UTILITIES COMMISSION MEETING
MINUTES
Wednesday, February 05, 2025 at 5:30 PM
Baxter City Hall, 13190 Memorywood Drive, Baxter, MN
“A Growing Community”
CALL TO ORDER
The regular meeting of the Baxter Utilities Commission was called to order at 5:30 p.m. by Chairman Rock Yliniemi.
ROLL CALL
Members Present: Commissioner Douglas Stenberg, John Brenny, Jack Christofferson, Chairman Rock Yliniemi and
Council Liaison Mark Cross.
Members Absent: None.
Staff Present: Assistant City Engineer Trevor Thompson, and Public Works Administrative Assistant Mary Haugen.
Other Present: SEH Consulting Engineer Neil Heinonen and WiDSETH Consulting Engineer Alex Bitter.
CONSENT AGENDA
1. Approve the Utilities Commission Minutes from January 8, 2025
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to approve the Utilities
Commission minutes from January 8, 2025. Motion carried unanimously.
BUSINESS ITEMS
2. 2025 Water Supply Improvements - Wells 5 & 6 Monthly Update
There was no new information or questions from the commission or the public.
3. Adopt Resolution No. 2025-0XX Approving Plans & Specifications and Ordering Advertisement for
Bids for Contract B - Raw Water Main and Electrical Improvements related to the 2025 Water Supply
Improvements - Wells 5 & 6, Municipal Project No. 6011-45040
SEH Consulting Engineer Heinonen reviewed the plans & specifications for construction of two (2)
additional water supply wells (Wells 5 & 6), raw watermain, and electrical components necessary to
connect the wells to the Water Treatment Plant. The project includes bidding three (3) separate
contracts to contractors and suppliers to expedite the construction timeline: (A) well construction, (B)
utilities construction, and (C) electrical/control panel procurement.
The City will advertise for bids in accordance with the requirement of the uniform municipal
contracting law. Bids are scheduled to be received and opened publicly on March 18, 2025.
Chair Yliniemi inquired about the construction of the panels and if they were the same as the old
panels. Mr. Heinonen stated there is a slight difference between the panels; however, the team has
2/5/2025 Utilities Commission Meeting Minutes Page 2
been working with AE2S Instrumentation & Controls Technician Allen Dostell on integrating the VFD’s
in the panels.
Assistant City Engineer Thompson informed the commission that the DNR will be using the monitoring
well, that was installed with the exploratory well south of the proposed well 6 that was not favorable
for a municipal well, to collect data on the water quality and flow conditions of the aquifer.
Commissioner Christofferson inquired about the note on page C002 regarding the removal of the fence
and gate. He inquired if these items will be salvaged and reused. Mr. Heinonen stated the fence and
gate will be salvaged and reinstalled.
MOTION by Commissioner Christofferson, seconded by Commissioner Brenny to adopt Resolution No.
2025-0XX Approving Plans & Specifications and Ordering Advertisement for Bids for Contract B - Raw
Water Main and Electrical Improvements Related to the 2025 Water Supply Improvements - Wells 5 &
6, Municipal Project No. 6011-45040. Motion carried unanimously.
4. Adopt Resolution 2025-0xx Awarding Contract C in the amount of $154,944.00 to Integrated Process
Solutions, Inc. for Well Control Panels Related to the 2025 Water Supply Improvements - Wells 5 &
6, Municipal Project No. 6011-45040
SEH Consulting Engineer Heinonen stated quotes were solicited from two vendors (Integrated Process
Solutions, Inc. and Primex) for well-control panels. Integrated Process Solutions, Inc. provided the low
quote for new panels. The value of the new panels is under the threshold for public bidding, thus
quotes were prepared and solicited.
