MINUTES OF THE GILBERT TOWN COUNCIL, IN SPECIAL MEETING FOR A STUDY
SESSION, TUESDAY, MAY 17, 2022, AT 5:15 P.M., GILBERT PUBLIC SAFETY
TRAINING FACILITY, ATLAS AUDITORIUM, 6860 SOUTH POWER ROAD, GILBERT,
ARIZONA
COUNCIL PRESENT: Mayor Brigette Peterson, Vice Mayor Aimee Yentes,
Councilmembers Scott Anderson, Laurin Hendrix, Yung
Koprowski, Scott September, and Kathy Tilque
COUNCIL ABSENT:None
STAFF PRESENT: Town Manager Patrick Banger, Town Clerk Chaveli
Herrera, Town Attorney Chris Payne, Development
Services Director Kyle Mieras, Transportation Planning
Supervisor Stephanie Bubenheim, Senior Transportation
Planner Nathan Williams
CALL TO ORDER OF SPECIAL MEETING
Mayor Peterson called the meeting to order at 5:15 p.m.
AGENDA ITEM
1. Discussion on Transportation Master Plan.
Development Services Director Mieras spoke of the importance of the
Transportation Master Plan (TMP), stating it was an item that had a lot of input
from multiple departments and outside input. He introduced outside consultants
Vamshi Yellisetty, Senior Principal Planner, and Phyllis Huegel, Associate Planner,
both of Kittelson & Associates, Inc., and Aaron Xavier, Senior Service Planner for
Valley Metro. He mentioned a close partnership with Valley Metro to compare
information from surrounding cities to address creating a transit plan that would
integrate with the TMP. He noted it was a twenty-year plan that had seven chapters
and six appendices and was a dynamic document as each chapter built on the
previous and included an implementation strategy that could be followed every year.
He explained that the Study Session was an introduction to the plan as it would be
presented to the Council on June 28th, 2022 for adoption, but they wanted to provide
an opportunity for an overview and allow for questions and modifications prior to the
intended adoption date.
Senior Principal Planner Yellisetty noted the TMP was a two-year endeavor thus far
and said he would present highlights from the plan and help to answer any
questions. He began with sharing the purpose of the plan was to understand
changes since the last plan was made approximately eight years ago; to create a
more viable, equitable and connected multimodal transportation network; and to
create a realistic Action Plan that the Town would truly use as a blueprint or
guidebook, adding it was in line with City of the Future initiative. He explained the
reasons for creating the plan consisted of the added stress to the transportation
system due to Gilbert’s observed and projected population and employment
increases, refocusing the plan to emphasize moving people rather than cars, should
they choose an alternate transportation mode, and to provide a prioritized list of
investments to the Town. He said the group followed a five-step approach of
internal working groups, multi-phase community engagement, stakeholder outreach,
and partnership with Valley Metro. He discussed the process to gain public input
and potential solutions that would make sense for each of the identified issues. He
highlighted the importance of the public engagement and the extreme lengths made
to ensure the public had access to the virtual approach of engagement. He stated
the approach was successful in garnering public engagement and shared figures
highlighting 4,968 visitors to the project website, a virtual open house, 1,975 surveys
completed, and 565 map comments provided.
Senior Principal Planner Yellisetty said solutions offered were an integrated TMP, a
connected network design, multi-use path implementation plan and design toolbox,
and emerging mobility playbook. He said the toolbox could be utilized by Gilbert
going forward.
Associate Planner Huegel reviewed the findings that helped move their project
forward. She said by 2050 there was a projected 20% population increase and a
48% projected employment increase in Gilbert and encouraged everyone to imagine
the impact that would have on transportation in the town. She said driving was the
primary mode of transportation in Gilbert and shared the survey results that 92% of
respondents found it easy to travel around Gilbert by car, and 67% of respondents
shared they saw Gilbert’s transportation network travel by car worsening in the
future. She discussed congestion and delays in travel as well as safety, with an in-
depth safety assessment to identify hotspots and to develop plans and counter
measures. She shared that the top public responses to the survey question of the
Town’s greatest transportation need were reducing travel congestion and improving
safety for all users.
