City Council/Successor Agency to the RDA
Regular MeetingCalimesa, CA · March 24, 2025
Agenda
City of Calimesa
Special Workshop of the Calimesa City Council
Meeting Agenda
Monday, March 24, 2025 – 3:00 p.m.
Norton Younglove Multipurpose Senior Center
908 Park Avenue, Calimesa, CA 92320
The Calimesa City Council will be conducting this meeting in the Norton Younglove Senior Center. Members of the
public may attend this meeting in person at the Norton Younglove Senior Center, 908 Park Avenue, Calimesa, CA
92320, or the public may view the City Council meetings live at https://www.facebook.com/cityof.calimesa.
Submission of Public Comments: If attending the meeting, public comment will be allowed by completing a speaker slip and
providing it to the City Clerk at the meeting. Please observe a time limit of three (3) minutes when giving your presentation. When
called upon, please step forward to the microphone, state your name for the record, whom you represent and any statement you wish to
make. Please be advised that you may not defer your three (3) minutes to another speaker.
Linda Molina, Mayor Jeff Cervantez, Mayor Pro Tem
Eric Cundieff, Council Member Edgar Garcia, Council Member John Manly, Council Member
Will Kolbow, City Manager Steven Flower, City Attorney
In compliance with the Americans with Disabilities Act, if you need special assistance to participate in a City meeting or other services offered by this City,
please contact the City Clerk’s Office, (909) 795-9801. Notification of at least 48 hours prior to the meeting or time when services are needed will assist the
City staff in assuring that reasonable arrangements can be made to provide accessibility to the meeting or service. Any public writings distributed by the City
to at least a majority of the Council Members regarding any item on this regular meeting agenda will be made available at the public counter at City Hall
located at 908 Park Avenue, Calimesa, CA 92320.
CALL TO ORDER
ROLL CALL: MAYOR MOLINA, MAYOR PRO TEM CERVANTEZ, COUNCIL MEMBER
CUNDIEFF, COUNCIL MEMBER GARCIA AND COUNCIL MEMBER MANLY.
STAFF: CITY MANAGER KOLBOW, CITY ATTORNEY FLOWER, CITY CLERK
GERDES, FINANCE DIRECTOR REID, INTERIM PUBLIC WORKS DIRECTOR
SHAKIR, CITY ENGINEER THORNTON, FIRE CHIEF O’CONNELL AND
SHERIFF CAPTAIN NORTHRUP.
PLEDGE OF ALLEGIANCE
APPROVAL OF THE AGENDA
RECOMMENDATION: Move to approve the agenda
Motion_______________________ Second_______________________ Vote______________________
Special Workshop Meeting of the Calimesa City Council
March 24, 2025 – 3:00 p.m.
Page 1 of 2
Page 1 of 31
COMMUNICATIONS FROM THE PUBLIC
PLEASE NOTE: members of the public will be provided the opportunity to directly address the City Council concerning the item
described below before the City Council considers such item. No other communications from the public of any other business
shall be considered.
WORKSHOP ITEM
1. REVIEW OF THE FISCAL YEAR 2025-26 CAPITAL IMPROVEMENT PLAN BUDGET FOR THE CITY
OF CALIMESA.
RECOMMENDATION: That the City Council review and discuss the Fiscal Year 2025-26 Capital
Improvement Program budget and provide direction as appropriate.
ADJOURNMENT
Adjourn to the Regular Meeting of the City Council on Monday, April 7, 2025 at 6:00 p.m.
Special Workshop Meeting of the Calimesa City Council
March 24, 2025 – 3:00 p.m.
Page 2 of 2
Page 2 of 31
City Council Meeting
Agenda Report
Agenda Item No. 1
SUBJECT: REVIEW OF THE FISCAL YEAR 2025-26 CAPITAL
IMPROVEMENT PLAN BUDGET FOR THE CITY OF CALIMESA
MEETING DATE: March 24, 2025
PREPARED BY: Will Kolbow, City Manager and
Celeste Reid, Finance Director & Treasurer
RECOMMENDATION: That the City Council review and discuss the Fiscal Year 2025-26 Capital
Improvement Program budget and provide direction as appropriate.
DISCUSSION: The Fiscal Year 2025-26 Capital Improvement Program budget is provided for
consideration of the City Council. The City Council will review, discuss and provide direction for the
City of Calimesa Capital Improvement Plan budget. Presentation of requested items as well as
updates of selected current capital projects will be made by City Staff for projects related to their
respective departments. Thereafter, from the results of discussion and direction, the final budget
document is expected to be presented for adoption at the regularly scheduled City Council meeting
June 2, 2025.
FISCAL IMPACT: The potential fiscal impact is based on results of discussion and direction from
the City Council and information will be provided directly at the budget workshop.
