Water Resources Municipal Property Corporation
Regular MeetingGilbert, AZ · February 10, 2025
Minutes
MINUTES OF THE BOARD OF DIRECTORS OF THE TOWN OF GILBERT, ARIZONA
WATER RESOURCES MUNICIPAL PROPERTY CORPORATION MEETING,
MONDAY, FEBRUARY 10, 2025 AT 2:00 P.M., IN-PERSON/VIRTUAL MEETING,
GILBERT, ARIZONA
BOARD MEMBERS PRESENT: President Shane Cook
Vice President James Graham
Secretary-Treasurer Kevin Boudreau - Online
Director John Dalen Wilcock
Director Nicholas Macaluso
BOARD MEMBERS ABSENT: None
COUNCIL LIAISON PRESENT: Vice Mayor Bobbi Buchli
TOWN STAFF PRESENT: Kelly Pfost, Management and Budget Director
Sarah Rogowski, CIP Project Supervisor
Emily Harmon, FM Services Accountant Supervisor
Anthony St. George, FM Services Accounting Manager
Rachel Shaver, Management and Budget Specialist
Chris Payne, Town Attorney
OTHERS PRESENT: None
CALL TO ORDER
President Shane Cook called the meeting to order at 2:01 p.m.
OATHS OF OFFICE
Not necessary as there are no new members in 2025.
ROLL CALL
Management and Budget Specialist Rachel Shaver called roll and declared a quorum was
present.
COMMUNICATIONS FROM CITIZENS
None received.
AGENDA ITEMS
1. ELECTION – Consider nomination and election of officers for 2025.
Town of Gilbert AZ Water Resources MPC
February 10, 2025
Page 2 of 7
President Shane Cook proposed that those eligible to keep their current office do so. Shane
Cook has already held the position of President for two years. Kevin Boudreau has also already
held the position of Secretary-Treasurer for two years.
Per the suggestion of Shane Cook, Nick Macaluso agreed to volunteer as President. James
Graham volunteered to continue as Vice President and Shane Cook volunteered as Secretary-
Treasurer.
A MOTION was made by Secretary-Treasurer Kevin Boudreau, seconded by Director Nick
Macaluso for the above nominations. Motion carried 5 – 0
2. MINUTES – Consider approval of the minutes of the meeting of February 12, 2024.
A MOTION was made by Secretary-Treasurer Shane Cook, seconded by President Nick
Macaluso to approve the minutes of the meeting held on February 12, 2024 as written. Motion
carried 5 - 0
3. CAPITAL PROJECTS – Status Report
CIP Project Supervisor, Sarah Rogowski, gave an update on the North Water Treatment Plant
(NWTP WA1589). She explained that the project team honors the importance of meeting the
community’s need for safe, reliable, resilient water, fiscally responsible project management,
and proactive communication. She then highlighted key takeaways of the presentation:
1. Gilbert’s North Water Treatment Plant was unable to meet system needs and it was
identified that substantial investment was required to continue to treat Gilbert water.
2. Time is of the essence as any delay risks system shortage as well as system compliance.
Ms. Rogowski then went on to discuss the NWTP Facility Background, talking the group
through a map showing the Town of Gilbert Water System by Pressure Zones. Service Area
was discussed, noting that the water treatment plant in north Gilbert has a capacity of 45
million gallons per day and currently serves 144,000 residents, with a plan to serve 250,000
at buildout. She then touched on Water Production, which functions as the backbone of the
sustainable water supply, with projected demands of over 55 million gallons per day. She also
explained that the Town has some very important customers that the treatment plant serves,
including the NW Redevelopment District, Heritage District, Gateway Employment Corridor,
and the Banner Gateway Medical Center Campus.
