Utilities Commission Meeting
Regular MeetingBaxter, MN · April 5, 2023
Minutes
UTILITIES COMMISSION MEETING
MINUTES
Wednesday, April 05, 2023 at 5:30 PM
Baxter City Hall, 13190 Memorywood Drive, Baxter, MN
“A Growing Community”
CALL TO ORDER
The regular meeting of the Baxter Utilities Commission was called to order at 5:30 p.m. by Chairman Rock Yliniemi.
ROLL CALL
MEMBERS PRESENT: Commissioners John Brenny, Jack Christofferson, Douglas Stenberg, Chairman Rock Yliniemi,
and Council Liaison Mark Cross.
MEMBERS ABSENT: None.
STAFF PRESENT: Public Works Director/City Engineer Trevor Walter, Assistant City Engineer Trevor Thompson, and
Administrative Assistant Mary Haugen.
OTHERS PRESENT: Bolton & Menk Consulting Engineer Bryan Drown, SEH Consulting Engineers Alex Voit, and
WiDSETH Consulting Engineer Alex Bitter.
CONSENT AGENDA
1. Approve the Utilities Commission Minutes from March 8, 2023
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to approve the Utilities
Commission Minutes of March 8, 2023. Motion carried unanimously.
BUSINESS ITEMS
2. Recommend Planning and Zoning approve the Preliminary & Final Plat of Batten Addition with the
Proposed Side Yard Setback Variance
Assistant City Engineer Thompson reviewed the Preliminary & Final Plat of Batten Addition. The
property owner currently owns Lots 1 & 2, of Block 1, Forestview-on-the-River Plat. The existing house
is located on Lot 2 and the detached garage is located on Lot 1. The proposed plat adjusts the lot line
between Lot 1 and Lot 2 by 34.88 feet to the east at the right-of-way. The lot line adjustment allows
the detached garage to be incorporated into Lot 2.
Mr. Thompson explained that by adjusting the lot line 34.88 feet to the east, the proposed plat will
meet the 100-foot minimum road frontage for Lot 1, but a side yard setback variance is needed for
the detached garage on Lot 2.
A requirement for platting is access to connect to city sewer and water. Each of the existing lots
received a sewer and water service with the 2020 South Interceptor and North Forestview
Improvements Project, after replating, each lot will still have a water and sewer service.
4/5/2023 Utilities Commission Meeting Minutes Page 2
Staff recommends approval of the Preliminary & Final Plat for the Batten Addition with the following
conditions:
1. Waive additional 7-feet of right-of-way.
MOTION by Commission Brenny, seconded by Commission Stenberg to recommend Planning and
Zoning approve the Preliminary & Final Plat of Batten Addition with the Proposed Side Yard Setback
Variance. Motion carried unanimously.
3. Recommend Planning and Zoning approve the Stoes Perch Preliminary & Final Plat
Assistant City Engineer Thompson reviewed the Preliminary & Final Plat of Stoes Perch. Mr.
Thompson explained the property owner is proposing to combine two parcels on the south side of
Perch Lake. The smaller parcel due to state shoreland regulations cannot be sold separately from the
adjacent larger parcel.
The proposed plat includes the existing 30-foot utility easement for the City sewer and water from the
2007 South Perch lake improvements Project along with the required 10-foot drainage and utility
easement adjacent to road and a 5-foot drainage and utility easement on all interior lot lines.
MOTION by Commissioner Christofferson, seconded by Commissioner Brenny to recommend Planning
& Zoning approve the Stoes Perch Preliminary & Final Plat. Motion carried unanimously.
4. Sanitary Sewer Mercury Testing Results Update
Public Works Director/City Engineer Walter informed the commission that Brainerd Public Utilities
contacted the City regarding higher levels of Mercury that were detected in the influent and effluent
water.
Testing for mercury in the City’s lift stations was performed on Monday, March 27, 2023 to try and
determine where the higher mercury concentrations are coming from and the results are listed below:
Lift Station No. 1 – 249
Lift Station No. 2 – 34.6
Lift Station No. 10 – 728
Lift Station No. 11 – 1650
Lift Station No. 13 – 18.9
Lift Station No. 16 – 29.5
Lift Station No. 18 – 57.5
Lift Station No. 24 – 13.6
Common use for mercury and mercury compounds are in amalgam for dental restoration, some food
manufacturing operations and is also used in fluorescent lighting.
