City Council - Public Works and Natural Resources Committee
Regular MeetingBellingham, WA · December 6, 2021
Minutes
City of Bellingham
Public Works and Natural Resources Committee Minutes
December 6, 2021, 10:00 AM
Mayor Seth Fleetwood Contact: (360) 778-8200, ccmail@cob.org
Council Members, Michael Lilliquist, Chair www.cob.org/council
Gene Knutson, Lisa Anderson All meetings are held in the City Hall Council Chambers at
210 Lottie Street, Bellingham, WA, unless otherwise noted.
Call to Order
Roll Call
Council Standing Committee Meeting
Open to the public to attend. Note: there is generally no public comment period for Committee
sessions. Standing Committee Members receive reports and information, ask questions and,
when appropriate, vote on a recommended action for consideration by the full Council at the
Regular Meeting. The notice of Committee Meetings identified below also serves as notice of
Special Meetings of the City Council at the times identified as Council Members who are not
members of the committee routinely attend and participate in the Committee Meetings.
Committee Chairs give a report of the Committee Meeting at the Regular Meeting in the
evening prior to deliberation and formal vote in the order shown below:
Public Works and Natural Resources
Michael Lilliquist, Chair
Gene Knutson, Lisa Anderson
23182 1. Post Point Resource Recovery Project Update p. 3
Eric Johnston, Public Works Director, opened the presentation by discussing the
fact that the incinerators have reached the end of their useful life and they need
to be replaced. He discussed that the approach for this project included the
triple bottom line plus methodology, factoring in the environmental, social,
technical and financial cost of replacing them, including a specific amount of
public outreach. The conclusion of the study led to the discovery that, while
minimal, PFAS contaminants do exist in Bellingham. Ultimately, he recognizes
that the ideal solution would be to not have PFAS contaminants in the system to
begin with (by a state of federal ban on the production of these systems). The
City of Bellingham does not have an industrial producer of these types of
chemicals and the sources are coming from us (consumers and users) from a
variety of sources. The next step is to pursue a different delivery method and he
is requesting Council approval for this. The Council has already taken action to
pursue in the direction of bio digestion.
Public Works and Natural Resources Committee Minutes Page 1
December 6, 2021
Natalie Sierra, Professional Engineer specializing in biosolids, presented on PFAS
with comparative studies of Michigan (industrially impacted biosolids), Maine
(soil-screening), and the San Francisco Bay area. People are the main
contributors to PFAS in the state of Washington. Department of Ecology has
concluded this as well. Humans get this from their diet. Other sources include
carpets and food packaging. Wastewater treatment plants are recipients of the
PFAS. PFAS have been found in groundwater near land application sites.
Legislatures and state environmental agencies are expressing increased concern
about PFAS in response to general public awareness. PFAS has been found in
residuals and land applied soils not impacted by industrial sources. In terms of
unit of measure, there is the need to differentiate between a part per trillion
(ppt) and a part per billion (ppb). The former is equivalent to a single drop of
water in 20-olympic sized swimming pools. In terms of time: ppt = 1 sec/31,799
years; ppb = 1 sec/31.7 years). 1 microgram(ug)/kg = 1 nanogram (ng)/g. This
can often be consuming, because different researchers use different
measurements for PFAS. In this presentation, Michigan uses the former (ug/kg)
and Maine uses the latter (ng/g). In general, typical PFAS ranges in biosolids
are 60-450 ug/kg. Conclusion from San Francisco (178 ng/g): the level of
treatment did not have a statistically significant impact on the PFAS
concentration, and the levels are generally comparable. Important to know is
how quickly PFAS samples can become contaminated – people who test these
samples are not supposed to shower that day, use chemicals (lotions,
shampoos, etc.) or wear fabrics that may contain PFAS in them. Published data
sets will include different PFAS species (some with 8, others with 20, etc.) An
unusual behavior of PFAS is that they can transform into other species through
the wastewater treatment process, in the soil matrix, in the environment in
general (making it very hard to track what is actually going on). Sierra discussed
a comparative study between Michigan and Maine where Michigan used a
targeted based approach on industrial inputs (analysis of land applied biosolids
across the state led to characterization of “industrially impacted biosolids at 150
ug/kg PFOS. Contrastingly, Maine applied soil screening standards and
conservative fate and transport models to regulate biosolids (5.2 ng/g PFOS, 2.5
ng/g PFOA). Compared to both Michigan and Maine, Bellingham is well below
both (Bellingham PFOS vs Maine: just over 3 vs 5.2; Bellingham just over .5 PFOA
vs Maine 2.5). When conducting a PFOA comparison, Bellingham is very close to
the levels of the San Francisco Bay Area. In a PFOS comparison between
Bellingham and the Bay area, Bellingham’s levels are a bit lower. Focusing
specifically on Washington State: Post Pont Wastewater lower for PFAS of 14
sampled plants in WA and below EPA advisory standard for drinking water (70
parts per trillion), no known industrial discharges in high-risk PFAS use
categories, Bellingham drinking water supply non-detect for PFAS.
