MPO Policy Committee
Regular MeetingFarmington, NM · January 28, 2016
Agenda
MPO POLICY COMMITTEE
AGENDA
January 28, 2016
1:30 p.m.
Commission Chambers
San Juan County Administrative Building
100 South Oliver Street
Aztec, New Mexico
AGENDA
FARMINGTON METROPOLITAN PLANNING ORGANIZATION
POLICY COMMITTEE MEETING
January 28, 2016 1:30 PM
This meeting will be held in Commission Chambers at San Juan County’s Administrative
Building, 100 South Oliver, Aztec, New Mexico.
ITEM PAGE
1. Call meeting to order
2. Approve the minutes from the November 17, 2015 Policy Committee meeting. 7
3. Consider approval of an amendment to the FFY2015-2016 Unified Work 1
Program (UPWP)
Presented by: Fran Fillerup
4. Consider approval of an amendment to the Public Participation Plan (PPP) 2
Presented by: Duane Wakan
5. Receive a Red Apple Transit Update 3
Presented by: Duane Wakan
6. Reports from NMDOT
a. District 5 (Paul Brasher)
b. Planning Division (Brian Degani)
7. Information Items 6
a. Complete Streets Design Guideline edits
b. Call for Projects
c. Transportation Acronym List
d. MPO/NMDOT Meeting on Performance Measures
e. Transportation Research Board Conference
f. Other
Presented by: Fran Fillerup
8. Business from Chairman, Members, and Staff
9. Business from the Floor
10. Adjournment
ATTENTION PERSONS WITH DISABILITIES: If you are an individual with a disability who is in need of
a reader, amplifier, qualified sign language interpreter, or any other form of auxiliary aid or service to
attend or participate in the hearing or meeting, please contact the MPO Administrative Aide at the
Downtown Center, 100 W Broadway, Farmington, New Mexico or at 505-599-1466 at least one week
prior to the meeting or as soon as possible. Public documents, including the agenda and minutes, can be
provided in various accessible formats. Please contact the MPO Administrative Aide if a summary or
other type of accessible format is needed.
FARMINGTON METROPOLITAN PLANNING ORGANIZATION
Agenda Item #3
Subject: FFY2015-2016 UPWP Amendment
Prepared by: Fran Fillerup, MPO Associate Planner
Date: January 18, 2016
BACKGROUND
The MPO maintains a Unified Planning Work Program (UPWP) document which
sets forth the tasks the MPO will undertake in a fiscal year.
In November, staff presented changes to tasks within the UPWP based on the
2040 MTP and direction from FHWA.
In December, staff presented a summary of carry over requests and new total
budget amounts for the FHWA PL grant and the FT 5303 grant.
According to Appendix A of the document, the total MPO budget amount for FFY
2016 is $369,168.97. The previous MPO budget amount for FFY2016 was
$302,458. Increases are due to new award letters and requested carryover in the
FHWA PL and FTA 5303 grants.
The total estimated expenses are $367,000. Details are also provided in the
second table of Appendix A.
The Technical Committee recommended approval on January 13, 2016.
CURRENT WORK and ATTACHMENTS
MPO staff will present the Draft Amendment to the FFY2015-2016 UPWP, which
will be provided as a separate document.
ACTION
The Draft Amendment to the FFY 2015-2016 UPWP is presented for
consideration and final action by the Policy Committee.
1
FARMINGTON METROPOLITAN PLANNING ORGANIZATION
Agenda Item #4
Subject: Public Participation Plan Amendment
Prepared by: Duane Wakan, MPO Planner
Date: January 18, 2016
BACKGROUND
The current Public Participation Plan (PPP) was adopted on January 19, 2012.
The PPP needs to be reviewed and amended at least every five years.
An overview of amendments are as follows:
o The public comment period is proposed to be 15 days instead of 30 days.
(See page 14). NMDOT has recommended, and the other MPOs
throughout the state have already adopted this change for most
documents including TIP amendments. A new TIP adoption would
continue to have a 30-day comment period.
o At their November 19 meeting, the Policy Committee recommended the
use of social media in MPO outreach efforts and this is reflected in this
amendment. (See pages 8 and 9).
o Representation by NMDOT on the Policy Committee, and by NMDOT and
Red Apple Transit on the Technical Committee, are updated. (See page
2.)
o Newsletters will be published at least three times per year (previously,
four newsletters have been published). (See page 8.)
o Planning factors of MAP-21 have been clarified and are included. (These
may again be updated as similar federal guidance is provided as part of
FAST Act, the new multi-year transportation bill.) (See page 2.)
o A series of demographic maps will be produced to help comply with Title
VI of the Civil Rights and issues of environmental justice. (See page 7.)
o Amendments related to these and other minor changes are shown as
track changes in the Draft Amendment of the PPP.
o In November, the Policy Committee also recommended developing a
Citizens (Civic) Advisory Committee. Staff will present on this topic in
February, and several documents may be amended in the future.
