MPO Policy Committee
Regular MeetingFarmington, NM · March 20, 2014
Minutes
MINUTES
FARMINGTON METROPOLITAN PLANNING ORGANIZATION
POLICY COMMITTEE MEETING
January 16, 2014
Policy Members Present: Sherri Sipe, City of Aztec
Dan Darnell, City of Farmington
Gayla McCulloch, City of Farmington
Scott Eckstein, San Juan County
Technical Members Absent: Pat Lucero, City of Bloomfield
Staff Present: Mary Holton, MPO Officer
Joe Delmagori, MPO Planner
June Markle, MPO Administrative Aide
Staff Absent: Duane Wakan, Associate MPO Planner
Also Present: David Quintana, NMDOT District 5
Karen Georgina, San Juan Center for
Independence
Larry Hathaway, San Juan County
1. CALL TO ORDER
Councilor Darnell called the meeting to order at 1:30 p.m.
2. APPROVE THE MINUTES FROM THE NOVEMBER 14, 2013 POLICY COMMITTEE
MEETING
Commissioner Eckstein moved to approve the minutes from the November 14, 2013
Policy Committee meeting. Councilor McCulloch seconded the motion. The motion was
passed unanimously.
3. CONSIDER APPROVAL OF AMENDMENT #4 TO THE FFY2014-2019
TRANSPORTATION IMPROVEMENT PROGRAM (TIP)
Subject: FFY2014-2019 TIP Amendment #4
Prepared by: Joe Delmagori, MPO Planner
Date: January 7, 2014
BACKGROUND
On December 1, 2013 the Farmington MPO advertised Amendment #4 to the
FFY2014-2019 Transportation Improvement Program (TIP).
The amendment adds one project to the TIP as described in the attached notice.
A public hearing on Amendment #4 was held on December 19, 2013 during the
Technical Committee meeting.
The Technical Committee recommended approval of Amendment #4 to the
FFY2014-2019 TIP.
CURRENT WORK
• For the East Arterial project in the City of Aztec, Legion Road will be upgraded to
city standards and will become the terminus for the next phase of the East
Arterial project (Phase 1B).
• The city will upgrade Legion Rd from its current terminus to the end of Phase 1B
of the East Arterial.
• This project creates a logical terminus for Phase 1B of the East Arterial.
RECOMMENDATION
It is recommended that the Policy Committee approve Amendment #4 to the
FFY2014-2019 TIP and the MPO Self-Certification for Amendment #4 to the
FFY2014-2019 TIP.
DISCUSSION: Mr. Delmagori explained that funding for Phase 1B of the East Arterial
project in the City of Aztec was declined when it was determined that there was no
logical terminus for the project. The City of Aztec has since identified Legion Road as a
logical terminus for Phase 1B and District 5 plans to reprogram the project in the near
term. One step toward achieving this is to get the Legion Road project into the
Transportation Improvement Program (TIP) as the logical termini for the project.
Mr. Delmagori referred to Page 2 of the Agenda which showed the Public Notice for the
Amendment and gave the project details. He noted that Legion Road does already exist
for a short distance from US 550. The City of Aztec will upgrade the road to city
standards from its current end and Phase 1B of the East Arterial project will then be able
to connect to this portion of Legion Road.
Mr. Delmagori also stated that the MPO Self- Certification for Amendment #4 could be
found on Page 3 of the Agenda.
ACTION: Councilor McCulloch moved to approve Amendment #4 to the FFY2014-2019
TIP and the MPO Self-Certification for Amendment #4 to the FFY2014-2019 TIP.
Commissioner Sipe seconded the motion. The motion was approved unanimously.
4. CONSIDER APPROVAL OF THE FFY2014-2015 UPWP BUDGET AMENDMENT
BASED ON FY2013 CARRYOVER AND NEW WORK AUTHORIZATION FUNDING
AMOUNTS
Subject: FFY2014-2015 UPWP Budget Amendment
Prepared by: Joe Delmagori, MPO Planner
Date: January 7, 2014
BACKGROUND or PREVIOUS WORK
The MPO prepared its FFY2014-2015 Budget based on initial funding estimates
from NMDOT for FHWA PL and FTA 5303.
Work Authorizations now provide official amounts for PL and 5303 funding.
