’ll call a public benefit? Um, and when I talk about the Holliday Farms piece,
I’m talking about, you know, the, the talk of a bridge over 421 to connect the –
our trails. Um, and I, I have the same concern as I read through this. I’m reading
through this paragraph here that says incentive allows for the development of the
PUD and there’s all the gray verbiage, authentically Zionsville – you know,
whatever that means, uh, you know, greenbelts, um, you know, for people to
enjoy when visiting the site to grab dinner, walk the trail – it’s just so much blah,
blah, blah. At what point when we start creating these TIFs and putting these
funds out there does the Town get in a position that we can actually get a benefit?
DeLong Great questions and certainly the, the TIF districts that you have seen in the past
have not been as aggressive in terms of split of the TIF dollars that are generated,
uh, but certainly your original Economic Development Area for, for, for the
downtown – the 900 acres that comprises that – I mean, you can count many
public projects that have been created from that TIF from the, from the bridge
over, over Eagle Creek at Lions Park to, uh, the Red Bridge enhancement south
of, south of downtown, other public enhancements through that area. Specifically
to Holliday Farms, the, the split that’s envisioned was $15 million towards the
Holliday Farms project and then $5 million for that civic enhancement just a
bridge – I mean, the bridge was going to be $4.3 million – probably escalated in
price since 2019 – we’re just going to guess that. Um, but in the meantime,
Holliday Farms is populating faster than what was anticipated, therefore, the
sewer flows are a bit more aggressive than what was contemplated, always
knowing that we would have a sewer improvement project coming up, uh, that
project is on the horizon a little bit earlier. Mr. Lantz gave a fantastic presentation
on this on the, on the 11th, uh, so to your point, there will be projects that will be
generated out of the Holliday Farms TIF that are public improvements, um, I’m
just going to say within the next three to five years – it will take us a little bit to
pull up a flyover bridge. Certainly this project here of the gateway district as
identified in your Economic Development Strategic Plan of 2012 certainly, uh,
folks here from the Scannell Team Pittman Team are here with any specific
details but, yes, uh, the reasoning to create this TIF district among other reasons
the EDA, is to help further faster install pedestrian improvements along 421,
along Michigan Road that might not all, you know, happen as quickly, for
example, the, the connection at Willow to Holliday Farms there’s actually a, a
Page 5 of 17
Zionsville Plan Commission
April 18, 2022
missing link that, uh, was not provided for by any project. Um, this is something
that would be more quickly remedied, uh, by, by having this EDA in place.
Jones Yeah. In other words, it’ll come at some point but it’s –
DeLong Sooner.
Jones Sooner rather than later.
Franz Has the – I’m assuming the split’s not been decided at this point in time?
DeLong Certainly in phase one of this project it’s, it’s very clear, um, as to how the
dollars would be allocated. Certainly a future, future issuances are, will have
more flexibility. Certainly if there’s any specifics you’d like to hear about, uh, I
believe we, you know, our financial advisors are online, I believe that’s the case,
and certainly, again, uh, the Scannell Pittman Team is, is here as well.
Franz Okay. Any further questions or comments? Would somebody like to make a
motion?
DeLong And it could be for, for sake of, of process, um, Heather James, if there is a
positive motion here is that something, kind of, just a recommendation from you
as to what that language would look like?
James Um, just a motion to approve the Order would be sufficient, Wayne.
Franz Okay.
DeLong Very good, thank you.
Grabianowski I move that we approve the Order.
Franz Is there a second?
Walker Second.
Franz Any further discussion? All in favor signify by aye.
All Aye.
Franz Opposed by nay.
[No response]
Motion is approved. So this will be forwarded to the Town Council?
DeLong Correct for their – we will look to place this on their May 2nd agenda.
Franz All right. Thank you.
James Thank you all. Appreciate it.
Page 6 of 17
Zionsville Plan Commission
April 18, 2022
Franz Next item on the docket is 2022-13-DP, Zionsville Presbyterian Church/Food
Pantry, 4775 West 116th Street, Zionsville, Petition for Development Plan
Approval of a ±5,600 square foot building to serve as a food pantry in the Urban
(B-O) Urban Office Business District and within the Urban (MRO) Michigan
Road Overlay Zoning District. Is the petitioner present? They online? Oh, you
are? Okay. Come on up.