Mike Olinger, Assistant Public Works Director of Operations, provided a
presentation with an update on the Point Post Resource Recovery Project. The
Public Works and Natural Resources Committee Minutes Page 2
December 6, 2021
following Post Point and Off-sire Facilities are required: Digestion at Post Point
(new digestion facilities located in northeast corner of Post Point), Off-site
Biosolids Processing (required to convey Class A digested solids to a marketable
product), Market Outreach (identify potential private partnerships for off-site
processing and/or marketing of product), Biogas – Pipeline Injection (scrub
digester gas for pipeline injection, establish gas utility requirements and
agreement). The RFP is set to open on December 16, 2021. Currently, they are
past 10% of design and are still on track for construction to commence in 2023
and for the project completion by 2025. Mike and Chad will bring forward to
Council a proposed long-term schedule on December 13, 2021 (including
milestones for Council actions for 2022 and 2023).
Chad Schulhauser, Assistant Public Works Director of Engineering, discussed
alternative project delivery. Typical project delivery includes design, bid, built
(two separate contracts and the City owns the project). However, an alternative
project delivery has a wide spectrum of deliverables. One of them is called,
“general contractor/construction manager (GC/CM)”. GC/CM is defined in the
RCW (39.10). The two standards in WA State include: GCCM and design build.
With GC/CM, the public agency will select the design contractor early on. The
selection would be based on qualification and overheard cost. The result: two
separate contracts (one with the designer/consultant and one with the GC/CM
firm). The contracts are closely tied and a relationship. Another option would be
Progressive Design-Build (one contractor and owner’s advisor/consultant). This
option would be in two phases. PW sat down with the consultant to understand
which is the better option (including comfort zone assessments, delivery
methods and key attributes): Progressive Design-Build versus GC/CM. The
result: GC/CM is the best option for a project of this magnitude. The two key
differences: specification-based delivery versus a performance-based delivery;
traditional roles and times vs brand new product with Design Build (which the
City has never done). Ultimately, Public Works recommends moving forward
with GC/CM and asks Council for their approval.