ATTACHMENTS: Proposed Capital Improvement Program and 5-Year Plan from FY2025-26
through Fiscal Year 2029-30 – Draft
Page 3 of 31
FY 2025-26
DRAFT
Page 4 of 31
CAPITAL IMPROVEMENT PROGRAM
DRAFT
CAPITAL IMPROVEMENT EXPENDITURES BY FUND
Fund Name 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
16 Capital Projects Fund $ 33,000 $ 1,510,000 $ 10,000 $ 5,000 $ 1,250,000 $ 2,808,000
20 ADA Capital Projects Fund 39,180 - - - - 39,180
32 Flood Control & Drainage Fees 3,625,079 300,000 - - - 3,925,079
36 Traffic Improvement Fees - 43,182,500 27,067,500 - 1,000,000 71,250,000
39 Park Improvement Fees 11,000 - - - - 11,000
75 Vehicle Replacement Fund 386,000 552,000 251,000 256,000 261,000 1,706,000
76 IT Replacement Fund 149,600 34,800 35,300 31,500 65,000 316,200
TOTAL CAPITAL IMPROVEMENT PROGRAM $ 4,243,859 $ 45,579,300 $ 27,363,800 $ 292,500 $ 2,576,000 $ 80,055,459
FUNDING SOURCES
Fund # Funding Source 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund $ 591,780 $ 1,006,800 $ 296,300 $ 292,500 $ 576,000 $ 2,763,380
16 Capital Projects Fund - 155,000 - - - 155,000
20 ADA Capital Projects Fund 27,000 - - - - 27,000
20 Grants - - - - - -
21 AQMD Fund - 90,000 - - - 90,000
22 Road Maintenance & Rehab 275,000 - - - - 275,000
25 Measure A - 845,000 - - 1,000,000 1,845,000
32 Other Governmental Agencies 3,601,344 300,000 - - - 3,901,344
32 Storm Drain DIF 23,735 - - - - 23,735
36 Street & Traffic DIF (275,000) - - - - (275,000)
36 Grants - 29,639,000 11,696,000 - - 41,335,000
36 Other Governmental Agencies - - 2,100,000 - - 2,100,000
36 Developer Contributions - 13,543,500 13,271,500 - 1,000,000 27,815,000
39 Park DIF - - - - - -
39 Grants - - - - - -
76 Grants - - - - - -
TOTAL CAPITAL IMPROVEMENT PROGRAM $ 4,243,859 $ 45,579,300 $ 27,363,800 $ 292,500 $ 2,576,000 $ 80,055,459
PROJECTS BY CATEGORY
Project Category 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Facilities $ 72,180 $ 510,000 $ 10,000 $ 5,000 $ 250,000 $ 847,180
Parks 11,000 - - - - 11,000
Transportation - 44,182,500 27,067,500 - 2,000,000 73,250,000
Storm Drains 3,625,079 300,000 - - - 3,925,079
Vehicles 386,000 552,000 251,000 256,000 261,000 1,706,000
Information Technology 149,600 34,800 35,300 31,500 65,000 316,200
TOTAL CAPITAL IMPROVEMENT PROGRAM $ 4,243,859 $ 45,579,300 $ 27,363,800 $ 292,500 $ 2,576,000 $ 80,055,459
Page 5 of 31
CAPITAL IMPROVEMENT PROGRAM
Carryover projects are those that are not expected to be completed within FY2024-25. Remaining budgets are calculated as of February 28, 2025. Additional
activity will change these figures before the end of FY2024-25. Please refer to the final schedule of carryovers once the books are closed for FY2024-25, in the
Fall 2025 for final carryover amounts.
SCHEDULE OF CARRYOVERS AS OF 2/28/25
Life-to-date Life-to-date FY2024-25
Budget thru Actuals thru Actuals thru Carryover as of
Fund # Project # Project Name FY2024-25 FY2023-24 2/28/2025 2/28/2025
Facilities
34 2070 New Library $ 1,416,146 $ - $ 7,517 1,408,629
20 2099 ADA Library Sidewalk - Phase I 34,482 - 18,010 16,472
20 XXXX ADA Library Sidewalk Phase II - - - -
16 2031 Civic Center Roof Replacements 110,000 - - 110,000
TOTAL FACILITIES 1,560,628 - 25,527 1,535,101
Parks
39 2077 Mountainview Park Phase 2 3,873,737 234,727 373,313 3,265,697
TOTAL PARKS 3,873,737 234,727 373,313 3,265,697
Transportation
36 2073 CLR/Calimesa Blvd. Intersection 7,188,760 1,016,233 39,483 6,133,044
36 2074 Cherry Valley Blvd. Interchange 9,750,000 3,719,539 981,323 5,049,138
36 2075 County Line Road Interchange 505,032 5,032 - 500,000
16 2082 Citywide Pavement Management (Phase II) & Carryover 2,529,059 - 98,643 2,430,416
36 2087 County Line Road Improvements 11,946,097 8,830,836 1,322,275 1,792,986
25 2082 Citywide Pavement Management (Street Inventory & Survey) 235,000 - 235,000
25 2088 County Line Road Paving 3rd to California 135,000 - - 135,000
25 2089 County Line Road Paving California to Bryant 70,000 - - 70,000
36 2092 Singleton Road Interchange 8,000,000 443,443 25,910 7,530,647
36 2094 Calimesa Blvd Realign @ Cherry Valley 5,550,000 2,169 16,018 5,531,813
TOTAL TRANSPORTATION 45,908,948 14,017,252 2,483,652 29,408,044
Storm Drains
32 2072 Calimesa Creek Stage III Improvements 12,666,118 4,109,304 18,159 8,538,655
32 2101 California St. Storm Drain 500,000 - - 500,000
32 XXXX Calimesa Master Plan of Drainage Update - - - -
TOTAL STORM DRAINS 13,166,118 4,109,304 18,159 9,038,655
Vehicles
75 2048 Vehicle & Rolling Stock Replacement - - - -
TOTAL VEHICLES - - - -
Information Technology
76 2045 Desktop & Laptop Replacement 57,651 - - 57,651
76 2046 Server Replacement & Upgrades 14,750 - - 14,750
76 2047 IT Major Software & Equipment 99,583 - - 99,583
TOTAL INFORMATION TECHNOLOGY 171,984 - - 171,984
TOTAL CONTINUING PROJECTS $ 64,681,415 $ 18,361,283 $ 2,900,651 $ 43,419,481
Page 6 of 31
CAPITAL IMPROVEMENT PROGRAM
5-YEAR CIP BUDGET SUMMARY
Project Name 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Facilities
2070 New Library $ - $ - $ - $ - $ - $ -
2099 ADA Library Sidewalk - Phase I - - - - - -
XXXX ADA Library Sidewalk Phase II 39,180 - - - - 39,180
2030 Facilities Improvements 20,000 510,000 10,000 5,000 250,000 795,000
XXXX Facilities Improvements - Yard 13,000 - - - - 13,000
2031 Civic Center Roof Replacements - - - - - -
TOTAL FACILITIES 72,180 510,000 10,000 5,000 250,000 847,180
Parks
2077 Mountainview Park Phase 2 11,000 - - - - 11,000
TOTAL PARKS 11,000 - - - - 11,000
Transportation
2073 CLR/Calimesa Blvd. Intersection - - - - - -
2074 Cherry Valley Blvd. Interchange - 38,182,500 27,067,500 - - 65,250,000
2075 County Line Road Interchange - - - - 1,000,000 1,000,000
2082 Citywide Pavement Management - 1,000,000 - - 1,000,000 2,000,000
2087 County Line Rd Trans Corr. Imprv. LPP - - - - - -
