City Council Committee: Appointments
Regular MeetingFalls Church, VA · January 11, 2023
Minutes
Public Works/Library Committee Meeting
August 14, 2019, 6:00 pm
Attendees Present:
Mayor Boudreau
Council Members: Beaton, Brocksmith, Hudson, Hulst, Moberg, Molenaar
Staff Members: Public Works – Bell, Chesterfield, Christen; Library – Huffman; Project
Development Manager – Donovan; Finance Director – Volesky
1. Approval of Public Works Committee Minutes:
Councilmember Hulst moved to approve the minutes from July 14, 2019; Seconded by
Councilmember Beaton; Carried by all.
2. Library Committee – Isaac Huffman
a) Library Card Sign Up Month
A leading indicator of overall growth in a library is the number of new cards issued. New card
signs ups are up 47 cards over this time last year, including 20 cards applied for via the new
online application process. This year the September promotional theme is “Back to the
Library” from the eighties. Library growth is typically influenced by five things; Policy,
Atmosphere, Awareness, Community, and Economy. The overall goal is to be up 100 cards by
years end.
b) Summer Reading Wrap Up
The summer reading program is wrapping up. Several events were held which included: Space
quest camp (including virtual reality, robots, and an electrical coil); Son of Reptile Man (with
150 attendees); Apollo 11 (about 50 people came and made lava lamps, ate moon pies, and
relived history); “Get Your Groot On” (planted baby Groot in cups); and a teen model rocket
event. These events included STEM/reading combo, math, science, and engineering through
hands on activities.
c) Monthly Updates
Upcoming library events include: “Dig Into Fall”, an urban farming series with the Library and
WSU Skagit Master Gardeners partnering to present fall classes on backyard sustainability and
free-range food; a Downtown Abbey Celebration; the celebration of Latino Heritage Month;
and an upcoming art show.
3. Program Coordination Division – Blaine Chesterfield
a) Maddox Creek Culvert Removal
There is an Interlocal Cooperative Agreement with Skagit County on the City Council agenda
tonight that would allow for design and construction of the Maddox Creek culvert removal
and stream enhancement project. This project would remove approximately 210 feet of
culvert (installed in the 1970s) and open up two plus miles of Maddox Creek to salmon near
August 14, 2019, Public Works/Library Committee Minutes
Page 1 of 3
Bonnie Rae Park. The project is grant funded by the Washington State Department of Ecology
in the amount of $450,647; the City’s match is $75,000.
b) Kulshan Pump Station Debris Removal System
The Kulshan Pump Station debris removal system became operational this morning.
Committee was shown a brief video of the rake in action. The system includes a hydraulic rake
that will keep the Kulshan bar screen clean of debris. The contractor is currently fine tuning
the rake controls and should be finished in September.
4. Project Updates – Esco Bell and Darin Christen
a) 2019 Sanitary and Storm Sewer Bid Award
The City opened bids on July 23, 2019, with a low bid of $699,406.77 by Insituform
Technologies. This project includes lining more than 5,000 lineal feet including areas under
Manito (a collapsing pipe between Division and Comanche), Roosevelt (a 3/8” steel pipe
installed in 1956 that goes under the railroad), and some storm sewer on Riverside Drive. Staff
will be asking Council to award the bid at the City Council session tonight.
b) 2018 Curb Ramp Improvements Project Acceptance
Staff is requesting Council accept the 2018 Curb Ramp Improvement project at Council session
tonight. The physical completion of this project was December 2018; however, final
acceptance was delayed by L&I investigation of a subcontractor. Final project contract amount
is $312,596.28.
c) College Way & Riverside Drive Corridor Signal Improvement
All but two or three of the curb ramps have been removed at 12 intersections on the College
Way and Riverside Drive corridors. As this is a federally funded project, all ramps must be
modernized to current ADA standards. During the next few weeks ramps and pedestrian
equipment will be installed. The final step will be to install flashing left turn arrows at most of
the signals. All work is expected to be completed by November 2019. Traffic disruptions are
anticipated to be relatively minor as most of the work will be completed off the roadway.
d) BNSF Agreement for 4th Street N / Riverside Drive BNSF RR Crossing
The City is working with BNSF and its contractor to install safety improvements at the railroad
crossing on Riverside Drive. Work will be coordinated with BNSF; main rail replacements will
begin after the Labor Day holiday and will include a five day road closure during rail
replacement. Traffic will be detoured onto Shop and Alder Lanes, electronic message boards
will be used to inform the public. Access to affected businesses will be provided throughout
the project and all feasible efforts will be made to minimize traffic impacts.
e) College Way Widening Under I-5
More than half of the finished concrete wall work underneath the interstate has been
completed and signal bases and drainage work have been installed. A large storm drain pipe
along Freeway Drive is being fused together this week and installation of the pipe along that
road will occur in September. Although traffic lanes under the interstate may be narrowed
during construction, any actual closures must be done during nighttime hours; the contractor
will utilize reader boards if necessary to keep the public informed.