Ms. Rogowski moved on to give the group a quick background on what brought about this
project. She summarized that we face water quality challenges as the plant treats water from
the Salt and Verde Rivers, whose watershed has changed dramatically over the past 10 years
due to all of the fires in that area. Sometimes the plant receives as little as 24 hours’ notice
from SRP that the water quality is changing, and the current conventional water treatment
plant doesn’t have the ability to make adjustments that quickly. It also treats water from SRP
wells, whose water is very clean, which actually makes it more difficult to treat. The new
treatment technology will actually be able to meet the ever-changing quality needs that are
encountered with SRP. Other challenges include significant population growth, the need to
fully utilize renewable water resources, and the structural challenges at the current facility.
Town of Gilbert AZ Water Resources MPC
February 10, 2025
Page 3 of 7
Ms. Rogowski then gave an overview of the current Program Status. She explained that the
future NWTP will be able to provide 70% of Gilbert’s water supply, will add 50+ years of
service life due to the upgrades and expansion, will have the capacity to serve 250,000
residents, and will have a daily capacity of 60 million gallons. She also explained the scope,
schedule, and budget which are broken down into five GMPs. GMP is construction language
for phases of the project.
GMP-1
Dewatering Facilities
Site Preparation
Field Offices/Laydown Areas
GMP Value: $23.82M
Final Completion Achieved
GMP-2
Long-Lead Procurement
Initial Site Demolition
Equipment Design Support
GMP Value: $15.8M
Final Completion Achieved
GMP-3
Primary Treatment Facilities
New Facility Access
GMP Value: $337M
NTP – June 2023
Substantial – June 2026
GMP-4
Granulated Activated Carbon and
Disinfection System
GMP Value: $160M
NTP – Dec 2023
Substantial – Dec 2026 (although expected to be completed sooner, possibly June 2026)
GMP-5
60% Design Phase:
Site Demolition & Restoration
Pre-Sedimentation Basins
Existing Bldg Rehab & Modifications
60% Cost Model: $113M
NTP – Mid 2026
Substantial – Late 2028
Ms. Rogowski also highlighted the volatility of challenging market conditions which consist
of international markets, supply chain delay, materials gap, labor shortages, local factor
impact, and general price pressures.
Town of Gilbert AZ Water Resources MPC
February 10, 2025
Page 4 of 7
Management and Budget Director Kelly Pfost asked a question regarding the impact the 25%
tariffs on steel and aluminum have on the final cost. Ms. Rogowski replied that the biggest
chunk of the final phase will be the presedimentation basins, which are all concrete and will
require steel, however the contractor is carrying escalation and will factor any increases in.
As they refine the design to 90%, the allowances they carry get smaller and smaller and the
risk gets lower and lower. She does not plan on the project costs going over budget and is
working to keep them as low as possible, but as soon as numbers are available, they will be
brought to the team.
Ms. Rogowski also walked the group through an image depicting color coded project phasing
at the new North Water Treatment Plant. She also shared photos of the construction site and
provided details regarding current construction. She also highlighted their project focus of
safety and craftsmanship. Approximately 796,000 hours have been worked on site and it has
been 838 days since the last recordable safety incident (which requires a worker to lose a day
of work) which is a huge accomplishment.
Ms. Rogowski also added that this summer the project will hit 300 craft workers on site, not
including staff and project managers. She also shared that 30,000 cubic yards of concrete have
been poured onsite, equal to 80 miles of sidewalk.
She went on to show the group a fly over of the NWTP and explained the different portions
of the plant shown.
Ms. Rogowski asked for questions, to which the board stated they had none.
4. ANNUAL REPORT – Consider approval of the annual financial report.
Finance and Management Services Accounting Supervisor, Emily Harmon introduced herself
and clarified that the first two financial statements are combined statements and the second
two have them broken out for water and wastewater. It is currently broken down as Water
MPC and Wastewater MPC, but it really is just one MPC. Ms. Harmon explained that she
would be reviewing the annual financial report dated June 30, 2024 and the interim report
dated December 31, 2024. Ms. Harmon began with the annual financial report (dated June 30,
2024) Statement of Net Position. She outlined four highlights from the Statement (broken up
between two slides):
1. Unspent bond processed decreased due to increased expenses at the NWTP and all
remaining 2016 bond funds were spent in Fiscal Year 2024.
