Castle Rock Water Commission
Regular MeetingCastle Rock, CO · October 24, 2018
Minutes
Todd Warnke, Chair
Amy Blackwell, Vice Chair
Castle Rock Water Commission
Ernie Foerster
Meeting Minutes Clark Hammelman
Caryn Johnson
Don Trujillo
Katherine Redmond
Wednesday, October 24, 2018 6:00 PM Castle Rock Water
175 Kellogg Ct., Bldg. 183
Castle Rock, CO 80109
This meeting is open to the public. Three or more Council members may also attend this
meeting, during which the items listed herein will be discussed
CALL TO ORDER / ROLL CALL
Present 7 - Caryn Johnson, Clark Hammelman, Ernie Foerster, Chair Todd Warnke, Vice Chair Amy
Blackwell, Don Trujillo, and Katherine Redmond
Attendance 5 - James Townsend, Mark Marlowe, Tim Friday, Jeanne Stevens, and Dawn Tiffany
Commissioner Redmond arrived at 6:07 p.m.
Council Member Townsend left at 6:30 p.m.
ADMINISTRATIVE BUSINESS
WC 2018-116 Approval of Minutes of September 26, 2018
It was moved by Commissioner Blackwell and seconded by Commissioner Johnson
to approve the meeting minutes of 9/26/18 as amended.
Yes: 5 - Johnson, Hammelman, Foerster, Chair Warnke, and Blackwell
Not Present: 1 - Redmond
Abstain: 1 - Trujillo
WC 2018-109 Meeting Date in December
It was agreed that this issue will be tabled until the November 28, 2018
commission meeting. A decision will then be made to cancel the meeting or
schedule a special meeting in December, if needed.
A motion was made by Commissioner Foerster and seconded by Commission
Hammelman that this item should be tabled until the November 28, 2018
commission meeting.
COUNCIL UPDATE
Council Member Townsend updated the commission on some recent Town
Council activity, including the Dawson Ridge Suspension issue and the Crystal
Valley Interchange Coalition. Mr. Marlowe provided some updates from the
October 16th Town Council meeting including the Environmental Leadership Gold
Award that was issued to Castle Rock Water from Colorado Department of Public
Health and Environment. Our Parks department also received a National Gold
Castle Rock Water Commission Meeting Minutes October 24, 2018
Medal for excellence in park and recreation management. The Our Town Academy
graduates were honored and Norris Croom was recognized, in a badge ceremony,
as the new fire chief. An economic incentive as a primary employer request was
approved for the Solaray Pugs Companies. Huddick Excavating was awarded the
contract for the East Plum Creek trail extension and construction will begin soon
on the connection from Plum Creek to Crystal Valley Parkway. The deep well
rehabilitation contract with Applied Ingenuity was approved as well as the Town's
3rd quarter budget amendments.
COMMISSION COMMENTS
Commissioner Johnson reported that she has spoken with residents that are
concerned with the high fee portion of their water bill. She wondered if these high
fees were detrimental to promoting conservation. Mr. Marlowe replied that with the
increases to the upper tier rate structure next year, savings will come with lower
water use. Castle Rock Water will be publishing its rate comparison with 30
nationwide cities and local south metro water utilities. Commissioner Johnson also
mentioned that she attended and enjoyed the Water Education Colorado Reuse
event.
Commissioner Blackwell asked about the deadlines for the Water Commission
Agenda posting to the Town Website. She also brought up the topic of lead
contamination that was occuring in Idaho Springs and the disinfection by-products
(DBPs) that were produced downstream, because of their pH manipulation. Mr.
Marlowe discussed our testing protocol for lead and copper. Customers have had
no issues in our regularly scheduled household sampling. Our Water Quality team
recently partnered with Douglas County Schools, to test lead levels in local
schools. There was only one high lead issue which was found in the science lab
sinks at Douglas County High School. The sink plumbing in the lab was replaced
and the issue resolved.
ACTION ITEMS (HIGH PRIORITY / TIME CRITICAL)
WC 2018-110 Water and Wastewater Criteria Manual Updates
Town Council Agenda Dates: Nov. 6, 2018 (1st Reading); Dec. 4, 2018 (2nd
Reading)
Ms. Stevens presented the Water and Wastewater Manual updates. She explained
that the last major update occurred in 2012 and that there were no major changes
to these documents, but a few items had been changed for clarity. In order to
protect the minimum fire flow of 1500 gallons per minute (gpm), all new distribution
main installations would be utilizing 8-inch diameter pipe, 6-inch pipe would no
longer be allowed. Also the installation of water or sewer mains under 48-inch or
larger stormwater pipes or box structures would now need to be encased in steel
casing to prevent damage from leaks and help with system repairs. This steel
casing would also be required for use on pipe located in 100 year flood plain areas.
There were no major concerns when these Criteria Manual changes were
presented to developers at a Town event.