Staff will be working on finding the root source and more testing will be conducted next week.
5. Adopt Title 8, Chapter 5 Stormwater Control and Regulations City Code of the Baxter City Code
Assistant City Engineer Thompson gave a brief review of the HR Green Agreement to perform updates
to the City’s Stormwater Ordinance language to modernize the ordinance and keep it in line with
Minnesota Pollution Control Agency requirements for the City’s MS4 Permit.
4/5/2023 Utilities Commission Meeting Minutes Page 3
A draft was submitted in 2022 and presented to the Utilities Commission but progress was paused
following the draft submission. HR Green has now completed this task and the design manual as
referenced in the city code.
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to adopt Title 8, Chapter 5
Stormwater Control and Regulations of the Baxter City Code. Motion carried unanimously.
6. Adopt City of Baxter Stormwater Design Manual
Assistant City Engineer Thompson stated that the Stormwater Design Manual has guidelines which
are meant to serve as a technical supplement to the City’s new Stormwater Ordinance language. The
design guidelines encourage infiltration where possible, promote the removal of suspended solids
and phosphorus from stormwater before entering the Mississippi River, and standardizes modeling
practices and design criteria for storm sewer, stormwater ponds, and erosion control efforts.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to adopt the City of
Baxter Stormwater Design Manual. Motion carried unanimously.
7. Approve the HR Green General Engineering Services Contract
Public Works Director/City Engineer Walter informed the commission this is the basic engineering
contract to assist the City of Baxter with general engineering services contract for upcoming non-
project specific tasks, such as stormwater construction compliance inspections during the summer of
2023.
Chairman Yliniemi inquired if HR Green has an office in town to assist with the stormwater
inspections. Mr. Walter stated there is no local office and that WiDSETH has helped out over the past
couple of years and their employees came up from Alexandria so the City has been paying travel
time. Mr. Walter stated that HR Green is the most familiar with the City’s stormwater code and MS4
Permit.
MOTION by Commissioner Christofferson, seconded by Commissioner Brenny to approve the HR
Green General Engineering Services Contract. Motion carried with Chairman Yliniemi voting no.
8. Approve the HR Green 2023 Municipal Separate Storm Sewer System (MS4) Program Contract in
the Not to Exceed Amount of $14,980.00.
Assistant City Engineer Thompson reviewed the HR Green 2023 Municipal Separate Storm Sewer
System (MS4) Program Contract. This contract is tied to the 2021 contract to provide assistance with
updating items related to its Municipal Separate Storm Sewer System (MS4) permit.
Mr. Thompson stated the project was not completed last year due to a staff workload and change in
personnel at HR Green and under this contract HR Green will provide various elements for the City’s
MCM programs which are currently not in compliance with the State of Minnesota.
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to approve the HR Green
2023 Municipal Separate Storm Sewer System (MS4) Program Contract in the not to exceed amount
of $14,980.00. Motion carried unanimously.
4/5/2023 Utilities Commission Meeting Minutes Page 4
9. 2022 Foley Road, Isle Drive, and Forthun Road Improvements Project Update, City Improvement
No. 4114
There was no new information or questions from the commission or the public.
10. Approve RL Larson Excavating, Inc. Change Order No. 7 in the increased amount of $20,154.16 for
the 2022 Foley Road, Isle Drive, and Forthun Road Improvements Project Update, City
Improvement No. 4114
Bolton & Menk Consulting Engineer Drown reviewed the RL Larson Excavating Change Order No. 7 in
the increased amount of $20,154.16 for the 2022 Foley Road, Isle Drive, and Forthun Road
Improvements Project.
Change Order No. 7 includes the following items:
Removing two concrete median sections at Isle Drive and Forthun Road mini roundabout and
replacing them with 8” thick concrete.
Constructing a 40’ long x 2.5’ wide x 8” thick concrete truck apron on north side of mini
roundabout.
Mr. Drown has no concerns with Change Order No. 7 and recommended approval.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the RL
Larson Excavating, Inc. Change Order No. 7 in the increased amount of $20,154.16 for the 2022
Foley Road, Isle Drive, and Forthun Road Improvements Project. Motion carried unanimously.