2. Property, plant, and equipment increased due to increased activity on the NWTP
reconstruction project.
3. Accounts payable increased due to increased activity on the NWTP reconstruction project.
4. Bonds payable decreased due to payment of Fiscal Year 2024 bond principal.
Ms. Harmon moved on to the Statement of Revenues, Expenses, and Changes in Net Position
– 1 Year Comparison, explaining four highlights from the Statement.
Town of Gilbert AZ Water Resources MPC
February 10, 2025
Page 5 of 7
1. Revenues associated with lease payments increased in accordance with increase in interest
and principal payments due to the 2022 bond issuance. These bonds were issued in late
Fiscal Year 2022, and no principal payments were due until Fiscal Year 2024.
2. Change in fair market value of investments increased due to an overall increase in the
market from prior year.
3. Interest expense increased due to the 2022 bond interest coming due.
4. Overall Net position increased which is projected to continue to increase as debt is repaid.
She then moved on to Future Debt Payments consisting of the remaining payment interest and
principal payments for the Series 2016, Series 2022, and Series 2018 funding bonds. Series 2022
is shown on two pages as it goes through year 2048.
Ms. Harmon continued on to the Interim Financial Report dated December 31, 2024 and explained
that it represents activity from July 1, 2024 through December 31, 2024. It is primarily the interest
payments that were made as of mid-year. She explained three highlights from the Interim Financial
Summary.
1. As of this presentation, interest payments have been made for each bond.
2. Interest expense has been offset by funding transfers from the Water Operating, Water
Replacement, Water SDF, and Water Resources SDF.
3. Next significant activity will be the 7/1/2025 Principal and Interest payments.
Secretary-Treasurer Shane Cook asked how the 50 million compares to what it was expected to
be. Director Pfost explained that it is within budget, but she isn’t sure what the cash flow
expectation was. Director Kevin Boudreau clarified that the 50 million is for a 6 month period of
time, so it is tough to tell. Director Pfost stated that we are watching the outflows and what is
needed when we finish these bond proceeds, which leads into the next presentation.
A MOTION was made by Secretary-Treasurer Shane Cook, seconded by Director Kevin Boudreau
to approve the annual financial report as written. Motion carried 5 – 0.
5. FUTURE BONDS NEEDS DISCUSSION – Status Report
Management and Budget Director, Kelly Pfost, shared a presentation regarding future WRMPC
bonds needs. As most are aware, all bonds need to be approved by Council before coming to the
WRMPC, so this is just an early look at what is on the horizon. She explained the current debt and
that there are currently four bonds series outstanding. The Series 2016 bonds paid for the Santan
Water Treatment plant expansion and other projects, Series 2018 paid for the Greenfield
Wastewater Treatment Plan expansion no. 3, and Series 2022 is paying for the water projects
already discussed. The bonds equal about $500 million total with $350 million remaining at the
beginning of the year and about $50 million spent so far this year. These are being watched
carefully so that we can get the next bond issuance ready or have the cash on hand. The final phase
of the NWTP will likely need an additional infusion of bonds to finish out that project, which will
likely be in Spring 2027. The repayments sources for these bonds will likely include the Water
Repair and Replacement and Water SDF.
Ms. Pfost went on to explain that the next group of potential bonds are Wastewater SDF projects,
with the need for Greenfield Wastewater Treatment Plant Expansion Phase 4 and other Wastewater
Town of Gilbert AZ Water Resources MPC
February 10, 2025
Page 6 of 7
Projects. Potential bond timing would be Spring 2027 with a likely repayment source of
Wastewater SDFs.
Ms. Pfost then addressed the third group, being Wastewater projects. There will be a need to Bond
finance Wastewater and Wastewater R&R projects, depending on Council decision for WW Rates.
Potential bond timing would be Spring 2027 with repayment sources likely to include Wastewater
Operating and Wastewater R&R.