Mr. Heinonen stated the project team would like to have the panels built & delivered to prevent any
hold-up once the project begins. Chair Yliniemi inquired where Integrated Process Solutions, Inc. is
based. Mr. Heinonen stated the company is located in Fosston, Minnesota.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to adopt Resolution
2025-0XX awarding Contract C in the Amount of $154,944.00 to Integrated Process Solutions, Inc. for
Well Control Panels Related to the 2025 Water Supply Improvements - Wells 5 & 6, Municipal Project
No. 6011-45040. Motion carried unanimously.
5. Approve Proceeding with a Bid Alternate for Additional Paving at the Public Works Facility related
to the 2025 Water Supply Improvements - Wells 5 & 6, Municipal Project No. 6011-45040
SEH Consulting Engineer Heinonen informed the commission that the pavement at the Public Works
Facility is 18 years old and is due for a mill and overlay in 2027. With 40% of the pavement being
replaced with the well project, the paving contractor already mobilized to the site, and being within 2
years of the programed mill & overlay date it is staff’s recommendation to bid the pavement as a bid
alternative.
Mr. Heinonen stated that by bidding as an alternative, it allows the City to review the bids and
determine if the mill & overlay pricing is favorable to proceed or if the well contract is awarded without
the bid alternative and to reevaluate the mill & overlay in 2027.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to proceed with a Bid
Alternate for Additional Paving at the Public Works Facility related to the 2025 Water Supply
Improvements - Wells 5 & 6, Municipal Project No. 6011-45040. Motion carried unanimously.
2/5/2025 Utilities Commission Meeting Minutes Page 3
6. Accept the Memorandum titled “Update to the TH 371 Development Traffic Review” related to the
TH 371 Development Traffic Review Report
SEH Consulting Engineer Heinonen informed the commission that this report, and a previous traffic
study, suggested restriping portions of Dellwood Drive. Ultimately, after a site review of the roadway
dimensions, restriping to a three-lane section is not desirable due to the limited roadway width. This
memorandum was prepared to document the updated recommendation and to provide formal
documentation to acknowledge the modification to the report.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to accept the
Memorandum titled “Update to the TH 371 Development Traffic Review” related to the TH 371
Development Traffic Review Report. Motion carried unanimously.
7. Lift Station No. 17 Reconstruction Project Monthly Update
There was no new information or questions from the commission or the public.
8. Approve the Lift Station No. 17 Reconstruction Project Plans & Specifications and Authorize
Advertisement for Bids
WiDSETH Consulting Engineer Bitter reviewed the plans and specifications for the Lift Station No. 17
Reconstruction Project. The project includes the following work:
Replacement of wet well and valve vault piping and valves
Replacement of wet well and valve vault covers and hatches
Installation of new pumps and guiderail system
Installation of new transducer and floats
Installation of new control panel
Removal and replacement of bituminous driveway
Site restoration
Assistant City Engineer Thompson had no concerns with the reconstruction project and recommended
approval.
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to approve the Lift Station
No. 17 Reconstruction Project Plans & Specifications and Authorize Advertisement for Bids. Motion
carried unanimously.
9. 2025 Commercial Full Depth Reclamation Improvements Project Monthly Update, Municipal Project
4425
There was no new information or questions from the commission or the public.
10. Approve the Widseth Fee Amendment for Professional Services in the Not to Exceed Amount of
$6,400.00 for the 2025 Mill & Overlay and Full Depth Reclamation Improvements Project, Municipal
Project No. 4425
WiDSETH Consulting Engineer Bitter reviewed the Fee Amendment for Professional Services in the Not
to Exceed Amount of $6,400.00 for the 2025 Mill & Overlay and Full Depth Reclamation Improvements
Project.
2/5/2025 Utilities Commission Meeting Minutes Page 4
Mr. Bitter stated the during the project there have been two significant updates to the project scope
as requested by the City. This first change being the removal of the residential roadways (moved from
2025 to 2026) and the second the removal of two of the four commercial roadways (moved from 2025
to 2027).
