City Council Workshop
Regular MeetingBlaine, MN · November 1, 2018
Minutes
Blaine City Hall
City of Blaine 10801 Town Sq Dr NE
Blaine MN 55449
Anoka County, Minnesota
Minutes
City Council Workshop
Thursday, November 1, 2018 7:20 PM Cloverleaf Farm Room A
NOTICE OF WORKSHOP MEETING
1 Call to Order
The meeting was called to order by Mayor Ryan at 7:10 p.m.
2 Roll Call
Quorum Present.
ALSO PRESENT: City Manager Clark Arneson; Public Works Director Jon
Haukaas; Police Chief/Safety Services Manager Brian Podany; Finance Director
Joe Huss; Public Services Manager/Assistant City Manager Bob Therres; City
Attorney Patrick Sweeney; City Engineer Dan Schluender; Senior Engineering
Technician Al Thorp; Communications Technician Roark Haver; and City Clerk
Catherine Sorensen.
Present: 7 - Councilmember Hovland, Councilmember Clark, Councilmember King,
Councilmember Garvais, Councilmember Jeppson, Mayor Ryan, and
Councilmember Swanson
3 New Business
3-2 2019 PROPOSED CAPITAL FUND BUDGET
Attachments: 2019 Cap Fund Bud Recommendation 11-08
Finance Director Huss stated a first draft of the Proposed 2019 Capital Budget
was distributed to the Council for review and consideration. Capital requests have
been submitted and Finance is compiling these requests and integrating them into
the five-year Capital Budget Plan. Staff reviewed the Capital Budget and requests
with the Council in detail noting several funding alternatives. It was noted the final
Capital Budget would come before the Council on December 6th for final approval.
Councilmember Jeppson asked why the fire garage shower was not a joint expense
for the SBM Fire Department. Mr. Huss explained the fire garage in Blaine was
owned solely by the City of Blaine and was used by local daytime fire responders.
Council consensus was to direct staff to bring the final budget back for
consideration on December 6th.
City of Blaine Page 1
City Council Workshop Minutes November 1, 2018
3-1 DISCUSSION ON CONSTRUCTION SCHEDULE FOR
SENIOR CENTER
Attachments: 292 Memo
Public Services Manager/Assistant City Manager Therres stated at a previous
workshop meeting, the City Council approved of the site location for the new
Senior Center. At the same meeting the Blaine Festival asked the Council to not
start construction until after the Blaine Festival (it is their 50th Anniversary), which
would make the start date after the July 4th holiday. The Council asked our
architect, 292 Design, to see what cost and construction issues the City would
encounter based on starting in July vs. March/April of 2019. Staff reviewed a letter
from Pam Anderson, 292 Design that recommends an April construction start for
several reasons including a 3%-5% increase in bid prices. The letter also indicates
that closing up the project for the week of the Blaine Festival will not be an issue.
The City is using the Capital Improvement Fund (CIF) to finance this improvement
and has set a maximum budget of $5.4 million. The early construction cost
estimates, which does not include soft costs or any parking lot and site
improvements is approximately $3.8 million.
Mayor Ryan asked when the project would be bid. Mr. Therres explained the
project would be bid sometime this winter.
Councilmember Garvais stated he was in favor of starting the project in April, so
long as equipment can be moved off site during the Blaine Festival.
Councilmember Swanson supported the contractor beginning the work in April as
well.
Councilmember Jeppson commented she did not support the project beginning in
April as she feared how construction would impact the Blaine Festival. She
believed these actions would reflect poorly on the City considering all of the time
and effort volunteers have already put in to planning the City’s 50th Anniversary
Celebration. She recommended the bid cycle still be held in January/February to
ensure a high-quality contractor was secured, but supported the construction work
beginning after the Blaine Festival.
Mayor Ryan explained that a July start date would have the senior center moving
out of their current space in the middle of winter. He indicated he supported the
April start date.
Councilmember Garvais stated it was very important to him to find the right
contractor with high quality workers for this project. He anticipated the contractor
City of Blaine Page 2
City Council Workshop Minutes November 1, 2018
could move equipment off-site and have the new building secured for the Blaine
Festival weekend in order to minimize the impact.
