Airport Advisory Committee
Regular MeetingFremont, NE · April 21, 2023
Minutes
AIRPORT ADVISORY COMMITTEE
Meeting Minutes: April 21st, 2023
1. Meeting called to order with Open Meetings Act announcement.
Meeting was called order at 8:17 A.M. Open Meeting Act is posted on the wall of the
Airport Terminal, the Act Poster was pointed out to those in attendance.
2. Roll call.
Board Members Present: Michael McGillick, Robert Steenblock, Jeff Peterson,
Eric Johnson, Dave Monke, and Kirk Diers.
3. Approval of the March 17th, 2023 meeting minutes.
Motion by Jeff Peterson, and seconded by Dave Monke to approve, motion passed by
vote of members: Michael McGillick, Robert Steenblock, Jeff Peterson,
Eric Johnson, Dave Monke, and Kirk Diers.
4. Update on Terminal Warranty Work.
a. Update from Cari Hoffart on final warranty items/repairs being completed.
-Columns will be sealed.
-East sidewalk and north access also need to be looked at.
-Overseeding plan is in place.
5. Update on Runway Rehab Project Plans and Bidding.
a. Runway Rehab
-Pre-construction meeting is required to bid and must be on DOT list to be eligible
for bid.
-Minimal utility re-work, minimal manhole work.
-There was a question on other panel repairs and that will be discussed how to
address further.
-Plans available at the City office for rehab.
-Plans going out to bid in May with pre-bid meeting scheduled for May 10th.
6. Update on Hangar Lease Updating.
a. Update from Justin Zetterman on lease options
-Next big lease will be ground leases. We will be using construction overburden to
raise the east end to prepare for additional hangar construction in the future.
-Meeting Thursday with a small group to finalize a lease draft.
-New lease will go before the Board next month for approval. There is some price
Increase. Discussion point on hangar builds moving forward.
7. Recommendation from the Board in regard to a contract amendment with Olsson for
their design contract.
a. This should be the final amendment with Olsson. They will finish design and
construction management.
-Motion by Eric Johnson and seconded by Kirk Diers to approve. Motion passed by
vote of members Michael McGillick, Robert Steenblock, Jeff Peterson, Eric
Johnson, Kirk Diers, and Dave Monke.
8. Action Items to Discuss – None.
9. Discussion of Maintenance Items.
a. East side walk is crumbling.
b. Yard seeding and landscaping
c. List from the city for hangar requirements for building your own personal hangar.
-Once the new hangar lease is in place this can be further looked into.
d. Thought on resurfacing the east ramp and north/south taxiway during runway
construction.
-Discuss options and work with FAA for grant money or other financing options.
e. Hangars coming in the future.
f. Hangar #18 needs new 12-foot sheeting and a few other repairs.
-Steenblock is contracted already for this repair.
g. Need to do an assessment of all hangars. Specially look at replacing wood
structures in some of the older hangars.
h. The shop hangar is in need of work.
10. Adjournment.
Motion by Michael McGillick and seconded by Jeff Peterson to adjourn, motion passed
by vote of members: Michael McGillick, Robert Steenblock, Jeff Peterson, Eric
Johnson, Kirk Diers, and Dave Monke. Meeting adjourned at 9:14 A.M.
Agenda
AIRPORT ADVISORY COMMITTEE
April 21st, 2023
8:15 A.M.
Fremont Municipal Airport Terminal Building
West 23rd Street, Fremont, Nebraska
1. Meeting called to order with Open Meetings Act announcement
2. Roll call.
3. Approval of the March 17th, 2023 meeting minutes
4. Update on Terminal Warranty work
5. Update on Runway Rehab Project plans and bidding
6. Update on Hangar Lease updating
7. Recommendation from the Board in regards to a contract amendment with Olsson
for their design contract
8. Action Items to Discuss – None
9. Discussion of Maintenance Items
a. East side sidewalk is crumbling
b. Yard seeding and landscape
c. List from the city for hangar requirements for building your own personal
hangar
d. Thought on resurfacing the east ramp and north/south taxiway during
runway construction
e. Hangars coming in the future
10. Adjournment
The agenda was distributed to the Mayor, City Council, and Advisory Committee members on April 20th,
2023. The official current copy is available at City Hall, 400 East Military, Public Works Department Office.
The Advisory Committee reserves the right to go into Executive Session when necessary. A copy of the
Open Meeting Law is posted at the Airport terminal building for review by the public. The Board reserves
the right to adjust the order of items on this agenda.
AMENDMENT NO. 2
to
AGREEMENT FOR CONSULTING SERVICES
CITY OF FREMONT
400 East Military Avenue
Fremont, NE 68025-5141
Re: AMENDMENT TO CONSULTANT AGREEMENT
CITY OF FREMONT
Airport Improvement Program (AIP) Project No. 3-31-0029-016
Olsson Project No. 022-04952
This amendment will revise the Agreement executed on October 11, 2022 and Amendment No.
1 executed on February 28, 2023 by amending Sections 2B item y (5) and 7 as described
below:
Amend Section 2B item y (5) to include the following items:
SECTION 2B: FINAL DESIGN PHASE – AMEND – EXHIBIT A ADDITIONS
y. Prepare and coordinate completion of Exhibit A – Property Map revisions with assistance
from FAA and City of Fremont. Exhibit A update will comply with ARP SOP 3.0. Note:
Timeline associated with the Exhibit A update will be dependent upon the subordinate
agreement, title search, and grant history coordination and may not be completed prior to
Grant Application.