The Technical Committee recommended approval of the FFY2014-2015 UPWP
Budget Amendment on December 19.
CURRENT WORK
The MPO is receiving a base amount in federal PL funding as part of the
transition to the federal fiscal year.
The MPO received approval to carryover federal PL funds from FY2013 to
FFY2014.
The MPO is receiving federal FTA 5303 funding that will cover transit activities
from October 1, 2013 to September 30, 2014.
RECOMMENDATION
It is recommended that the Policy Committee approve the amendment to the
FFY2014-2015 UPWP Budget based on FY2013 carryover and new Work
Authorization funding amounts.
DISCUSSION: Mr. Delmagori reported that the annual work program is initially
developed in June using estimated amounts for both the PL and FTA 5303 funding
sources. Once the final work authorizations are received several months later, the
budget can be amended to reflect final amounts.
Mr. Delmagori referred to Page 5 of the Agenda which provided a summary of the
current MPO budget status and showed what the final budget would be following
approval of the budget amendment. Mr. Delmagori noted that the FHWA PL estimate
from June 2013 was the actual authorized amount received in July 2013. The FTA 5303
estimate from June 2013 was significantly lower at $36,000 than the authorized amount
of $51,175.87.
Farmington MPO FFY2014 Budget – October 1, 2013 to September 30, 2014
FFY2013 FFY2014
FY2014 Est. Authorized FFY2014 FY2013 Authorized Amt FFY2014 Final
Budget (June Amts (Jul 2013) Authorized Carryover (Oct (Dec 2013) Budget (Dec
Fund Source 2013) P513130 Amt (Jul 2013) 2013) P500020 P514120 2013)
FHWA PL - Federal Share $ 196,487.00 $ 196,487.00 $ 71,863.82 $ 170,013.00 $ 438,363.82
FHWA PL Required Match $ 33,483.74 $ 33,483.74 $ 12,246.46 $ 28,972.25 $ 74,702.45
FHWA PL Total $ 229,970.74 $ 229,970.74 $ 84,110.28 $ 198,985.25 $ 513,066.27
FHWA PL Traffic Counts - Federal
FHWA PL Required Match
FHWA PL Traffic Counts Total
FTA 5303 - Federal Share $ 36,000.00 $ 51,175.87 $ 51,175.87
FTA 5303 Required Match $ 9,000.00 $ 12,793.97 $ 12,793.97
FTA 5303 Total $ 45,000.00 $ 63,969.84 $ 63,969.84
Federal Share of MPO Budget $ 232,487.00 $ 489,539.69
Local Required Match $ 42,483.74 $ 87,496.42
Additional Local Funding Total $ 51,827.26 $ 0.00
MPO Grand Budget $ 326,798.00 $ 577,036.11
Maximum Total Local Contribution
(Required Match & Additional Local) $ 94,311.00 $ 87,496.42
Maximum Aztec Share (10%) $ 9,431.10 $ 8,749.64
Maximum Bloomfield Share (10%) $ 9,431.10 $ 8,749.64
Maximum Farmington Share (60%) $ 56,586.60 $ 52,497.85
Maximum SJ County Share (20%) $ 18,862.20 $ 17,499.28
Increase in federal PL $ 241,876.82
Increase in federal 5303 $ 15,175.87
Overall federal Increase $ 257,052.69
Aztec Contribution Reduction $ 681.46
Bloomfield Contribution Reduction $ 681.46
Farmington Contribution Reduction $ 4,088.75
SJ County Contribution Reduction $ 1,362.92
Overall Local Reduction $ 6,814.58
With the transition to the federal fiscal year by the MPO, Mr. Delmagori commented that
work authorizations were received for both 2013 and 2014 along with approval for
$71,863.82 in carryover money. The federal share of the FFY2014 final budget is
$438,363.82 which is the largest budget the MPO has ever had. Mr. Delmagori stated
that added to this amount was the $51,175.87 in FTA5303 dollars, which raised the
federal share of the MPO budget to $489,539.69. The corresponding local match is
$87,496.42 and each of the entities has a reduction in their contribution amount due to
the higher level of federal funding.
Mr. Delmagori stated that the action being sought was to approve the amendment to the
budget from the estimates shown in June 2013 to the final budget amounts shown for
December 2013.