The 45-day public noticing requirement for the Public Participation Plan began on
November 29, 2015.
The Technical Committee recommended approval on January 13, 2016.
CURRENT WORK and ATTACHMENTS
Staff will review the proposed amendments to the PPP. The Draft Amendment to
the Public Participation Plan with proposed track changes will be sent as a
separate attachment.
ACTION ITEM
It is recommended that the Policy Committee consider approval of the proposed
changes to the Public Participation Plan.
2
FARMINGTON METROPOLITAN PLANNING ORGANIZATION
Agenda Item #5
Subject: Red Apple Transit Update
Prepared by: Duane Wakan, MPO Planner
Date: January 21, 2016
BACKGROUND or PREVIOUS WORK
Staff will need to collect transit data on an ongoing basis to comply with MAP-21
performance measurement requirements.
New ridership collection methods have been in place since March 2015 using
tablets which can also collect basic demographic data.
Red Apple Transit recently released a Transit Trip Planner interface which can
be accessed on the Red Apple Transit and MPO websites.
CURRENT WORK
Several route changes were implemented in August 2015 as a way to: (1)
remove non-revenue miles; (2) add service to concentrated areas; (3) get
workers into the COF by 8 am; (4) get students to San Juan College by 8 am;
and, (5) provide a link with Navajo Transit.
2015 Ridership volumes decreased by 4.54 percent compared to 2014 volumes.
Revenue during the same period went up by 9.69 percent*
Farmington routes decreased by -4.08 percent while the regional routes
decreased by -7.55 percent.
ANTICIPATED WORK
The MPO will hire an intern in the early spring to help tabulate and map boarding
and alightment data.
Staff will analyze gaps in the transit system, the walkable catchment areas of
each transit stop as well as demographic mapping for the Title VI Plan.
INFORMATION ITEM
This is an information report requesting feedback from Policy Committee
members.
3
2015 Regional Ridership
800
700
600
500
400
300
200
100
-
Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15
Tiger (Aztec) Bobcat (Bloomfield) Bronco (Kirtland)
2015 Farmington Ridership by Route
4,000
Red Green Purple Yellow Blue
2,000
0
Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15
4
Red Apple Transit - Annual Total Ridership (All Routes)
160,000
150,446
139,467
140,000 132,534 130,422
125,995 131,263
125,299
120,000 111,356
101,955
100,000
80,000 71,985
60,000
48,087
44,554
40,000 32,869
20,000
-
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
Red Apple Transit: Total Ridership Comparison
16,000
14,000
12,000
10,000
2015 Route
8,000
Changes
6,000
4,000
2011 2012 2013 2014 2015
2,000
-
Jan Feb March April May June July Aug Sep Oct Nov Dec
5
FARMINGTON METROPOLITAN PLANNING ORGANIZATION
Agenda Item #7
Subject: Information Items
Prepared by: Fran Fillerup, MPO Associate Planner
Date: January 18, 2016
INFORMATION ITEMS
a. Complete Streets Design Guidelines. The Complete Streets draft edits are
now available for review on the MPO website. The Technical Committee will
review the document and hold a meeting specifically about the Design
Guidelines during February (date to be determined).
b. TIP Call for Projects. Staff sent out a Call for Projects for the FFY 2016-
2021 TIP Amendment cycle.
c. Transportation Acronym List. The MPO has an acronym list on its website
under the heading of MPO Documents. (See www.farmingtonmpo.org.)
Please note other terms which may need to be added.
d. MPO/NMDOT Meeting on Performance Measures. On December 16, 2015,
staff of FHWA, NMDOT and MPOs throughout the state met in Las Cruces to
coordinate performance measurement in the state’s NM Transportation Plan
and MPO MTP’s.
e. Transportation Research Board Conference. Mr. Wakan attended the
Transportation Research Board Annual Conference the week of January 10.
f. Other
6
PC Draft Meeting Minutes
November 19, 2015
MINUTES
FARMINGTON METROPOLITAN PLANNING ORGANIZATION
POLICY COMMITTEE MEETING
November 19, 2015
Policy Members Present: Sherri Sipe, City of Aztec
Nate Duckett, City of Farmington
Linda Rodgers, City of Farmington
Scott Eckstein, San Juan County
David Quintana, NMDOT District (via phone)
Policy Members Absent: Curtis Lynch, City of Bloomfield
Staff Present: Mary Holton, MPO Officer
Duane Wakan, MPO Planner
June Markle, MPO Administrative Aide
Staff Absent: Fran Fillerup, MPO Associate Planner
Others Present: None
1. CALL TO ORDER
Commissioner Sipe called the meeting to order 1:35 p.m.
2. APPROVE THE MINUTES FROM THE SEPTEMBER 24, 2015 POLICY
COMMITTEE MEETING
Councilor Duckett moved to approve the minutes from the September 24, 2015 Policy
Committee meeting. Commissioner Eckstein seconded the motion. The motion was
passed unanimously.
