MINUTES
A meeting of the Committee on the Department of Public Works was held in Johnson Chambers,
Braintree Town Hall, on Tuesday, September 21, 2021 at 7:00p.m.
There was a moment of silence for all those serving in our armed services, past and present, and the
meeting was opened with the pledge of allegiance to the flag.
Councilor Charles Ryan, Chairman was in the Chair.
Clerk of the Council, Susan Cimino conducted the roll call.
Present: Charles Ryan, Chairman
Lawrence Mackin, Vice-Chairman
Julia Flaherty, member
Also Present: James Arsenault, DPW Director
John Thompson, Assistant DPW Director/Town Engineer
Mary Mulroney, National Grid Representative
Homeowner, 100 Adams Street
APPROVAL OF MINUTES
• None
OLD BUSINESS
• None
September 21, 2021 Department of Public Works Page 1 of 3
NEW BUSINESS
• 21 042 Resident Petition: Gas Installation – 100 Adams Street or take up any action relative thereto
Chairman Ryan stated we have a recommendation from the DPW stating Adams Street is under
moratorium. This street was totally reconstructed in 2019. For transverse service trenches, the
moratorium is 5 years, therefore any excavation made during or prior to 2024 requires waiving of the
ordinance. Chairman Ryan stated we want to help residents especially new homeowners who want to
upgrade their new home. The gas connection is located on the other side of the street.
It was noted to the homeowner this could be costly for them. The will need to contact National Grid
and get on their list and find out the pricing and costs that National Grid will pay and what is required
from the homeowner.
Motion was read by Councilor Mackin for favorable recommendation to the full Council with Staff
Recommendations:
MOTION: Resident hereby requests petition for the installation of a gas service line to the residence at
100 Adams Street with Staff Recommendations:
BELD: BELD has no utility conflicts with this petition Order 21 042.
DPW: The DPW has reviewed the subject petition for the installation of a gas service line to the
residence at 100 Adams Street. This section of Adams Street is under the moratorium enacted by the
Council in 2015, having been totally reconstructed in 2019. For transverse service trenches, the
moratorium is 5 years, therefore any excavation made during or prior to 2024 requires waiving of the
ordinance. The gas main is located on the opposite side of Adams Street from the property, near the
curb line in the eastbound travel lane. If the Council does elect to waive the ordinance in this instance,
our recommendation is that the petition be granted with the following conditions:
A temporary patch shall be placed immediately after the work. The street excavation should be saw-
cut, backfilled and compacted in 8-inch lifts, paved to match existing asphalt depth (with a minimum
depth of four inches) in two-inch lifts to match the existing street grade.
After maintaining the temporary patch through one winter, a permanent patch shall be placed the
following May. The permanent patch should be milled curb to curb as to provide at least five feet of
overlap on both sides from the temporary patch, but for a length no less than fifteen feet, and machine
laid with 2-inches of asphalt top course. Tack coat should be applied to milled surfaces and joints prior
to paving. Finished joints should be treated with infrared or with a rubberized asphalt sealer, at the
Highway Superintendent’s discretion. All thermoplastic pavement markings should be replaced in-kind
following the permanent patching, and surety in the amount of $5000 should be put in place to
guarantee the satisfactory completion of the repairs.
We also recommend that the following requirement be added to the permit, if it is to be granted:
September 21, 2021 Department of Public Works Page 2 of 3
“Neither National Grid nor any contractor is authorized to close any street or to close a direction of
travel to facilitate their work without authorization from the Director of the Department of Public
Works or the Highway Superintendent. The Chief of Police can also authorize a closure for a police or
fire emergency. Construction zone traffic safety issues are to be addressed by using appropriate traffic
control signs and devices and the use of police officers for traffic control to safely guide traffic through
the work zone. If a closure is authorized by the DPW, it shall not be implemented until signs and police
officers (where needed) are properly in place in conformity with the written plan prepared by the
contractor’s engineer and approved by the DPW and Police Department.”
Motion: by Councilor Mackin to Approve Order 21 042
Second: by Councilor Flaherty
Vote: For (3 – Flaherty, Mackin, Ryan), Against (0), Absent (0), Abstain (0)
It was unanimously voted to adjourn the meeting at 7:26p.m.
Respectfully submitted,
Susan M. Cimino
Clerk of the Council
Documents provided for Meeting
• Minutes of June 15, 2021
• 21 042 Resident Petition: Gas Installation – 100 Adams Street or take up any action relative thereto
September 21, 2021 Department of Public Works Page 3 of 3