Engineering Services Committee Meeting
Regular MeetingAugusta, GA · July 30, 2007
Agenda
Engineering Services Committee Committee Room- 7/30/2007- 1:30 PM
Meeting
ENGINEERING SERVICES
1. Motion to abandon an alley known as Telfair Lane to Attachments
Demarcpoint, LLC.
2. Approve award for Additional Design Services in the Attachments
amount of $84,775.00 to W.R. Toole Engineers, Inc.
(WRTE) in order to incorporate changes in design
requirements to both the Doug Barnard Parkway 16inch
Water Main and Lumpkin Rd 20inch Water Main
Improvements at the 90% stage of design.
3. Approve award for Additional Design Services in the Attachments
amount of $42,238.00 to Johnson, Laschober &
Associates, P.C. (JLA) in order to incorporate changes
from the original Horsepen Phase II design requirements
which are currently at 100% stage of design.
4. Approve award of design contract modification in the Attachments
amount of $36,742 to ZEL Engineers, Inc. for providing
additional engineering services for 3 separate
construction contracts in lieu of 2 for Project 10801-
Morgan Road Pump Station/Ft.Gordon 20” Water Main
Connection.
5. Approve the Engineering Department to authorize Attachments
Supplemental Agreement Number Three and Capital
Project Budget Change Number Three (CPB# 324-04-
203824335) authorizing the allocation of funds in the
amount of $29,000.00 to W.R. Toole Engineers, Inc. to
complete the design for the MM Scott Park in the Belair
Hills Subdivision.
6. Motion to approve changing Benson Drive to Benson Attachments
Road.
7. Motion to authorize condemnation of a portion of Attachments
Property # 052-0-117-00-0 3906 Carolyn Street, which
was owned by the late Jonathan and Christine Edwards,
for 1,025 Square Feet of Permanent Easement and 2,793
Square Feet of Temporary Easement. PW Project: Belair
Hills Subdivision Improvement Project.
8. Motion to authorize condemnation of a portion of Attachments
Property # 051-0-220-00-0 1608 Hilda Avenue and 051-
0-221-00-0 3917 Bolton Street, which are owned by
Leonard M. Gaines, for 2,000 Sq. Feet of Temporary
Easement. PW Project: Belair Hills Subdivision
Improvement Project.
9. Motion to authorize condemnation of a portion of Attachments
Property #065-2-003-00-0 3912 Padrick Street, which is
owned by Lonell and Carol Y. Spurgeon, for 653 Square
Feet of Right of Way and 1,802 Square Feet of
Temporary Easement. PW Project: Belair Hills
Subdivision Improvement Project.
10. Motion to authorize condemnation of a portion of Attachments
Property # 051-0-234-00-0 3946 Carolyn Street, which is
owned by Ruth N. Gray and Thomas D. Gray, for 3,805
Sq. Feet of Permanent Easement and 3,387 Sq. Feet of
Temporary Easement. PW Project: Belair Hills
Subdivision Improvement Project.
11. Approve of utility items to be constructed by Mabus Attachments
Brothers Construction, Inc., in the East Boundary
Drainage & Improvement Project in the amount of
$97,148.67.
12. Approve the Financial Closeouts of SPLOST projects that Attachments
were programmed over 10 years ago for the Engineering
Department and never designed or constructed. The
funding for these projects will be redirected back into
their respective Fund Recapture Account. (Referred from
July 10 Commission meeting)
13. Approve the purchase of a Trimble R8 GNSS Receiver Attachments
Kit, Data Collector and Accessories in the amount of $27,
455.75.
14. Motion to approve an Option for Right-of-Way between Attachments
Augusta, Georgia, as owner and Augusta, Georgia, as
optionee, in connection with the St. Sebastian Way
Project, for 0.206 acre (8,965.86 sq. ft.) in fee and 0.032
acre (1,410.21 sq. ft.) of permanent construction and
maintenance easement for the following property located
at 1522 & 1547 & 1548 Broad Street for a purchase price
of $86,100.00.
15. Report from the Utilities Department/Administrator Attachments
regarding the installation of the water main in the area of
the South Augusta Flea Market.
www.augustaga.gov
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Abandonment of an Alley known as Telfair Lane
Department: County Attorney - Stephen E. Shepard, Attorney
caption2: Motion to abandon an alley known as Telfair Lane to
Demarcpoint, LLC.
Background: Telfair Lane is a 0.05 acre tract of land, measuring 194.39
feet by 12 feet and is located off of 11th Street. Telfair Lane
runs parallel to and 160 feet south of Telfair Street, as shown
on the attached plat. Demarcpoint, LLC, is the current owner
of the adjacent parcel located between Telfair Lane and
Walker Street. Demarcpoint, LLC, desires the abandonment
of this property so that it may use it in conjunction with its
adjoining property.
Analysis: Abandonment of the property will not block egress or access
to any adjacent property owner.
Financial Impact: An appraisal valued the property's market value to be
$1,500.00.
Alternatives: Approve or deny the motion to abandon the alley known a
Telfair Lane.
Recommendation: Approve the motion to abandon the alley known a Telfair
Lane.
Funds are
Available in the
N/A
Following
Accounts:
REVIEWED AND APPROVED BY:
Cover Memo
Item # 1
Administrator.
Clerk of Commission
Cover Memo
Item # 1
Attachment number 1
Page 1 of 1
Item # 1
Attachment number 1
Page 1 of 1
Item # 1
Attachment number 1
Page 1 of 1
Item # 1
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Award Change Order for Design Contract for Augusta Utilities Department
Department: Augusta Utilities Department
caption2: Approve award for Additional Design Services in the amount
of $84,775.00 to W.R. Toole Engineers, Inc. (WRTE) in
order to incorporate changes in design requirements to both
the Doug Barnard Parkway 16inch Water Main and Lumpkin
Rd 20inch Water Main Improvements at the 90% stage of
design.