Councilmember Jeppson explained there were many unknowns as to when
construction could begin, given the fact the weather may impact the start date.
However, she knew understood the Blaine Festival Committee had already spent
$150,000 on next year’s event and encouraged the Council to reconsider the start
date.
Councilmember Hovland agreed with Councilmember Jeppson and believed it was
only fair to take into consideration the time and effort the Blaine Festival Committee
has put into planning next year’s event. He stated he did not believe it would hurt
the project by delaying construction by three months.
Councilmember Swanson asked how the City would cover overages on this
project. Mr. Huss explained the maximum draw the City could have on this project
was $5.4 million and if the project exceeded this amount the Council would have to
reduce the scope or find an additional funding source.
Councilmember King stated he supported the March/April timeline. He indicated
this was a small enough construction site that could be fenced in order to keep
people out of the area. He encouraged the City to work closely with the
contractor and Blaine Festival Committee to ensure things go smoothly.
Councilmember Clark reported he agreed with Councilmember Jeppson and
Councilmember Hovland. He did not want to see this project overrunning the
City’s 50th Anniversary Celebration of the Blaine Festival. He recommended the
contract include a stop-work or fencing clause if the project were to begin in April.
Councilmember Garvais stated he supported the contractor fencing the site and
removing equipment during the Blaine Festival in order to minimize impact on the
event.
Mayor Ryan anticipated that if construction were to begin in April, the building
would be enclosed by the time the Blaine Festival was held. Mr. Therres
anticipated if the City were to make the contractor aware of the timeline, the area
could be secured in order to minimize the impact on the Blaine Festival.
Councilmember Jeppson asked if staff had spoken to the Blaine Festival Committee
regarding the proposed construction. She explained she has heard from this group
that they may pursue another site if construction begins in March/April. Mr.
Therres stated he was not aware of this but would be in communication with the
Blaine Festival Committee.
City of Blaine Page 3
City Council Workshop Minutes November 1, 2018
Councilmember Jeppson recommended the Council hold a conversation with the
Blaine Festival Committee and the senior center before moving this forward.
Councilmember Garvais stated he supported the Council speaking with the Festival
Committee in order to ease their concerns regarding this project.
Councilmember Hovland asked when staff needed direction on this item. Mr.
Therres reported he would like direction from the Council this evening in order to
move forward with project design plans.
Tim Duevel, Blaine Festival Committee member, commented on the numerous
events that were being planned for the 50th Anniversary Celebration. He discussed
how the reduced space and parking would impact the event. He noted that the start
date would be weather permitting and feared where the project would be when the
Blaine Festival was held. He stated it would help him to better understand the size
of the project area.
Mayor Ryan stated the City could get this information to the Blaine Festival
Committee.
Councilmember Jeppson requested City staff further communicate with the Festival
Committee in order to work through all areas of concern. Mr. Therres reported
staff would meet with the Blaine Festival Committee to further discuss the City’s
construction plans and address the site layout concerns.
Council consensus was to begin construction on the Senior Center in April of
2019.
ADJOURN
The Workshop was adjourned at 7:50 p.m.
City of Blaine Page 4
Agenda
Blaine City Hall
City of Blaine 10801 Town Sq Dr NE
Blaine MN 55449
Anoka County, Minnesota
Meeting Agenda - Final
City Council Workshop
Thursday, November 1, 2018 7:20 PM Cloverleaf Farm Room A
NOTICE OF WORKSHOP MEETING
In accordance with the provisions of Section 3.01 of the Blaine City Charter, a Council
Workshop meeting is scheduled for the following purpose:
1 Call to Order
2 Roll Call
3 New Business
3-1 WS 18-84 DISCUSSION ON CONSTRUCTION SCHEDULE FOR SENIOR CENTER
Sponsors: Therres
Attachments: 292 Memo
3-2 WS 18-79 2019 PROPOSED CAPITAL FUND BUDGET
Sponsors: Huss
Attachments: 2019 Cap Fund Bud Recommendation 11-08
ADJOURN