Boyle I’m Mike Boyle, 8091 Crawfordsville Road, with, uh, Boyle Construction. We’re
the, uh, general contractor design build for the ZPC food pantry. This is Eileen
Davis she is actually with, uh, ZPC.
Franz Okay. Please proceed.
Boyle Uh, so, yeah, what, we’re, we’re trying to – so for the proposed food pantry what
we’re looking to do is, uh, it’s actually a 5,600 square foot building. It’s a, um,
um, wood framed, uh, building with a brick, uh, façade, um, that matches the, uh,
church, um, brick veneer and, and, um, it has – basically it’s, it’s, uh, an area that
has, uh, is mainly it has like, uh, cold storage for food and then dry foods, canned
foods and whatnot. They have 8 to 10, um, volunteers that help out the people,
you know, pick out their food, whatever, whatever necessities they do need and
then they take them out to their cars and help them load it up. Uh, there’s two
bathrooms in, in it for, you know, for the use of the, you know, the people as well
as the volunteers and there’s a garage that would house just their, uh, food van –
it’s like an E2500 Ford van and then also they, they can use that to when they
back up trucks to receive food and whatnot they can pull in there out of the
elements and load it into their freezers. They, they have two walk-in coolers, uh,
that will be, uh, in, in the building and then the other will actually be like a, like a
freezer chest or refriger-chest, uh, type, uh, equipment and, and throughout and
throughout the building and also then they’ll have racks with all the dry foods,
you know, for the, uh, you know, for the, for, for distribution.
Franz Okay. Is there anybody here who would like to make a comment on this matter in
person or online? All right. Staff report Roger.
Kilmer Thank you. Um, Mr. Boyle did a fine job covering some of the basics. I’ll go
ahead and, and fill in some additional details for you. Uh, requested is
Development Plan Approval for a 5,600 square foot building to serve as the food
pantry, uh, for the church. Currently they operate this out of the existing, uh,
building and it is a ministry that has grown where it is now warranting its own
separate facility. Um, uh, this project, uh, while before you tonight is the
Development Plan Approval, you should also be aware that they have filed for,
um, two different development standards variances which will be heard by the
Board of Zoning Appeals at the May meeting so any motion that you make
tonight, uh, should you move to approve this will need to be conditioned upon
approval of those BZA, uh, requests. Specifically, those two BZA requests, um,
one is for the architectural design of the, of the, uh, food pantry. Um, this is a
little unique to you, uh, because this is a requirement of the Michigan Road
Overlay and on previous projects where this has come up, you have been able to
address this through the waiver process. The difference in this case is that the
Zionsville Presbyterian Church is in the urban section of the Michigan Road
Overlay as opposed to the other cases that you’ve heard which have been in the
Page 7 of 17
Zionsville Plan Commission
April 18, 2022
rural section of the Michigan Road Overlay. The rural section allows for this
requirement to be treated by the Plan Commission as a waiver item. The urban
section of the Michigan Road Overlay does not give that same flexibility to the
Plan Commission so, therefore, it will be a variance request that goes before the
BZA. The second, uh, development standards variance that they are going to
request, um, uh, for involves the greenbelt requirements of the Michigan Road
Overlay, specifically, the amount of plantings that, that run along Michigan
Road. Uh, the site, the, the way the building was constructed, uh, essentially does
allow for the required 30 foot width of greenbelt through that area and they’ve
provided for that but the amount of plantings within that area has changed since
when the, the church was first constructed to what is required now. They are
proposing appropriate landscaping around the food pantry building itself, uh, but
the variance request will be that additional plantings will not be required out in
the greenbelt area which is somewhat removed from the location of the food
pantry itself. So those are the, those are the two items that will be going before
the BZA, um –
Lake On that second variance they just want to keep it status quo and not have to
upgrade to the new, newer standards?
Kilmer Yes sir.
Lake Okay.