Background: The Lumpkin Rd 20-inch Water Main Improvements project
involves the design of 5,650 linear feet of 20-inch diameter
ductile iron pipe from the HWY56 and Lumpkin Rd
intersection to Doug Barnard intersection. Doug Barnard
Parkway 16-inch Improvements project involves the design
of 12,860 LF of 16-inch diameter ductile iron pipe along
Doug Barnard Parkway, starting North of I-520 to the
intersection of Gordon HWY. The design of both proposed
20-inch and 16-inch waterline is a transmission main that
will allow the Augusta Utilities Department to supply surface
water from the new N. Max Hicks Tobacco Road Water
Treatment Plant into areas primarily served by the existing
ground water system.
Analysis: Based on AUD's Hydraulic Model analysis, it was
determined that the current design pipe size of 20-inch
waterline on Lumpkin Rd and 16inch water line on Doug
Barnard Parkway does not meet upcoming projected water
demands. In addition, AUD is unable to obtain the necessary
easement for the last section of 3,000LF of water main on
Doug Barnard Parkway to Gordon HWY. Therefore this last
section of pipe has to be redesigned from the originally
proposed route of the east side to the more feasible route on
the west side of Doug Barnard. W.R. Toole Engineers, Inc.
submitted an acceptable proposal for additional design fees
to modify both plans which are currently at the 90% design
phase. The staff of the utilities department has reviewed the
Cover Memo
Item # 2
proposal and recommend award of the additional design fees.
Financial Impact: The change order for this project $84,775.00. These funds
are available from the following accounts:510043410-
5212115/80210168-5212115
Alternatives: 1. Reject WRTE Proposal, which would delay the design of
the project and the construction of the water main extension.
2. Approve WRTE Proposal for Additional Engineering
Design Fee to complete the design of the two waterline
projects.
Recommendation: It is recommended to award the Additional Design Fee to
W.R. Toole Engineers, Inc. in the amount of $84,775.00
Funds are
Available in the
510043410-5212115/80210168-5212115
Following
Accounts:
REVIEWED AND APPROVED BY:
Clerk of Commission
Cover Memo
Item # 2
Attachment number 1
Page 1 of 7
Lumpkin Road Water Main Project Plan Revisions
Project Limits (Update Existing Design): Professional services will be provided to revise
the existing Lumpkin Road Water Main Plans and specifications to reflect changes in the
pipe diameter size as requested by AUD.
Anticipated Services and Design Issues: The following services will be provided in
addition to the original scope of work outlined for the Lumpkin Road Water Main
Project:
• Update plan/profiles/easement maps and resubmit 90% Preliminary Plans and
attend 90% Review Meeting.
• Review/update permits as necessary.
• Update restrained joint calculations.
• Prepare 100% Final Plans and Specifications.
• Draft digital “red-line” construction plans. Field notes to be provided by
Contractor.
Deliverables: The following deliverables were considered for calculation of direct costs
and fee estimates:
• 90% Preliminary Plans – 8 Sets (Including revised easement maps)
• 100% Contract Documents Including Soil Erosion, Sedimentation and Pollution
Control Plans– 5 Sets
• One hardcopy and one digital copy of “red-lined” construction plans.
NOTE: 1 set of Contract Documents will be provided to the Purchasing
Department.
NOTE: WRTE does not anticipate a 30% or 60% Plan Submittal.
Doug Barnard Parkway Water Main Project – Phase I Plan Revisions:
Project Limits (Update Existing Design): Professional services will be provided to revise
the existing Doug Barnard Parkway Phase I Water Main Plans and specifications to
reflect changes in the route and change the pipe diameter size as requested by AUD. The
changes in alignment are due to conflicts with a parallel access road located along the
east side of Doug Barnard Parkway. Services will include the redesign of approximately
3,000 linear feet of the project beginning near Gordon Highway and continuing south
toward Dan Bowles Road.
Anticipated Services and Design Issues: The following services will be provided in
addition to the original scope of work outlined for the Doug Barnard Parkway Water
Main Project:
Item # 2
Attachment number 1
Page 2 of 7
• Coordinate with Atlanta Gas Light Company for crossing of gas mains.
• Coordinate with Atlanta Gas Light Company for determination of anode beds and
potential conflicts with ductile iron water mains.
• Assess options for PVC water mains in areas in conflict with anode beds.
• Coordinate with Georgia Power Transmission Department for permitting around
transmission poles located along Doug Barnard Parkway.
• Investigate options for wrapped piped in areas conflicting with anode beds or in
areas with corrosive soils.
• Develop new field survey required along west side of Doug Barnard Parkway to
update existing basemap.
• Coordinate with Georgia Department of Transportation for utility permitting in
R/W.
• Coordinate with Army Corp of Engineers for wetland impacts.
• Construction could potentially impact 6 property owners on west side of Doug
Barnard Parkway. Additional easement maps will be prepared.
• A sub-surface investigation will be prepared. Soil tests will be completed at 500
foot intervals at depths up to 6 feet. Soil PH will be addressed to identify
corrosive soils. Additionally, soil borings will be taken in areas proposed for jack
and bore construction to determine presence of rock and ground water.
• Evaluate wetlands on west side of Doug Barnard Parkway.
• Update plan/profiles/easement maps and resubmit 30% Preliminary Plans and
attend 30% Review Meeting.
• Review/update permits as necessary.
• Update restrained joint calculations.
• Prepare 90% Preliminary Plans, Final Easement Maps, and attend 90% Review
Meeting.
• Prepare 100% Final Plans and Specifications.
• Draft digital “red-line” construction plans. Field notes to be provided by
Contractor.
• WRTE anticipates utilizing DIPRA for field testing services. Should design
services be necessary then WRTE will utilize CORRPRO
Deliverables: The following deliverables were considered for calculation of direct costs
and fee estimates:
• 30% Preliminary Plans – 8 Sets (Including preliminary easement maps)
• Sub-surface investigation report.