11. 2022 Trunk Highway 210 & Inglewood Drive Railway Crossing Improvements Project Update -
Municipal Project No. 4121
Bolton & Menk Consulting Engineer Drown informed the commission a Preconstruction meeting was
held on March 29th and the project will start up on May 2, 2023.
12. Approve Anderson Brothers Construction Change Order No. 1 in the amount of $29,195.82 for 2022
Trunk Highway 210 & Inglewood Drive Railway Crossing Improvements Project
Bolton & Menk Consulting Engineer Drown reviewed the Anderson Brothers Construction Change
Order No. 1 in the increased amount of $29,195.82 for the 2022 Trunk Highway 210 & Inglewood
Drive Railway Crossing Improvements Project
Change Order No. 1 includes the following items:
Adding a concrete median and south bound stop sign at the north leg of the Inglewood Drive
and Fairview Road intersection. This will create a 3-way stop condition like the Woida Road
and Edgewood Drive intersection to keep traffic control consistency within the City for these
frontage road intersections.
Revising the east bound right turn lane from TH 210 to Inglewood Drive.
Mr. Drown has no concerns with Change Order No. 1 and recommended approval.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve Change
Order No. 1 in the amount of $29,195.82 for the 2022 Trunk Highway 210 & Inglewood Drive Railway
Crossing Improvements Project. Motion carried unanimously.
4/5/2023 Utilities Commission Meeting Minutes Page 5
13. Approve the BNSF Invoice 90248987 in the amount of $30,128.18 for the 2022 TH 210 and
Inglewood Drive Improvements Project, City Improvement No. 4121
Bolton & Menk Consulting Engineer Drown reviewed BNSF Invoice 90248987 in the amount of
$30,128.18. The invoice includes work completed between 1/18/2023 and 2/14/2023 related to the
railway signal. The invoice includes bill preparation, signal material, and material handling costs.
MOTION by Commissioner Brenny, seconded by Commissioner Christofferson to approve the BNSF
Invoice 90248987 in the amount of $30,128.18 for the 2022 TH 210 and Inglewood Drive
Improvements Project. Motion carried unanimously.
14. Approve Plans & Specifications and Authorize Advertisement for Bids for 2023 Micro Surfacing
Project
Bolton & Menk Consulting Engineer Drown stated the signed plan were in the Utilities Commission
packet and inquired in anyone had any question or comments to be incorporated into the plans. The
commissioner had no questions or comments.
MOTION by Commissioner Christofferson, seconded by Commissioner Brenny to approve plans and
specifications and order advertisement for bids for the 2023 Micro Surfacing Project. Motion carried
unanimously.
15. 2023 Knollwood Drive Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
16. Approve the Knife River Corporation – North Central Change Order No. 1 in the Increased Amount
of $15,000 for the 2023 Knollwood Drive Improvements Project
WiDSETH Consulting Engineer Bitter reviewed the Knife River Corporation – North Central Change
Order No. 1 in the increased amount of $15,000.00 for the 2023 Knollwood Drive Improvements
Project
Change Order No. 1 includes the following items:
At the time of bidding, a $15,000 Cash Allowance was added by addendum for Irrigation
System Repairs. This addendum was recognized and the $15,000 was included in the
Contractors Bid. A clerical error took place as the final award documents and resolutions
were being drafted and the $15,000 allowance was omitted from the total project cost.
WiDSETH reviewed the omission with Knife River, and it was agreed to add the $15,000
allowance to the total project cost by Change Order.
Mr. Bitter has no concerns with Change Order No. 1 and recommended approval.
MOTION by Commissioner Christofferson, seconded by Commissioner Brenny to approve Change
Order No. 1 in the amount of $29,195.82 for the 2022 Trunk Highway 210 & Inglewood Drive Railway
Crossing Improvements Project. Motion carried unanimously.
17. Lift Station 13 Reconstruction Project Update
There was no new information or questions from the commission or the public.
4/5/2023 Utilities Commission Meeting Minutes Page 6
18. Accept the Anderson Brothers Construction Company of Brainerd, LLC Lump Sum Bid in the
Amount of $180,217.07 for the Lift Station No. 13 Reconstruction project and increase the project
budget from $240,000.00 to $251,117.07
WiDSETH Consulting Engineer Bitter informed the commission that pursuant to authority of the City
Council and after proper legal advertisement, bids for the reconstruction of Lift Station No. 13, located
on Forest Drive and just north of Excelsior Road, were obtained on Thursday, March 30, 2023, at 4:00
P.M., at the Baxter City Hall.
