HPMPO Transportation Advisory Committee (TAC)
Regular MeetingHigh Point, NC · January 26, 2016
Minutes
Attachment 1
MINUTES
TRANSPORTATION ADVISORY COMMITTEE
January 26, 2016
TAC MEMBERS PRESENT:
Jim Myers –Lexington
Neal Grimes – Thomasville
Keith Volz – Jamestown
Cheryl McQueary – NCDOT Board
Bill Bencini – High Point
Larry Ward – Denton
Joe Geigle – FHWA
Larry Warlick - Archdale
TCC MEMBERS PRESENT: Greg Venable, Guy Cornman, Bryan Fulbright, Ed
Lewis, Heidi Galanti, Chuck George, Mark McDonald, Pat Ivey, Jason Miller, Mark
Kirstner, Darius Sturdivant, John Gray, Wayne Davis, Kelly Larkins, Chuck Smith, Mike
Mills, Brandon Jones, and Carrie Spencer.
OTHERS PRESENT: John Hanes (Transportation Planning), Vickie Embry(COHP
Transportation), Gwen Ford (COHP), Randy McCaslin (COHP), Gary Kennedy (Citizen,
Wallburg), Beth Kennedy (Citizen, Wallburg), Lee Gill (Citizen, Wallburg)
RECORDING SECRETARY: Marianne Janiszewski, City of High Point
Item 1: Reading of the Ethics Statement.
Neal Grimes read the Ethics Awareness and Conflict of Interest Reminder. No one had
any conflicts.
Item 2: Public Comment Period
Neal opened up the public comment period.
Lee Gill spoke in opposition to the NC 109 project and its financial impact on the
homeowners in the area.
Neal closed the public comment period.
Item 3: Report from the Nominating Committee and Election of TAC Chair
and Vice Chair.
Neal Grimes was nominated as Chair and Keith Volz was nominated as Vice-Chair.
They were voted in with no opposition.
Motion by: Jim Myers
1
Attachment 1
Seconded: Cheryl McQueary
Vote:
For: Unanimous
Against: None
ACTION ITEMS
Item 4: Consideration of the November 17, 2015 TAC meeting minutes.
There were no corrections to the minutes.
Motion by: Jim Myers
Seconded: Keith Volz
Vote:
For: Unanimous
Against: None
Cheryl McQueary abstained from the vote since she was not present at the November
meeting.
Item 5: Consideration to release the 2016-1017 Unified Planning Work
Program for public review and comment.
The Draft 2016-2017 UPWP is the work plan for the MPO for the upcoming fiscal year. As
part of the Public Participation Policy for the MPO the Draft UPWP must be available for a
minimum 30 day public review and comment period. The draft document will be released to
for public review and comment on February 8 and close on March 11. It will come back to
the TAC for approval at the March meeting. NCDOT put out a new format this year. The
draft document will be sent out to all TAC and TCC members this afternoon. A public
notice will go out stated that the document will be available for public review at all
jurisdictions. Greg handed out the local match which is based on population from the 2010
census numbers. The budget this year is $580,000 which is an increase over last year’s
budget. Money will be taken out of the new budget for a new position that will be opening
up. Some additional funding has also been included for special studies. There is a bike plan
the MPO would like to do and there has been some requests for some small feasibility studies
to be done.
Motion by: Cheryl McQueary
Seconded: Jim Myers
2
Attachment 1
Vote:
For: Unanimous
Against: None
Item 6: Consideration to amend the 2016-2025 Metropolitan Transportation
Improvement Program.
These amendments are due to additional funding of approximately $1.6 million from the
State for a ten year period. The Jamestown bypass has been moved up from 2025 to 2019
for construction with completion expected in 2022. ROW plans on this project are
complete and funding is available to start purchasing ROW.
Motion by: Keith Volz
Seconded: Cheryl McQueary
Vote:
For: Unanimous
Against: None
INFORMATION ITEMS
Item 7: SPOT 4.0 Update.
Greg reported that NCDOT has to approve all prioritization processes throughout the
State. Greg handed out a draft version that will be submitted to NCDOT. The ranking
criteria along with the DOT vote will be released on March 23rd for public review and
comment period. The regional impact/local input points window opens on April 1 and
runs until May 31. Review of public comments and final ranking criteria will take place
at the April TAC meeting. The division needs window opens August 1st and runs through
September 30. Unlike last year this year we will know ahead of time which projects will
be funded regionally and what projects will fall to the division level. The dates of the
public information sessions will be released at the March meeting. Greg will send an
email with the dates as soon as he gets them. Staff has considered changing the number
of DOT votes from 12 to 10. Members can vote on as many projects as they want but the
maximum number of votes that can be put on one project is five. This change is up for
discussion. This year bike and ped projects will be included in the ranking. A project
spreadsheet was handed out dividing projects into highway, bicycle and ped, rail, aviation
and transit. In the past a maximum of 100 points was given to the highest ranking
projects. This is how it is written currently but there will be a discussion before it is sent
to NCDOT as to if it is going to be kept like this. Greg also presented a map of the SPOT
projects.