• 90% Preliminary Plans – 6 Sets (Including final easement maps)
• 100% Contract Documents Including Soil Erosion, Sedimentation and Pollution
Control Plans– 5 Sets
• One hardcopy and one digital copy of “red-lined” construction plans.
Item # 2
Attachment number 1
Page 3 of 7
NOTE: 1 set of Contract Documents will be provided to the Purchasing
Department.
NOTE: WRTE does not anticipate a 60% Preliminary Plan Submittal.
Anticipated Permits: The following permits are anticipated for construction:
• Approval of Plans by GDOT - Utility Permit
• Approval of Plans by Georgia Power – Encroachment Permit
• Approval of Plans by Atlanta Gas Light – Encroachment Permit
• Approval of Plans by ACOE – Wetlands Nationwide Permit or Individual Permit
Professional Services: WRTE will provide all engineering services for this project with
in-house personnel. Probable sub-consultant services will include surveying/base
mapping, wetland delineation, environmental permitting and soil testing. WRTE has
successfully coordinated the professional services noted above with the following
professionals:
o Surveying/Base mapping: Toole Surveying Company, Inc. (Augusta,
GA)
o Wetland Delineation/Environmental Permitting: Graves Engineering
Services (Augusta, GA) and Sligh Environmental Consultants
(Savannah, GA)
o Geotechnical Evaluation: Graves Engineering Services (Augusta, GA)
Unforeseen Environmental Conditions (Corrosion Engineering)
WRTE will coordinate with DIPRA for field testing to determine the need for corrosion
testing/protection. Currently, these services are free for ductile iron pipe diameters less
than 30”. However, should DIPRA policy change or should there be a need for specialty
engineering services, then WRTE will utilize the services of CORRPRO. A lump sum
fee has been included for these services. WRTE will not utilize these fees without
submitting a separate fee proposal and receiving written authorization from AUD.
Item # 2
Attachment number 1
Page 4 of 7
Prime Consultant: W.R. Toole Engineers, Inc. Date: 2/13/2007
Proposal Number: P-06001A
Client: Augusta Utilities
Project Name: Doug Barnard /Lumpkin Road
County: Richmond
Man-Hour Summary
Principal-in-Charge Project Manager Engineering Tech Administrative Assist
Senior Engineer Staff Engineer Cadd Operator
Total
Phase I - Concept Validation 0 0 0 0 0 0 0 0
Phase II - Database Preparation 0 0 0 0 0 0 0 0
Phase III - Sub-Consultant Services 0 0 0 0 0 0 0 0
Phase Description
Phase IV - 30% Plans 0 8 28 0 30 60 0 126
Phase V - Easement Maps 0 0 0 0 0 0 0 0
Phase VI - 60% Plans 0 0 0 0 0 0 0 0
Phase VII - 90% Plans 0 12 40 0 38 52 0 142
Phase VIII - Final Plans 0 12 40 0 38 52 0 142
Phase IX - Construction 0 0 0 0 0 0 0 0
Totals 0 32 108 0 106 164 0 410
Cost Summary By Phase
Percentage
Cost Summary
Total Direct Cost of Cost
Total Labor
(Sub-Consultants & Reproduction Costs)
Total Phase Cost By Service
By Service
Phase I - Concept Validation $0.00 $0.00 $0.00 Engineering = $32,235.00 38.02%
Phase II - Database Preparation $0.00 $15,840.00 $15,840.00 Surveying = $15,840.00 18.68%
Phase III - Sub-Consultant Services $0.00 $34,000.00 $34,000.00 Environmental = $3,500.00 4.13%
Phase Description
Phase IV - 30% Plans $9,160.00 $330.00 $9,490.00 Geotechnical = $5,500.00 6.49%
Phase V - Easement Maps $0.00 $2,700.00 $2,700.00 Easement Maps = $2,700.00 3.18%
Phase VI - 60% Plans $0.00 $0.00 $0.00 Corrosion Engineering = $25,000.00 29.49%
Phase VII - 90% Plans $10,960.00 $330.00 $11,290.00 Total = $84,775.00 100.00%
Phase VIII - Final Plans $10,960.00 $495.00 $11,455.00
Phase IX - Construction $0.00 $0.00 $0.00
Total Estimated Cost = $84,775.00
Item # 2
Date: 2/13/2007
Project: P-06001A
Project Name: Doug Barnard /Lumpkin Road
County: Richmond
Phase IV: 30% Plan Man-Hour Estimates
Principal-In-Charge Engineering Technician
Project Manager Senior Engineer CAD Operator Administrator
Engineer % of Total
Task Item/ Task Description Total
1 Water Main Alignments 0 0 2 0 8 16 0 26 20.63%
2 Water Main Profiles 0 0 2 0 8 16 0 26 20.63%
3 Water Main Details 0 0 2 0 2 4 0 8 6.35%
4 Soil Erosion Control Plans 0 0 2 0 4 8 0 14 11.11%
5 Utility Coordinations 0 2 4 0 4 8 0 18 14.29%
6 GDOT Permitting 0 2 4 0 4 8 0 18 14.29%
7 Specifications 0 0 0 0 0 0 0 0 0.00%
8 Site Visits 0 0 0 0 0 0 0 0 0.00%
9 Meetings 0 4 4 0 0 0 0 8 6.35%
10 QA/QC 0 0 8 0 0 0 0 8 6.35%
11 Task 0 0 0 0 0 0 0 0 0.00%
12 Task 0 0 0 0 0 0 0 0 0.00%
13 Task 0 0 0 0 0 0 0 0 0.00%
14 Task 0 0 0 0 0 0 0 0 0.00%