Kilmer Yes sir.
Franz Because they’re opening this up so to speak with this they have to get a waiver
on that?
Kilmer Because they are doing new development –
Franz Right.
Kilmer On their site that now exposes the entire site –
Franz Okay.
Kilmer To the current development standards.
Franz Okay.
Kilmer So with, with that brief or flyover, staff does recommend approval of this
Development Plan for a 5,600 square foot building to serve as the food pantry.
I’m glad to answer any questions you might have.
Franz All right. Thank you. At this point is there any questions or comments from any
of the members of the Plan Commission?
Grabianowski I want to commend the Presbyterian Church. That’s been, it’s been a wonderful
ministry in the county. It really has been.
Page 8 of 17
Zionsville Plan Commission
April 18, 2022
Madrick I second that.
Walker And count me in too.
Davis Thank you.
Franz Any further questions or comments? If not, is there a motion on this matter?
Lake I move that Docket Number 2022-13-DP, a Development Plan for a 5,600±
square foot building to serve as a food pantry in the Urban Office Business Urban
B-O District and within the Urban Michigan Road Corridor Overlay Zone be
approved based on the Findings of Fact in the staff report and the staff
recommendations, the submitted Findings of Fact subject to resolution of
outstanding review items identified by the Engineering Review Memo in Exhibit
5 of the staff report and subject to approval of the two requested development
standards variances by the Board of Zoning Appeals.
Franz Is there a second?
Grabianowski Second
Franz Any further discussion? If there is none, all in favor signify by aye.
All Aye.
Franz Opposed by nay.
[No response]
Motion carries 6-0. Thank you very much.
Boyle/Davis Thank you.
Franz Next on the docket is 2022-16-DPA, Tim Lai/COhatch Modification, 75 North
Main Street, Zionsville, Petition for the Modification of the Development Plan
regarding building elevations in the (VBD) Village Business Zoning District. Is
the petitioner present? Online? Okay. Please proceed. Name and address. Thanks.
Lai Hi, um, good evening. Uh, my name is Tim Lai. I’m the architect of the project.
Um, um, my address is, uh, uh, 401, uh. West Town Street, Columbus, Ohio.
Franz All right. Thank you. Please proceed.
Lai Um, do you want me to kind of talk about the project in general?
Franz Yeah. I mean, just what the petition request is, reasons why, etc.
Lai I see. So, uh, okay, that’s that’s fine. That’s cool. So, um, so this is actually a,
um, um, a project that we got approved about a year ago. Um, it’s um, actually
you guys probably noticed, uh, it’s, uh, the COhatch, uh, building, um, that we
just got the temporary occupancy for the COhatch, uh, side, uh, and, uh, the, um,
the North High Brewing side, the restaurant side, is kind of finishing, uh, as, as
Page 9 of 17
Zionsville Plan Commission
April 18, 2022
we speak. The, um, one of the main reason why we come back, um, for this, uh,
small revision is because, um, when we submitted, originally submitted for the
approval, some of the engineering was not completed and, um, and, uh,
especially the, um, the rooftop unit, uh, at the back of the building, um, that
needed to be added on because of the restaurant use, um, and, uh, so we, um, we
have to add, you know, a rooftop unit basically on the back on the, on the east
side, uh, of the building and, uh, and there is some, uh, disconnect, uh, with the,
uh, with the revision when we filed for it and so, anyway, so now we are coming
back to, um, to present, um, a basically an updated design package of, of, um, of
the, of the site plan and the, and the exterior elevation. Uh, and that’s kind of the
majority of it is really that rooftop unit and how we propose to, screen part of it
and, and, and leave the outer part somewhat open so that we can actually
preserve the view of the, uh, of the circular, uh, window on the, on the east side,
um, as a suggestion from, from a neighbor, um, through, uh, communication with
our construction team. Uh, there’s some minor, um, adjustment also on the site
plan that we have to add a, uh, a small kind of, uh, rim, uh, in the patio area just
because the elevation was, was quite a bit different than what we originally, um,
anticipated so we have to add that for code reason really, uh, and then there’s a
couple of planter that we changed the colors. Um, and there’s also some
downspout configuration that we have to do, uh, uh, make adjustment, uh, from
the original design because of the, um, because just the way the, the, the roof and
the, the roof drains, uh, is needed to, to, to be adjusted. So that’s kind of the, the
main thing, um, for, for the package.