(5) Coordinate with City and local title company to complete a title search and provide a
title certificate. Including: approximately 70 properties research with grantee,
grantor, acquisition type, acquisition/release date, acreage, federal project,
book/page, legal description.
i. Property owned in fee
ii. Airport Clear Zone Easement and all associated properties
iii. Avigation Easements
iv. Released property.
1
SECTION 7: FEES AND CHARGES
The Sponsor shall pay Olsson for the services described in this Agreement as follows:
Section 2B: Final Design Phase – Amend – Exhibit A Additions. Payment for the items
included in Section 2B, Final Design Phase – Amend, shall be the lump sum of $20,000
shown on Exhibit A2- Amend, attached, and made a part hereto. Payment shall be due
monthly based on the percentage of work completed, except that 15% of the payment will
be withheld until the Exhibit A is approved.
If this amendment is satisfactory, please sign in the space provided. Keep one copy and
return two copies to Olsson. This proposed amendment is open for acceptance for thirty days
from the date set forth above, unless changed by us in writing.
OLSSON
By ______________________________ By ______________________________
CITY OF FREMONT
By ______________________________ By ______________________________
Attest Mayor
Date ____________________________
Summary of Engineering Costs
Phase Total Costs
Preliminary Design $43,200.00
Preliminary Design
Contract Geotechnical Design and
$21,767.00
Petrographic Analysis
Preliminary Design - Amend $5,100.00
Final Design $219,700.00
Amendment No. 1 Bidding $16,600.00
Contract Construction
$299,700.00
(includes testing)
Close Out Phase $15,100.00
Amendment No. 2 Final Design - Amend
$20,000.00
Contract (Exhibit A)
$641,167.00
2
EXHIBIT A2
FINAL DESIGN PHASE (2B) - AMEND
Fremont Municipal Airport 3-31-0029-016
1. Direct Salary Costs
Total Direct Salary Total
Title Hours Rate/Hour Costs ($)
Team Leader 4.0 $84.90 $339.60
Sr. Project Engineer 10.0 $64.50 $645.00
Project Engineer 0.0 $47.70 $0.00
Elec. or Mech. Engineer 0.0 $71.10 $0.00
Associate Engineer 0.0 $38.80 $0.00
Assistant Engineer 0.0 $31.25 $0.00
Registered Surveyor 0.0 $53.50 $0.00
Sr. Technician 32.0 $33.00 $1,056.00
Asst. Technician 0.0 $27.50 $0.00
Sr. Clerical 0.0 $30.50 $0.00
Total Direct Salary Costs: $2,040.60
2. Labor and General & Administrative Overhead
Percentage of Direct Salary Costs** 181.95% $3,712.87
3. Fixed Fee: 15% of Items 1 & 2 $863.02
4. Direct Nonsalary Expenses
Travel - Miles @ $0.625 $0.00
Meals - Days @ $59.00 $0.00
Motel - Days @ $96.00 $0.00
Copies, Prints, Shipping $0.00
Title Company Expenses $13,425.00
Total Expenses: $13,425.00
5. Subtotal of Items 1 - 4 $20,041.49
6. Subcontract costs $0.00
7. Lump Sum Amount - Total Items 5 & 6 $20,041.49
Rounded: $20,000.00
** For Item 2, the consultant should submit a statement of auditable overhead expenses, certified by the consultant's auditor, the sponsor's
auditor, the state's auditor, or a Federal government auditor.
STAFF REPORT
TO: Airport Advisory Committee
FROM: Justin Zetterman, P.E., Director of Public Works/City Engineer
DATE: April 21, 2023
SUBJECT: Runway 14/32 Rehabilitation Engineering Services Agreement Amendment
Recommend that City Council approve Resolution 2023-100 to amend
Recommendation: engineering services contract with Olsson to provide updated Exhibit A –
Airport Property Map.
Background:
On October 11, 2022, the City of Fremont entered into an agreement with Olsson for the
completion of a preliminary engineering design and report for the rehabilitation of Runway
14/32 at the Fremont Municipal airport. The report was completed in December of 2022.
On February 28, 2023, the City Council approved a contract amendment with Olsson for the
completion of final design, bid phase and construction phase activities for the rehabilitation of
Runway 14/32. That work is nearing completion with a planned bid date of May 10, 2023 for
the 2024 construction project.
As a part of their final approval of the plans, the Federal Aviation Administration (FAA) is
requiring that an updated Exhibit A be provided prior to the issuance of the grant. To that end,
Olsson has submitted a contract amendment in the amount of $20,000 to complete the
additional work.
Exhibit A is the Airport Property Map that is associated with the Airport Layout Plan (ALP). The
map includes ownership information and easements. The work will include researching all
parcel ownership and easements associated with the airport and its operations. A more
detailed account of the items they will be researching can be found in the amendment
document.
This amendment was presented to the Airport Advisory Committee on April 21, 2023.
Fiscal Impact:
The professional services agreement amendment is in the amount of $20,000.00. With this
second amendment the contract amount with Olsson is $641,167.00. The City of Fremont’s
share of the engineering services is 10% of the total cost or $64,116.70.
Runway 14/32 Rehabilitation
Professional Services Agreement Amendment No. 2