15 Task 0 0 0 0 0 0 0 0 0.00%
16 Task 0 0 0 0 0 0 0 0 0.00%
17 Task 0 0 0 0 0 0 0 0 0.00%
18 Task 0 0 0 0 0 0 0 0 0.00%
19 Task 0 0 0 0 0 0 0 0 0.00%
20 Task 0 0 0 0 0 0 0 0 0.00%
0 0.00%
Totals 0 8 28 0 30 60 0 126 100.00%
Item # 2
Date: 2/13/2007
Project: P-06001A
Project Name: Doug Barnard /Lumpkin Road
County: Richmond
Phase VII: 90% Plan Man-Hour Estimates
Principal-In-Charge Engineering Technician
Project Manager Senior Engineer CAD Operator Administrator
Engineer % of Total
Task Item/ Task Description Total
1 Water Main Alignments 0 0 2 0 8 12 0 22 15.49%
2 Water Main Profiles 0 0 2 0 8 12 0 22 15.49%
3 Water Main Details 0 0 2 0 2 4 0 8 5.63%
4 Soil Erosion Control Plans 0 0 2 0 8 8 0 18 12.68%
5 Utility Coordinations 0 2 8 0 4 8 0 22 15.49%
6 GDOT Permitting 0 2 8 0 4 8 0 22 15.49%
7 Specifications 0 0 2 0 4 0 0 6 4.23%
8 Site Visits 0 0 0 0 0 0 0 0 0.00%
9 Meetings 0 6 6 0 0 0 0 12 8.45%
10 QA/QC 0 2 8 0 0 0 0 10 7.04%
11 Task 0 0 0 0 0 0 0 0 0.00%
12 Task 0 0 0 0 0 0 0 0 0.00%
13 Task 0 0 0 0 0 0 0 0 0.00%
14 Task 0 0 0 0 0 0 0 0 0.00%
15 Task 0 0 0 0 0 0 0 0 0.00%
16 Task 0 0 0 0 0 0 0 0 0.00%
17 Task 0 0 0 0 0 0 0 0 0.00%
18 Task 0 0 0 0 0 0 0 0 0.00%
19 Task 0 0 0 0 0 0 0 0 0.00%
20 Task 0 0 0 0 0 0 0 0 0.00%
0 0.00%
Totals 0 12 40 0 38 52 0 142 100.00%
Item # 2
Date: 2/13/2007
Project: P-06001A
Project Name: Doug Barnard /Lumpkin Road
County: Richmond
Phase VIII: Final Plan Man-Hour Estimates
Principal-In-Charge Engineering Technician
Project Manager Senior Engineer CAD Operator Administrator
Engineer % of Total
Task Item/ Task Description Total
1 Water Main Alignments 0 0 2 0 8 12 0 0 22 15.49%
2 Water Main Profiles 0 0 2 0 8 12 0 0 22 15.49%
3 Water Main Details 0 0 2 0 2 4 0 0 8 5.63%
4 Soil Erosion Control Plans 0 0 2 0 8 8 0 0 18 12.68%
5 Utility Coordinations 0 2 8 0 4 8 0 0 22 15.49%
6 GDOT Permitting 0 2 8 0 4 8 0 0 22 15.49%
7 Specifications 0 0 2 0 4 0 0 0 6 4.23%
8 Site Visits 0 0 0 0 0 0 0 0 0 0.00%
9 Meetings 0 6 6 0 0 0 0 0 12 8.45%
10 QA/QC 0 2 8 0 0 0 0 0 10 7.04%
11 Task 0 0 0 0 0 0 0 0 0 0.00%
12 Task 0 0 0 0 0 0 0 0 0 0.00%
13 Task 0 0 0 0 0 0 0 0 0 0.00%
14 Task 0 0 0 0 0 0 0 0 0 0.00%
15 Task 0 0 0 0 0 0 0 0 0 0.00%
16 Task 0 0 0 0 0 0 0 0 0 0.00%
17 Task 0 0 0 0 0 0 0 0 0 0.00%
18 Task 0 0 0 0 0 0 0 0 0 0.00%
19 Task 0 0 0 0 0 0 0 0 0 0.00%
20 Task 0 0 0 0 0 0 0 0 0 0.00%
Totals 0 12 40 0 38 52 0 0 142 100.00%
Item # 2
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Award Change Order to the Design Contract for Augusta Utilities Department
Department: Augusta Utilities Department
caption2: Approve award for Additional Design Services in the amount
of $42,238.00 to Johnson, Laschober & Associates, P.C.
(JLA) in order to incorporate changes from the original
Horsepen Phase II design requirements which are currently at
100% stage of design.
Background: The Horsepen Sanitary Improvements project involved the
design of sanitary sewer lines to service the Sand Ridge Area
of Tobacco Road. These improvements project is further
subdivided into two separate design projects, Phase I and
Phase II. The Phase II design involves 36,652 linear feet of
8-inch sanitary sewer line to serve the Sandrige subdivision
area.
Analysis: The construction effort for the Horsepen Phase I design was
not able to capture several properties along Crest Drive and
Pinnacle Place. In addition, during the Phase II design effort
to 100% stage, a large tract of property was subdivided into 5
separate parcels, and the route through a couple properties
had to be redesigned in order to meet current stream buffer
requirements. AUD has requested JLA to perform additional
design work to modify current Phase II 100% plans to
capture the changes due to environmental permitting and the
three line extensions to serve the additional properties
previously identified. JLA submitted an acceptable proposal
for additional design fees to modify the Phase II design plans
which includes engineering work for design of additional
3,755LF and preparation of 48 additional easement plats. The
staff of the Augusta Utilities Department has reviewed the
proposal and recommend award of the additional design fees.
Financial Impact:
The change order for this project $42,238.00. These funds
are available from the following accounts:510043420-
Cover Memo
Item # 3
5212115/80250202-5212115
Alternatives: 1. Reject JLA Proposal, which would delay the design of the
project and the construction of the water main extension. 2.