Franz All right. Thank you. Uh, is there anybody in the public who would like to
comment on this matter? Online? No? Roger, staff report. Thanks.
Kilmer Thank you. Uh, as Mr. Lai, um, mentioned, uh, the project before you is
Development Plan Amendments, uh, for the COhatch project. Uh, just to provide
you a little bit of a history, back on May 17 of 2021 the Plan Commission
approved, uh, Docket Number 2020-19-DP. That was for the renovation of a
10,800 square foot mixed use building, uh, which is now known as the COhatch
project. Uh, the petitioner is requesting to amend the, the plans and primarily the
building elevations, uh, that were approved at that meeting, uh, due to, um, uh,
some modifications they’ve had to make during the construction process. Um,
the, there are really four items that I highlighted within the staff report, uh, four,
the four largest items of the, uh, um, modifications. One is the addition of the
rooftop unit, uh, on, on the, uh, rear or east façade, um, and they are proposing a
screening element to that rooftop unit, as Mr. Lai mentioned, uh, around a
portion of it because they’ve had conversations with a neighbor who asked
essentially don’t screen the whole thing because we would prefer to be able to
see the round window on the rear façade and so they have, uh, accommodated
that request and that is what is reflected within your packet. Uh, the second, uh,
uh, item that I mentioned is really, second and third kind of go together, is that
the, uh, screening materials for, um, the, the dumpster enclosure and also the, um,
uh, mechanical yard on the, on the property had been proposed to be vertically
mounted composite material. Uh, they’ve changed that to a horizontally mounted
wooden material, uh, in both locations and then finally the, the, uh, last item I
noted was that the previously approved planter boxes would be changed from a
wooden material to a black metal product. Uh, the location of these planter boxes
would be, uh, essential on the south side of the outdoor dining area providing
Page 10 of 17
Zionsville Plan Commission
April 18, 2022
somewhat of a buffer between the seating area and an adjacent alley. Um, staff
does recommend approval of the Development Plan Amendments, uh, for this, in
this petition. I’d be glad to answer any questions you might have.
Franz All right. Thank you. At this point is there any questions or comments?
Lake Sure. Uh, what material are you, what type of wood, I guess I should say, are you
planning to, uh, use for the screen wall and what finish will it have around the
mechanical units?
Lai Uh, sure. So, um, the, the screen actually, um, because we do need to maintain
some kind of ventilation requirement so it is not a solid screen, uh, it is, as you
can see in the drawing, it’s, there’s active frames to it and the wood components
of it is actually going to wrap with a, a, um, a tube steel, uh, structure, uh, for, uh,
for, for the structural, uh, stability. And, um, so the wood components of that,
um, would be a, um, would be a, I believe it’s a painted cedar so there are two
colors to it one is the frame and the other is the, uh, we call it the lattice, which is
the open portion of the, of the wood frame, um, the color of that would be
painted to match the, the existing building. The existing building would basically
have a white trim for all the trim work and then have a kind of a, a taupe color for
the siding part of it. So it would match that basically. So the frame would be a
white color to match and then the, the ______ 35:50 would be the beige/taupe
colors if you will and then there’s also railing around it for the open portion it.
That would be a tube steel and that would be painted, uh, a kind of a, a warm, uh,
dark grey basically.
Lake Yeah. Painted cedar was really what I was concerned about versus treated
lumber.
Lai Right.
Lake Thank you.
Franz Roger, if this wasn’t the rooftop unit in that would this have come back to us or
would the other be viewed as minor and could be handled administratively?
Kilmer The, the rooftop unit on its own would have probably brought this back –
Franz Right.
Kilmer As a, as a major, uh, change for you and the other items on their own it is
possible they would’ve qualified as a minor.
Franz Okay.