2088 CLR Paving 3rd to California - - - - - -
2089 CLR Paving California to Bryant - - - - - -
2092 Singleton Road Interchange - 5,000,000 - - - 5,000,000
2094 Calimesa Blvd Realign @ Cherry Valley - - - - - -
2097 Sandalwood Drive Interchange - - - - - -
TOTAL TRANSPORTATION - 44,182,500 27,067,500 - 2,000,000 73,250,000
Storm Drains
2072 Calimesa Creek Stage III Improvements 3,463,579 - - - - 3,463,579
2101 California St. Storm Drain 161,500 - - - - 161,500
XXXX Calimesa Master Plan of Drainage - 300,000 - - - 300,000
TOTAL STORM DRAINS 3,625,079 300,000 - - - 3,925,079
Vehicles
2048 Vehicle & Rolling Stock Replacement 386,000 552,000 251,000 256,000 261,000 1,706,000
TOTAL VEHICLES 386,000 552,000 251,000 256,000 261,000 1,706,000
Information Technology
2045 Desktop & Laptop Replacement 24,600 12,800 20,300 31,500 65,000 154,200
2046 Server Replacement & Upgrades 15,000 - - - - 15,000
2047 IT Major Software & Equipment 110,000 22,000 15,000 - - 147,000
TOTAL INFORMATION TECHNOLOGY 149,600 34,800 35,300 31,500 65,000 316,200
TOTAL CAPITAL IMPROVEMENT PROGRAM $ 4,243,859 $ 45,579,300 $ 27,363,800 $ 292,500 $ 2,576,000 $ 80,055,459
Page 7 of 31
CAPITAL IMPROVEMENT PROGRAM
New Library
Project Number
2070
Category
Facilities
Department
Administration
Proposed Project Timeline
July 2021 - June 2025
Project Description & Justification
In Fiscal Year 2021-22, the City Council approved the construction of a new 5,500 square foot library to be built on the current library
site. The County of Riverside, Office of Economic Development, in partnership with the City, has provided a project manager to
manage the construction of the new library. Funding for the cost of the facility includes funding from the County of Riverside ($2.5
million), Riverside County Library System ($85,000), Library Facilities Fees ($1.11 million), and Library tax proceeds and donations
($305,000) for a total project cost of $4 million.
The City budget includes the City's portion of the cost only since the County is the lead agency for the construction of the library.
As of February 2025, total life-to-date project costs are $7,517.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
New Library 1,416,146 - - - - - 1,416,146
TOTAL (FUND 34) 1,416,146 - - - - - 1,416,146
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
34 Library DIF 1,110,000 - - - - - 1,110,000
19 Library Operations 228,285 - - - - - 228,285
19 Donations 77,861 - - - - - 77,861
TOTAL 1,416,146 - - - - - 1,416,146
Page 8 of 31
CAPITAL IMPROVEMENT PROGRAM
ADA Library Sidewalk - Phase I
Project Number
2099
Phase I
Category
Facilities
Department
Public Works
Proposed Project Timeline
September 2024- June 2025
Project Description & Justification
The City Council in December 2023, approved an application to CDBG for the ADA (Americans with Disabilities Act) Improvement
Project, located at the sidewalk in front of the Library location on Calimesa Blvd. The project will bring access from the public street
into the library in compliance and provide a safer path of travel from the street to the front door. Included in the plans are an ADA
ramp at the crosswalk and reconstruction of the driveway to include an ADA compliant sidewalk behind the approach at the library
driveway. The total estimated cost of the project is $42,185 with funding sources from CDBG funding of $40,658, with anticipated
use of funds available from the ADA fund as well as the general fund for the plans and bidding. The project is expected to start in Fall
2024 and be completed by June 2025.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Plans/Bids 10,000 - - - - - 10,000
Construction Mngt/Inspection 10,000 - - - - - 10,000
Construction 22,185 - - - - - 22,185
TOTAL (FUND 20) 42,185 - - - - - 42,185
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
20 ADA Fund 1,527 - - - - - 1,527
20 CDBG 40,658 - - - - - 40,658
TOTAL 42,185 - - - - - 42,185
Page 9 of 31
CAPITAL IMPROVEMENT PROGRAM
ADA Library Sidewalk Phase II
Project Number
XXXX
Category
Facilities
Phase II
Department
Public Works
Proposed Project Timeline
July 2025- June 2026
Project Description & Justification
The City Council in December 2024, approved an application to CDBG for the construction of ADA sidewalk extention improvements,
north of the Calimesa Library. The proposed improvements will bring access into the Library into compliance and provide a safer path
of travel from the the library frontage to the next intersection to the north, Avenue K. Included in the plans is an ADA ramp at the
intersection. The total estimated cost of the project is $39,180 with funding sources from CDBG requested funding of $27,000, with
anticipated additional program income for the balance of the project. The project is expected to start in early summer 2025 and be
completed by June 2026.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Construction Management Survey - 15,000 - - - - 15,000
Engineer - 17,180 - - - - 17,180
Materials Testing - 7,000 - - - - 7,000
TOTAL (FUND 20) - 39,180 - - - - 39,180
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund - 12,180 - - - - 12,180
20 CDBG - 27,000 - - - - 27,000
TOTAL - 39,180 - - - - 39,180
Page 10 of 31
CAPITAL IMPROVEMENT PROGRAM
Facility Improvements and Equipment
Project Number
2030
Category
Facilities
INSERT PICTURE/MAP HERE
Department
Public Works and City Clerk
Proposed Project Timeline
Ongoing
Project Description & Justification
This project will support various capital project needs of all Civic Center facilities including City Hall, City Hall expansion, Planning
Annex, Senior Center, and Fire Department facilities. The useful life of capital projects will approximate 5 to 30 years depending on
capital project.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Senior Center Conference Chairs - 10,000 - - - - 10,000