Approve JLA Proposal for Additional Engineering Design
Fee to complete the design of the two waterline projects.
Recommendation: It is recommended to award the Additional Design Fee to
JLA in the amount of $42,238.00
Funds are
Available in the
510043420-5212115/80250202-5212115
Following
Accounts:
REVIEWED AND APPROVED BY:
Clerk of Commission
Cover Memo
Item # 3
Item # 3
Item # 3
Item # 3
Item # 3
Attachment number 1
Page 5 of 8
Item # 3
Attachment number 1
Page 6 of 8
Item # 3
Attachment number 1
Page 7 of 8
Item # 3
Attachment number 1
Page 8 of 8
Item # 3
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Award design modification for Morgan Road pump Station Improvements and Ft. Gordon Water
Main Connection projects
Department: Utilities Engineering
caption2: Approve award of design contract modification in the
amount of $36,742 to ZEL Engineers, Inc. for providing
additional engineering services for 3 separate construction
contracts in lieu of 2 for Project 10801-Morgan Road Pump
Station/Ft.Gordon 20” Water Main Connection.
Background: An engineering contract in the amount of $247,000 was
awarded to ZEL Engineers June 6, 2006 to design an upgrade
to the Morgan Road pump station and to design a 20” water
main to service Tobacco Road and Ft. Gordon. The project
design included providing 2.5 MGD of water to Ft. Gordon
sourced from the Tobacco Road elevated Tank and upgraded
Morgan Road Pump Station and storage facility via a 20”
diameter pipeline. During the course of the design AUD
determined the project should be executed by 3 construction
contracts in lieu of 2. Three contracts will provide more
certainty that AUD will meet the scheduled required in the
Ft.Gordon/City of Augusta contract for water/sanitary sewer
services. Also, due to the nature of the work involved, 3
construction contracts are considered more practical to
execute. There is specialized work at the Morgan Road Pump
Station, special entry and clearance requirements installing
the pipeline on the Ft. Gordon Army installation, and
considerable construction concerns working on the busy
Tobacco Road corridor.
Analysis: ZEL Engineers submitted a proposal of $36,742 to prepared
3 sets of constructions plans and specifications as directed.
The proposal also includes additional normal engineering
services during the bidding and construction phases of the 3
contracts. The AUD staff evaluated the proposal and
considers it fair and reasonable and in line with prior design
costs for similar services.
Cover Memo
Item # 4
Financial Impact: The proposal submitted for this project change was $36,742.
These funds are available from accounts
#511043410/5212115 and 80310810/5212115.
Alternatives: None
Recommendation: It is recommended to award the design change order to ZEL
Engineers, Inc.
Funds are
Available in the
511043410/5212115 and 80310810/5212115
Following
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Administrator.
Clerk of Commission
Cover Memo
Item # 4
Attachment number 1
Page 1 of 1
Item # 4
Attachment number 2
Page 1 of 1
Item # 4
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Belair Hills Subdivision Change Number Three
Department: Engineering Department, Abie L. Ladson Director
caption2: Approve the Engineering Department to authorize
Supplemental Agreement Number Three and Capital Project
Budget Change Number Three (CPB# 324-04-203824335)
authorizing the allocation of funds in the amount of
$29,000.00 to W.R. Toole Engineers, Inc. to complete the
design for the MM Scott Park in the Belair Hills Subdivision.
Background: This project proposes to consolidate the dirt roads in the
Belair Hills Subdivision and allow them to be constructed
under one construction contract. This project also funded by
the Utility Department, and the MM Scott Park
Improvements funded by the Recreation Department.
Analysis: Currently, the design to improve the storm drainage and dirt
roads in Belair Hills Subdivision is completed. A large
portion of the City’s property where MM Scott is located has
been surveyed and designed to accommodate any additional
drainage. For an additional $29,000, W.R. Toole can
complete the survey and design for the MM Scott walking
trail. The design completion is scheduled for 1-1/2 months to
2 months. The construction of MM Scott Park Improvements
will be included in the construction bid for the Belair Hills
Subdivision project, but funded through the Recreation
Department.
Financial Impact: Funds are available through the Recreation Department in
account (325061110-5212115/206065006-5212115)
Alternatives: 1) Approve the Engineering Department to authorize
Supplemental Agreement Number Three and Capital Project
Budget Change Number Three (CPB# 324-04-203824335)
authorizing the allocation of funds in the amount of
$29,000.00 to W.R. Toole Engineers, Inc. to complete the
Cover Memo
Item # 5
design for the MM Scott Park in the Belair Hills Subdivision.
2) Do not approve and risk delaying the project.
Recommendation: Approve Alternative Number One.
Funds are
Available in the
325061110-5212115/206065006-5212115
Following
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Administrator.
Clerk of Commission
Cover Memo
Item # 5
Attachment number 1
Page 1 of 7
Item # 5
Attachment number 1
Page 2 of 7
Item # 5
Attachment number 1
Page 3 of 7
Item # 5
Attachment number 1
Page 4 of 7
Item # 5
Attachment number 1
Page 5 of 7
Item # 5
Attachment number 1
Page 6 of 7
Item # 5
Attachment number 1
Page 7 of 7
Item # 5
Attachment number 2
Page 1 of 1
AUGUSTA, GEORGIA
ENGINEERING DEPARTMENT
SUPPLEMENTAL AGREEMENT
Project No.: 324-04-203824335
SUPPLEMENTAL AGREEMENT NO.: 3
P.O.: 78600
WHEREAS, We, WR Toole Engineers, Inc. Consultant, entered into a contract with Augusta-
Richmond County on April 15, 2003, for engineering design services associated with the Belair
Hill Subdivision Improvements, Project No. 324-04-203824335, File Reference No. 06-014 (A),
and
WHEREAS, certain revisions to the design requested by Augusta, Georgia are not covered by
the scope of the original contract, we desire to submit the following Supplemental Agreement to-
wit:
Additional engineering services to the proposed detention pond located
In the center MM Scott Park.