WiDSETH made internal adjustments to labor hours associated with these changes as follows:
Original Contracts Original Commercial Commercial FDR Residential moved
Contract FDR moved to 2027 to 2026
Amount
Feasibility Report $15,000 $1,800 $5,100 $8,100
Jetting & Televising $53,014 $5,650 $16,085 $31,278
Topographic Survey $43,000 $5,140 $14,640 $23,220
Design & Bidding $64,435
Totals $111,014 $77,025 $35,825 $62,598
The added scope to the project has resulted in additional time on the project that was not accounted
for in previous proposals. The added scope is as follows.
Modify the Cost Estimate twice, once for the removal of the Residential Road and once for the
removal of the two commercial roads.
Modify the Feasibility Report twice, once for the removal of the Residential Road and once for
the removal of the two commercial roads.
Prepare for and assist the City with the Supplemental Improvement Hearing.
Project management time to update supporting documents such as RCA’s, resolutions and
schedules.
The estimated effort associated with the additional work outlined above is $6,400.00. This will bring
the total contract amount to a Not To Exceed Total Fee of $83,425. Mr. Bitter noted the fee
amendment does not include tasks related to professional services beyond bidding the project. A
separate proposal for final assessment and construction-related services will be brought forward after
Bidding is complete.
MOTION by Commissioner Brenny, seconded by Commissioner Stenberg to approve the Widseth Fee
Amendment for Professional Services in the Not to Exceed Amount of $6,400.00 for the 2025 Mill &
Overlay and Full Depth Reclamation Improvements Project, Municipal Project No. 4425. Motion
carried unanimously.
11. 2026 Mill & Overlay & Full Depth Reclamation and Reconstruction Improvements Project Monthly
Update
There was no new information or questions from the commission or the public.
12. Approve the Widseth Fee Amendment for Professional Services in the Not to Exceed Amount of
$6,600.00 for the 2026 Mill & Overlay and Full Depth Reclamation Improvements Project, Municipal
Project No. 4426
2/5/2025 Utilities Commission Meeting Minutes Page 5
WiDSETH Consulting Engineer Bitter reviewed the Fee Amendment for Professional Services in the Not
to Exceed Amount of $6,600.00 for the 2026 Mill & Overlay and Full Depth Reclamation Improvements
Project.
Mr. Bitter stated the during the project there have been two significant updates to the project scope
as requested by the City.
WiDSETH made internal adjustments to labor hours associated with these changes as follows:
Original Contracts Original Residential Commercial Adjusted 2026 Residential
Contract moved from (2026) Project Budget moved to
Amount 2025 2027
Feasibility Report $15,000 $8,100 $9,000 $17,100 $6,000
Jetting & Televising $42,584 $31,278 $25,550 $56,828 $17,034
Topographic Survey $23,220 $23,220
Totals $57,584 $62,598 $34,550 $97,148 $23,034
The added scope to the project has resulted in additional time on the project not accounted for in
previous proposals. The added scope is as follows.
Modify the Feasibility Report to remove the previous residential roads and include the
residential roads from the 2025 project.
Modify the Cost Estimate to remove the previous residential roads and include the residential
roads from the 2025 project.
Project management time to update supporting documents for the project such as RCA’s,
resolutions and schedules.
The estimated effort associated with the additional work outlined above is $6,600.00. This will bring
the total contract amount to a Not To Exceed Total Fee of $103,748.00.
MOTION by Commissioner Christofferson, seconded by Commissioner Brenny to approve the
WiDSETH Fee Amendment for Professional Services in the Not to Exceed Amount of $6,600.00 for the
2026 Mill & Overlay and Full Depth Reclamation Improvements Project, Municipal Project No. 4426.
Motion carried unanimously.
13. Approve the Crow Wing Construction Cost Share Agreement for Roadway Pavement Markings on
Various City of Baxter Streets Project No. CP 18-200-144
Assistant City Engineer Thompson reviewed the 2025 Crow Wing County Cost Share Agreement with
the standard 3% Contract Administration Fee for the 2025 Roadway Pavement Marking Project.