3
Attachment 1
AGENCY REPORTS
Item 8: NCDOT Board of Transportation Report.
Cheryl McQueary gave a presentation on division 7 projects and showed a slide show on
the Honda Aircraft Type Certification Event.
Item 10: Division Engineer’s Reports.
Division 7
Mike Mills reported that they are working with the COHP on some pedestrian projects.
The High Point Rd. Project has a let date of 2019. The ROW plans are complete. The
Johnson St./Sandy Ridge Rd. project has a let date of July 2019. Planning and Design is
underway and the ROW plans will be complete in 2017. There will be a public workshop
sometime in early spring for the I-74/US 311 and NC 68 interchange improvement
project. The let date for this project is June, 2018. There are a couple of bridge projects
currently in progress. There are three pavement rehab projects. The pavement project on
I-74 to the Guilford/Forsyth County Line has a let date of February, 16, 2016 with a
completion date of Summer 2017. The project on I-85 from I-85 Business past the
Randolph County Line has a let date of April 19, 2016 with a completion date of Summer
2017. The project on I-40 from Gallimore Dairy Rd. to the Forsyth County Line has a let
date of March 15, 2016 with a completion date of Summer 2017.
Division 8
Darius Sturdivant reported that the Pedestrian Crosswalk project at the Main St./Balfour
Dr. intersection in Archdale is complete. The asphalt project is expected to resume in
April, 2016 with a completion Spring, 2016. The Prospect St. Bridge Project is 33%
complete with an estimated completion date of March, 2017. There are two SPOT Safety
Projects, one is the upgrade of traffic signals at the intersections of NC 62 and Finch
Farm Rd., and at Trinity Rd. and Archdale Rd. A flashing yellow arrow will be added.
Plans have been completed and the materials have been ordered for the upgrade. There
are some pavement rehab and bridge resurfacing projects coming up.
Division 9
Pat Ivey reported that new bridge project on Winston Rd. over 2970. Utility relocation is
underway and will be available to start construction on April 1, 2016. The 2970/ Bus 85
rehabilitation project on the southern end has a revised completion date of February 1,
2016. There is currently traffic on both new bridges. All lanes are anticipated to be open
on February 1. Division 9 has a consultant onboard for the new interchange project on
2970 at DCCC. The planning, environmental work and design are anticipated to start
later this year.
Item 10: Triad Air Awareness.
Lorelei Elkins was not present. Greg stated that there will be a lunch and learn
tomorrow, January 27.
4
Attachment 1
Item 13: NCDOT Transportation Planning Branch Report.
No one was present. Hemal Shah was promoted and is now with the Fayetteville MPO.
Item 14: Hi tran Report
Angela Wynes was not present.
Item 15: PART Report
Mark Kirstner referred to the report in the TAC packet.
Item 16: Other Business
The next meeting will be Tuesday, February 23, 2016.
There was no other business. The meeting was adjourned.
5
Agenda
HIGH POINT URBAN AREA MPO
Agenda for the January 26, 2016 TAC Meeting
10:00 AM
High Point Parks and Recreation Department
Administration Building
136 Northpoint Avenue, High Point
Ethics Statement
In accordance with the State Government Ethics Act, it is the duty of every TAC member to avoid
conflicts of interest. Does any TAC member have any known conflict of interest with respect to any
matters coming before the TAC today? If so, please identify the conflict and refrain from any
participation in the particular matter involved.