Fire Dept PPE Equipment - - 250,000 - - - 250,000
Planning Housing & Gen Plan - - 250,000 - - 250,000 500,000
City Hall Kitchen - 10,000 - - - - 10,000
City Artifacts Storage and Maint. - - 10,000 10,000 5,000 - 25,000
TOTAL (FUND 16) - 20,000 510,000 10,000 5,000 250,000 795,000
Fund # Funding Source Prior Year (s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund - 20,000 510,000 10,000 5,000 250,000 795,000
16 Capital Project Fund - - - - - - -
TOTAL - 20,000 510,000 10,000 5,000 250,000 795,000
Page 11 of 31
CAPITAL IMPROVEMENT PROGRAM
Facility Improvements and Equipment
Project Number
XXXX
Category
Facilities
Department
Public Works and Fire Department
Proposed Project Timeline
July 2025-June 2026
Project Description & Justification
The proposed steel structure will optimize space within the Public Works Yard, providing better organization and parking for essential
equipment. Additionally, it will protect valuable machinery from prolonged exposure to the elements, preventing damage such as
brittle and leaking high-pressure hoses on the backhoe and skid steer. This investment will extend the lifespan of equipment, reduce
maintenance costs, and improve overall efficiency in city operations.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Yard Steel Structure - 13,000 - - - - 13,000
TOTAL (FUND 16) - 13,000 - - - - 13,000
Fund # Funding Source Prior Year (s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund - 13,000 - - - - 13,000
16 Capital Project Fund - - - - - - -
TOTAL - 13,000 - - - - 13,000
Page 12 of 31
CAPITAL IMPROVEMENT PROGRAM
Civic Center Roof Replacements
Project Number
2031
Category
Facilities
INSERT PICTURE/MAP HERE
Department
Public Works
Proposed Project Timeline
June 2025 - July 2026
Project Description & Justification
This project will support the roof replacement needs of Civic Center Facilities for the Senior Center. The Senior Center is over 30
years old and roof replacement is required in the near term due to compromised sheathing and roofing paper. The useful life of roof
replacements will approximate 15 to 30 years depending on type of roof.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Senior Center Roof 110,000 - - - - - 110,000
City Hall Roof - - - - - - -
Fire Department Roof - - - - - - -
- - - - - - -
TOTAL (FUND 16) 110,000 - - - - - 110,000
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund - - - - - - -
16 Capital Projects Fund 110,000 - - - - - 110,000
TOTAL 110,000 - - - - - 110,000
Page 13 of 31
CAPITAL IMPROVEMENT PROGRAM
Mountainview Park Phase 2
Project Number
2077
Category
Parks
Department
Public Works
Proposed Project Timeline
July 2021 - September 2025
Project Description & Justification
Mountainview Park is a 2.79 acre park located at 960 4th Street. This project is for the expansion of the park on a 2.31-acre lot
located at 941 5th Street, directly to the west of the existing park. The expansion includes four pickleball courts, walking trails, an
adaptable open sports area, parking lot, maintenance shed, and bathrooms. CalSense Irrigation requested in FY2025-26 will enhance
water efficiency, reducing water waste and runoff by automatically stopping irrigation when excess water is detected. Designed for
water conservation, the system monitors budgets and weather conditions to optimize water distribution based on actual needs.
Implementing this technology will promote healthier turn and shrubs while supporting the city's sustainability efforts and reducing
uncessary water consumption.
As of February 2025, total life-to-date project costs are $608,040.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Landscape Architects 244,940 - - - - - 244,940
Design/Bidding/Project Mngt 193,680 193,680
Equipment and Modular 724,897 724,897
CalSense Irrigation - 11,000 11,000
Construction 2,710,220 - - - - - 2,710,220
TOTAL (FUND 39) 3,873,737 11,000 - - - - 3,884,737
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund 161,000 11,000 - 172,000
39 Parks DIF 3,529,187 - - - - - 3,529,187
39 Prop 68 Grant 183,550 - - - - - 183,550
TOTAL 3,873,737 11,000 - - - - 3,884,737
Page 14 of 31
CAPITAL IMPROVEMENT PROGRAM
County Line Road/Calimesa Boulevard Intersection
Improvement Project
Project Number
2073
Category
Transportation
INSERT PICTURE/MAP HERE
Department
Engineering
Proposed Project Timeline
July 2014 - June 2026
Project Description & Justification
The County Line Rd/Calimesa Blvd intersection has a long history of traffic collisions. The proposed Project will install a 90 ft
diameter roundabout together with street improvements between Park Avenue and Interstate 10 to accommodate the increased
traffic volume. Pedestrians will benefit from the implementation of the innovative roundabout design and the addition of sidewalk
throughout the Project area. Previously the City received federal funding (DEMO-SAFTEA-LU) to complete preliminary engineering
and environmental compliance processing – both tasks are complete as well as additional federal funding to complete right-of-way
acquisition. Final design is currently in progress and construction is anticipated to begin by Early 2026 Construction is planned to be
funded, in part, through federal Community Project Funding (CPF) in the amount of $4 million. Appropriation of construction costs,
currently programmed in FY2024-25 estimated at $7.2 million, will occur once the City receives approval of CPF and confrims
contributions from the City of Yucaipa. City of Yucaipa will be asked to contribute the difference between Yucaipa's right of way
costs and the amount provided by grant funding. It is projected Yucaipa will provide approximately 25% of total project costs.
Other balances have been supported through grant contributions and prior year collections of mitigation fees.