ACTION: Commissioner Eckstein moved to approve the amendment to the FFY2014-
2015 UPWP Budget based on FY2013 carryover and new Work Authorization funding
amounts. Commissioner Sipe seconded the motion. The motion was approved
unanimously.
5. CONSIDER APPROVAL OF THE JOINT POWERS AGREEMENT (JPA)
AMENDMENT, REFLECTING MAP-21 PROVISIONS AND A CONFLICT
RESOLUTION PROCESS
Subject: Joint Powers Agreement Amendment
Prepared by: Joe Delmagori, MPO Planner
Date: January 8, 2014
BACKGROUND
The FHWA MPO Review indicated that the MPO needs to amend the current
Joint Powers Agreement (JPA) to meet new provisions of MAP-21 and to include
a conflict resolution process to address disagreements.
The proposed MAP-21 provisions to be included in the JPA and the development
of the conflict resolution process for the JPA have been reviewed by the
Technical and Policy Committees.
The Technical Committee recommended approval of the Joint Powers
Agreement Amendment on December 19.
CURRENT WORK
MAP-21 provisions are included in Section 4 referencing performance measures
for the MTP, TIP, and other planning documents.
Section 7 is expanded to address conditions that would indicate when the JPA
needs to be updated.
Staff developed a conflict resolution process based on the FHWA-NMDOT
oversight agreement.
The conflict resolution process includes working with the Technical and Policy
Committees on agreement.
If an issue is not resolved at that point, local entity councils and commissions will
work to reach agreement.
Staff provided the revisions to FHWA for review and they were accepted on
December 5.
RECOMMENDATION
It is recommended that the Policy Committee approve the JPA Amendment with
the MAP-21 provisions and the new conflict resolution process.
DISCUSSION: Mr. Delmagori stated that the proposed revisions have been reviewed by
both the Policy and Technical Committees over the past several months. The
recommended revisions came out of the FHWA MPO Review in September 2012. Staff
incorporated general language with regard to MAP-21 and specifically referenced the
performance targets and measures that are part of that bill and will be a recurring theme
in many MPO planning documents in the future. Mr. Delmagori said that the Review also
asked for a conflict resolution process to be identified by the MPO.
Mr. Delmagori reviewed the proposed revisions to the JPA:
Section Four
Added to Section Four are the National Planning Goals from MAP-21.
Where the JPA referenced the Long Range Plan and the TIP, additional language was
added regarding the incorporation of performance based measures and various
approaches to those documents.
As a way to reference other planning documents, items #9 and #10 were added:
- Coordinate performance targets with NMDOT to ensure consistency;
- Integrate performance-based processes into other transportation plans.
The language in the JPA is kept general since this is an all-encompassing document.
More detailed and specific language will be added to the individual documents.
Section Seven
Additional language was added to this Section to expand on the situations where the
JPA might need to be amended.
Section Ten
This Section was added to address the conflict resolution process. It explains how the
process would begin with the Technical Committee and if the disagreement was not
resolved, it would then be brought to the attention of the Policy Committee. If agreement
could still not be reached, the issue would escalate to the local councils and
commissions.
Mr. Delmagori noted that this process reflects the current process used by FHWA and
NMDOT in resolving their issues.
Mr. Delmagori explained the addition of the use of mediation and facilitation at any level
to help expedite resolution and that these would be held within the MPO planning area.
Councilor Darnell asked if there had been a conflict resolution process in the JPA prior to
now. Mr. Delmagori said that the current JPA had nothing specific to address conflict
resolution.
ACTION: Commissioner Sipe moved to approve the JPA Amendment with the MAP-21
provisions and the new conflict resolution process. Councilor McCulloch seconded the
motion. The motion was approved unanimously.
6. RECEIVE A REPORT ON THE 2040 METROPOLITAN TRANSPORTATION PLAN
Subject: 2040 Metropolitan Transportation Plan
Prepared by: Joe Delmagori, MPO Planner
Date: January 8, 2014
BACKGROUND OR PREVIOUS WORK
The Metropolitan Transportation Plan (MTP) is the long range planning document
that addresses transportation needs for the next twenty-five years.
The 2035 MTP was adopted in 2010.
Development of the 2040 MTP began in November 2013 and is expected to be
adopted in April 2015.