3. HOLD THE ANNUAL ELECTION OF OFFICERS
Subject: Annual Election of Officers
Prepared by: Duane Wakan, MPO Planner
Date: November 12, 2015
BACKGROUND
As outlined in the MPO Committee Bylaws, the Annual Election of Officers was
moved to September to allow newly elected members to become familiar with
Policy Committee proceedings.
Each September the Policy Committee selects the Chair and Vice-Chair from
their membership who will serve until the following annual election.
The Chair presides over the meetings and is responsible for the other duties
7
PC Draft Meeting Minutes
November 19, 2015
outlined in the Committee Bylaws and Operating Procedures document.
The Vice-Chair presides over the meetings in the absence of the Chair.
Commissioner Sipe has been serving as the current Policy Committee Chair;
Councilor Duckett serves as the current Vice Chair.
ELECTION
Elections will take place to select a Policy Committee Chair and Vice-Chair until
September 2016.
RECOMMENDATION
It is recommended that the Policy Committee accept nominations and vote to
elect the Chair and Vice-Chair.
DISCUSSION: Commissioner Eckstein nominated Councilor Duckett as Policy
Committee Chair and he accepted the nomination.
Action: Commissioner Sipe moved to elect Councilor Duckett as Policy Committee
Chair. Councilor Rodgers seconded the motion. The motion was passed unanimously.
Commissioner Sipe offered to serve as Vice Chair.
Action: Councilor Rodgers moved to elect Commissioner Sipe as Policy Committee
Vice Chair. Commissioner Eckstein seconded the motion. The motion was passed
unanimously.
4. CONSIDER APPROVAL OF AMENDMENT #1 TO THE FFY2016-2021
TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND THE SELF-
CERTIFICATION TO AMENDMENT #1
Subject: FFY2016-2021 TIP Amendment #1
Prepared by: Duane Wakan, MPO Planner
Date: November 10, 2015
BACKGROUND
On October 21, 2015 the Farmington MPO advertised Amendment #1 to the
FFY2016-2021 Transportation Improvement Program (TIP).
The amendment involves several projects in the TIP as described in the attached
notice.
A public hearing on Amendment #1 was held on November 5.
The Technical Committee recommended approval on November 5.
AMENDED TIP PROJECTS
US 64 Phase IV - (CN F100110) – At the request of NMDOT, delete this project from
the TIP/STIP as it was able to be constructed using FY 2015 funds.
US 64 Phase V - (CN F100112) – At the request of NMDOT, changes FY 2017 funds
by removing $4,240,116 in NHPP while adding $5,800,000 in State Severance Tax
8
PC Draft Meeting Minutes
November 19, 2015
funds. Also, reduces FY 2018 NHPP funding from $7,059,081 to $6,343,676.
US 64 Phase VI – (CNF100113) – At the request of NMDOT, remove $1,123,797 in
STP Sm Urb funds in 2019 to be replaced with $5,980,800 in NHPP funds in FY 2020.
NM 173 – (CN F100170) – At the request of NMDOT, adds an additional $2,880,000 in
HSIP funds in FY2016 and adjusts the termini from MP 2.0 to MP 4.5.
Vereda del Rio San Juan River Trail Phase II – (CN F100230) – At the request
of the City of Bloomfield, add $189,465 in Local Non-Match funds in FY 2016.
Vereda del Rio San Juan River Trail Phase III – (CN F100231) – At the request
of the City of Bloomfield, add $115,135 in Local Non-Match funds in FY 2016.
Red Apple Transit Bus Route Accessibility – (CN TF00010) – At the request of
the City of Farmington, amend this project’s management from Federal Highway
Administration to Federal Transit Administration.
ACTION ITEM
It is recommended that the Policy Committee approve Amendment #1 to the
FFY2016-2021 TIP and the MPO Self-Certification for Amendment #1 to the
FFY2016-2021 TIP.
DISCUSSION: Mr. Wakan stated that this was the first TIP Amendment to the new
FFY2016-2021 Transportation Improvement Program (TIP). The Amendment has been
advertised for the required 30 days, and at a public hearing held during the Technical
Committee meeting on November 5, no comments were received. Mr. Wakan added that
the Technical Committee had recommended approval of Amendment #1.
Mr. Wakan reviewed the projects included in Amendment #1:
US 64 – Phase IV
NMDOT requested that this project be deleted as it has already been obligated.
Mr. David Quintana said that this project was being deleted because it has already been
obligated and construction begun. The bid for this Phase came in under what had been
programmed and some of the funding for FY 2016 was not needed. The project will not
be affected by this reprogramming of funds.
US 64 – Phase V
NMDOT requested this project be changed by removing $4,240,116 in NHPP and
adding $5,800,000 in State Severance Tax funds. Also, in FY 2018, the NHPP funding
will be reduced from $7,059,081 to $6,343,676.
