City Council
Regular MeetingFredericksburg, VA · July 10, 2012
Minutes
CITY OF FREDERICKSBURG, VIRGINIA HON. MARY KATHERINE GREENLAW, MAYOR
HON. BRADFORD C. ELLIS, VICE -MAYOR, WARD ONE
CITY COUNCIL HON. KERRY P. DEVINE, AT-LARGE
HON. MATTHEW J. KELLY, AT-LARGE
HON. GEORGE C. SOLLEY, WARD TWO
HON. FREDERIC N. HOWE, III, WARD THREE
Council Chambers, 715 Princess Anne Street HON. BEATRICE R. PAOLUCCI, WARD FOUR
Fredericksburg, Virginia 22401
Council Work Session
July 10, 2012
Tour of Juvenile and Domestic Relations Court
Courthouse Project
The Council of the City of Fredericksburg, Virginia held a work session on Tuesday,
July 10, 2012, beginning at 5:30 p.m. in the Juvenile Domestic Relations Courthouse, 601
Caroline Street and then moved to the Suite at City Hall, 715 Princess Anne Street.
Council Present. Mayor Mary Katherine Greenlaw, Presiding. Vice-Mayor
Bradford C Ellis. Councilors Kerry P. Devine, Frederic N. Howe, III, Matthew J. Kelly,
Beatrice R. Paolucci and George C. Solley.
Also Present. City Manager Beverly R. Cameron, Assistant City Manager Mark
Whitley, City Attorney Kathleen Dooley, Robert Antozzi, Director of Parks, Recreation and
Public Facilities, Sheriff Paul Higgs, Budget Manager Amanda Lickey, Clerk of Council
Tonya B. Lacey.
Others Present. Juvenile and Domestic Relations Court Judge David Peterson,
Construction Manager Bill Downey of Downey and Scott, Allen Hamlin from the Design
Build Team of English Construction.
Juvenile and Domestic Relation Court Tour. Judge Peterson and Sheriff
Paul Higgs led City Council on a short tour of their interim facility. They demonstrated the
metal detector and the x-ray machine and they discussed the many other new features. The
interim facility has four holding cells, a finger printing room and two interview rooms. Judge
Peterson stated that the two interview rooms would work on an interim period, but they would
need at least four. The courtroom itself was more spacious than the old space. The judge’s
bench and the clerk’s desk are much more efficient because they each have more room. There
1
are now three separate entrances to the courtroom one for the judge, one for the public and one
for the inmates. The clerk also added that the office space was small but efficient and she said
she finally had her own office.
Judge Peterson said he is without a conference room which makes it difficult to meet
with attorney’s and truancy officers, but he could deal with it on an interim period. He said
JDR has never had a permanent home this is the fourth interim court space.
Courthouse Project. Mayor Greenlaw reconvened the work session at 6:30 p.m.
in the Suite. Councilors Greenlaw, Ellis, Devine, Howe, Kelly, Paolucci and Solley were in
attendance.
City Manager Cameron stated that there were four court related issues that needed
council action. One decision needed to be decided on by August 1 the other three could be
decided on in early fall. The first of the four decisions are whether the second General District
Court (GDC) Room be finished or left as a warm lit shell. This decision should be made by
August 1 and considered at the August 24 work session. The second decision is on the existing
GDC, should there be a major or minor renovation. This decision can be made at a work
session in early September. The third decision is on the Renwick Building, what is the
preferred reuse of the building. This could be discussed at a work session on October 9.
Finally, the last issue was Council’s desired course of action on downtown parking. Mr.
Cameron said this could be a part of discussions at the planning retreat in October. City
Attorney Dooley agreed with Mr. Cameron that a decision had to be made on whether Council
wanted to leave the second courtroom as a shell or finish the space. She said they were at the
35% review of the design development documents and the comments were due back to First
Choice on or before August 1.
Councilor Ellis suggested that the Council should have regular updates from the Project
Manager (PM) so that they can understand and address issues as they arise. He felt it would be
beneficial to have and to continue as the building is under construction. Councilor Solley
disagreed stating that the PM should brief the CEO or Manager and the Manager would brief
the Council. He stated that he doesn’t want to see Council getting to the point of micro-
managing the project and he said Council does not have the experience to make changes. He
felt all of Council’s decisions could be made now and allow the City staff to manage the
project.
2
Councilor Kelly stated that on other projects such as the trails the Council had the
opportunity to comment on the design as they went through. He said Council had that
opportunity on all projects. He was concerned that the only document he had on the project
were very basic plans and he did not feel comfortable making decisions based on that. He also
stated that he still had questions that were left unanswered from the previous work session on
courts and he would like those answered.