Overview presentations have been given to the Technical and Policy
Committees.
CURRENT WORK
Overview presentations will be given to various groups in the coming month.
Staff is organizing a stakeholder workshop and public meetings in early
February.
These meetings will seek to gather ideas on transportation projects that can then
be analyzed later in the MTP process.
The current MTP Vision, Goals, and Objectives will be discussed and reviewed.
RECOMMENDATION
It is recommended that the Policy Committee receive a report on the 2040
Metropolitan Transportation Plan.
DISCUSSION: Mr. Delmagori reported that the Metropolitan Transportation Plan (MTP)
is the long range planning document for the MPO is up for renewal and Staff is targeting
April 2015 for final adoption of the plan.
Mr. Delmagori said that an update of the MTP process had been provided at the Policy
Committee’s November meeting. Staff has now begun to branch out to other stakeholder
groups and to the local councils and commissions to provide them with an overview of
the MTP. Mr. Delmagori said that, to date, Staff has spoken with the Farmington
Chamber of Commerce Redcoats and San Juan Rotary. Presentations are scheduled
with the Farmington Chamber’s Young Professionals group and all four local
governments. Additional stakeholder groups have been identified and presentations with
these groups will be scheduled over the next month or two to explain the MTP and how
they can be involved in the process.
Mr. Delmagori also reported on the MTP Stakeholder Workshop scheduled for February
5 from 10:00 am to 12:00 pm at the MPO Office. Mr. Delmagori stated that Policy
Committee members were invited to attend the workshop and the final agenda would be
provided to them when completed. Mr. Delmagori reported that the Technical Committee
members requested the workshop to get initial feedback and input from the public that
they could then react to. The workshop will provide an opportunity to learn what the
community would like to see in terms of transportation for this area, as well as discuss
with them what is already identified in the current MTP. As the MTP process progresses,
additional workshops may be planned to provide for additional public input.
Mr. Delmagori referred to Pages 8 and 9 of the Agenda which showed the vision and
mission statements, as well as the goals and objectives that were identified for the
current 2035 MTP.
Councilor Darnell asked if the e-mail the Policy Committee members received about a
workshop on February 5 was the same workshop Mr. Delmagori had referred to. Mr.
Delmagori said this was the same workshop. Councilor Darnell asked if the workshop
would be open to the public. Mr. Delmagori said it would be, but that specific invitations
had already been sent to various stakeholder groups.
Councilor Darnell also asked if individuals from the groups being presented to were
being invited to the workshop to give input or were the presentations simply to inform
them about the MTP process. Mr. Delmagori said the presentations begin as a way to
inform the public about the MTP but, following the presentations, many participants do
ask how they can become involved with the process. Ms. Holton said the MPO is
stressing the inclusion of all interested individuals and that the workshop would be
advertised in the newspaper.
ACTION: The report was received.
7. RECEIVE A REPORT FROM NMDOT
Mr. David Quintana reported that District 5 is working with Staff to outline the workshop
to discuss community concerns. He said this would be an all day workshop on February
20 with representatives from the general office also being invited. They will provide a
breakdown of local government procedures and the expected increased oversight by
District 5 on local projects.
District 5 is in the process of selecting a consultant for the final design of a safety project
on NM 173 from mile marker 2.5 to 3.0 to address vertical concerns and drop-offs. Mr.
Quintana said it is hoped to identify the consultant in the next couple of months and
begin a construction project in FY2016.
Mr. Quintana said that once the Legion Road project is completed by the City of Aztec,
there will then be a logical terminus for Phase 1B of the East Arterial project. Mr.
Quintana said District 5 then plans to reprogram the project in time for the January STIP
preview and for the anticipated April amendment approval process. The funding would
then be available in FY2015 and would coincide with the design package the City of
Aztec expects to have ready in July or August. Mr. Quintana said District 5 wants to
ensure the Legion Road project is underway before they reprogram the project.
Mr. Delmagori asked if District 5 had a dollar amount for Phase 1B. Mr. Quintana said
there is enough money in FY2015 to cover the estimated $3,500,000 cost of the project.
He stated that the remainder of the corridor would be phased out in the STIP over the
next five to six years.
The intersection project on US 64 is almost completed. Mr. Quintana reported it should
be completed in four to five weeks pending the completion of punch list items.