Associate Planner Huegel reiterated that the plan was developed from an all-modes
perspective and emphasized the partnership with Valley Metro throughout the
process starting with evaluating the current transit routes. She noted that, according
to the public survey results, most people felt it was easy to get around by car at 92%
of respondents, but less by walking at 66%, bicycles at 63%, and even less by bus or
other public transportation at 32%. She reported that when respondents were asked
what they would do to improve transit, 52% said they would expand public
transportation to new areas, and 30% said they would increase the frequency and
stop amenities on popular routes. She added that the existing conditions analysis,
community profile, and socio-economic analysis helped drive Valley Metro’s
assessment to find solutions going forward.
Associate Planner Huegel explained that freight movement was also considered,
with companies like Amazon and UPS using the roadways at high rates, so they
worked with Maricopa Association of Governments (MAG) to identify and address
corridors in need of improvement for goods movements. She added that they needed
to look at all their users and reported that people said they wanted additional
transportation options for more livable community space. She stated that given the
public feedback, they evaluated Gilbert’s biking and walking networks compared to
neighboring communities and found that Gilbert trended lower on walking and biking
scores compared to those other communities.
Associate Planner Huegel addressed the importance of the analysis and public
outreach done and emphasized what they then wanted to know was what the public
prioritized the Town to invest in. She explained that they asked the public some hard
decisions involving investments in trade-off scenarios; such as whether people
preferred to improve, expand, or preserve the current transportation system,
expansion versus modernization versus preservation. She reported some of the
results included almost an even split in interest in upgrading or expanding the
transportation system, and a high interest in more protected facilities for bike lanes,
as well as more miles of trails and enhanced connectivity. She elaborated that the
public response focus on connectivity and access to the transit network shifted the
focus of the plan and helped set a baseline for the strategies, programs, and
projects identified in the TMP.
Associate Planner Huegel summarized the key findings and outcomes of the work
conducted in creating the plan. She first addressed the lack of mobility options and
why that was the case; she then introduced the topic of complete networks and how
they assigned each corridor with its modal needs. She provided visual examples of
Gilbert’s freight, transit, vehicle, bicycle, and pedestrian networks, then explained
that each current network highlighted where the corridors were for that
transportation mode and how that related to the considerations that should be made
when developing a transportation plan. She expanded on complete networks,
explaining that complete networks made for safer and more comfortable
transportation by mode.
Associate Planner Huegel shared that one of the metrics used to assess the
complete network effectiveness considered how much of Gilbert could be reached
via a 20-minute bike ride. They found that only 3.4% of Gilbert could be reached via
the current low-stress network, but with a complete bicycle network, 13% of the
Town could be accessed in that same timeframe. She added the impact it would
have on accessibility to jobs that could be reached via a 20-minute bike ride;
whereas, currently only 2,957 jobs could be reached within those parameters, a
complete network would provide bike access to 7,922 jobs. She then discussed
another key finding was that the lack of flexibility in street design resulted in the
lack alternative modes; as was seen across the country as most streets were based
on functional classification only. She discussed street typologies and that street
design was not a one size fits all approach when the street and corridor context and
needs were taken into consideration. She said the 16 street typologies were based
on how people use the street, land use context (urban, suburban, rural, etc.), and
the modal needs of the corridor. She explained they were pulled directly from the
General Plan in collaboration with the General Plan consultant and the Planning
Department to develop the plan types, or land use types. She elaborated that the 16
street typologies allowed for a flexible approach when designing corridors to meet
future needs.
Senior Principal Planner Yellisetty discussed the plan to prioritize the following
investment types: capacity projects, maintenance projects, intersection and safety
projects, pedestrian improvements, bicycle and multi-use path projects, and transit
recommendations. He discussed how the investments were prioritized and what the
projects were evaluated on, including the TMP goals and objectives, benefits and
issues addressed, and cost and feasibility. He discussed the priorities in Tier I, the
highest priority with a 1-7-year timeframe; Tier II, medium priority with an 8-15-year
timeframe; and Tier III, projects that may not be needed immediately but may
develop over time as funding and opportunities arose. He emphasized that Tier II
projects were not necessarily of lower importance, but could be more expensive
projects or may not have accessible funding in place.