As of February 2025, total life-to-date project costs are $1,055,716.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Preliminary
Engineering/Environmental 595,000 - - - - - 595,000
Management - Project 65,000 - - - - - 65,000
Final Design - - - - - - -
Right-of-Way 1,500,000 - - - - - 1,500,000
Management - Construction 540,000 - - - - - 540,000
Construction 4,488,760 - - - - - 4,488,760
TOTAL (FUND 36) 7,188,760 - - - - - 7,188,760
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
36 SAFETEA-LU (Fed.) 840,475 - - - - - 840,475
36 Other Gov't Agencies 1,800,000 - - - - - 1,800,000
36 Street & Traffic DIF 548,285 - - - - - 548,285
36 Comm. Project (Fed.) 4,000,000 - - - - - 4,000,000
TOTAL 7,188,760 - - - - - 7,188,760
Page 15 of 31
CAPITAL IMPROVEMENT PROGRAM
Cherry Valley Blvd. Interchange Improvements
Project Number
2074
Category
Transportation
INSERT PICTURE/MAP HERE
Department
Engineering
Proposed Project Timeline
July 2014 - June 2027
Project Description & Justification
This project will reconstruct the interchange at Interstate 10 and Cherry Valley Blvd. The selected design alternative is a Diverging
Diamond Interchange (DDI). This will be the first interchange in the region to use this design feature. The Project Study
Report/Project Initiation Document was completed in 2019. The Project Approval/Environmental Document was completed in
December 2023. In FY 2023-24, design began and is expected to take about 18 months. Construction is expected to commence in FY
2025-26, with a completion in late FY 2026-27. RCTC and federal funding is subject to a competitive process and will continue to be
pursued beginning in FY 2024-25.
As of February 2025, total life-to-date projects costs are $4,700,864.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Project Management 250,000 - 100,000 100,000 - - 450,000
Project Study 450,000 - - - - - 450,000
Approval/Environmental 3,000,000 - - - - - 3,000,000
Design 4,000,000 - - - - - 4,000,000
Right-of-Way 2,050,000 - - - - - 2,050,000
Construction Management - - 2,107,500 2,107,500 - - 4,215,000
Construction - - 35,975,000 24,860,000 - - 60,835,000
TOTAL (FUND 36) 9,750,000 - 38,182,500 27,067,500 - - 75,000,000
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
36 Developer Contribution 7,744,724 - 13,543,500 13,271,500 - - 34,559,724
36 WRCOG -Beaumont Sett. - - - 2,100,000 - - 2,100,000
36 CMAQ Grant - - 500,000 - - - 500,000
36 RCTC/Federal Grants 2,000,000 - 24,139,000 11,696,000 - - 37,835,000
36 Street & Traffic DIF 5,276 - - - - - 5,276
TOTAL 9,750,000 - 38,182,500 27,067,500 - - 75,000,000
Page 16 of 31
CAPITAL IMPROVEMENT PROGRAM
I-10 and County Line Road Interchange Improvements
Project Number
2075
Category
Transportation
Department
Engineering
Proposed Project Timeline
July 2022 through June 2031
Project Description & Justification
This project will reconstruct the interchange at Interstate 10 and County Line Road. The Project Study Report/Project Initiation
Document will commence in 2026. Initial funding may be a combination of TUMF Zone Allocation and contribution from the City of
Yucaipa and will be appropriated once identified. Future phases of the project are being funded by developer contributions and is
contingent upon development activity.
As of February 2025, total life-to-date projects costs are $5,032.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Project Management 5,032 - - - - 5,032
Project Study Report 500,000 - - - - - 500,000
Project Approval & Environmental
Document - - - - - 1,000,000 1,000,000
Plans, Specifications & Estimates - - - - - - -
Right-of-Way Acquisition - - - - - - -
Construction - - - - - - -
TOTAL (FUND 36) 505,032 - - - - 1,000,000 1,505,032
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
36 TUMF Zone Allocation 500,000 - - - - - 500,000
36 Other Gov't Agencies - - - - - - -
36 Street & Traffic DIF 5,032 - - - - - 5,032
36 Developer Contribution - - - - - 1,000,000 1,000,000
TOTAL 505,032 - - - - 1,000,000 1,505,032
Page 17 of 31
CAPITAL IMPROVEMENT PROGRAM
Citywide Pavement Management
Project Number
2082
Category
Transportation
Department
Engineering
Proposed Project Timeline
Ongoing
Project Description & Justification
This project will support the City of Calimesa's ongoing Pavement Management Program. Pavement management is the process of
planning the maintenance and repair of the City of Calimesa's network of roadways to optimize pavement conditions over the entire
network. Depending on analysis of each respective street, the process includes preservation, corrective maintenance, catastrophic
maintenance and pavement reconstruction. Carryover includes the conclusion of a contract from Fiscal Year 2024-25 which reflects
a pavement survey estimated cost of $135,000 and a comprehensive street inventory analysis with an estimated cost of $100,000
and citywide pavement management Phase II with a contract approved by City Council in November 2024. As of February 2025, total
life-to-date Phase II project costs are $98,643.
PROPOSED BUDGET AND 5-YEAR PLAN
Estimated
Project Allocation Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Pavement Management 457,559 - 1,000,000 - - 1,000,000 2,457,559
Pavement Management Ph II 2,071,500 - - - - - 2,071,500
Pavement/Street Inventory 100,000 - - - - - 100,000
Pavement Survey 135,000 - - - - - 135,000
TOTAL (FUND 16) 2,764,059 - 1,000,000 - - 1,000,000 4,764,059
Estimated
Fund # Funding Source Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
16 Capital Proj. ARPA 350,532 - - - - - 350,532
16 Capital Proj. Prior Year FB 1,578,527 - 155,000 - - - 1,733,527
01 General Fund - - - - - - -
25 Measure A 835,000 - 845,000 - - 1,000,000 2,680,000
TOTAL 2,764,059 - 1,000,000 - - 1,000,000 4,764,059
Page 18 of 31
CAPITAL IMPROVEMENT PROGRAM
County Line Road Transportation Corridor Improvements
Project Number
2087
Category
Transportation
Department
Engineering
Proposed Project Timeline
April 2022 - February 2026
Project Description & Justification
This is a joint project between the City of Calimesa and City of Yucaipa to construct four single-lane and one multi-lane roundabouts,
together with street, pedestrian, and bicycle improvements on County Line Road between Park Avenue and Bryant Street. In March
2021, the City received a SB1 Local Partnership Program (LPP) grant for the project construction. Construction contract was awarded
in February of 2022.