Mr. Quintana reported that the next phase of the US 64 project from mile marker 60 to
62 was awarded to Mountain States Construction. He noted that they are mobilizing and
that construction on this phase should begin once the weather warms up and that it
should be completed by the end of the construction season. Commissioner Eckstein
commented that Mountain States has already begun some preliminary work along the
roadway and already seem to be moving quicker than Sterling Brothers. Mr. Quintana
added that Mountain States is better equipped for the project and better steady progress
on the next phase is expected.
The phase of US 64 from mile marker 58 to 60 is currently under design. Mr. Quintana
reported that District 5 will be working on acquiring rights-of-way during this calendar
year. This project is programmed for construction over FY2016 and FY2017. He
anticipates this project beginning in early FY2017.
Mr. Quintana reported that $25,000,000 in state funding has been requested from the
legislature to assist with the US 64 project. If approved, the US 64 project from mile
marker 58 to 60 could be accelerated.
Councilor Darnell asked about the safety study for the intersection of NM 371 and N36.
Mr. Quintana said there is a phasing study being conducted on NM 371 all the way south
to I-40. Councilor Darnell asked if this was in conjunction with the emphasis on getting
rail to the Farmington area. Mr. Quintana said there was no rail connected to this study
although he thought an RFP was going to be written to study the corridor for freight rail.
Mr. Quintana said that for the intersection of NM 371 and N36, District 5 is completing a
signal warrant analysis this month. A temporary warning flasher will be installed now and
then District 5 will begin developing a signalized project. Mr. Quintana thought a project
would be programmed in the next year to get the intersection signalized. He commented
that the traffic counts prior to the casino opening warranted a signal. Mr. Miguel
Gabaldon has met with Representative Sharon Clahchischilliage and informed her that
the signalized project for this intersection will be fast-tracked.
Mr. Brian Degani could not attend the Policy Committee meeting. Mr. Delmagori said
that at the Technical Committee meeting in December, Mr. Degani had reported that the
state is working on their long-range plan update process which involves all the MPOs
and RTPOs. Additionally they are working on the freight rail plan and the functional
classification updates.
8. RECEIVE A REPORT ON COMPLETE STREETS
Subject: Complete Streets
Prepared by: Joe Delmagori, MPO Planner
Date: January 7, 2014
BACKGROUND or PREVIOUS WORK
Complete Streets is a means of designing a roadway so that it accommodates all
modes of travel, such as walking, biking, and transit.
On August 7, the Policy Committee approved a vision statement, values, and
goals for Complete Streets which create the framework for the program.
Staff has been working with the Advisory Group on development of land use
context areas and road types overlays.
The Advisory Group held its latest meeting on November 20.
CURRENT WORK
The Advisory Group completed exercises in which they identified titles and
descriptions for land use context areas and road types for the MPO Complete
Streets program.
Land use context areas are areas that comprise of a unique combination of
building types, densities, and development form.
Road types better represent how a street functions within a neighborhood.
These overlays better represent the built environment and relate to the Complete
Streets elements that would be expected to be found in that area.
Land use context areas and road types will be matched for creating Complete
Streets design guidelines.
RECOMMENDATION
It is recommended that the Policy Committee receive a report on Complete
Streets.
DISCUSSION: Mr. Delmagori reported that just prior to the holidays the Complete
Streets Advisory Group wrapped up a final draft of the land use context areas and road
types. Mr. Delmagori reiterated that these are overlays to the traditional land use
categories and road types that better represent the built environment as well as how the
road interacts with the adjacent development.
Mr. Delmagori referred to Pages 11-13 which provided the final draft titles and
descriptions for the land use context areas and road types developed by the Advisory
Group. Preliminary approval of these titles and descriptions is expected by the Advisory
Group at their January 22 meeting. The design guidelines will be developed using these
context areas and road types overlays.
Mr. Delmagori showed some maps developed by Staff that illustrated the interaction of
the context areas and road types. These maps are only the first iteration of the
information and the Advisory Group will review and comment on the information at their
January meeting. The maps have only been completed for the Farmington area but will
be expanded to include all areas of the MPO. The maps will help to verify that the titles
for the context areas will best represent the area. The same mapping process was used
to illustrate the road types that the Advisory Group developed. Mr. Delmagori gave 30th
Street as an example saying it is categorized as a minor arterial but it moves back and
forth into residential and commercial. The mapping and coloring of the road types will
show how 30th Street changes based on the land use context area. This information will
help to provide a better understanding of how the built environment interacts with the
road types.