The 2025 Streets Budget has $58,000.00 allocated for the various roadway pavement marking. Mr.
Thompson noted the project is estimated over budget and staff will review where cutbacks can be
made to meet the 2025 Streets budget when bid prices have been received.
2/5/2025 Utilities Commission Meeting Minutes Page 6
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to approve the Crow Wing
Construction Cost Share Agreement for Roadway Pavement Markings on Various City of Baxter Streets
Project No. CP 18-200-144. Motion carried unanimously.
14. Minnesota Biosolids PFAS Strategy
Assistant City Engineer Thompson informed the commission of the state’s growing problem of per-
and polyfluoroalkyl substances (PFAS) — a group of thousands of human-made chemicals known to be
toxic that do not break down in the environment, earning them the nickname "forever chemicals.
The chemicals are produced, used, processed, and released into the environment, yet we haven't
thoroughly studied their toxicity and danger to people's health and the environment. PFAS have been
found in groundwater and surface water throughout Minnesota and have seeped into some drinking
water systems.
The State of Minnesota considers PFAS hazardous substances and has developed long-term
comprehensive strategies to address PFAS contamination, including a pollution prevention plan that
will phase out avoidable PFAS use by 2032.
PFAS is also present in wastewater due to their widespread use in industrial and consumer
products. The Environmental Protection Agency (EPA) has established regulations for PFAS in drinking
water, but there are currently no federal regulations for PFAS in wastewater.
Mr. Thompson noted the commission will continue updates on this important issue.
INFORMATIONAL ITEMS
15. 2022 Full Depth Reclamation and Reconstruction Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
16. 2022 Trunk Highway 210 & Inglewood Drive Railway Crossing Improvements Project Update
There was no new information or questions from the commission or the public.
17. 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone Improvements Project
Monthly Update
There was no new information or questions from the commission or the public.
18. 2023 Knollwood Drive Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
19. 2023 Novotny Road Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
20. 2024 Mill & Overlay and Full Depth Reclamation Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
2/5/2025 Utilities Commission Meeting Minutes Page 7
21. 2024 South Forestview Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
22. 2025 Design Road & TH 371 Stormwater Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
23. 2025 Micro Surfacing Project Monthly Update
There was no new information or questions from the commission or the public.
24. 2025 Well 1 and Well 4 Pump and Motor Replacement Monthly Update
There was no new information or questions from the commission or the public.
25. Baxter 20-Year Public Works Facility Assessment Project Monthly Update
There was no new information or questions from the commission or the public.
26. Eagle Drive Area Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
27. Holiday Station Store Contamination Project Monthly Update
There was no new information or questions from the commission or the public.
28. Lift Station No. 15 Reconstruction Project Monthly Update
There was no new information or questions from the commission or the public.
29. Project Timber Wolf Project Monthly Update
There was no new information or questions from the commission or the public.
30. Wellhead Protection Plan Part II Project Monthly Update
There was no new information or questions from the commission or the public.
31. Whiskey Creek Planting Plans Project Monthly Update
There was no new information or questions from the commission or the public.
32. 2023 Whiskey Creek Pedestrian Bridge Inspection Project Monthly Update
There was no new information or questions from the commission or the public.
33. Water Enterprise Fund 20-year CIP and 2025 CAMP Update Monthly Update
There was no new information or questions from the commission or the public.
ADJOURN
2/5/2025 Utilities Commission Meeting Minutes Page 8
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to adjourn the meeting at 6:30 p.m.
Motion unanimously approved.