It is agreed that as a result of the above modification the contract amount is increased by
$28,750.00 from $383,085.74 to a new total of $411,835.74.
This agreement in no way modifies or changes the original contract of which it becomes a part,
except as specifically stated herein.
NOW, THEREFORE, We, WR Toole Engineers, Inc., Consultant, hereby agree to said
Supplemental Agreement consisting of the above mentioned items and prices, and agree that this
Supplemental Agreement is hereby made a part of the original contract to be performed under
the specifications thereof, and that the original contract is in full force and effect, except insofar
as it might be modified by this Supplemental Agreement.
This 10th day of May, 2007.
RECOMMEND FOR APPROVAL:
CITY OF AUGUSTA, GEORGIA
Fred Russell, Administrator
Approved: Date Approved: Date
[ATTACHED CORPORATE SEAL]
ATTEST: ATTEST:
Title: Title:
(SA02 – For changes greater than $20,000) April 2005
Item # 5
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Benson Road
Department: Augusta Utilities Department
caption2: Motion to approve changing Benson Drive to Benson Road.
Background: On September 2, 2003, the Augusta Commission approved
the name Benson Drive for the new roadway, located off of
Richmond Hill Road, to the proposed Public Works and
Utilities buildings. Inadvertently, the roadway name was
picked up as Benson Road and all plans, plats, contracts and
other documents refer to Benson Road.
Analysis: For future projects, maintenance and reference, there needs
to be a clear paper trail on this roadway. Changing the name
on all of the records and documentation would be a major
monetary expense, whereas renaming Benson Drive to
Benson Road would be a change made in the mapping
system.
Financial Impact:
Alternatives: Do not approve renaming Benson Drive Benson Road and
revise all records and documentation.
Recommendation: Approve the name change from Benson Drive to Benson
Road.
Funds are
Available in the
N/A
Following
Accounts:
REVIEWED AND APPROVED BY:
Cover Memo
Item # 6
Finance.
Procurement.
Administrator.
Clerk of Commission
Cover Memo
Item # 6
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Condemnation - Jonathan and Christine Edwards
Department: County Attorney - Steven E. Shepard, Attorney
caption2: Motion to authorize condemnation of a portion of Property #
052-0-117-00-0 3906 Carolyn Street, which was owned by
the late Jonathan and Christine Edwards, for 1,025 Square
Feet of Permanent Easement and 2,793 Square Feet of
Temporary Easement. PW Project: Belair Hills Subdivision
Improvement Project.
Background: The appraised value of the easement is $633.00. Due to
inability to verify that Ms. Joyce I. Chandler is the trustee of
Mr. Jonathan Edwards and Mrs. Christine Edwards Estate.
Therefore, it is necessary to pursue condemnation.
Analysis: Condemnation is required in order to acquire easement.
Financial Impact: The necessary costs will be covered by the project budget.
Alternatives: Deny the authorization to condemn.
Recommendation: Approve the authorization to condemn.
Funds are
Available in the
G/L 324-04-1110-54.11120 J/L 203824335-54.11120
Following
Accounts:
REVIEWED AND APPROVED BY:
Administrator.
Clerk of Commission
Cover Memo
Item # 7
Cover Memo
Item # 7
Attachment number 1
Page 1 of 1
Item # 7
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Condemnation - Leonard M. Gaines
Department: County Attorney - Stephen E. Shepard, Attorney
caption2: Motion to authorize condemnation of a portion of Property #
051-0-220-00-0 1608 Hilda Avenue and 051-0-221-00-0
3917 Bolton Street, which are owned by Leonard M. Gaines,
for 2,000 Sq. Feet of Temporary Easement. PW Project:
Belair Hills Subdivision Improvement Project.
Background: The appraised value of this easement is $160.00. Due to
numerous unsuccessful attempts to contact the owner, it is
necessary to pursue condemnation.
Analysis: Condemnation is required in order to acquire the easement.
Financial Impact: The necessary costs will be covered by the project budget.
Alternatives: Deny the authorization to condemn.
Recommendation: Approve the authorization to condemn.
Funds are
Available in the
G/L 324-04-1110-54.11120 J/L 203824335-54.11120
Following
Accounts:
REVIEWED AND APPROVED BY:
Administrator.
Clerk of Commission
Cover Memo
Item # 8
Attachment number 1
Page 1 of 1
Item # 8
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Condemnation - Lonell and Carol Y. Spurgeon
Department: County Attorney - Stephen E. Shepard, Attorney
caption2: Motion to authorize condemnation of a portion of Property
#065-2-003-00-0 3912 Padrick Street, which is owned by
Lonell and Carol Y. Spurgeon, for 653 Square Feet of Right
of Way and 1,802 Square Feet of Temporary Easement. PW
Project: Belair Hills Subdivision Improvement Project.
Background: The appraised value of the easement is $666.00. Due to
unsuccessful attempts to obtain the necessary partial releases
from two banks for the purchase of the right of way, it is
necessary to pursue condemnation.
Analysis: Condemnation is required in order to acquire right of way
and temporary easement.
Financial Impact: The necessary costs will be covered by the project budget.
Alternatives: Deny the authorization to condemn.
Recommendation: Approve the authorization to condemn.
Funds are
Available in the
G/L 324-04-1110-54.11120 J/L 203824335-54.11120
Following
Accounts:
REVIEWED AND APPROVED BY:
Administrator.