US 64 – Phase VI
At the request of NMDOT, removes $1,123,797 in STP Small Urban funds in FY 2019.
These funds will be replaced with $5,980,800 in NHPP funds in FY 2020.
Mr. Quintana added that Phases V and VI will incorporate state funding provided by the
Governor for major priority projects. The State Severance Tax funds received are being
incorporated in FY 2017 and the federal funds reduced accordingly. For FY 2020,
NMDOT will add additional NHPP funds. All these changes are to balance the funding
for this project after receipt of the $5,800,000 in State Severance Tax funds.
9
PC Draft Meeting Minutes
November 19, 2015
NM 173
At the request of NMDOT, this project will receive an additional $2,880,000 in HSIP
funds in FY2016 and the termini adjusted from MP 2.0 to MP 4.5. Mr. Wakan noted that
with HSIP funding, there is a state match and no local funds are required.
Vereda del Rio San Juan River Trail – Phases II and III
The City of Bloomfield has requested to add $189,465 in local non-match funds in FY
2016 for Phase II in order to complete this phase of the project.
The City of Bloomfield has also requested to add $115,135 in local non-match funds in
FY 2016 for Phase III in order to complete this phase.
Commissioner Sipe asked where this project was located. Commissioner Eckstein
clarified that this project would extend the river trail from First Street south to the river
and extends it to the east.
Red Apple Transit
The Red Apple Transit was awarded TAP funding to improve their bus stops. At the
request of the City of Farmington, this project’s management will move from Federal
Highway Administration to Federal Transit Administration.
ACTION: Commissioner Eckstein moved to approve Amendment #1 to the FFY2016-
2021 TIP and the MPO Self-Certification for Amendment #1 to the FFY2016-2021 TIP.
Councilor Duckett seconded the motion. The motion was approved unanimously.
5. RECEIVE A REPORT ON AN AMENDMENT TO THE FFY2015-2016 UNIFIED
PLANNING WORK PROGRAM
Subject: FFY2015-2016 UPWP Amendment
Prepared by: Duane Wakan, MPO Planner
Date: November 11, 2015
BACKGROUND
The MPO maintains a Unified Planning Work Program which sets forth the tasks
the MPO will undertake in a fiscal year.
In 2014, the MPOs in the state converted to using UPWP covering two fiscal
years. The current UPWP covers FFY 2015 and 2016.
The recently adopted 2040 MTP identifies tasks which the MPO will undertake
and which need to be reflected in the UPWP.
FHWA has provided direction on other work to be added to the UPWP.
This Amendment was presented to the Technical Committee for discussion on
November 5.
CURRENT WORK and ATTACHMENTS
MPO staff has prepared draft amendments to the UPWP for FFY 2016. The
proposed changes are in a “track changes” document which will be provided
10
PC Draft Meeting Minutes
November 19, 2015
separately.
Dollar amounts under each task have not been adjusted at this time. This item
will be presented again in January, and dollar amounts will be re-allocated as
needed.
INFORMATION and DISCUSSION
The draft changes to the FFY 2016 UPWP are being presented for information
and discussion by the Policy Committee.
DISCUSSION: Mr. Wakan explained that the Unified Planning Work Program (UPWP)
outlines the work of MPO staff for the next fiscal year and notes some of the relevant
financials.
Mr. Wakan reviewed some of the proposed revisions to the UPWP:
- New Committee members: add Councilor Linda Rodgers and Mr. Quintana to the
voting membership of the Policy Committee; add Mr. Quintana and Mr. Andrew
Montoya as voting members to the Technical Committee;
- Update some of the MPO tasks to include a review and inventory of the bicycle
and pedestrian facilities and transit riders to meet the performance measures
required by MAP-21;
- Remove the corridor and alignment study task. The Technical Committee said
that a corridor study of any size would cost upwards of $250,000 and well
beyond the current MPO budget. This will be considered in the future should the
MPO budget be increased;
- Update the Title VI Plan to ensure equity in planning; with demographic mapping
etc.
- Update the Public Participation Plan (PPP) to ensure our community outreach
efforts are thorough as well as innovative;
- Coordinate and share best practices with local governments and other agencies
in the surrounding areas (Shiprock, Rural Transportation Planning Organization
(RTPO in Gallup, 4CEDs) now being required by FHWA;
- TIP development and the implementation of the Project Prioritization
Methodology. This scoring process will be used as new projects are proposed to
be added to the TIP and highlight the funding opportunities;
- Scenario planning – look at land use and transportation together. Use software
the MPO already has available to gather needed data, and developing a steering
committee to help analyze the data;
- Perform and integrate performance measures;
- Safety Plan – other MPOs throughout the state with safety plans receive priority
when HSIP funds become available. HSIP funding is federal with matching state
funds with no local funds required. These funds are used to correct dangerous
corridors and intersections identified through crash data. This is the top priority
for Staff;
- Safe Routes to School (SRTS) – MPO will help other interested entities identify
funding to get a SRTS coordinator position funded;
- Update the financial tables to reflect the 2016 budget.