The City received the following bids:
Anderson Brothers Construction $180,217.07
CCS Contracting, Inc. $189,500.00
TNT Construction Group, LLC $218,800.00
Tom’s Backhoe Service, Inc. $230,000.00
Engineer’s Estimate $160,000.00
The City received a total of four bids. The apparent low bidder is Anderson Brothers Construction
Company of Brainerd, LLC with a lump sum bid of $180,217.07.
Anderson Brothers bid was not read aloud at the bid opening because they did not acknowledge
issuance of Addendum 3. Addendum 3 was issued late on Wednesday, March 29, 2023, just one day
prior to the bid opening. The Addendum clarified that all discharge piping in the wet well above the
pump base elbows needed to be furnished and installed by the contractor.
Anderson Brothers has acknowledged in writing their material supplier was aware of Addendum 3 and
the costs for the wet well piping and fittings is included in their lump sum bid. The City Attorney has
reviewed the issue and determined the City has discretion to say the omission was not material and
can accept the bid.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to accept the
Anderson Brothers Construction Company of Brained, LLC’s Lump Sum Bid in the Amount of
$180,217.07 for the Lift Station No. 13 Reconstruction Project and increase the project budget from
$240,000.00 to $251,117.07.
INFORMATIONAL ITEMS
19. 2022 Full Depth Reclamation and Reconstruction Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
20. 2023 Commercial and Residential Full Depth Reclamation Improvements Project & Quiet Zone
Design, Implementation, and Notification Monthly Update
There was no new information or questions from the commission or the public.
21. 2023 Cypress Drive and Douglas Fir Drive Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
22. 2024 Mill & Over and Full Depth Reclamation Improvements Project Monthly Update
4/5/2023 Utilities Commission Meeting Minutes Page 7
There was no new information or questions from the commission or the public.
23. 2024 Design Road & TH 371 Stormwater Improvements Project Update
There was no new information or questions from the commission or the public.
24. 2024 South Forestview Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
25. Brainerd Public Utilities Electric Consumption Notice
There was no new information or questions from the commission or the public.
26. Brainerd Public Utilities Solar Array Screening Concept Plan and Bluff Analysis Update
There was no new information or questions from the commission or the public.
27. Eagle Drive Area Improvements Feasibility Study Project Monthly Update
There was no new information or questions from the commission or the public.
28. Project Update – 2023 Evergreen Drive Improvements Feasibility Study
There was no new information or questions from the commission or the public.
29. Holiday Station Store Contamination Project Monthly Update
There was no new information or questions from the commission or the public.
30. Inglewood Drive to Garrett Lane Stormwater Outlet Study Project Monthly Update
There was no new information or questions from the commission or the public.
31. Lift Station 16 Reconstruction Project Monthly Update
There was no new information or questions from the commission or the public.
32. MnDOT Highway Users Tax Distribution Fund for Local Road and Bridges (2023)
There was no new information or questions from the commission or the public.
33. Section 6 Area A1 Outlet Project Monthly Update
There was no new information or questions from the commission or the public.
34. TH 210 Street Lighting Improvements
There was no new information or questions from the commission or the public.
35. Wastewater Management Board
There was no new information or questions from the commission or the public.
4/5/2023 Utilities Commission Meeting Minutes Page 8
36. Wastewater Treatment Plant Charges for February 2023
There was no new information or questions from the commission or the public.
37. Whiskey Creek Stormwater Improvements Project Update
There was no new information or questions from the commission or the public.
38. Local Road Research Board – Guidance to help Local Agencies Address Deferred Maintenance
There was no new information or questions from the commission or the public.
39. PSI Water Technologies Service Report
There was no new information or questions from the commission or the public.
40. Tree Trimming Letter for Proposed Micro Surfacing Project Residents
There was no new information or questions from the commission or the public.
ADJOURN
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to adjourn the meeting at 6:32 p.m.
Motion unanimously approved.