In summary, this update included a summary of recent laboratory test results
from the Post Point Resource Recovery Plant as well as a discussion of
alternative project-delivery methods. The update was broken into two sections:
testing results and project delivery. Samples were tested for Per-and
Polyfluorinated Substances (PFAS) compounds as requested by the Council on
July 26, 2021. Comparisons to other studies and regulatory requirements were
also presented. Furthermore, staff provided an update on the project, which
included options for delivery of a multi-hundred-million-dollar project. The
results: PFAS compounds were found in the waste, but that the levels were
relatively low. As has been discussed, no national standards are currently in
place for what are acceptable levels of exposure in biosolids as a result of waste
treatment. A couple of states have adopted standards, including Maine
Public Works and Natural Resources Committee Minutes Page 3
December 6, 2021
(Bellingham’s levels are toxic and enduring molecules, but they remain below
Maine’s level). There was continued discussion on what that would mean if we
continued with biosolids and did indeed have contaminants, what the available
uses for those would be, the regulations would be, and what the cost would be
for continuing with that as the approved method, or what the cost would be
with other methods. This discussion will be continued with possibly altering or
putting a pause to proceeding. For now, as an interim step, the City will
continue to proceed along the pathway as initiated in 2017, to move towards
bio digestion as a way to replace the current incineration technology for human
waste at Post Point, which is energy intensive, polluting, destructive, and
increasingly unviable. Staff requested Council to apply to the Washington State
Project Review Board to use the General Contractor-Construction Manager
project delivery method for the project. In this situation, a contractor is brought
in early in the design process, so the design process can proceed based on their
knowledge and understanding of how it would be built to reduce future
problems and also to share the risk when the building processes occurred.
MOTION to move forward to recommend staff to direct staff to apply to the
state Project Review Committee for certification to use the general
contractor/construction manager (GC/CM) contracting procedure for delivery of
the Post Point Resource Recovery project.
MOTION CARRIES 3-0.
Adjournment
Public Works and Natural Resources Committee Minutes Page 4
December 6, 2021
Agenda
City of Bellingham
Public Works and Natural Resources Committee Agenda
December 6, 2021, 10:00 AM
Mayor Seth Fleetwood Contact: (360) 778-8200, ccmail@cob.org
Council Members, Michael Lilliquist, Chair www.cob.org/council
Gene Knutson, Lisa Anderson All meetings are held in the City Hall Council Chambers at
210 Lottie Street, Bellingham, WA, unless otherwise noted.
Council members will participate in this meeting remotely through an online web-based
meeting platform. Per Washington State Proclamation 20-28, in-person attendance at meetings
is not required at this time.
Council meetings are streamed live via the City’s website at meetings.cob.org and on the City’s
YouTube channel. Meetings are broadcast in high definition on BTV on Comcast channel 321,
and in standard definition on Comcast channel 10. Members of the public who do not have
cable or Internet access may contact the City Council office to receive phone numbers in order
to listen to the meeting via telephone.
Those who would like to listen in by phone can do so using any of the following phone
numbers:
(253) 215-8782
(346) 248-7799
(669) 900-6833
(301) 715-8592
(312) 626-6799
(929) 205-6099
Meeting ID: 982 0492 7724
Password: 9
Call to Order
Council Standing Committee Meeting
Open to the public to attend. Note: there is generally no public comment period for Committee
sessions. Standing Committee Members receive reports and information, ask questions and,
when appropriate, vote on a recommended action for consideration by the full Council at the
Regular Meeting. The notice of Committee Meetings identified below also serves as notice of
Special Meetings of the City Council at the times identified as Council Members who are not
members of the committee routinely attend and participate in the Committee Meetings.
Committee Chairs give a report of the Committee Meeting at the Regular Meeting in the
evening prior to deliberation and formal vote in the order shown below:
Public Works and Natural Resources
Michael Lilliquist, Chair
Gene Knutson, Lisa Anderson
23182 1. Post Point Resource Recovery Project Update p. 3
Adjournment
Agenda Information:
Council Committee and Regular Meeting agendas and agenda packets, which contain the
supporting documentation for agenda items, are available to the public Wednesday afternoon
prior to the meeting. They are posted at https://meetings.cob.org/. Meetings are streamed live
on the internet as they occur.
Accessibility:
The Council Chambers is fully accessible. Elevator access to the second floor is available at City
Hall’s west entrance. Hearing assistance is available, and a receiver may be checked out
through the Deputy City Clerk prior to the evening session. For additional accommodations,
contact the Legislative Assistant at 778-8200 in advance of the meeting. Thank you.
Next City Council Committee Meetings
Monday, December 13, 2021
Deadline to submit material for any public hearing for inclusion in the published agenda
packet is 8:00 a.m. on Wednesday prior to the meeting.