11
PC Draft Meeting Minutes
November 19, 2015
MPO Staff will seek approval of this UPWP Amendment in January.
ACTION: The report was received.
6. RECEIVE A REPORT ON AN AMENDMENT TO THE PUBLIC PARTICIPATION
PLAN
Subject: Public Participation Plan Amendment
Prepared by: Duane Wakan, MPO Planner
Date: November 10, 2015
BACKGROUND
The current Public Participation Plan (PPP) was adopted on January 19, 2012.
The PPP needs to be reviewed and amended at least every five years.
Staff is proposing changes to the PPP.
Changing the public comment period to 15 days instead of the stated 30 days
(see Page 14 of the current document)
NMDOT has recommended, and the other MPOs throughout the state have
already adopted, a 15-day public comment period for most documents including
TIP amendments.
A new TIP adoption would continue to have a 30-day comment period.
On November 29, 2015 the Farmington MPO will advertised the amendments to
comply with the 45-day public noticing requirements in the Public Participation
Plan.
The draft changes were discussed with the Technical Committee on November
5.
ANTICIPATED WORK
Staff reviewed the PPP for additional needed changes.
Seek recommended approval of the amendment to the PPP at the December 10,
2015 Technical Committee meeting.
Seek approval of the amendment to the PPP at the January 2016 Policy
Committee meeting (tentative date is January 28, 2016).
DISCUSSION ITEM
This item is presented for review only.
DISCUSSION: Mr. Wakan stated that the Public Participation Plan (PPP) was last
approved in 2012 and approval of this amendment will be sought in January. Mr. Wakan
reviewed the proposed changes to the PPP:
• Integrate new technology to noticing requirements (sources and social media);
• Update the list of committee voting members;
• Change references from the previous federal transportation bill (SAFETEA-LU) to
MAP-21 and identify the new goals and objectives;
12
PC Draft Meeting Minutes
November 19, 2015
• Create maps to identify concentrations of seniors, define transit and other needs,
make recommendations on how to meet those needs;
• Consider broader use of social media: MPO follows City of Farmington guidelines so
use of Facebook, Twitter, other is restricted.
Councilor Duckett and Commission Eckstein commented that the Policy Committee had
discussed this previously and recommended broader use of social media. Ms. Holton
commented that the City of Farmington does allow the use of the City’s Facebook
account, and that a Twitter account could be considered.
The Committee discussed the MPO possibly piggy-backing on each entity’s site to
provide an additional level of outreach. Councilor Duckett recommended that MPO set
up their own account and then each city could share pertinent and relevant information
on their own webpages. The Committee agreed that a stronger social media presence
was important. Ms. Holton said that Staff would put together a comprehensive plan for a
social media presence and then present it to the Committee for their approval.
• Proposal to develop a Citizens Advisory Committee (CAC). This group would be
made up of citizens from the region in compliment to the technical staffs from the
cities. The MPO wants to involve any interested persons and those with broader
backgrounds (seniors, schools, public health) to provide their own recommendations
to the Policy Committee. Mr. Wakan reported that some CACs use a hierarchy where
they would first report to a technical body and then to the policy body, while others
report directly to a policy board. The Policy Committee members agreed that a CAC
sounded like a good idea and they recommended having the CAC report directly to
them. Councilor Duckett and Rodgers thought this committee could also provide
information to them as City Councilors.
It was noted that being able to find individuals willing to serve on this type of committee
would be a priority. Mr. Wakan said that many of the Complete Streets Advisory Group
members want to continue being involved with transportation issues even after the
Complete Streets design guidelines are completed. More information on a CAC will be
forthcoming in January.
• MTP – the 2040 MTP was recently update;
• TIP call for projects – project ranking will be determined by the PPM;
• Public comment period on TIP amendments – reduce the required 30-day comment
period to 15 days. This change will allow more flexibility for NMDOT and the entities
when requested amendments to projects especially with last minute changes. The
Farmington MPO is the only MPO state-wide still using the 30-day period.
Mr. Wakan stated that any amendments to the PPP require a 45-day comment period.
This proposed amendment will be advertised beginning November 29 and will be
brought back to both the Technical and Policy Committees in January for final input. Ms.
Holton encouraged the members to provide any input to Staff now so that it can be
incorporated into the amendment. The members reiterated the need for a greater MPO
social media presence primarily on Facebook and to create a Citizens Advisory
Committee.
13
PC Draft Meeting Minutes
November 19, 2015
ACTION: The report was received.