Senior Principal Planner Yellisetty discussed some of the roadway improvement
projects such as the Baseline Road Improvements—Greenfield Road to Power Road,
and the Heritage District—Ash Street Realignment, Vaughn Ventilator. He also
discussed some intersection improvement examples such as the intersections of
Guadalupe Road at McQueen Road, Lindsay Road and Val Vista Drive. He explained
that at the congested intersections they assessed the needs for new signals,
upgraded signal infrastructure, retiming of the signals, and other options to make
them more efficient. He discussed safety improvements and concerns brought forth
by residents expressing their lack of trail use was due to feeling unsafe when in
crossings to access the existing trail systems. He explained that they expanded on
the Town’s initial study recommendations and identified more locations that would
benefit from improvements.
Senior Principal Planner Yellisetty discussed transit improvements and the many
aspects considered and influence of neighboring cities when they did the analysis
for determining the plan to prioritize investments. He noted that expanding transit
was expensive, so they explored potential microtransit areas, which was essential to
on-demand ridesharing systems. He also discussed their review of Gilbert’s active
transportation and sidewalks, which was extensive but included gaps in the system
preventing pedestrian usage. He stated they did a similar review with bicycle trails
and multi-use path/trail facilities. He described the vision and design guidance for
designing the trail network to address the gaps, and lastly, he discussed
implementation and moving forward strategies.
Councilmember September stated while reviewing the materials he understood how
intensive the work was and expressed appreciation to staff and the outside partners
that worked on it. He acknowledged how they discussed the matter and highlighted
investments. Senior Planner Yellisetty praised the Town staff for their collaboration
and dedication. Mayor Peterson thanked him for his comment and stated she agreed
that Gilbert had a wonderful staff.
Councilmember Tilque asked how the priorities of the Capital Improvement Plan
(CIP) priorities tied in with those of the TMP and how they would possibly change.
Senior Planner Yellisetty responded that CIP projects, as well as bond projects,
were taken into consideration and were evaluated with the current data they had,
then used that to group the priorities in the tiers previously discussed. He added
that, based on data, some recommendations were to enhance certain CIP projects
to get more “bang for your buck”.
Director Mieras commented that each Fall CIP projects were reviewed and prepared
to bring forth to the Council during the current time of year in order to have analysis
and prioritization of the projects. Mayor Peterson noted both the TMP and CIP were
fluid documents that could be changed as priorities changed and reassessment was
needed each year.
Councilmember Koprowski thanked the staff and consultants for the presentation,
for the additional time to review the documents prior to the June 28, 2022 adoption
date, as well as for their context-driven approach and not treating all roadways the
same. She noted it was forward- thinking and she appreciated the public
engagement as well, especially as they needed to consider the next 20 years of
transportation for the Town.
Senior Planner Yellisetty acknowledged the hard work of the Digital Government
Team as they were critical to the outreach component.