August 14, 2019, Public Works/Library Committee Minutes
Page 2 of 3
f) 2019 Complete Streets Award
Tonight’s City Council agenda includes an award of $350,000 by the Transportation
Improvement Board to make curb ramp improvements on Laventure and Division Street. This
project includes updating curb ramps to meet current requirements for slope, minimum
widths, and clearances. Any project that includes alterations of any kind to the curb ramps
must include fixing all deficiencies to meet current ADA standards.
5. Public Works Director Comments – Esco Bell / Erin Keator
a) Big Ditch/Maddox Creek Drainage Improvements Investigation Briefing
WSDOT and Drainage District 17 are currently investigating the “Big Ditch/Maddox Creek
Drainage Improvement” project as part of WSDOT’s mandated efforts to fix several culverts
under I-5 to restore fish habitat. The project may provide drainage and environmental
benefits to the Maddox Creek Drainage basin on the south side of Mount Vernon. As the
majority of this project is outside of Mount Vernon city limits, the City does not have an active
role in this project. Project cost is estimated at $10 million. A public outreach meeting is
expected to occur in upcoming weeks.
b) Outstanding Performance Award for Wastewater Treatment Plant
The City has received another Outstanding Performance Award for its Wastewater Treatment
Plant. The award recognizes perfect permit compliance for the year of 2018. This is now the
City’s 9th consecutive year receiving this award.
6. Traffic Safety Committee (TSC) Update – Esco Bell
The last Traffic Safety Committee was on Tuesday, June 18, 2019.
The next Traffic Safety Committee is on Tuesday, August 20, 2019.
7. Miscellaneous / For the Good of the Order
Councilmember Brocksmith asked for additional details on what to expect on the College Way
Widening under I-5 project. The project must keep daylight traffic flowing; if anything requires
working in the travel lane, that work will be conducted during nighttime only. The biggest
disruption will entail the pipeline work on Freeway Drive; the contractor will work to maintain
minimal disruption to traffic. The sidewalk work under I-5 will require narrowing the lanes to 10
feet; however, the travel lanes will remain open to traffic. When the project is complete, the new
outside lanes will dip down slightly to accommodate clearance standards for height requirements.
Esco reminded Committee that the City’s website is a great tool for the community to be able to
look at project updates, including a live camera for the College Way widening under I-5 project.
Meeting adjourned at 6:43 pm
Sherri Pritchard
Sherri Pritchard
Public Works Department
August 14, 2019, Public Works/Library Committee Minutes
Page 3 of 3
Agenda
CITY COUNCIL APPOINTMENTS COMMITTEE MEETING AGENDA
Wednesday, January 11, 2023 ❖ 8:00 p.m.
Oak Room, City Hall, 300 Park Avenue, Falls Church, VA 22046
Current vacancies & reappointments for terms ending in January.
Board and Commission chairs invited to attend interviews. √
Candidate Schedule:
8:00 p.m. a) New Applicant: Valerie Cloutier – Aurora House Citizens’ Advisory Committee - (10/01/19) –
09/30/23 (Unexpired Term)
8:15 p.m. b) New Applicant: Sharon Friedlander – Planning Commission - 01/01/23 – 12/31/26 (Unexpired
Term) *
*Planning Commission: 3 applicants, 1 vacancy
Previously interviewed:
11/9/22: Gene Gresko – Planning Commission - 01/01/23 – 12/31/26*
12/14/22: Peter Kien – Planning Commission - 01/01/23 – 12/31/26*
The City of Falls Church is committed to the letter and spirit of the Americans with Disabilities Act. To request
a reasonable accommodation for any type of disability, call 703-248-5014, TTY 711.
Get email alerts for Falls Church
A daily email when new agendas and minutes are posted.