As of February 2025, total life-to-date projects costs are $10,153,111.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Preliminary
Engineering/Enviromental 1,658,839 - - - - - 1,658,839
Right-of-Way 687,000 - - - - - 687,000
Construction 9,600,258 - - - - - 9,600,258
TOTAL (FUND 36) 11,946,097 - - - - - 11,946,097
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
21 AB 2766 50,000 - - - - - 50,000
22 RMRA (SB 1) 1,582,710 275,000 - - - - 1,857,710
36 LPP Grant 3,747,000 - - - - - 3,747,000
36 MSRC Grant 50,000 - - - - - 50,000
36 Developer Contrib. 1,200,000 - - - - - 1,200,000
36 City of Yucaipa 4,962,070 - - - - - 4,962,070
36 Street & Traffic DIF 354,317 (275,000) - - - - 79,317
TOTAL 11,946,097 - - - - - 11,946,097
Page 19 of 31
CAPITAL IMPROVEMENT PROGRAM
County Line Road Paving - 3rd St. to California St.
Project Number
2088
Category
Transportation
Department
Engineering
Proposed Project Timeline
April 2022 - February 2026
Project Description & Justification
This project is related to the County Line Road Improvement Project (Project 2087). This project will provide the additional funding
needed to complete pavement on County Line Road from 3rd Street to California Street.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Construction 135,000 - - - - - 135,000
TOTAL (FUND 25) 135,000 - - - - - 135,000
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
25 Measure A 135,000 - - - - - 135,000
TOTAL 135,000 - - - - - 135,000
Page 20 of 31
CAPITAL IMPROVEMENT PROGRAM
County Line Road Paving - California St. to Bryant St.
Project Number
2089
Category
Transportation
Department
Engineering
Proposed Project Timeline
April 2022 - February 2026
Project Description & Justification
This project is related to the County Line Road Improvement Project (Project 2087). This project will provide the additional funding
needed to complete pavement on County Line Road from California Street to Bryant St.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Construction 70,000 - - - - - 70,000
TOTAL (FUND 25) 70,000 - - - - - 70,000
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
25 Measure A 70,000 - - - - - 70,000
TOTAL 70,000 - - - - - 70,000
Page 21 of 31
CAPITAL IMPROVEMENT PROGRAM
I-10 and Singleton Road Interchange Improvements
Project Number
2092
Category
Transportation
Department
Engineering
Proposed Project Timeline
July 2019 through June 2027
Project Description & Justification
During initial freeway construction in the 1960s, Caltrans did not construct the West bound on ramp or the East Bound off ramp.
However, grading and drainage system improvements were completed. The project proposes to construct these missing ramps and
related improvements. This project will horizontally realign Calimesa Boulevard approximately 400 feet easterly while widening
approximately 3,300 linear feet of Calimesa Boulevard and 3,000 linear feet of Singleton Road to their ultimate street widths. Street
improvements will consist of new curb, gutter sidewalk, two (2) vehicular lanes in each direction, construction of signalized
intersection, and existing storm drain channel modifications. The realignment of Calimesa Boulevard at Singleton Road will provide
additional horizontal clearance from the I-10/Singleton Interchange in order to provide the minimum intersection set back for future I-
10/Singleton interchange improvements. Construction on the realignment of Calimesa Blvd. will begin in Summer 2025 and is
scheduled to be completed by the end of 2025. The missing freeway ramps are tentatively scheduled to begin in early 2026 (subject
to funding availability as noted below) and take approximately nine months to complete. This project is being funded by a
combination of TUMF Pass Zone Funds and Federal Community Project Funding (CPF). CPF is currently shown as being received in
Fiscal Year 2026-27 since the FY25 federal budget eliminated earmarks. CPF funds will be requested for the FY26 federal budget
cycle.
As of February 2025, total life-to-date projects costs are $469,353.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Project Approval & Environmental 300,000 - - - - - 300,000
Design 600,000 - - - - - 600,000
Right-of-Way 2,100,000 2,100,000
Construction 5,000,000 - 5,000,000 - - - 10,000,000
TOTAL (FUND 36) 8,000,000 - 5,000,000 - - - 13,000,000
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
36 TUMF Zone Allocation 8,000,000 - - - - - 8,000,000
36 Federal Grant - - 5,000,000 - - - 5,000,000
36 Street&Traffic DIF/Dev Cont - - - - - - -
TOTAL 8,000,000 - 5,000,000 - - - 13,000,000
Page 22 of 31
CAPITAL IMPROVEMENT PROGRAM
Realignment of Calimesa Blvd At Cherry Valley Blvd
DRAFT ALIGNMENT
Project Number
2094
Category
Transportation
Department
Engineering
Proposed Project Timeline
May 2023 through June 2027
Project Description & Justification
This project will horizontally realign Cherry Valley Boulevard approximately 950 feet easterly while widening approximately 3,000
linear feet of Calimesa Boulevard to its ultimate street width. Street improvements will consist of new curb, gutter sidewalk, two (2)
vehicular lanes in each direction, and construction of signalized intersection. The realignment of Calimesa Boulevard at Cherry Valley
Boulevard will provide the additional horizontal clearance from the I-10/Cherry Valley Interchange in order to provide the minimum
intersection set back for future I-10/Cherry Valley ultimate interchange improvements. Project design has begun and is anticipated to
be ready for construction in Fiscal Year 2025-26.