7. REVIEW THE PROPOSED MEETING CALENDAR FOR 2016
Subject: 2016 Annual Meeting Schedule
Prepared by: Duane Wakan, MPO Planner
Date: November 10, 2015
BACKGROUND
Each year the Policy Committee approves a resolution ensuring compliance with
the open meetings act and establishes its meeting schedule for the coming year.
NMDOTs STIP Procedures Manual outlines an annual calendar for TIP
Amendments which may impact the meeting schedule on a quarterly basis.
CURRENT WORK
Staff will present a proposed meeting schedule for discussion with the Policy
Committee
It is suggested that the Policy Committee hold seven regular meetings during
2016.
Meetings are recommended for January, February, April, May, August,
September, and November.
Meeting can continue to be held on the fourth Thursday at 1:30 pm, unless
otherwise indicated, on a rotating basis among the entities.
Formal action to adopt a meeting resolution will be done in November.
ACTION ITEM
It is recommended that the Policy Committee consider approval of the proposed
2016 meeting schedule.
DISCUSSION: Mr. Wakan stated that no changes were made to the current schedule of
meeting on the fourth Thursday of the month at 1:30 p.m. on a rotating basis among the
entities (proposed 2016 Meeting Schedule was on Page 12 of the Agenda). Mr. Wakan
noted that the grayed out months shown on the calendar were months when TIP
amendments would be brought to the committee for approval.
ACTION: Commissioner Eckstein moved to approve the 2016 Policy Committee meeting
schedule. Councilor Duckett seconded the motion. The motion was approved
unanimously.
8. REPORTS FROM NMDOT
District 5 Engineer Update – David Quintana
Mr. Quintana informed the group that the EPA was holding a public meeting from 6:30 to
8:00 p.m. tonight at the Courtyard Marriott regarding MS4 permits. All identified urban
clusters from the 2010 Census must become permittees for discharge for storm water
14
PC Draft Meeting Minutes
November 19, 2015
pollution. Any public user that discharges into the San Juan River must permit their
activities (City of Farmington, City of Aztec, San Juan County, NMDOT, and Kirtland).
The permittees will need to coordinate and develop plans for mitigating and maintaining
certain discharge levels for certain pollutants.
US 64 – Phase IV – this project was recently let and is currently underway. There is side
construction taking place on the side of the roadway, but the project will go on winter
suspension soon until February or March of 2016.
US 64 – Phases V and VI – development of these two phases is continuing. Phase V is
at 60% design completion and Phase VI is at about 30% design completion. Mr.
Quintana stated there is quite a bit of right-of-way to be acquired for the next four miles
and this will dictate the schedule and the cost.
NM 173 – NMDOT is adding some funding to this project to ensure it can all be
constructed in the coming season. It is expected to be let in May and based on time
frames for NMDOT to secure and award a contract, a notice to proceed should be out by
early August 2016.
Bridge preventative maintenance – along US 550 south of Bloomfield and also along US
64 just west of the MPO area in the Hogback area.
Bridge replacement on NM 574 in La Plata – NMDOT is currently planning to close NM
574 for about 30 days to complete this bridge replacement. The length of detour will be
significant, but they believe that closing the roadway will be the quickest way to get the
work completed. Mr. Quintana said that public meetings are planned for the spring of
2016. Although the work is outside of the MPO area, it does impact the region.
Intersection of NM371 & N36 – installation of a flashing beacon at this intersection is
expected to start up soon in the next month or two. The project is not weather sensitive
so Mr. Quintana expects that the project will be completely shortly.
NMDOT will be holding public meetings on December 3 to discuss Phases V and VI of
the US 64 project. The notice announcing the meeting is expected to go out next week
and Mr. Quintana will forward that information to Staff.
Planning Division Update – Brian Degani
Mr. Degani was not able to participate in the meeting in person, but provided the
following written Planning Division Update:
NMDOT Asset Management Planning Division will be rolling over MPO FFY15
balances for FFY16. FMPO would have to request a rollover of any remaining
FFY15 funds into FFY16. Consequently, FMPO would have to amend their FFY15-
FFY16 UPWP for these remaining rolled over funds. December 15 is the deadline
for the MPO to submit 1st Quarter Unified Planning Work Program (UPWP)
Amendments, if any, for our compiled Planning Work Program Amendments
sent to FHWA. The 2nd Quarter UPWP Amendment deadline is March 15, 2016.
Farmington MPO will have to have their Annual Listing of Obligated Projects
compiled and posted on the FMPO website by 12/28/15.
15
PC Draft Meeting Minutes
November 19, 2015
Tribal/Local Planning Agencies (T/LPAs)
Per NMDOT Project Oversight Department (POD), important deadlines for T/LPA
projects:
1) March 15 for signed (by entities) agreements to be returned to NMDOT.
Design agreements will be executed and funds obligated. Construction
agreements will be held for execution pending PSE (9-day letter requirements).
2) June 15th is the obligation deadline. In most cases this would be when the 9-
day letter.