Kilmer But, but when we saw the accumulative effect of everything –
Franz No, I, I mean, I was just –
Kilmer _______ 36:54 bringing that back.
Page 11 of 17
Zionsville Plan Commission
April 18, 2022
Franz Curious so about that. I figured it was primarily driven by the rooftop unit. Okay.
Lake I feel like the flower box change is an upgrade just from a maintenance
standpoint. To have the metal there. They’re going to have less maintenance than
a, a painted wood that’s got soil in it –
Franz Yeah.
Lake That’s getting watered all the time. So –
Franz All right. Any other questions or comments? Can we have a motion on this
matter?
Lake I move that Docket Number 2022-16-DPA, Development Plan
Amendment/Modification for the modifications of the previously approved
Development Plan Docket Number 2021-19-DP being in the Village Business
District (VBD) be approved based on the Findings in the staff report, staff
recommendation, materials as presented and the submitted Findings of Fact.
Franz Is there a second?
Jones Second.
Franz Any further discussion or comment? If not, all those in favor signify by aye.
All Aye.
Franz Opposed by nay.
[No response]
Motion carries 6-0. Thank you.
Lai Thank you very much.
Franz Additional items on the docket to discuss is the 2022 filing schedule. Wayne,
Roger? Who’s going to handle that?
DeLong Certainly, I actually have two quick items to, to walk you through. First is the, is
the listed item 2022 filing schedule. Certainly this, this body may recall in, in
2010 certainly there is a, a very strong attitude and then it continues to still carry
forward of, of to give the information and, and the picture that the Town of
Zionsville is open for business. And certainly one of your actions at that time was
to move your BZA to monthly meetings instead of, uh, bi-monthly. So that’s sort
of a representation of how, how times have changed. Now you have these bodies
and Boards that are meeting two nights in a row, heavy caseloads – these actions
probably will continue on, that intensity, and coupling that with the Plan
Commission historically receiving matters from the staff that may have ample
amount of items that are still open ended from a petitioner, uh, but certainly we,
that is left to petitioner to remedy, uh, prior to receiving a building permit.
Certainly the action of the enhanced caseload coupled against all of these other
items that are left open ended to be addressed during a final permit review is, uh,
Page 12 of 17
Zionsville Plan Commission
April 18, 2022
taxing the system a little, a little too much and then coupling that against,
coupling that against, uh, the, the caseload just generally speaking. So certainly
outlining for you that, you know, looking for your support of, of some concepts
first, uh, the petitions that we bring to you will be more finalized. Uh, they will
have less open-ended items, um, certainly working with petitioners to exercise,
uh, bringing you more petitions that are ready to go so to speak, um, certainly
working with petitioners so they understand that. Uh, secondly, is the idea of
lengthening your timeline from the time the petition comes in until the time it
actually comes to a hearing and this is to allow staff to work, uh, more diligently
to prepare this matter for ultimately a hearing and also to allow petitioner to
have, uh, things better put together. Uh, the 30-day time window that we’ve
given ourselves, uh, is rapid, um, is not typical for the market in terms of petition
processing so we feel like with these two, uh, ideas coupled together, um,
certainly the community will have better products to, uh, hear about at the
petition process because they will feel higher confidence in the number of items
that, uh, need to be, uh, addressed. Certainly, um, with your support of these, of
these concepts, we’ll move forward, uh, anything from, uh, amendments to your
rules of procedure, to modifications, to, to schedules and, and somewhere in
there, um, is the opportunity to just move to first class notice for, for, uh, for the,
the mailings, uh, just making that a codified portion of your rules of procedure
now. So there’s a couple of things, improvements just for the petition process
and, and moving things forward that way. So that’s the conclusion of this first,
uh, discussion topic.
Franz And the goal of this would be potentially to reduce continuance, continuations?
DeLong Certainly can be an outcome. Uh, it seems like an overall enhancement to the
program to have, uh, projects that are more ready to go so to speak, uh, less likely
to be continued, uh, and public seeing petitions that are, are more complete and
allowing staff to have more time to more thoroughly review projects.
Franz And then you would go through the rules of procedure and mod, I mean,
recommend modifications then we’d have to pass that?