As of February 2025, total life-to-date project costs are $18,187.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Preliminary
Engineering/Environmental 220,000 - - - - - 220,000
Final Design 100,000 - - - - - 100,000
Right-of-Way - - - - - - -
Construction 5,230,000 - - - - - 5,230,000
TOTAL (FUND 36) 5,550,000 - - - - - 5,550,000
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
36 RCTC Grant 5,200,000 - - - - - 5,200,000
36 Developer Contribution 350,000 - - - - - 350,000
TOTAL 5,550,000 - - - - - 5,550,000
Page 23 of 31
CAPITAL IMPROVEMENT PROGRAM
I-10 and Sandalwood Road Interchange Improvements
Project Number
2097
Category
Transportation
Department
Engineering
Proposed Project Timeline
July 2023 through December 2029
Project Description & Justification
This project will reconstruct the interchange at Interstate 10 and Sandalwood Road. The Project Study Report/Project Initiation
Document will commence in 2026. Since this project is being funded by developer contributions and is contingent upon development
activity, there are no costs associated at this time.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Project Management - - - - - - -
Project Study Report - - - - - - -
Project Approval & Environmental
Document - - - - - - -
Plans, Specifications & Estimates - - - - - - -
Right-of-Way Acquisition - - - - - - -
Construction - - - - - - -
TOTAL (FUND 36) - - - - - - -
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
36 Developer Contribution - - - - - - -
TOTAL - - - - - - -
Page 24 of 31
CAPITAL IMPROVEMENT PROGRAM
Calimesa Creek Stage III Improvement Project
Project Number
2072
Category
Storm Drains
Department
Engineering
Proposed Project Timeline
July 2014 - December 2026
Project Description & Justification
This Project will construct the proposed Calimesa Creek Stage III improvements that are a continuation of the Calimesa Channel
“Stage I” and “Stage II” projects that were completed by the Riverside County Flood Control and Water Conservation District
(RCFC&WCD) in 2002. Stage III improvements will consist of a 4.5-acre detention basin on the north side of Calimesa Creek
approximately 150 feet west of 3rd Street, 18”, 24”, 54”, 72” and 78” underground storm drains, box culverts, roadway crossings and
minor grading of the bank slopes of Calimesa Creek to protect the adjacent properties from a 100-year storm event. Once completed,
the Calimesa Creek Stage III Project would provide 100-year flood protection to existing and future development along County Line
Road and Calimesa Creek from 5th Street on the east to Interstate 10 on the west. Project is split into two phases, phase 1 is for the
main pipeline within public right-of-way and phase 2 is for the basin and final system connections. Phase 1 construction is anticipated
to begin in July 2025. Construciton for Phase 2 is antipcated to begin construction in mid 2026 once final design processing with
Riverside County Flood Control and environmental permitting is completed.
As of February 2025, total life-to-date projects costs are $4,127,463.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Preliminary Engineering/Design 1,127,818 - - - - - 1,127,818
Environmental 576,600 - - - - - 576,600
Right-of-Way/Property Acquisition 3,147,400 - - - - - 3,147,400
Construction Management 1,020,000 188,345 1,208,345
Construction 6,794,300 3,275,234 - - - - 10,069,534
TOTAL (FUND 32) 12,666,118 3,463,579 - - - - 16,129,697
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
32 EPA Grant 247,547 - - - - - 247,547
32 Riverside County Flood 11,447,260 3,601,344 - - - - 15,048,604
32 Other Gov't Agencies - - - - - - -
32 Storm Drain DIF 971,311 (137,765) - - - - 833,546
TOTAL 12,666,118 3,463,579 - - - - 16,129,697
Page 25 of 31
CAPITAL IMPROVEMENT PROGRAM
California St. Storm Drain
Project Number
2101
Category
Storm Drains
Department
Engineering
Proposed Project Timeline
June 2025 - July 2026
Project Description & Justification
Public storm runoff accumulates along California Street between County Line Road and Avenue L. An existing catch basin captures
this runoff and a channel along the South end of the California Mobile Home Park (Park) conveys the runoff to the West where it
discharges into the Park’s most Westerly drive resulting in historic flooding. To address the drainage deficiency, the City proposes to
construct a storm drain system connecting the existing California Street system near Avenue L to the existing California Street catch
basin. The new system will redirect runoff to the California Street/Avenue L system.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Preliminary Engineering/Design 500,000 58,000 - - - - 558,000
Environmental - - - - - - -
Right-of-Way/Property Acquisition - - - - - - -
Construction Management - 73,000 73,000
Construction - 30,500 - - - - 30,500
TOTAL (FUND 32) 500,000 161,500 - - - - 661,500
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
32 Storm Drain DIF 500,000 161,500 - - - - 661,500
TOTAL 500,000 161,500 - - - - 661,500
Page 26 of 31
CAPITAL IMPROVEMENT PROGRAM
Calimesa Master Plan of Drainage Update
Project Number
XXXX
Category
Storm Drains
Department
Engineering
Proposed Project Timeline
June 2025 - July 2026
Project Description & Justification
Calimesa's Master Plan of Drainage has not been updated since 1992. The City intends to work with Riverside County Flood Control
(RCFC) to update it's master plan of drainage which will include recomendations for future drainage improvements and
attenuation/recharge basins. In the previous fiscal year RCFC allocated $300,000 to Calimesa to study and update their drainage
master plan.
PROPOSED BUDGET AND 5-YEAR PLAN
Project Allocation Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Preliminary Engineering/Design - 300,000 - - - - 300,000
Environmental - - - - - - -
Right-of-Way/Property Acquisition - - - - - - -
Construction Management - - -
Construction - - - - - - -
TOTAL (FUND 32) - 300,000 - - - - 300,000
Fund # Funding Source Prior Year(s) 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
32 Riverside County Flood - 300,000 - - - - 300,000
32 Storm Drain DIF - - - - - - -
TOTAL - 300,000 - - - - 300,000
Page 27 of 31
CAPITAL IMPROVEMENT PROGRAM
Vehicle & Rolling Stock Replacement
Project Number
2048
Category
Vehicles
INSERT PICTURE/MAP HERE
Department
Public Works/Fire
Proposed Project Timeline
Ongoing
Project Description & Justification
This project will support the replacement of City vehicles and rolling equipment. The useful life ranges from 5 years to 25 years.