Councilor McCulloch asked when Complete Streets might be ready to be taken to the
entities for adoption. Mr. Delmagori said this was probably several months out as the
Advisory Group will next begin looking at the design guidelines. Once the design
guidelines are developed, Staff should have a better understanding of the timeframe for
bringing Complete Streets to the entities.
Ms. Holton stated that the MPO has invited Mr. Dan Burden of the WALC Institute to
return to the area on May 11, 12 and 13. During his visit there will be a public workshop
as well as a technical workshop for the Advisory Group. He will also present to each of
the local entity’s councils and commissions.
Councilor McCulloch asked about incorporating some Complete Streets concepts into
the City of Farmington’s Foothills project and design. Mr. Delmagori said that at a recent
public meeting to discuss the plans, the project consultant provided some cross-sections
of potential options that he believed were in line with Complete Streets guidelines.
Councilor McCulloch asked if MPO participation was being sought and would they be
involved in the process going forward. Mr. Delmagori said the City’s Public Works
Department has kept the MPO informed of the process. Ms. Holton added that in this
design phase, the lead is with Public Works, but they will continue to keep the MPO in
the loop.
Councilor Darnell stated that the Farmington City Council is revisiting the East Main
Street corridor and he asked if Complete Streets concepts could be incorporated there.
He commented that the focus of many individuals in the community is to keep traffic
moving and to minimize wait times along this corridor. The opposite argument is that the
community wants a vibrant East Main Street to encourage economic development in the
area. Councilor Darnell asked if this roadway had been considered for Complete Streets
designs and ideas.
Ms. Holton thought the concepts in Complete Streets will involve a cultural change and a
move from the past focus of simply moving vehicles. She reminded everyone that
Complete Streets focuses on accommodating all users, not just vehicles. She said that
there are many facets to Complete Streets which include making the streets safer for
pedestrians and encouraging walking between businesses. Ms. Holton said these
changes will require people to think about getting out of their vehicles and starting to
walk. The roads need to be made safe enough for those who do choose to walk while
still moving traffic along the corridor.
Councilor Darnell noted that he has been working with several disabled individuals who
need to cross East Main Street on a regular basis. Crossing Main Street for these
individuals is currently very difficult as there is no staging area in the middle of the road
for them to rest. Ms. Holton said that one aspect of Complete Streets is to look at safety
medians that would provide a barrier for a pedestrian to cross half way across the street
and then be able to wait there for the light to change. Councilor Darnell said these types
of changes need to be addressed not only by policy individuals, but also by the technical
individuals.
Councilor McCulloch commented on the lack on Complete Streets concepts considered
for the US 64 project. She was disappointed that with the millions of dollars spent on the
project, no Complete Streets ideas were incorporated. Mr. Quintana commented that
NMDOT tried to incorporate as many multi-modal features as possible for a regional
connector. The new roadway does include sidewalks and medians to provide a safe
harbor for pedestrians. He said this type of roadway, however, functioned differently and
did not lend itself to pedestrian walkability that might be seen in a downtown or main
street setting.
Councilor McCulloch said that the new stretch of US 64 in Bloomfield is so wide, so fast,
and offers no aesthetics. She added that she does not believe the roadway has helped
the Bloomfield community. She thought that the cultural change of incorporating
complete streets designs also needed to happen within NMDOT and that, perhaps, it
should actually begin there. Councilor McCulloch emphasized that these cultural
changes needed to happen at the state level. She commented on the section of East
Main near Villa View Drive and how she wanted that good visual provided by Complete
Streets designs to be what people saw when they entered the city. She added that she
was encouraged that Complete Streets ideas were beginning to be discussed in a
setting that included NMDOT.
Councilor McCulloch asked how best to add input into the roadway decision making
process. Mr. Quintana said that the entities were strongly encouraged to participate in
the planning processes. He noted that when planning began for the US 64 project in
2000, the purpose was determined to be regional mobility and the need to speed up
traffic. Ms. Holton added that at a recent MPO Quarterly meeting, there was discussion
with NMDOT planners on when to provide local input on project design. Their
recommendation was to include complete streets designs and ideas in their TIP.