It was moved by Commissioner Trujillo and seconded by Commissioner Redmond to
recommend to Town Council approval of the updated Water and Wastewater
Criteria Manuals as presented
Castle Rock Water Commission Meeting Minutes October 24, 2018
Yes: 7 - Johnson, Hammelman, Foerster, Chair Warnke, Blackwell, Trujillo, and Redmond
WC 2018-119 Turf Type Water Budget Change
Mr. Marlowe explained the planned update to the turf type water budget and
ordinance change for non-residential customers. The change to the ordinance will
allow more flexibility in the future by changing the 'turf type' language to 'landscape
type'. New non-residential customers in 2019 will now have their water budgets
based on the type of landscaping installed as well as irrigated area and
evapotranspiration rates. Previously the budgets were created based on Kentucky
Bluegrass turf, which has a high water requirement. By using the actual turf type
installed, the budget will be aligned with the actual needs of the landscape.
It was moved by Commissioner Blackwell and seconded by Commissioner Johnson
to recommend to Town Council the Turf Type Water Budget Change as presented.
Yes: 7 - Johnson, Hammelman, Foerster, Chair Warnke, Blackwell, Trujillo, and Redmond
WC 2018-113 Metzler Park Turf Replacement
Mr. Marlowe explained that the Metzler Park Turf Replacement Project was a
partnership between Castle Rock Water (CR Water) and the Parks Department.
The project consists of replacing the outfield of the baseball diamonds with
artificial turf. This project is still in the development phase and all of the details of
the deal with Parks have not yet been acquired. Because of the critical time frame,
for project completion before irrigation season, it needs to be approved by Town
Council at the November 6th meeting.
In general the thought is the cost of this replacement would be paid up front by
Castle Rock Water, by conducting an inter-fund loan, with an interest rate of 1.5%,
for a loan amount of $1.3 million and a capital contribution from water resources of
$800,000. The Parks Department would pay back this loan by continuing to pay
CR Water the amount of their normal monthly water bill; this payback process
would occur over a period of 20 to 30 years.
Replacing the bluegrass turf with artificial turf would result in an immediate water
savings of 18-19 acre feet, during the peak demand irrigation season. The other
benefits of this project include: year round use of the Parks facility, reduced
maintenance and a public demonstration of the water conservation ethic promoted
by the Town. Four bids were received. The low bid was from Academy Sports Turf
for $2.1 million.
It was moved by Commissioner Trujillo and seconded by Commissioner Blackwell
to recommend to Town Council approval of the Metzler Park Turf Replacement.
Yes: 5 - Johnson, Hammelman, Chair Warnke, Blackwell, and Trujillo
No: 2 - Foerster, and Redmond
WC 2018-117 Escrow Agreement for Construction Phase Engineering Services for
Wastewater Treatment Plant 3.0 MGD Expansion
Town Council Meeting Date: November 6, 2018
Castle Rock Water Commission Meeting Minutes October 24, 2018
Mr. Marlowe presented an overview of the escrow agreement. Castle Rock Water
is seeking the Town Council approval of a Resolution for the Construction Phase
Engineering Escrow Agreement with Plum Creek Water Reclamation Authority
(PCWRA), Castle Pines North Metropolitan District and Castle Pines Metro District
for the wastewater treatment plant's 3.0 million gallons per day (MGD) expansion.
Burns and McDonnell submitted the selected proposal for construction phase
engineering services. Due to the complexity of the overall project, it will be crucial
to have the Design Engineer onsite to ensure that the project is constructed in
accordance with the design intentions and assist PCWRA in meeting effluent
water quality requirements during and after construction. Their proposal is
$1,078,323 and the Town's share of these costs is $917,613 (based on 85.1%
project participation rate). In the near term, the Town will front the full cost. The
expansion agreement will outline the cost responsibilities of all PCWRA entities
participating in the plant expansion as well as any repayment terms and conditions
necessary. This agreement will come to commission in November or December
for consideration.
It was moved by Commissioner Blackwell and seconded by Commissioner
Hammelman to recommend Town Council approval of the Escrow Agreement for
Construction Phase Engineering Services for the Plum Creek Water Reclamation
Authority as presented.
Yes: 7 - Johnson, Hammelman, Foerster, Chair Warnke, Blackwell, Trujillo, and Redmond
DIRECTOR FOLLOW-UP AND INFORMATIONAL / UPDATE ITEMS
WC 2018-111 Conservation Impact Model
Mr. Marlowe presented the update on the Conservation Impact Model (CIM).
Developed in 2007, the CIM is an excellent model for evaluating price elasticity
impacts; provided appropriate data are available for populating the model. This
data includes annual billing data by class, price elasticity estimates, and
Evapo-Transpiration requirements by month.
One of Stantec's 2018 rates and fees study recommendations was to complete a
more thorough review of cost of service for a future test year. Updating the CIM
with cost-of-service model generated rates during that review and comparing the
results with existing rates would be beneficial. The current CIM did not deliver the
level of detail that was needed; we will be looking in depth at our cost of service
figures and other data used in the model in 2019.