Clerk of Commission
Cover Memo
Item # 9
Cover Memo
Item # 9
Attachment number 1
Page 1 of 1
Item # 9
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Condemnation - Ruth N. and Thomas D. Gray
Department: County Atotrney - Stephen E. Shepard, Attorney
caption2: Motion to authorize condemnation of a portion of Property #
051-0-234-00-0 3946 Carolyn Street, which is owned by
Ruth N. Gray and Thomas D. Gray, for 3,805 Sq. Feet of
Permanent Easement and 3,387 Sq. Feet of Temporary
Easement. PW Project: Belair Hills Subdivision
Improvement Project.
Background: The appraised value of the easement is $1,793.00. After
numerous unsuccessful attempts to reach Mr. McMullen of
McMullen and Associates, who represents the property
owners, it is in our best interest to pursue condemnation.
Analysis: Condemnation is required in order to acquire to the
easement.
Financial Impact: The necessary costs will be covered by the project budget.
Alternatives: Deny the authorization to condemn.
Recommendation: Approve the authorization to condemn.
Funds are
Available in the
G/L 324-04-1110-54.11120 J/L 203824335-54.11120
Following
Accounts:
REVIEWED AND APPROVED BY:
Administrator.
Cover Memo
Item # 10
Clerk of Commission
Cover Memo
Item # 10
Attachment number 1
Page 1 of 1
Item # 10
Engineering Services Committee Meeting
7/30/2007 1:30 PM
East Boundary Water & Sewer Construction
Department: Utilities
caption2: Approve of utility items to be constructed by Mabus Brothers
Construction, Inc., in the East Boundary Drainage &
Improvement Project in the amount of $97,148.67.
Background: The East Boundary Drainage Improvement Project is
currently under construction under the direction of the Public
Works Department. The project limits runs along East
Boundary from Broad Street to Laney Walker Blvd. During
construction of the new storm lines, Mabus Brothers
Construction found that there were sanitary sewer
connections to the old storm lines. The flow needs to be
removed as soon as possible. From this discovery it has been
determined that there is an area along East Boundary that
currently has no sanitary sewer piping in place. Approval of
this item will allow for the construction of 640 linear feet of
sewer main, along with the additional services that will tie to
the new main. It has also been determined that there is
approximately 525 linear feet of old AC waterline along East
Boundary. It is the desire of AUD to replace this old line
while the drainage improvement project is under
construction.
Analysis: The construction of 640 linear feet of sanitary sewer main
and appurtenances will allow for the sanitary sewer flow to
be removed from the new storm lines and will provide for the
needed sewer service along East Boundary. The construction
of 525 linear feet of new waterline will replace the old AC
waterline with a newer and more reliable waterline.
Financial Impact: Funds are available in the renewal & extension budget
507043420-5425210 / 80700050-5425210 in the amoount of
$97,148.67.
Cover Memo
Item # 11
Alternatives: 1) Leave the existing waterline in place and task Mabus
Brothers with the new sewer line only. 2) Obtain pricing
from other contractors for the construction of the new
waterline and/or the new sewer line
Recommendation: It is recommended to: Approve of utility items to be
constructed by Mabus Brothers Construction, Inc., in the East
Boundary Drainage & Improvement Project in the amount of
$97,148.67.
Funds are
Available in the
$97,148.67
Following
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Administrator.
Clerk of Commission
Cover Memo
Item # 11
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Financial Closeouts of Splost Projects
Department: Abie L. Ladson, P.E., Director Engineering Drpartment
caption2: Approve the Financial Closeouts of SPLOST projects that
were programmed over 10 years ago for the Engineering
Department and never designed or constructed. The funding
for these projects will be redirected back into their respective
Fund Recapture Account. (Referred from July 10
Commission meeting)
Background: Below is a list of projects budgeted over 10 years ago. No
documentation to initiate any activity to start the process of
any of these projects can be found in The Engineering
Department or The Finance Department. Therefore, in an
effort to continue the progress of funding current projects and
with the costs of construction rising, we are asking to redirect
funding from these projects to their respective Fund
Recapture Phase. Year Budgeted Project Project # Amount
Budgeted 1996 Crane Creek 296812303 $ 150,000
1996 Laney Walker@East B N/A $ 15,000 1996
Martin L. King Dr Imp 296812010 $ 273,794 1996
New Savannah Road 296823120 $ 1,431,000 1996
RaesCreek Ph II 296812305 $ 257,000 1996 Third
Level Cleaning 296812014 $ 491,506 1996 Willow
Creek N/A $ 40,000 1999 Fury Ferry Road
296823205 $ 22,000 1999 Walton Way Ext
299822370 $ 1,385,000 1999 Washington Sidewalk N/A
$ 176,000 2000 PhinizySwamp Drainage 200823170
$ 273,884 2002 Rifle Range 202824830 $
55,000 $ 4,570,184
Analysis: While these projects are still deemed important, it will be
beneficial and in the best interest of Augusta-Richmond
County to continue with the progress of current projects.
Financial Impact:
Funds will be transferred to the respective Recapture Phase
Cover Memo
Item # 12
Accounts.
Alternatives: 1) Approve the Financial Closeouts of SPLOST projects that
were programmed over 10 years ago for The Engineering
Department and never designed or constructed. The funding
for these projects will be redirected back into their respective
Fund Recapture Account. 2) Do not approve and discontinue
projects due to funding that are currently in progress.
Recommendation: Approve Alternative Number One
Funds are
Available in the
N/A
Following
Accounts:
REVIEWED AND APPROVED BY:
Clerk of Commission
Cover Memo
Item # 12
Engineering Services Committee Meeting
7/30/2007 1:30 PM
GPS / Glonass Receiver and Base Station
Department: Utilities
caption2: Approve the purchase of a Trimble R8 GNSS Receiver Kit,
Data Collector and Accessories in the amount of $27, 455.75.