Mayor Greenlaw asked the City Manager and the Project Manager Bill Downey what
they felt would be the appropriate level of reporting out to Council. Mr. Cameron said all the
design work done on the project has expanded to the schematic design that was presented in
the First Choice PPEA proposal that was adopted by Council as a part of the Comprehensive
Agreement. The 35% design development drawings are just an advancement of the work on a
more detailed level to completion. He said this is what will happen throughout the process at
65%, 95% and to final construction documents that will be taken into the field to build the
project. He said the concepts are the same terms that Council has seen and talked about up to
this point. Mr. Cameron stated that he did not understanding the reasoning for wanting to
revisit the fundamental aspects of the project.
Councilor Ellis stated that if Council could not be briefed at the 35%, 65%, and 95%
then they may never know what issues come up and they can’t discuss or talk about the project
intelligently. He feels as the decision makers they should be briefed so that if something cames
up Council could take care of it. Councilor Solley said he feels that those decisions were the
City Manager’s job.
Councilor Howe stated that all the issues needed to be discussed especially the staffing
and operation and management cost. He said these are business decisions that need to be made
before going down this path.
Councilor Devine said if there are questions on the design along the way it is
appropriate to have those discussions but she felt as though personnel issues are the purview of
the City Manager and she did not want to discuss staff issues with design issues.
Councilor Paolucci said she does not want to get into staffing issues either, but the
bases for building the courthouse is to address security needs and if the city is not going to be
able to insure the security needs than it needs to be discussed. She also explained that this was
the opportunity for Council to look at the plans to possibly modify it to save money to put
towards the Renwick building.
3
Mr. Downey added that he has the most qualified person on his staff working with City
staff to determine staffing needs. He will be working on at least a 30 year life cycle analysis.
He will be looking at the Renwick Building, the General District Court, the Executive Plaza
and the new court facility. This analysis will include what the projected operating and
maintenance cost would be. He said they are in the information gathering process and he said
it takes a little while to gather the information. Mr. Downey said that he has worked on 30
courts between Washington, DC, Maryland and Virginia and he said there are courtrooms that
he would consider small, moderate and large and the City’s courtrooms would be considered
moderate and the support areas are not extravagant or large. He said he met weekly with the
design team and he reports issues to the Parks, Recreation and Public Facilities Director
Antozzi and City Manager Cameron. Mr. Downey also agreed to meet with Council as there
are milestones in the project or whenever Council wishes.
Mayor Greenlaw suggested that Council reconvene after the regular session meeting to
review the 35% plans.
Councilor Kelly asked if his questions could be answered on the cost savings before he
is asked to make any decisions. He also had concerns with the project fitting on the property.
He suggested looking at additional modifications such as shortening the ceilings so that the
project would not have to have so many special use permits and special exceptions.
The Mayor re-convened the work session at 9:50 p.m. in the Suite. Councilors
Greenlaw, Ellis, Devine, Howe, Kelly and Paolucci were in attendance.
Bill Downey of Downey & Scott presented the 35% design development plans for the
new courthouse facility in an informal session. Council members discussed the proposed
ceiling height of 14 feet and whether it could be reduced to 12 feet, the proposed building
height, and various office spaces that could be left unfinished as a cost saving measure.
Councilors requested additional information on these items for their consideration on July 24.
Adjournment. There being no further business to come before the Council at this
time, Mayor Greenlaw declared the work session officially adjourned at 10:30 p.m.
Tonya B. Lacey
Tonya B. Lacey
Clerk of Council
City of Fredericksburg
4
Agenda
CITY OF FREDERICKSBURG, VIRGINIA
CITY COUNCIL
City Hall, 715 Princess Anne Street, Second Floor Conference Room
Fredericksburg, Virginia 22401
Tuesday, July 10, 2012
5:30 p.m.
Executive Plaza
601 Caroline Street, Suite 100
• A tour of the Juvenile and Domestic Relations Court Interim Facility and
Council will return to City Hall, 715 Princess Anne Street, Second Floor
Conference Room for follow-up discussion on Courts
HON. MARY KATHERINE GREENLAW, MAYOR
HON. BRADFORD C. ELLIS, VICE-MAYOR
HON. KERRY P. DEVINE, AT-LARGE
HON. BRADFORD C. ELLIS, WARD ONE
HON. GEORGE C. SOLLEY, WARD TWO
HON. FREDERIC N. HOWE, III, WARD THREE
HON. BEATRICE ROSE PAOLUCCI, WARD FOUR
Get email alerts for Fredericksburg
A daily email when new agendas and minutes are posted.