Muyni
← Back to Ballwin

Planning and Zoning Commission Meeting

Regular Meeting

Ballwin, MO · November 1, 2021

AgendaPacketMinutes

Minutes

MINUTES OF THE PLANNING AND ZONING COMMISSION MEETING 1 GOVERNMENT CTR  BALLWIN MO 63011 NOVEMBER 1, 2021 Chairman Weaver called the meeting to order at 7:00 p.m. Members in attendance were: PRESENT ABSENT Chairman Mark Weaver Commissioner Mike Swain Secretary Olivia Pieknik Commissioner Victoria Winfrey Commissioner Grant Alexander Alderman Michael Finley Commissioner Gary Carr Commissioner Chad Silker Mayor Tim Pogue Planning Technician Shawn Edghill City Attorney Robert E. Jones Approval of Minutes A motion was made by Mayor Pogue to accept the minutes of the July 6, 2021 meeting as submitted. Commissioner Silker seconded the motion, which received unanimous approval from the Commission members present. Capital Improvement Plan Budget Finance Officer Denise Keller presented the 2022 Capital Improvement Plan Budget (CIP) for review per Section 89.380 of the Revised MO Statutes, which states that all improvements to land, infrastruc- ture and public facilities are to be reviewed by this commission before being approved by the Board of Aldermen. Our CIP only includes true capital projects. These are defined as: land and building acquisition, major land and building improvements with a cost of $250,000 or more, and systems reconstruction or replace- ment with a cost of $250,000 or more. We also include all major street, culvert and bridge reconstruc- tion projects that are partially offset by federal grants. Any design or planning work for capital pro- jects is also included in the CIP. A recurring expense in this budget is the TIF municipal revenues. They are the City’s contribution to the Old Town Center TIF bond repayments and are calculated based upon the prior year TIF sales tax collections. We anticipate expense of $64,335 to be paid out in 2022 and $48,300 in 2023. The final bond maturity is in October, 2022 and at that time the TIF District will terminate. In 2023 there will be the final payment of taxes collected in 2022. One major Park project is planned in 2022. This is redevelopment of Holloway Park incorporating recommendations from the 2019 Parks Master Plan. Total expenses are budgeted at $552,600. A Land Water Conservation Fund (LWCF) grant has been applied for and we expect to learn if it will be ap- proved in January. The amount requested was $271,300. If the grant is not approved the project will be delayed until another funding source is found. Planning & Zoning Commission Meeting Minutes November 1, 2021 Page 1 The Parks Master Plan advised the preparation of a stand-alone Master Plan for Vlasis Park because of its complexity. That is currently in progress and is being conducted by The Lawrence Group. Con- struction in Vlasis Park is tentatively scheduled for 2023 and 2025, with the hope that Municipal Park Grants can be used to offset the costs. Historically, Muni Park Grants are not received in consecutive years, hence the spread in time. Major elements identified thus far during a recent stakeholder meet- ing are walking/biking paths and improvements to the playground, lakes and pavilions. The cost esti- mates at this point are just ballpark numbers. In 2024 we hope to replace the playground adjacent to The Pointe. The cost is expected to be $300,000, and we will apply for a LWCF grant of $150,000. In 2026 we hope to make improvements to the lake in New Ballwin Park at a cost of $500,000, with 95% offset by grant funding. Detailed design work for the new police building is nearly complete. With permission from the Board of Aldermen, construction for this project will be put out for bid in December, 2021. $8.5 million of the construction cost is expected to be incurred in 2022, with the remaining $3.4 million is 2023. Proposed funding for this project will be discussed at a meeting of the Finance Committee immedi- ately preceding the Board of Alderman meeting on November 8th. Funding sources will include the Public Safety tax, the Infrastructure Fund and monies received from the American Rescue Plan Act. Outside financing is not currently expected. Engineering design for the resurfacing of New Ballwin Road from Manchester Road to Twigwood Drive is in progress now, and construction will occur in 2022. This project encompasses pavement resurfacing, curb repair, ADA ramp replacements and upgrades to the intersection pedestrian signal. It also includes 25 new streetlights which will be the property of the city. Total construction cost will be $873,204 with offsetting federal funds of $652,863. Last week the City was awarded federal funding for the resurfacing of Ries Road. Engineering will oc- cur in 2022 at a cost of $85,577 and construction will be in 2024 at a cost of $919,956. Another element of the Vlasis Park master plan is a needs analysis of the Public Works yard. Expen- sive equipment needs to be moved under cover and space is at a premium. Cost to address these needs is preliminarily estimated at $1,000,000. Revenues to fund the 2022 capital projects will come from five different sources: an allocation of sales taxes of $1,258,000, an LWCF grant of $271,300, a Federal Highway grant passed through MoDOT of $652,863, a transfer from the general fund of $7,740,000 and beginning capital fund balance of $242,210. Total revenues budgeted are $10,164,373. All expenses combined for 2022 total $10,154,565, with a residual fund balance expected of just under $10,000. Mayor Pogue made a motion to approve the Capital Improvement Plan Budget. Commissioner Silker seconded the motion, which received unanimous approval from the Commission members present. Adjournment Secretary Pieknik made a motion to adjourn the meeting. Commissioner Alexander seconded the mo- tion, which received unanimous approval from the Commission members present. The meeting was ad- journed at 7:33 p.m. J. Mark Weaver, Chairman Planning & Zoning Commission Planning & Zoning Commission Meeting Minutes November 1, 2021 Page 2

Agenda

PLANNING AND ZONING COMMISSION MEETING 1 GOVERNMENT CTR, BALLWIN, MO 63011 MONDAY, NOVEMBER 01, 2021 at 7:00 PM AGENDA 1. Call to Order 2. Approval of Minutes a. July 6, 2021 Meeting Minutes 3. Agenda Items a. SUE 21-04 - Amended Special Use Exception Tim King of Crown Castle, USA, is requesting the Commission review a request for the amendment of a previously approved Special Use Exception to allow for the removal of a flag on a disguised support structure at 884 Woods Mill Rd. The current structure is designed to appear disguised as a flagpole housing four antenna bays. According to the petitioner, Bay 3 cannot house a new antenna intended for Dish Network due to conflict with the flag. The flag is required per Ordinance 02-01 which includes under Exhibit One, (16): “…The flag shall be proportional in size to the flagpole with a size of approximately 20 feet x 30 feet.” b. Capital Budget 2022 4. Adjourn NOTE: Due to ongoing City business, all meeting agendas should be considered tentative. Additional issues may be introduced during the course of the meeting. ADA NOTICE: Residents of Ballwin are afforded an equal opportunity to participate in the programs and services of the City of Ballwin regardless of race, color, religion, sex, age, disability, familial status, national origin or political affiliation. If one requires an accommodation, please call (636) 227-8580 V or (636) 527-9200 TDD or 1-800-735-2466 (Relay Missouri) no later than 5:00 p.m. on the third business day preceding the hearing. Offices are open between 8:00 a.m. and 5:00 p.m. Monday through Friday.

Get email alerts for Ballwin

A daily email when new agendas and minutes are posted.

Report an issue with this meeting