Vice Mayor Yentes stated she would offer a contrary opinion for the sake of
discussion, highlighting a major disconnect between the presented document and
valid and recent survey regarding the bond that only passed by 164 votes. She asked
who prepared the survey instrument, either Valley Metro or Gilbert Digital
Government. Senior Planner Yellisetty responded they had not been a part of the
bond process. Vice Mayor Yentes confirmed her question was regarding the TMP
related survey; she noted that when she reviewed the bond question, she saw their
guidance on how some of the projects could be prioritized or where funding might
come from. She stated the bond may be the backbone of the project and read the
bond language provided in the TMP. She explained that she felt there was a
disconnect between the bond-related language that was on the ballot when the
public voted and the language that was presented in the TMP. She stated that bike
paths and hiking trails were recreation projects, not transportation projects, and
though she appreciated the approach the basis of the plan was focused on moving
people, not cars. She emphasized that 95% of the population were moved with cars
and noted the involvement of freight transportation and consumer behaviors, thus
setting the investment in roadways even higher. She added that parks and
recreation projects were better served being on a parks and recreation bond for
transparency to the public and felt the TMP survey was skewed in leading to
favorable responses due to the survey question design. She commented that it may
not be wise to have 20-year planning envelopes for projects that were so fluid and
disruptive in the technological space as transportation was. She made a comparison
to the scenario if people were asked if they would use the gym more if they were
offered a free entry pass, the results would be overwhelmingly positive, but the
reality would likely be they would not actually use the gym. She stated that
investments should be made to encourage people to bike and walk more, but did not
feel the investments would make an impact in changing behavior because people
did not want to use those transportation methods outside of recreational purposes.
She added there were important details that needed to be addressed, such as
throughput and diminishment on capacity, that were not included in the plan and the
document missed the mark in guiding those that wanted to invest in transportation
via the bond.
Mayor Peterson stated she agreed with many of Vice Mayor Yentes’ comments in
that it was a large Town with large roads and large families that required movement
by vehicle. She added that she would not go to the gym more if offered a free pass,
as in Vice Mayor Yentes’ comparison example, and that she answered no to the
TMP public survey for the questions related to whether she would walk bike, or hike
more. She agreed that the transportation bond should be separated from the TMP,
as they were separate, noting the TMP was a living, breathing, transitioning
document and elements could change and get updated.
Councilmember Koprowski responded that those were good points, but historically
there was no city that had built its way out of congestion and it was not possible.
She stated that the way to tackle the matter was to approach it with a holistic view,
as the COVID-19 Pandemic provided a clear example of significantly lessened
congestion as people were commuting to work. She noted that multi-modal
approach did need to be included for the holistic approach, but agreed that vehicle
transportation should still be prioritized. She stated that looking at smart, alternative
solutions, including telecommuting, would support the overall improvement for
residents. She acknowledged that the TMP was a 20-year plan and was
disconnected from the bond voting language. She asked how often the Town was
required to update the plan. Director Mieras responded that, according to the
implementation strategy of the plan, it would be reviewed each year, but he was not
sure if there was a statutory requirement to update the plan. He addressed the
concerns regarding the 20-year scope of the plan and explained that, though many
changes could happen in that timeframe, the tiers of the plan allowed them to
prioritize the projects.
Councilmember Tilque commented that the disconnect between the TMP
recreation-related projects and the bond question were because the consultants
took into account that, if the bond passed, the parks and recreation projects would
be included and considered how they would be impacted by the TMP. She noted
that what she saw the plan doing was looking at the current projects and
determining how they could be enhanced to accommodate connectivity. She
highlighted the public’s interest in increased connectivity, primarily via car, but there
were a lot of people looking for connectivity via other modes. She noted trail
improvements being made to the Greenfield Road area to increase safety and
lessening potential accidents, and examples as such, were how she expected the
plan to enhance projects rather than shift priorities.
Vice Mayor Yentes stated they received a high-level presentation with the Parks and
Recreation Board and she asked if the goal was to try to reduce the number of
drivers in total. She added that the response to her question was yes, so she then
asked what the metrics were to determine if they were successful in achieving that
goal by reconfiguring entire networks. She said it was explained that, once the
changes were made, they could check and see if more people were walking and
biking. She said she did not want to adopt a plan or roadmap presenting to the
public priorities that were not rooted in reality, but rather in social engineering. She
noted some other cities across the country did have written in their planning
documents that they would optimize signals to create congestion in order to try to
force people out of their vehicles. She said that approach was a red flag and she
wanted to move in the opposite direction.
Councilmember Anderson responded that he agreed that he did not want to force
that to happen and that was not the intent of the plan; however, every year the
transportation category was rated worst on the National Citizen Survey. He stated
they needed to address that, and everyday Council received emails from the
community regarding transportation concerns. He added that those reasons were
why the TMP and bond were needed, but the Council needed more time to review
the plan and supporting materials.