Approved by: Respectfully submitted:
_______________________ ___________________________
Rock Yliniemi Mary Haugen
Chair Administrative Assistant
Agenda
UTILITIES COMMISSION MEETING AGENDA
Wednesday, April 05, 2023 at 5:30 PM
Baxter City Hall, 13190 Memorywood Drive, Baxter, MN
“A Growing Community”
CALL TO ORDER
ROLL CALL
CONSENT AGENDA
1. Approve the Utilities Commission Minutes from March 8, 2023
BUSINESS ITEMS
2. Recommend Planning and Zoning approve the Preliminary & Final Plat of Batten Addition with the
Proposed Side Yard Setback Variance
3. Recommend Planning and Zoning approve the Stoes Perch Preliminary & Final Plat
4. Sanitary Sewer Mercury Testing Results Update
5. Adopt Chapter 5 Stormwater Control and Regulations City Code
6. Adopt City of Baxter Stormwater Design Manual
7. Approve the HR Green General Engineering Services Contract
8. Approve the HR Green 2023 Municipal Separate Storm Sewer System (MS4) Program Contract in the
Not to Exceed Amount of $14,980.00.
9. 2022 Foley Road, Isle Drive, and Forthun Road Improvements Project Update, City Improvement No.
4114
10. Approve RL Larson Excavating, Inc. Change Order No. 7 in the increased amount of $20,154.16 for
the 2022 Foley Road, Isle Drive, and Forthun Road Improvements Project Update, City Improvement
No. 4114
11. 2022 Trunk Highway 210 & Inglewood Drive Railway Crossing Improvements Project Update -
Municipal Project No. 4121
12. Approve Anderson Brothers Construction Change Order No. 1 in the amount of $29,195.82 for 2022
Trunk Highway 210 & Inglewood Drive Railway Crossing Improvements Project
13. Approve the BNSF Invoice 90248987 in the amount of $30,128.18 for the 2022 TH 210 and Inglewood
Drive Improvements Project, City Improvement No. 4121
14. Approve Plans & Specifications and Authorize Advertisement for Bids for 2023 Micro Surfacing
Project
15. 2023 Knollwood Drive Improvements Project Monthly Update
4/5/2023 Utilities Commission Meeting Agenda Page 2
16. Approve the Knife River Corporation – North Central Change Order No. 1 in the Increased Amount of
$15,000 for the 2023 Knollwood Drive Improvements Project
17. Project Update - Lift Station 13 Reconstruction
18. Accept the Anderson Brothers Construction Company of Brainerd, LLC Lump Sum Bid in the Amount
of $180,217.07 for the Lift Station No. 13 Reconstruction project and increase the project budget
from $240,000.00 to $251,117.07
INFORMATIONAL ITEMS
19. 2022 Full Depth Reclamation and Reconstruction Improvements Project Monthly Update
20. 2023 Commercial and Residential Full Depth Reclamation Improvements Project & Quiet Zone
Design, Implementation, and Notification Monthly Update
21. 2023 Cypress Drive and Douglas Fir Drive Improvements Project Monthly Update
22. 2024 Mill & Over and Full Depth Reclamation Improvements Project Monthly Update
23. 2024 Design Road & TH 371 Stormwater Improvements Project Update
24. 2024 South Forestview Improvements Project Monthly Update
25. Brainerd Public Utilities Electric Consumption Notice
26. Eagle Drive Area Improvements Feasibility Study Project Monthly Update
27. Project Update – 2023 Evergreen Drive Improvements Feasibility Study
28. Holiday Station Store Contamination Project Monthly Update
29. Inglewood Drive to Garrett Lane Stormwater Outlet Study Project Monthly Update
30. Lift Station 16 Reconstruction Project Monthly Update
31. MnDOT Highway Users Tax Distribution Fund for Local Road and Bridges (2023)
32. Section 6 Area A1 Outlet Project Monthly Update
33. TH 210 Street Lighting Improvements
34. Wastewater Management Board
35. Wastewater Treatment Plant Charges for February 2023
36. Whiskey Creek Stormwater Improvements Project Update
37. Local Road Research Board – Guidance to help Local Agencies Address Deferred Maintenance
38. Brainerd Public Utilities Solar Array Screening Concept Plan and Bluff Analysis Update
4/5/2023 Utilities Commission Meeting Agenda Page 3
39. PSI Water Technologies Service Report
40. Tree Trimming Letter for Proposed Micro Surfacing Project Residents
ADJOURN
Get email alerts for Baxter
A daily email when new agendas and minutes are posted.