Regular MeetingAlbany, NY · September 9, 2022
Agenda
CITY OF ALBANY, NY
BOARD OF CONTRACT AND SUPPLY
Friday, September 9, 2022
Present:
JOEL STETSON, Budget Department
DARIUS SHAHINFAR, Treasurer
MARISA FRANCHINI, Corporation Counsel
RANDALL MILANO, City Engineering
FRANK ZEOLI, Deputy Commissioner of DGS
This meeting is being held according to legislation signed by Governor Hochul extending the
ability for local governments to meet remotely to reduce the risk of COVID-19 spread. If the
legislation is revoked this will be an in person meeting. This meeting will be live streamed to
YouTube at: https://www.youtube.com/channel/UCw2w4CdeaI5sd8lQPUDlcyw
*Motion to accept the agenda made by Zeoli and seconded by Milano
*Motion to adjourn made by Milano and seconded by Shahinfar
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Page | 1 Affirmative 5 Negative 0
Friday, September 9, 2022
The following was offered on behalf of the Department of Recreation:
RESOLVED, that the Secretary be authorized and directed to advertise for bids for the
following:
SOUTH END FITNESS COURT
BIDS TO BE RECEIVED
Said proposals to be received by the Board at a regular meeting to be held on Tuesday, October 4
at 12:00 P.M. Bidders are not required to submit a deposit for entry.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 2
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: September 9, 2022
Title: South End Connector Phase II
Department: Department of Planning & Development
Name of Bidder Security Amount of Bid
No Bid Submissions
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 3
Friday, September 9, 2022
Mr. Milano offered the following:
Resolved, that the bid of the following named bidder be accepted and the contract
awarded to them, at and for the prices specified in their proposal, they being the lowest
qualified bidder and theirs being the lowest qualified bid, and that the Mayor be authorized
to sign the contract on behalf of the City and affix its seal thereto.
Project: Maintenance Contract for Pest Control Services
for Various City Owned Buildings
City of Albany, New York
Bidder: Attention Pest Solutions, LLC
233 Greenfield Avenue
Ballston Spa, NY 12020
Bid Amount: $16,323.84
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 4
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 4 to the
Beaver Creek Clean River Project Phase IV- Third Avenue Tunnel Contract with
Rifenburg Contracting Corp. for the amount of $36,400. This will increase the contract
amount to a new value of $7,609,278. There is no change to the Contract Completion
Date of October 3, 2022.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 5
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 1 to the
Beaver Creek Clean River Project Phase V- Electrical Contract with Kasselman Electric
Co, Inc. for the amount of $17,680. The will increase the contract amount to a new
value of $1,751,607. There is no change to the Contract Completion Date of December
15, 2022.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 6
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 2G-02 to the
Beaver Creek Clean River Project Phase 2 contract with Jett Industries, Inc. increasing
the contract value by $44,500.46. The new contract value is $2,014,786.33. The new
contract completion date is August 31, 2022.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 7
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 5G-06 to the
Beaver Creek Clean River Project Phase 3/5 Contract with Wm. J. Keller & Sons
Construction Corp in the amount of $360,500. The new Contract value is
$33,880,387.48. The contract completion date of December 15, 2022 is unchanged.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 8
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 1 to the
2022 Lead Service Replacement Project contract with Peter Luizzi & Bros Contracting
Inc. for the amount of $14,630.39. The will increase the contract amount to a new value
of $1,735,642.39. There is no change to the Contract Completion Date of October 31,
2022.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 9
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 1 to the 35
Erie Blvd. Site Improvements and Alterations Project HVAC Contract with RMB
Heating & Cooling, LLC. The new contract increases the completion time by 90 days,
bringing the new total days for contract completion to 260 days.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 10
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 1 to the 35
Erie Blvd. Site Improvements and Alterations Project Electrical Contract with O’Connell
Electric Company, Inc. The new contract increases the completion time by 57 days,
bringing the new total days for contract completion to 229 days.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 11
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 1 to the 35
Erie Blvd. Site Improvements and Alterations Project Plumbing Contract with RMB
Heating & Cooling, LLC. The new contract increases the completion time by 90 days,
bringing the new total days for contract completion to 260 days.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 12
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 1 to the
Marlborough Ct. & Northern Blvd. Improvements Contract with WM. J. Keller & Sons
Construction Corp. The new contract increases the completion time by 123 days, bringing
the new contract completion date to December 15, 2022.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Page | 13 Affirmative 5 Negative 0
Friday, September 9, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 3 to the 35
Erie Blvd. Improvements General Construction Contract with Murnane Building
Contractors, Inc. The new contract increases the completion time by 57 days, bringing the
new contract completion to 229 days.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Page | 14 Affirmative 5 Negative 0
Friday, September 9, 2022
APD Traffic Engineering Division has offered the Following:
Resolved, that in accordance with the existing contract provisions of City Contract
No.9051 that the bid of the following named contract be extended until July 31, 2023 and with no
increase to the original contract amount.
PROJECT: 2019 Traffic Signal Improvements (Various Locations) – Contract
#9051
BIDDER: Stilsing Electric Inc.
BID AMOUNT: Base bid: $2,019,833.00
Unchanged Project total: $2,019,833.00
New Project Completion date: July 31, 2023
Extension needed due to material supply chain delays and computer chip shortage for
materials needed to comple the project.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 15
Friday, September 9, 2022
APD Traffic Engineering Division has offered the Following:
Resolved, that in accordance with the existing contract provisions of City Contract
No.9044 that the bid of the following named contract be extended until May 31, 2023 and no
additional increase to the Contract amount.
PROJECT: Local Pedestrian Safety Action Plan – Contract #9044
BIDDER: Stilsing Electric Inc.
BID AMOUNT: Project Total: $257,958.40
New Project Completion date: May 31, 2023
Extension needed due to material supply chain delays for completing the project.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 16