She noted that 2027 would likely be a very busy year, with a possible additional MPC meeting that
year.
Director Dalen Wilcock asked if this would all be one big bond. Director Kelly Pfost explained
that it would likely be structured as one bond with multiple funding sources as that saves us on
cost of issuance.
Director Dalen Wilcock also asked if SDFs could cover these projects. Ms. Pfost explained that
the cash flow in them isn’t enough because all of the households that will be served by the
wastewater treatment plant haven’t moved in yet. If they did, we wouldn’t have the plant ready to
provide them service, so we have to build ahead of the growth and then it gets paid back as they
build over the next ten years.
Director Kevin Boudreau asked at what point in time the SDF rates get reevaluated. Ms. Pfost
explained that they have to be reevaluated every five years, which happened recently, with new
rates going into place in July of 2024. It was a pretty substantial increase across the board.
FUTURE AGENDA ITEMS/MEETINGS:
President stated there were no future agenda items to discuss.
COMMUNICATIONS
From the PRESIDENT on current events.
None.
From the BOARDMEMBERS on current events.
None.
From the COUNCIL LIAISON on current events.
Vice Mayor Buchli thanked the members of the board and the time they devote to the
WRMPC.
From STAFF on current events.
Town of Gilbert AZ Water Resources MPC
February 10, 2025
Page 7 of 7
ADJOURN
President adjourned the meeting.
The meeting was adjourned at 2:43 p.m.
ATTEST:
___________________________ ________________________________
Nick Macaluso, President Shane Cook, Secretary-Treasurer
CERTIFICATION
I hereby certify that the foregoing minutes are a true and correct copy of the minutes of the Annual
Meeting of the Town of Gilbert Arizona Water Resources Municipal Property Corporation was
held on the 10th day of February 2025. I further certify that the meeting was duly called and held
and that a quorum was present.
Dated this __ day of _____________, ______.
___________________________________
Shane Cook, Secretary-Treasurer
Agenda
WATER RESOURCES MUNICIPAL PROPERTY
CORPORATION AGENDA
February 10, 2025
Shane Cook, President ● James Graham, Vice President ●
Kevin Boudreau, Secretary-Treasurer ●
Dalen Wilcock, Director ● Nicholas Macaluso, Director
Water Resources Municipal Property Corporation
2/10/2025 2:00:00 PM
50 E. Civic Center Dr, Room 202
Gilbert, Arizona
AGENDA ITEMS MAY BE DISCUSSED IN A DIFFERENT SEQUENCE.
ITEMS WILL NOT BE DISCUSSED PRIOR TO POSTED MEETING TIME.
Items on the agenda may be shortened, continued to a future public meeting, or taken out of
order. Participants will be allotted a limited amount of time to speak at public meetings (the
exact amount of time will be determined at the meeting by the Chair depending on the number of
participants, as permitted by Town Code and state law).
MEETING ACCESS
Listening Via Conference Line
A conference line will be available in order to listen to the WRMPC meeting. The
conference line number and access code for this meeting are: +1-323-591-8434 Access
code: 168 361 03#
Microsoft Teams Online Meeting Platform
Members of the public and Town staff who will also have the availability to participate in
the WRMPC meeting via Microsoft Teams. Click here to join the meeting
AGENDA ITEM
CALL TO ORDER
OATHS OF OFFICE
ROLL CALL
COMMUNICATION FROM CITIZENS
AGENDA ITEMS
1 Election - Consider nomination and election of officers for 2025
2 Minutes - Consider approval of the minutes of the WRMPC meeting of
February 12, 2024.
3 Capital Projects - Status report
4 Annual Report - Consider approval of financial report
5 Future Bonds Needs Discussion
FUTURE AGENDA ITEMS/MEETINGS
COMMUNICATIONS
From the PRESIDENT on current events
From the DIRECTORS on current events
From the COUNCIL LIAISON on current events
From STAFF on current events
ADJOURN