Approved by: Respectfully submitted:
_______________________ ___________________________
Rock Yliniemi Mary Haugen
Chair Administrative Assistant
Agenda
UTILITIES COMMISSION MEETING AGENDA
Wednesday, February 05, 2025 at 5:30 PM
Baxter City Hall, 13190 Memorywood Drive, Baxter, MN
“A Growing Community”
CALL TO ORDER
ROLL CALL
CONSENT AGENDA
1. Approve the Utilities Commission Minutes from January 8, 2025
BUSINESS ITEMS
2. 2025 Water Supply Improvements - Wells 5 & 6 Monthly Update
3. Adopt Resolution No. 2025-0XX Approving Plans & Specifications and Ordering Advertisement for
Bids for Contract B - Raw Water Main and Electrical Improvements related to the 2025 Water Supply
Improvements - Wells 5 & 6, Municipal Project No. 6011-45040
4. Adopt Resolution 2025-0xx Awarding Contract C in the amount of $154,944.00 to Integrated Process
Solutions, Inc. for Well Control Panels Related to the 2025 Water Supply Improvements - Wells 5 & 6,
Municipal Project No. 6011-45040
5. Approve Proceeding with a Bid Alternate for Additional Paving at the Public Works Facility related to
the 2025 Water Supply Improvements - Wells 5 & 6, Municipal Project No. 6011-45040
6. Accept the Memorandum titled “Update to the TH 371 Development Traffic Review” related to the
TH 371 Development Traffic Review Report
7. Lift Station No. 17 Reconstruction Project Monthly Update
8. Approve the Lift Station No. 17 Reconstruction Project Plans & Specifications and Authorize
Advertisement for Bids
9. 2025 Commercial Full Depth Reclamation Improvements Project Monthly Update, Municipal Project
4425
10. Approve the Widseth Fee Amendment for Professional Services in the Not to Exceed Amount of
$6,400.00 for the 2025 Mill & Overlay and Full Depth Reclamation Improvements Project, Municipal
Project No. 4425
11. 2026 Mill & Overlay & Full Depth Reclamation and Reconstruction Improvements Project Monthly
Update
12. Approve the Widseth Fee Amendment for Professional Services in the Not to Exceed Amount of
$6,600.00 for the 2026 Mill & Overlay and Full Depth Reclamation Improvements Project, Municipal
Project No. 4426
2/5/2025 Utilities Commission Meeting Agenda Page 2
13. Approve the Crow Wing Construction Cost Share Agreement for Roadway Pavement Markings on
Various City of Baxter Streets Project No. CP 18-200-144
14. Minnesota Biosolids PFAS Strategy
INFORMATIONAL ITEMS
15. 2022 Full Depth Reclamation and Reconstruction Improvements Project Monthly Update
16. 2022 Trunk Highway 210 & Inglewood Drive Railway Crossing Improvements Project Update - City of
Baxter - Municipal Project No.: 4121 BMI Project No. T42.120675
17. 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone Improvements Project
Monthly Update
18. 2023 Knollwood Drive Improvements Project Monthly Update
19. 2023 Novotny Road Improvements Project Monthly Update
20. 2024 Mill & Overlay and Full Depth Reclamation Improvements Project Monthly Update
21. 2024 South Forestview Improvements Project Monthly Update
22. 2025 Design Road & TH 371 Stormwater Improvements Project Monthly Update
23. 2025 Micro Surfacing Project Monthly Update
24. 2025 Well 1 and Well 4 Pump and Motor Replacement Monthly Update
25. Baxter 20-Year Public Works Facility Assessment Project Monthly Update
26. Eagle Drive Area Improvements Project Monthly Update
27. Holiday Station Store Contamination Project Monthly Update
28. Lift Station No. 15 Reconstruction Project Monthly Update
29. Project Timber Wolf Project Monthly Update
30. Wellhead Protection Plan Part II Project Monthly Update
31. Whiskey Creek Planting Plans Project Monthly Update
32. 2023 Whiskey Creek Pedestrian Bridge Inspection Project Monthly Update
33. Water Enterprise Fund 20-year CIP and 2025 CAMP Update Monthly Update
ADJOURN