Background: The Augusta Utilities Department maintains critical
infrastructure to support it's Water Production and
Wastewater Collection and Distribution Operations. The
Engineering Department has developed GIS tools and utilizes
GPS Technology to accurately locate, measure and inventory
Water and Sewer assets. Additionally, AUD is constructing
modifications to the water plant at Highland Avenue and the
JB Messerly Wastewater Plant. The existing rover will be
assigned to those projects to capture locations of piping and
valves during construction.
Analysis: The purchase of the R8 GNSS Unit will greatly enhance the
capabilites of our data collection process. It is a fully
integrated, lightweight receiver, antenna and datalink radio
that provides submeter accuracy and supports Modernized
GPS L2C and L5 signals as well as GLONASS L1/L2
signals. The R8 unit is capable of switching from base to
rover functions to provide greater flexibility in the field.
Financial Impact: $27,455.75 from account 506043110-5213119
Alternatives: No Alternatives
Recommendation: We recommend the purchase of the Trimble R8 GNSS
GPS/GLONASS unit and enhanced warranties in the amount
of $27,455.75 to support our expanding infrastructure,
including Fort Gordon.
Funds are
Cover Memo
Item # 13
Available in the
Following 506043110-5213119
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Administrator.
Clerk of Commission
Cover Memo
Item # 13
Attachment number 1
Page 1 of 1
Chuck Drouillard
Duncan-Parnell
3150 West Montague Ave
North Charleston, SC 29418
800-849-7710
Mobile: 843-709-3784
Fax 843-744-8073
chuckd@duncan-parnell.com
Quotation R8 GNSS GPS/Glonass eRTK Rover 6/22/07
Bill to: Ship to:
City of Augusta City of Augusta
Tom Carpenter Tom Carpenter
tcarpenter@augustaga.gov Augusta, GA. 30901
360 Bay St Tel 706-312-4150
Augusta, GA. 30901 Fax 706-312-4129
Qty Catalog # Description Price Total
Trimble R8 GNSS Receiver Kit with base accessories,
1 R8200-91-66 Internal UHF Receive Radio $22,258.50 $22,258.50
TSC2 w/Survey Controller and integrated bluetooth, 802.11b
1 TSC216 wireless, and 512Mb memory $5,315.25 $5,315.25
1 56044-00 TSC2 GPS Accessory Kit - Pole bracket, cabling $304.00 $304.00
1 48237-00 Discount - R8 GNSS Receiver with Data Collector -$2,500.00 -$2,500.00
2M Composite Prism Pole Lightweight, mobile, collapsible
1 5129-50 with fixed height pin $245.00 $245.00
1 5217-04 SECO Bipod Use for control points and site calibration $139.00 $139.00
1 47926-00 Pouch for Cell Phone $29.00 $29.00
Shipping $55.00
Subtotal $25,845.75
1 Year software and firmware updates included with Sales Tax $0.00
purchase. Additional 1 yr update agreements available. Total $25,845.75
Trade in credit for New Trimble GPS base or rover. 10" or
better digital theodolite or 7" or better electronic total station
1 48811-00 or old survey grade GPS - Offer Valid through Jun 30 2007 -$2,500.00 -$2,500.00
Trade In of Old Datalogger against new datalogger - Offer
1 48814-50 Valid through Jun 30 2007 -$1,000.00 -$1,000.00
Additional Warranties
TRIMBLE R8 Extended Warranty - Covers hardware and
1 EWR8 firmware $1,030.00 $1,030.00
TSC2 w/ Trimble Survey Controller Extended Warranty
Extended warranty includes hardware, application software,
firmware, and the Windows® CE operating system where
1 EWTSC2-SC applicable. $580.00 $580.00
Quoted prices are valid for 30 days. Thank you for the opportunity to submit this quotation.
Signed: Chuck Drouillard
Item # 13
Engineering Services Committee Meeting
7/30/2007 1:30 PM
Parcel 31 Acquisition of Right-of-Way,Tax Map: 036-1-140-00-0; 036-1-141-00-0; 036-1-142-00-0;
St. Sebastian Way/Greene St./15th St., GDOT Project No. DE-00MS(389), P.I. 26750, ARC
Project No. 327-04-296812003
Department: County Attorney - Stephen E. Shepard, Attorney
caption2: Motion to approve an Option for Right-of-Way between
Augusta, Georgia, as owner and Augusta, Georgia, as
optionee, in connection with the St. Sebastian Way Project,
for 0.206 acre (8,965.86 sq. ft.) in fee and 0.032 acre
(1,410.21 sq. ft.) of permanent construction and maintenance
easement for the following property located at 1522 & 1547
& 1548 Broad Street for a purchase price of $86,100.00.
Background: The property owner has agreed to convey a right-of-way for
the St. Sebastian Way Project.
Analysis: The purchase of the referenced property is necessary for the
improvements.
Financial Impact: The costs necessary for this purchase will be covered under
the project budget. The County will advance the necessary
funds for the purchase and the Georgia Department of
Transportation will reimburse the funds advanced by
Augusta, Georgia after acquisition of the property.
Alternatives: Deny the motion to approve the purchase of the referenced
property.
Recommendation: Approve the motion to purchase the referenced property.
Funds are
Available in the
Will be reimbursed by Georgia DOT.
Following
Accounts:
Cover Memo
Item # 14
REVIEWED AND APPROVED BY:
Administrator.
Clerk of Commission
Cover Memo
Item # 14
Item # 14
Item # 14
Item # 14
Item # 14
Engineering Services Committee Meeting
7/30/2007 1:30 PM
South Augusta Flea Market Water Main
Department: Clerk of Commission
caption2: Report from the Utilities Department/Administrator
regarding the installation of the water main in the area of the
South Augusta Flea Market.
Background:
Analysis:
Financial Impact:
Alternatives:
Recommendation:
Funds are
Available in the
Following
Accounts:
REVIEWED AND APPROVED BY:
Clerk of Commission
Cover Memo
Item # 15
Get email alerts for Augusta
A daily email when new agendas and minutes are posted.