DeLong If there are any.
Franz Right.
DeLong Yeah.
Franz So this really would be for more for 2023 or would you try to capture it for 2022?
DeLong We’re going to look at it today.
Franz Okay.
Clutter In my experience, it’s very common to from the time of filing until you get to the
Plan Commission or BZA to have 60 days and you guys are at 40-45.
DeLong Yeah.
Page 13 of 17
Zionsville Plan Commission
April 18, 2022
Clutter So that extra two weeks can go a long way in resolving a lot of these outstanding
issues before you actually hear it.
Franz So you would just move up the initial filing date?
DeLong Right. If it’s as simple as that then we would take care of that internally. I mean,
yes, we’ve always brought your filing schedule to you just so you’re aware of all
the steps. So these are things that we’ll make these adjustments and talk about it
next month.
Franz Okay.
Lake As an architect, I will tell you that you may get through your issues in that time
period but you’re going to get less finalized plans and drawings submitted to you
because of the amount of time that we have from when a project starts to when it
needs to be filed for you guys to review to when we need to get permits and what
the client is willing to pay for before they get approval. So, you may resolve
more of your issues but the drawings and stuff that we’re going to be looking at
may be less developed than they would otherwise be. I’m not suggesting we
don’t do it because I fully understand the time that you guys need – just
understand that this doesn’t, while it fixes lots of things, there are also potentially
some drawbacks, um, to this.
Franz And even if you tell somebody that it’s not, this is not ready to go – I mean, just
like, I mean, they can have their day in court whether it’s ready or not.
Clutter Uh huh.
Franz It’s essentially a right.
DeLong Correct. This doesn’t change the rules and certainly as, as Board members have
pointed out before, uh, there’s different levels of clarity that are offered by
drawings, um, and that, ultimately, if, if the petitioner wants to push the ball
forward, uh, absent staff’s suggestions, um, certainly sometimes projects that are
in front of you, uh, that are less than fully ready to go.
Franz Okay. Would this take a motion or is this just something that he can –
Clutter Yeah I think it’s, just a concurrence that Wayne and Roger will look at these and
see what changes –
Franz Okay.
Clutter Might be necessary to incorporate those types of things and then bring it back to
you for more formal approvals.
Franz Okay. Sounds good. What was the other item that –
DeLong Uh, certainly back on an email that we sent out earlier as a direct result of the
Town Council’s actions this morning, uh, on the 18th at their meeting, uh,
referencing, uh, a project that they’ve had conversations about in Creekside
Page 14 of 17
Zionsville Plan Commission
April 18, 2022
Corporate Park Lots 10 and 11, uh, Graham Rahal has a, has a business interest,
uh, in Brownsburg and that same business, business interest would be something
that would relocate potentially or expand, uh, to Zionsville and certainly that
conversation has engaged the, the Redevelopment Commission. Uh, this was a
presentation that was offered to them on March 28th, uh, you can fully see the
slide show that was offered and the, and the YouTube videos. Certainly it was
mentioned at the Town Council this morning because it’s also well known that
the use, the combination of uses, does not fully fit the PUD as it’s written today.
Uh, therefore, uh, if this project, uh, is to receive any consideration, uh, it would
require the, uh, the PUD to be updated, uh, to encapsulate the, uh, the land uses
that the, the Town will have the land uses that are, that are in the mix.
Franz And the process there would be the Town Council would request a change that
would come to us and then we would –
DeLong Well there’s a number of different ways. I mean certainly, certainly –
Clutter That’s one way.
DeLong Certainly this morning the Town Council, uh, made the statement that it did. Um,
at least Town Council President, uh, Plunkett. I, I did provide direction to Mr.
Plunkett where I thought very specifically as to, um, what wording could be used.
You may recall that you have seen, uh, both this, this happened two times prior,
uh, at least in my tenure here, uh, with the Calico Corners site and more recently
with the, uh, the Cato site. Um, certainly, um, certainly the Plan Commission if it
does not view this morning’s, uh, discussion as, uh, direction to commence with
the, the rezoning, certainly the Plan Commission, uh, in support, um, of the, of
the interest of the Town Council as represented in the video and certainly the, the
interest as indicated in the, uh, the RDC’s video, uh, from the body could, could
ask staff to commence with that rezoning activity. This was something that
would come back to your docket, uh, for, uh, for your June meeting.