Vice Mayor Yentes noted she had not had the chance to go through all the specific
projects, but appreciated that there were specific paragraphs discussing tradeoffs
and asked if additional highlights on the projects’ tradeoffs could be made in order
to aid the policy body conversations and clarify the process.
Councilmember September stated that everyone could benefit from more time to
review the plan and asked if there would be another Study Session on the matter or
if it would go straight to a meeting agenda. Mayor Peterson explained that the goal
was to bring the plan to Council for approval in June, as it had been in progress for
two year, but could be brought to another Study Session as that was the first time it
had been presented to Council. Councilmember September reiterated that additional
time to review would be a good idea. Mayor Peterson stated that she realized it was
a lot of information and that was the reason to hold the Study Session, to provide
the document, information from staff, and time to take into consideration what was
discussed at the Study Session to discuss the matter again later with a better
understanding.
Vice Mayor Yentes commented she felt the plan was a little thin on adapting to
technology in order to be in alignment with the City of the Future initiative. She
stated that walking was the oldest form of transportation but if they wanted to adapt
to ridesharing, autonomous vehicles, more sophisticated traffic optimization
signaling, and more, then that was what the network should be built around in order
to be nimble in having funds to adopt new technology to improve the efficiency and
quality of life for residents and businesses.
Councilmember Hendrix stated he had no comment.
Mayor Peterson stated there were some great comments from the Council and they
could have an additional Study Session with staff prior to the item adoption to
discuss the questions and concerns highlighted from the discussion they had that
evening. She thanked the staff and partners for their participation and the
presentation.
2. Discussion on Ocotillo Road Bridge Project.
This item was rescheduled for May 24, 2022.
3. Discussion on Billboards.
This item was removed from the agenda.
ADJOURN
Mayor Peterson adjourned the meeting at 6:20 p.m.
ATTEST:
___________________________ ___________________________________
Brigette Peterson, Mayor Chaveli Herrera, MMC, Town Clerk
CERTIFICATION
I hereby certify that the foregoing minutes are a true and correct copy of the minutes
of the Study Session of the Town Council of the Town of Gilbert held on the 17th day
of May, 2022. I further certify that the meeting was duly called and held and that a
quorum was present.
Dated this __________ day of ______________, 2022.
___________________________________
Chaveli Herrera, MMC, Town Clerk
Agenda
COUNCIL STUDY SESSION AGENDA
May 17, 2022
5/17/2022 5:15 PM
Members may attend in person or by telephone.
Brigette Peterson, Mayor ● Aimee Yentes, Vice Mayor
Scott Anderson ● Laurin Hendrix ● Yung Koprowski ● Scott September ● Kathy Tilque
Gilbert Public Safety Training Facility, Atlas Auditorium
6860 S. Power Road
Gilbert, Arizona
Study Sessions are held at the Gilbert Public Safety Training Facility, 6860 S. Power Road, Gilbert,
Arizona. Study Sessions are open to the public. Discussion of agenda items is reserved for the
Council and Staff. No decisions are made or action taken during the Study Session.
Please Note: There has been a revision to the agenda as reflected below.
CALL TO ORDER
AGENDA ITEMS
1. Discussion on Transportation Master Plan.
2. Discussion on Ocotillo Road Bridge Project.
Item has been rescheduled to May 24, 2022.
3. Discussion on Billboards.
Item has been removed from agenda.
ADJOURN
NOTICE TO PARENTS: Parents and legal guardians have the right to consent before the Town of Gilbert makes a video or
voice recording of a minor child. A.R.S. 1-602.A.9. Gilbert Council Meetings are recorded and maybe viewed on Gilbert Live
website. If you permit your child to participate in the Council Meeting, a recording will be made. If your child is seated in
the audience your child may be recorded, but you may request that your child be seated in a designated area to avoid
recording. Please submit your request to the Town Clerk.
Get email alerts for Gilbert
A daily email when new agendas and minutes are posted.