Performance Measures and Targets – Anne McLaughlin, Bureau Chief, is
currently working with MPOs, AMPD Director and FHWA to coordinate a half-
day workshop on Performance Measures and Targets on 12/16 from 8:00 am to
noon, after the 12/15 MPO Quarterly which is scheduled in Las Cruces.
Upcoming Meetings/Trainings/Timelines
• The Pedestrian and Bicycle Information Center (PBIC) is offering a webinar
series on pedestrian safety countermeasures. Since NM and Albuquerque are a
focus state and city, respectively, due to our high numbers of per capita
pedestrian fatalities, these strategies are very relevant. Registration is FREE. It’s
a 12 part webinar series, running from Oct. 2015 to Jan. 2016. Info and
registration:
http://www.pedbikeinfo.org/training/webinars_PSAP_countermeasurestrategie
s.cfm
• Recreational Trails Advisory Board (RTAB) meeting Tuesday, November 17,
2015 from 1:00 to 3:00 P.M. at NMDOT, District 3 Offices, 7500 Pan American
Blvd., Albuquerque, NM 87199. Contact Aaron Detter at
aaron.detter@state.nm.us for more information or questions.
• Next Talking Freight Seminar: International Urban Freight Conference
Presentation – Warehouse Locations and Community Impacts (webinar) on
November 18, 2015 from 1:00 – 2:30 ET. Registration:
http://www.ops.fhwa.dot.gov/freight/fpd/talking_freight/index.htm. Eligible for
AICP CM credits.
FTA published the Transit Asset Management Plan NPRM and the PDF has a 60
day comment period (comments are due to FTA by November 30, 2015). Dave
Harris is the lead for NMDOT comments, so please copy him on any comments
your agencies submit. Docket Number: FTA–2014–0020 Website:
http://www.regulations.gov/#!documentDetail;D=FTAFRDOC0001-0595 Due
Date: Nov. 30, 2015
Reminder: FHWA-HQ Office of Freight Management and Operations (HOFM)
MPO Freight Program Assessments are due to Paul Sittig, NMDOT by
November 30, 2015. He sent out an email regarding this on October 13, 2015.
The intent of these reviews is the following:
• For State DOTs/MPOs to define what they are doing relative to freight
transportation.
• To help FHWA, States and local entities identify potential gaps in freight
planning and programs
16
PC Draft Meeting Minutes
November 19, 2015
• To enable FHWA to focus resources to advance freight transportation
Mr. Wakan reviewed some of the items noted in Mr. Degani’s report:
- Staff is working to finalize the FFY2015 balances and NMDOT has agreed to roll
over those unspent dollars to FFY2016. The tentative unspent dollars are $5,855
in PL funds and $13,186.21 in FTA 5303 funds. These numbers, however, have
not been finalized. New FFY2016 budget numbers are also being incorporated
into the UPWP;
Ms. Holton said that the MPO prepares their budget like other City of Farmington
department but is on the federal fiscal year. Once the federal work authorizations
are received, a budget adjustment is prepared for the City of Farmington budget;
- The Annual List of Obligated Projects is a list of projects obligated during the
year. Mr. Wakan will review this list with Mr. Quintana in the next few weeks to
verify the final list. This list will be posted on the MPO website by the end of
December;
- MPO Quarterly will be held in December and the required performance measures
will be discussed with NMDOT and they will provide the details on how and
where to collect the data. Once this has been identified, the 2040 MTP will have
to be updated to reflect the changes.
9. REVIEW THE 2015 FALL WEEKDAY TRAFFIC COUNT LIST
Subject: 2015 Fall Traffic Counts
Prepared by: Duane Wakan, MPO Planner
Date: November 10, 2015
BACKGROUND
The MPO conducts traffic counts at locations throughout the MPO area twice a
year, on a rotating basis such that each location is counted every three years.
Counts are posted to a web-based map with a link from the MPO website.
The MPO collects directional volume counts at most count locations, and speed
and vehicle classification at select locations.
The traffic count list was presented to the Technical Committee on November 5.
The Technical Committee asked that the dates for the counts be rescheduled
with the consultant so that counts were not taken on Veterans’ Day, November
11.
CURRENT WORK
This fall, 44 locations will be counted, 16 of which will count speed and vehicle
classification.
Staff reviewed the locations and verified that there were no conflicts with
construction or maintenance work that might impact the roadways being counted.
17
PC Draft Meeting Minutes
November 19, 2015
INFORMATION ITEM
The 2015 Fall Traffic Count list is presented for information and review only.
DISCUSSION: Mr. Wakan reported that the fall weekday traffic counts were ongoing this
week. There are 44 locations being counted which are spread out throughout the county
(list of locations on Page 14 of the Agenda). The counts are done semi-annually, in the
spring and then again in the fall.
Councilor Rodgers asked how the locations were selected. Mr. Wakan replied that the
locations are on a three-year rotation.