Franz Would a, would a formal request from the Town Council, would that take a
motion or –
Clutter It, it would for the Town Council to do it but as Wayne mentioned, you can do it
on your own.
Franz Okay.
Clutter Um, so that’s one of, one of the different options. The Town Council can
formally move to, to have you –
Franz Okay.
Clutter Proceed forward with that but the Plan Commission has had authority statutorily
to do it on their own also –
Franz Okay.
Clutter If you’re so inclined.
Page 15 of 17
Zionsville Plan Commission
April 18, 2022
Franz Discussions/thoughts?
Walker I printed that off. It’s really interesting. I had seen some things they had in
Brownsburg because I was down there with some other leads and so I thought I
wonder if they would be moving any of that up here. It looks pretty neat.
Jones And just what parts of the PUD are we needing to modify?
DeLong Well certainly on Lots 10 and 11 at a minimum, um, full retail is not something
that is, uh, permitted by right. Certainly on Lots 10 and 11 it envisions a use and
you could have accessory retail such as a first floor restaurant or a bank
component or a coffee shop. Um, it does not fully speak to stand-alone buildings
that are 100% retail. So that’s just one of a few, uh, examples.
Lake I would say some of the architectural standards too that don’t, you know, don’t fit
with – I would even say the Zionsville theme for in talking about pediments and
columns and stuff that’s not – we don’t see in the Zionsville theme let alone
would see in a commercial building in that area either. I would just say that if
we’re going to make an accommodation for them that we try and look at the
entire site because I know that, uh, some of the things that they’re going to want
from a materiality or a use may also be able to be adapted in other areas of the
site and I would hate to give them, uh, a different standard than everybody else is
held to.
DeLong Yeah certainly that’s a great point. We, and in Creekside right now as the RDC’s
agenda last month indicated and certainly their agenda will indicate this month,
there are, there is strong interest in almost every lot in Creekside and almost
every lot in Creekside could benefit – any remaining open lot/for sale lot – uh,
could benefit from some PUD modifications. In looking at a PUD that is 6, 7
years old at this time and certainly any document needs to be refreshed, yes that
document has been refreshed four times, I believe, since it was written. Um,
zoning ordinances should constantly be updated to constantly adapting to
innovation and certainly also constantly adapting to market pressures and
changes and this is representative of that based on Town Council’s conversations
certainly they are focused on that. There are other opportunities here to look at
the remainder of the park in terms of other opportunities to modify zoning to be
more reflective of market and we would certainly look to take advantage of that.
Franz And if we wanted to direct Wayne and his team to start that, I mean, drafting that
we would make a motion for that, correct?
Clutter Correct sir.
Franz Anybody’s thoughts on this?
Grabianowski I think moving sooner than later is probably a good thing.
Franz Yeah.
Lake I think to Wayne’s comment there’s a lot of activity in the park –
Page 16 of 17
Zionsville Plan Commission
April 18, 2022
Franz Yeah.
Lake And we have, uh, really the chance right now with the conditions as they are that
if we can make some of these changes we may see that park be full this time next
year. At least with lots under design and/or construction.
Franz With complete development plans so we cannot continue it.
Lake Yes.
Clutter Working both of those in there at the same time.
Franz All right, so is there a motion to – what is it – begin, uh, a redraft or a
modification –
Clutter Modification of the Creekside PUD.
Franz Is there a motion?
Lake So moved.
Franz Is there a second?
Walker Second.
Franz Any further discussion? All in favor signify by aye.
All Aye.
Franz Opposed by nay.
[No response]
Motion carries 6-0. Is there anything else?
DeLong Thank you.
Franz Is there a motion to adjourn?
Grabianowski So moved.
Franz Second?
Lake Second.
Franz All in favor signify by aye.
All Aye.
Franz We’re adjourned.