Commissioner Eckstein stated that after numerous discussions with NMDOT, there will
be some landscaping incorporated into the medians along US 64 in Bloomfield.
Commissioner Sipe agreed that the cultural changes and focus on complete streets
needed to begin at the state level and then work down. She commented on how difficult
it was to merge a vehicle into traffic along the new section of US 64 because of the
speed of the road section and the multiple lanes.
Mr. Hathaway commented on the plan for Dan Burden to visit with each of the entity’s
councils and commissions in May. He noted that the San Juan County Commission
meeting did not fall on the dates Mr. Burden was to be in town. Mr. Delmagori said he
would look at the schedule again to see what type of rearrangement might be
accomplished.
ACTION: The report was received.
9. RECEIVE A REPORT ON THE STATEWIDE FUNCTIONAL CLASSIFICATION
UPDATE
Subject: State Functional Classification Update
Prepared by: Joe Delmagori, MPO Planner
Date: January 8, 2014
BACKGROUND OR PREVIOUS WORK
The NMDOT Planning Bureau held a meeting in Albuquerque on November 5 to
discuss the statewide update of the functional classification system.
All of the MPOs and RTPOs will assist NMDOT by making recommendations for
classification changes to their regional roads.
NMDOT and its consultant team are targeting February 2015 for completion of
the review and update.
Staff reviewed the list of proposed class changes from 2011 with the Technical
Committee on December 19.
CURRENT WORK
The Functional Classification Guidance Manual explains the new class types and
the criteria for the specific classes.
The MPO identified many classification changes in 2011.
The adopted MPO Major Thoroughfare Plan identifies the recommended current
and proposed classifications for the region.
All of these potential changes will serve as the basis for recommended changes
by the MPO to NMDOT.
RECOMMENDATION
It is recommended that the Policy Committee receive a report on the Statewide
Functional Classification Update and the proposed functional class change list
from 2011.
DISCUSSION: Mr. Delmagori stated that in November, the NMDOT Planning Bureau
had held a meeting to discuss the statewide update of the functional classification
system. The MPOs and RTPOs have been asked to make recommendations for
classification changes to regional roads in their respective areas.
Mr. Delmagori referred to Pages 15-17 of the Agenda which showed a list of proposed
class changes developed in 2011. Unfortunately, due to changeover in the NMDOT
department that reviewed functional classification, these recommended changes were
never addressed. With this new update, the MPO now has the opportunity to submit
these changes for consideration.
Mr. Delmagori said the list of proposed changes from 2011 provided a basis to begin
working from. This existing list will be reviewed to make sure it is still valid or determine if
there are additions or deletions to the list based on changing conditions.
Mr. Delmagori reviewed NMDOT’s functional classification listing that was last published
in 2004 in conjunction with the proposed classification changes submitted by the MPO in
2011. As an example of what the process would involve, Mr. Delmagori referred to Page
15 of the Agenda. Listed there is Twin Peaks/CR 6480 which parallels US 64 heading
west toward Kirtland. NMDOT’s listing showed this as a Principal Arterial and the MPO
recommendation was to classify this down to a Minor Arterial. The reason for this was
that US 64 is the Principal Arterial that moves traffic out of town to the west and there
was no need for a second principal arterial for this rural part of the county.
Mr. Delmagori explained that the road classifications shown on Page 16 are those being
recommended to be reclassified upward. As an example of this, NMDOT shows CR 350
as a Rural Collector. Back in 2004 when the NMDOT list was published, this road was in
the process of being expanded to the current four-lane facility. CR 350 is the main
north/south roadway across Crouch Mesa to move traffic from US 64 to NM 516. The
MPO recommendation was to reclassify this up to a Principal Arterial because of its
function and purpose.
Mr. Delmagori referred to Page 17 of the Agenda which listed roads that were never
identified by NMDOT in 2004. The MPO recommended that they be added to the
NMDOT functional classification database.
Mr. Delmagori said Staff would be reviewing this list with the Technical Committee at
their meeting on January 23 to get their input. Staff will also meet with the individual
Technical Committee members to talk specifically about their entity’s classifications in
more detail. The information gathered will then be presented and recommended
approval sought at the February Technical Committee meeting. Final approval will be
sought by the Policy Committee at their March meeting.