Councilor Duckett asked the cost of the counts. Mr. Wakan said that a ballpark figure
would be $200-$300 per location and the consultant can collect both volumes and
speeds. Although the MPO budget does not allow counting for speed and class at all
locations, there are 16 locations that will be counted for both speed and class during this
fall count. Councilor Rodgers asked why Browning Parkway was not showing up on the
list of locations. Mr. Wakan said that was likely because that location had been
previously counted.
Councilor Duckett asked where the information was posted. Mr. Wakan said the data is
available on the MPO website and although the information is reflected in static maps,
there is a separate link to another website that provides an interface to a Google map
that provides detailed information about any specific count location.
Ms. Holton said that this information is available to commercial developers who request
this information. Since the state is slow in verifying the traffic counts, the MPO has been
providing this information to developers.
Ms. Holton stated that weekend counts had been done a couple of years ago to see how
traffic increased during a weekend which was the perception. The actual counts showed
very little difference in traffic counts when compared to a weekday counts. This might be
partly due to those who live in Farmington do not travel the same patterns on the
weekend or do not get out on the weekends and the weekday work travel patterns are
absent on the weekends. Mr. Wakan explained that the counts at the “escape points” out
of or into the MPO area showed that there was a slight increase in traffic leaving the
MPO area versus that coming into the MPO. When the peak hour traffic was illustrated,
they showed that the patterns changed during the day when compared to a week day.
Ms. Holton stated that the weekend counts may be done again in the next year or two for
comparison purposes.
ACTION: The report was received.
18
PC Draft Meeting Minutes
November 19, 2015
10. INFORMATION ITEMS
Subject: Information Items
Prepared by: Duane Wakan, MPO Planner
Date: November 9, 2015
INFORMATION ITEMS
a. T/LPA Semi-Annual Training – State and Federal Inception to
Completion for a Successful Project. Mr. Fillerup attended this two and
one-half day training in Albuquerque on November 3-5.
b. MPO Quarterly. The MPO Quarterly will be held on December 14 and 15 at
the Mesilla Valley MPO in Las Cruces.
c. Joint MPO & NMDOT Meeting. The next joint Technical Committee and
NMDOT meeting is scheduled for December 10 in Bloomfield.
d. Data Needs for NMDOT Collaboration. Staff is working with NMDOT on
asset management and other data collection efforts and more details on local
participation will be known prior to the MPO Quarterly.
e. Other.
DISCUSSION: Mr. Fillerup attended the Inception to Completion training earlier in
November. Mr. Wakan reported that this training is needed in order for Staff to provide
the project oversight being required of them by NMDOT. Staff must now attend the 30%,
60%, and 90% review meetings as well as PS&E meetings on projects throughout the
MPO.
The MPO Quarterly will be held at the Mesilla Valley MPO in Las Cruces on December
14, 15, and 16.
The next regular Technical Committee is on December 10 in Bloomfield and this is
scheduled to be a joint meeting with NMDOT. Mr. Quintana asked Mr. Wakan to send
out the meeting invitation so people could add it to their calendars.
Performance measures is a requirement now and Staff is looking at what needs to be
measured and what will need to be maintained in the future. This will be looking at asset
management of the local facilities.
Mr. Wakan reported on a public meeting held in Santa Fe on the Phase V of the US 64
project and no notification was given to the MPO of the meeting. Once the project
reaches the 60% design review, any desired design changes, such as buffered or
unbuffered sidewalks and bike lanes, are very difficult to incorporate. Mr. Quintana said
that this roadway will remain rural in nature and, except for the tie-ins at Browning
Parkway, there will be minimal to no sidewalks along the section of US 64 currently
under construction.
19
PC Draft Meeting Minutes
November 19, 2015
Mr. Wakan stated that when issues affect the MPO region, it would be preferable to have
public meetings in San Juan County and not in Santa Fe. This allows for greater local
participation in making design recommendations. Ms. Holton said the MPO would gladly
host a public meeting during the joint meeting on December 10 in Bloomfield. The Policy
Committee was invited to participate and provide their thoughts and comments. The
MPO will notice the possibility of a Policy Committee quorum at this joint meeting.
11. BUSINESS FROM THE CHAIRMAN, MEMBERS AND STAFF
Commissioner Sipe announced that the City of Aztec had broken ground on the next
phase of the East Arterial project. She also wished everyone a happy Thanksgiving.
There was no additional business from the Chairman, Members or Staff.
12. BUSINESS FROM THE FLOOR
There was no business from the floor.
13. ADJOURNMENT
Councilor Duckett moved to adjourn the meeting. Councilor Rodgers seconded the
motion. Commissioner Sipe adjourned the meeting at 2:50 p.m.
___________________________ _____________________________
Commissioner Sipe, Chair June Markle,
MPO Administrative Aide
20
Get email alerts for Farmington