During Fiscal Year 2023-24, the City entered into a 10-year capital lease to purchase a Fire Engine at a cost of approximately
$121,000 per year with the final year of payment to be in FY2033-34. Funds will be transferred from the General Fund for the
annual payments on the lease. The General Fund is prefunding three years of annual payments for an estimated $375,000 in
transfers from the General Fund to the Vehicle Replacement Fund. This project includes a portion of the projected vehicle
replacements over a five-year cycle, with the exception of significant vehicle replacements with estimated costs of over $500,000.
Vehicles with replacement cost of over $500,000 will be analyzed on an annual basis and are not included in this schedule.
PROPOSED BUDGET AND 5-YEAR PLAN
Estimated
Project Allocation Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Monarch G2 Pumper Cap. Lease - 121,000 121,000 121,000 121,000 121,000 605,000
Electric Vehicle Replacement - - 90,000 - - - 90,000
COP Vehicle Replacement -Ranger - 45,000 - - - - 45,000
Squad 1 Vehicle Replacement 2005 - 80,000 - - - - 80,000
Brush Engine Type III - - - - - - -
Ford F350 Crew Cab - 100,000 - - - - 100,000
Cold Planer Attachment - 40,000 - - - - 40,000
Back Hoe Replacement - - 175,000 - - - 175,000
Cat Roller for Hot Patching - - 41,000 - - - 41,000
Vehicle Replacements - - 125,000 130,000 135,000 140,000 530,000
TOTAL (FUND 75) - 386,000 552,000 251,000 256,000 261,000 1,706,000
Estimated
Fund # Funding Source Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund - 386,000 462,000 251,000 256,000 261,000 1,616,000
21 AQMD Fund - - 90,000 - - - 90,000
TOTAL - 386,000 552,000 251,000 256,000 261,000 1,706,000
Page 28 of 31
CAPITAL IMPROVEMENT PROGRAM
Desktop & Laptop Replacement
Project Number
2045
Category
Information Technology
INSERT PICTURE/MAP HERE
Department
Administration
Proposed Project Timeline
Ongoing
Project Description & Justification
This project will support management of the routine replacement of computer desktops and laptops. The estimated useful life of
each workstation will range from 3 to 5 years.
PROPOSED BUDGET AND 5-YEAR PLAN
Estimated
Project Allocation Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
(9) 9 Desktops - - - - 24,000 - 24,000
(3) 2 Desktops 1 Laptops - - - - 7,500 - 7,500
(5) Laptops 28,751 - - - - 33,000 61,751
(8) 14 Desktops 28,900 - - - - 32,000 60,900
(12) 6 Desktops 6 Laptops - 24,600 - - - - 24,600
(6) 2 Desktops 4 Laptops - - 12,800 - - - 12,800
(11)10 Desktops 1 Laptop - - - 20,300 - - 20,300
TOTAL (FUND 76) 57,651 24,600 12,800 20,300 31,500 65,000 211,851
Estimated
Fund # Funding Source Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund 57,651 24,600 12,800 20,300 31,500 65,000 211,851
TOTAL 57,651 24,600 12,800 20,300 31,500 65,000 211,851
Page 29 of 31
CAPITAL IMPROVEMENT PROGRAM
Server Replacement & Upgrades
Project Number
2046
Category
Information Technology
INSERT PICTURE/MAP HERE
Department
Administration
Proposed Project Timeline
Ongoing
Project Description & Justification
This project will support management of Server replacements and required transitions to cloud based supported services on a
rotation of every three years. The estimated useful life of each server is approximately 5 years.
PROPOSED BUDGET AND 5-YEAR PLAN
Esimated
Project Allocation Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Server CALIHOST1 Refresh 14,750 - - - - - 14,750
Server CALIHOST3 Refresh - 15,000 - - - - 15,000
TOTAL (FUND 76) 14,750 15,000 - - - - 29,750
Esimated
Fund # Funding Source Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund 14,750 15,000 - - - - 29,750
TOTAL 14,750 15,000 - - - - 29,750
Page 30 of 31
CAPITAL IMPROVEMENT PROGRAM
Information Technology Major Software & Equipment
Project Number
2047
Category
Information Technology
INSERT PICTURE/MAP HERE
Department
Administration
Proposed Project Timeline
Ongoing
Project Description & Justification
This project will support management IT services of software and components not related to workstation or server replacement.
Capital projects in this category will include software implementation, IT streaming services, and network infrastructure. The
estimated useful life of each project varies from 3 to 10 years.
In FY 24, the City selected permitting software which will be implemented in April 2025. The permitting software is being partially
funded by a State grant to satisfy Solar Application requirements. With the new permititing software, the City will have available
online permits and workflow tracking which will enhance customer service. The City's financial software, Tyler FundBalance, will be
retired in by the software company as of December 31, 2026. Staff is making recommendations for selection of new accounting
software in the Spring of 2025, with an anticpated implementation date of July 1, 2026. To ensure quality streaming of City meetings,
this project also includes funding for camera and equipment replacement as items reach end-of-life. Finally, network infrastructure
includes routine replacement of switches, routers, and wireless access points.The City will also be providing an interactive touch
screen visual aid televsion in the Community Developement Annex Lobby to aid and assist with presentation and review of large
scale plans, maps and assistance for the general public.
PROPOSED BUDGET AND 5-YEAR PLAN
Estimated
Project Allocation Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
Finance Software & Consultant 80,000 50,000 - - - - 130,000
City Council Meeting AV Imp. - 50,000 50,000
Interactive Touch Screen Lobby - 10,000 - - - - 10,000
IT Streaming Upgrades 15,583 - 16,000 - - - 31,583
Network Infrastructure 4,000 - 6,000 15,000 - - 25,000
TOTAL (FUND 76) 99,583 110,000 22,000 15,000 - - 246,583
Estimated
Fund # Funding Source Carryover 2025-26 2026-27 2027-28 2028-29 2029-30 TOTAL
01 General Fund 59,583 110,000 22,000 15,000 - - 206,583
76 Solar App State Grant 40,000 - - - - - 40,000
TOTAL 99,583 110,000 22,000 15,000 - - 246,583
Page 31 of 31