City Council
Regular MeetingColumbia City, OR · March 9, 2015
Minutes
Water and Sewer Committee Meeting Minutes - March 9, 2015 - 6 pm
City Hall, 1840 Second Street, Columbia City of Columbia City
Members Present-
Josh Fromm, Chair
Gordon Thistle
John Burdett
Robert Campbell
Chuck Garman
Finos Lunsford
Attendees-
Leahnette Rivers, City Administrator/Recorder
Micah Rogers, Public Works Superintendent
Meeting called to order at 6 pm.
1. Water Improvements Project Update: Staff updated Committee Members
about the status of the Water Improvements Project, which involved the installation of a
fully automated meter reading system, the purchase of new automated meter reading
equipment, several pressure reducing valve (PRV) projects, a system-wide leak detection
survey, and the abandonment of redundant 4-inch piping.
The automated meter reading system is complete with the exception of a handful of
meters remaining to be replaced. Meter reading now takes one Public Works employee
just a few hours to complete, which is significantly more effective than the manual reads,
which previously took several workers several days to perform.
The contractor, NW Kodiak Construction, was hired to do the PRV and line
abandonment work, and went out of business before the project was substantially
complete. They abandoned the water line and completed the PRV work to the point that
it was functional, but a punch list and some electrical work at a new pump station remain
to be completed. The City has negotiated a takeover agreement with the Surety
Company, which includes $10,455.93 in liquidated damages to cover the extra expense
that the City has incurred as a result of the contractor’s failure to perform. The Surety
Company will enter into a new construction contract with another contractor to finish the
work. The project manager from NW Kodiak that previously worked on our project will
resume work again on the project as an employee for the new construction company. The
Surety Company is also handling several claims from companies that provided supplies
for the project under the Payment Bond.
The leak detection survey is complete, and a list of potential leaks will be investigated by
the Public Works crew. The City is experiencing an 18% leak loss, and a loss of 10% or
less is our target.
This project is funded under a Safe Drinking Water Loan, with 40% debt forgiveness.
2. Sewer Improvements Project Update: This project, which consists of pump
and electrical upgrades to the RCE pump station, the replacement or abandonment of 17
steel septic tanks, the installation of a wastewater telemetry, monitoring and alarm
system, and lining 25 manholes, is in the design phase. 50% design drawings are
currently under review. This project is funded under a DEQ Clean Water Loan.
3. 2015-16 Five Year Capital Improvement Plan: Members reviewed the 20-year
capital improvement plans contained in the Water System Master Plan and Wastewater
Collection System Facility Plan, and prioritized the following project list for inclusion in
the 2015-16 Five Year Capital Improvement Plan:
Water Projects:
Upper Reservoir Restoration and Level Monitoring 2015-16
Fire Hydrant Replacement 2015-16
“I” Street and The Strand Waterline Replacement/Hydrant 2016-17
“First Street Water Line Replacement/Hydrant 2017-18
Fourth Street Water Line Replacement/Hydrant 2018-19
Data Storage and Retrieval System 2019-20
Sewer Projects:
I & I Reduction 2015-16
Steel Tank Replacement and Abandonment 2015-16
I & I Reduction 2016-17
Steel Tank Replacement and Abandonment 2016-17
Steel Tank Replacement and Abandonment 2017-18
Tank Abandonment 2018-19
Tank Abandonment 2019-20
Micah will conduct further research about the Ranney Collector to see if it has been
designated as being under the influence of surface water before it is added to the Five
Year Capital Plan.
4. Adjournment. Meeting adjourned at 7:26 p.m.