Councilor Darnell asked why it was important for these functional classifications to be
accurate. Mr. Delmagori explained that the classifications represent how the road
functions and its purpose. Roads typically are meant for mobility and to move traffic
through town or from town to town. Mr. Delmagori referred back to CR 350 begin labeled
a rural collector. He noted that this road is not collecting traffic but rather its purpose is to
get traffic between communities. Mr. Quintana added that the functional classifications
identify which roads are eligible for federal funding.
ACTION: The report was received.
10. INFORMATION ITEMS
Subject: Information Items
Prepared by: Joe Delmagori, MPO Planner
Date: January 7, 2014
INFORMATION ITEMS
a. Workshop with NMDOT. The Technical Committee and NMDOT expect to hold
the workshop on regional priorities, communications, and maintenance on
February 26.
b. Regional Traffic Model. The consultant provided an update on January 8 and
indicated that all calibration statistics for the base 2010 model are within
acceptable parameters. The consultant will now calibrate the mid-range (2025)
and long range (2040) model networks.
c. Other
DISCUSSION: Mr. Delmagori reported that the workshop with the Technical Committee
and NMDOT to discuss regional priorities, communications, and maintenance concerns
is now being planned for February 20. Discussion with the Local Government Unit will be
held in the morning and then have discussions with Mr. Quintana and other
representatives from District 5 in the afternoon. The workshop will be advertised as a
public meeting and any interested Policy Committee member would be welcome to
attend. The agenda will be provided as it is finalized.
The update process for the regional traffic model is going well. Staff and the consultant
discussed some of the statistical outputs of the model in terms of calibration. Mr. Shull is
taking the population/employment data provided by Staff, assigning trip rates to the data
and then assigning traffic throughout the network. The consultant then compared the
model output to traffic counts over the past five or six years. If the model output is within
a reasonable threshold of actual counts, it means the calibration is on track. The base
year calibration will now be taken out to the mid-year of 2025 traffic model and then out
to the long-range 2040 traffic model. As long as the calibration for the base year is
accurate, validations for the long range model should also be on track. Mr. Delmagori
said that Staff hoped the traffic model update would be completed and available for use
within the next month or two.
Mr. Delmagori reiterated that Mr. Dan Burden would be in town on May 12 and 13 and
will present workshops and presentations to the local councils and commissions and the
public. Another individual from the WALC Institute will be accompanying Mr. Burden who
is an advocate for the Safe Routes to School (SRTS) program. Mr. Delmagori said some
SRTS activities will also be incorporated into the two days. The plan is to identify a
school in Farmington that may have heard of SRTS but is not currently participating and
see if they can be encouraged to join SRTS.
Councilor Darnell said the last time Mr. Burden was here he had hoped Mr. Burden
could provide some ideas on how to incorporate Complete Streets concepts into the US
64 project. Councilor Darnell asked if on this visit, Mr. Burden could take a local roadway
where there is a struggle on vision (East Main Street) and provide some ideas on what
could be done along that stretch. Councilor Darnell said he comprehends the concepts
of Complete Streets, but then has difficulty understanding the actual application of
Complete Streets.
Mr. Delmagori said this idea is being discussed with WALC Institute representatives as
the agenda is prepared for Mr. Burden’s visit. Staff plans to provide some existing local
examples of the area and ask Mr. Burden for recommendations on how they could be
converted to a complete street design.
Ms. Holton added that Staff has asked the WALC Institute if Mr. Burden can provide
more specifics on how Complete Streets might function for some local examples. Ms.
Holton commented that Mr. Burden typically comes in the day before his presentation to
tour the area and take his own photographs. The technical presentation and discussion
is planned for Monday morning, May 12.
11. BUSINESS FROM THE CHAIRMAN, MEMBERS AND STAFF
There was no business from the Chairman, Members or Staff.
12. BUSINESS FROM THE FLOOR
There was no business from the floor.
13. ADJOURNMENT
Commissioner Eckstein moved to adjourn the meeting. Commissioner Sipe seconded
the motion. Councilor Darnell adjourned the meeting at 2:32 p.m.
__________________________ ________________________________
Dan Darnell, Chair June Markle, MPO Administrative Aide