WC 2018-112 Water Court Cases
Town Council Agenda Date: October 16, 2018
Mr. Marlowe presented an update on our current water court cases. The Town
currently has three active cases where we are the applicant. These cases will
provide maximum benefit for use of our water rights and our goal is to obtain
stipulations from opposers as quickly as possible.
There are six active cases that the Town is opposing, that could injure our water
Castle Rock Water Commission Meeting Minutes October 24, 2018
rights. On cases we oppose, we want to stipulate as early as possible but we
must make sure we can do this while protecting our rights.
Castle Rock Water budgeted $220,000 for Water Court cases in 2018. So far this
year we have spent $158,500 on legal fees and $35,000 on consulting services.
For 2019 $110,000 has been budgeted for legal fees and $110,000 has been
budgeted for engineering fees.
WC 2018-114 Non-residential Smartscape Pilot Results
Town Council Agenda Date: November 6, 2018
Mr. Shultz provided a recap of the Non-Residential Smartscape Pilot results.
Presentations were given to area Home Owner Associations (HOAs) and many
expressed interest in including Smartscape landscaping renovation in future
budgets. There were three HOAs that participated in the 2018 Smartscape
program: The Woodlands, Castlewood Ranch and Sapphire Point. A total of
30,363 square feet of high water use landscaping was replaced with low or no
water landscape materials. Of the original budget of $100,000, rebates of $30,363
were distributed. Staff recommends evaluating the program to increase the
minimum square footage and the amount of reimbursement per square foot for the
2019 program.
WC 2018-115 Plum Creek Water Purification Facility Advanced Treatment Open Houses
Mr. Marlowe updated the commission on the use of Plum Creek Water Purification
Facility open houses for public outreach. Consideration is being giving to utilizing
other public events, such as the Star Lighting celebration, to reach out to citizens.
This will enable staff to interact with more residents at events that have higher
public attendance. Our Customer Relations Program Manager, Sandra Aguilar,
has created sign boards and displays, that could be used at a booth, for these type
of events.
WC 2018-118 Graywater Systems
Mr. Marlowe updated the commission on the work progress for an ordinance that
will allow certain gray water systems in the Town of Castle Rock. These types of
indoor contained systems would filter and chlorinate shower and sink water, then
recycle them to the tank of the toilet for flushing; potentially resulting in water
savings of up to 20 percent. An ordinance is being developed and will come back
to commmission for consideration.
COMMISSIONER MEETING COMMENTS
Agenda
Todd Warnke, Chair
Castle Rock Water Commission Amy Blackwell, Vice Chair
Ernie Foerster
Agenda - Final Clark Hammelman
Caryn Johnson
Don Trujillo
Katherine Redmond
Wednesday, October 24, 2018 6:00 PM Castle Rock Water
175 Kellogg Ct., Bldg. 183
Castle Rock, CO 80109
This meeting is open to the public. Three or more Council members may also attend this
meeting, during which the items listed herein will be discussed
6:00 pm CALL TO ORDER / ROLL CALL
ADMINISTRATIVE BUSINESS
WC 2018-116 Approval of Minutes of September 26, 2018
Attachments: CRW09-26-2018minutes
WC 2018-109 Meeting Date in December
COUNCIL UPDATE
COMMISSION COMMENTS
ACTION ITEMS (HIGH PRIORITY / TIME CRITICAL)
WC 2018-110 Water and Wastewater Criteria Manual Updates
Town Council Agenda Dates: Nov. 6, 2018 (1st Reading); Dec. 4, 2018
(2nd Reading)
Attachments: Attachment A: TC Memo Water WW Criteria Manual Updates
Attachment B: Water Criteria Manual Summary of Changes
Attachment C: Wastewater Criteria Manual Summary of Changes
WC 2018-119 Turf Type Water Budget Change
Attachments: Attachment A: Draft ordinance
WC 2018-113 Metzler Park Turf Replacement
WC 2018-117 Escrow Agreement for Construction Phase Engineering Services for
Wastewater Treatment Plant 3.0 MGD Expansion
Town Council Meeting Date: November 6, 2018
Attachments: PCWRA TC Memo
DIRECTOR FOLLOW-UP AND INFORMATIONAL / UPDATE ITEMS
Castle Rock Water Commission Agenda - Final October 24, 2018
WC 2018-111 Conservation Impact Model
Attachments: CRW_Conservation Impact Model Purpose-draft_10-05-18
WC 2018-112 Water Court Cases
Town Council Agenda Date: October 16, 2018
Attachments: Water Court Case Memo Packet
WC 2018-114 Non-residential Smartscape Pilot Results
Town Council Agenda Date: November 6, 2018
Attachments: Non Res. Pilot Study Town Council Memo
WC 2018-115 Plum Creek Water Purification Facility Advanced Treatment Open Houses
WC 2018-118 Graywater Systems
COMMISSIONER MEETING COMMENTS