Public Comment Period
Report from the Nominating Committee and Election of TAC Chair and Vice Chair. (Neal Grimes)
Action Items
1. Consideration of the November 17th TAC meeting minutes. (TAC Chair) Pages 1-5
2. Consideration to release the 2016-2017 Unified Planning Work Program for public review
and comment. (Greg Venable) Page 6
3. Consideration of amendments to release the 2016-2025 Metropolitan Transportation
Improvement Program. (Greg Venable) Pages 7-10
Information Items
4. SPOT 4.0 update. (Greg Venable) Page 11
Agency Reports
5. NCDOT Board of Transportation Report (Cheryl McQueary – NCDOT Division 7
Board Member) Pages 13-35
6. Division Engineer’s Reports
a. Division 7 (Mike Mills) Pages 36-37
b. Division 8 (Darius Sturdivant Pages 38-41
c. Division 9 (Pat Ivey) Pages 42-44
7. Triad Air Awareness Report (Lorelei Elkins) Pages 45-46
8. NCDOT Transportation Planning Branch Report (Wayne Davis)
9. Hi tran Report (Angela Wynes)
10. PART Report (Scott Rhine) Pages 47-48
11. Other Business
TAC
Meeting
Meeting Date 1/26/2016 Agenda Item No. 1
Action Requested Approve
Section Tab
Consideration of the November 17th TAC meeting minutes. (TAC Chair)
Information Summary Attachments Yes No
The complete meeting minutes are in your packet as Attachment 1.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
1
MINUTES
TRANSPORTATION ADVISORY COMMITTEE
November 17, 2015
TAC MEMBERS PRESENT:
Jim Myers –Lexington
Neal Grimes – Thomasville
Fred McClure – Davidson County
Clyde Lynn Reece – Wallburg
Keith Volz – Jamestown
Jesse Hill - Trinity
TCC MEMBERS PRESENT: Greg Venable, Guy Cornman, Hemal Shah, Bryan
Fulbright, Zeb Holden, Ed Lewis, Diane Hampton, Heidi Galanti, Chuck George, Mark
McDonald, Pat Ivey, Mike Mills, Jason Miller, Oliver Bass, Raven Gore, Mark Kirstner,
Darius Sturdivant, and Carrie Spencer.
OTHERS PRESENT: John Hanes (Transportation Planning), Vickie Embry(COHP
Transportation), Cari Hopson (Transportation Planning).
RECORDING SECRETARY: Marianne Janiszewski, City of High Point
Item 1: Reading of the Ethics Statement.
Neal Grimes read the Ethics Awareness and Conflict of Interest Reminder. No one had
any conflicts.
Item 2: Public Comment Period
Neal opened up the public comment period. No one spoke. Neal closed the public
comment period.
ACTION ITEMS
Item 3: Consideration of the October 27, 2015 TAC meeting minutes.
There were no corrections to the minutes.
Motion by: Jim Myers
Seconded: Keith Volz
Vote:
For: Unanimous
Against: None
2
Item 4: Consideration of amendments to the 2016-2025 Metropolitan
Transportation Improvement Program.
This is a revision to the NC 47 bridge replacement over Swearing Creek in Davidson
County.
Motion by: Jim Myers
Seconded: Keith Volz
Vote:
For: Unanimous
Against: None
Item 5: Appointment of the Nominating Committee for the selection of 2016
Officers.
At the November meeting the TAC Chair appoints a nominating committee to select a
chair and Vice-Chair of the TAC for the upcoming year. The nominating committee will
then report back to the TAC at the meeting in January for approval.
Jim Myers and Larry Warlick were picked to be on the nominating committee.
Item 6: Consideration of the proposed 2016 TAC schedule.
The Draft 2016 TAC Meeting schedule is below. Staff is requesting approval of the schedule.
Draft 2016 TAC Meeting Schedule
January 26, 2016
February 23, 2016
March 22, 2016
April 26, 2016
May 24, 2016
June 28, 2016
July - No meeting scheduled
August 23, 2016
September 27, 2016
October 25, 2016
November 15, 2016
December - No meeting Scheduled
Motion by: Jim Myers
3
Seconded: Keith Volz
Vote:
For: Unanimous
Against: None
INFORMATION ITEMS
Item 7: SPOT 4.0 Update.
NCDOT has now opened the window for new project submittal for SPOT 4.0. MPOs and
th
Divisions have until November 20 to submit all new projects. HPMPO staff will be entering
new projects in the system over the next few weeks. Over the next few months Greg will
present information on the methodology and point assignments. The State will release the
scores for the regional projects in April, 2016 and division projects in August, 2016.
AGENCY REPORTS
Item 8: NCDOT Board of Transportation Report.
Cheryl McQueary was not present.
Item 10: Division Engineer’s Reports.
Division 7
Ed Lewis reported that the High Point Signal System project was awarded. The NC 68
(Eastchester Dr.) interchange improvements project central design is in progress. A
public meeting will be scheduled for some time after the 1st of the year. The noise wall
voting procedures will be available. There are several pavement rehab projects that are in
the planning stages and will be let after the first of the year. Ed met with the planning
and design staff from Raleigh to talk about the Sandy Ridge Rd and I-40 interchange
revision project. This is being coordinated with the Sandy Ridge/ Johnson St. project that
is already underway. ROW will take place in 2019 and let in 2021.
Division 8
Darius reported that work on the pedestrian project in Archdale started on October 7,
2015. The bridge replacement project at I-85 and Prospect St. is 25% complete. Plans
for the two SPOT projects; upgrade traffic signal on NC 62 at Finch Farm Rd and Trinity
Rd. and Archdale Rd. are currently in the design and review phase. There are several
paving rehab projects, one on I-73 and one on I-85 are scheduled to be let in January.
He also announced that they have hired Brandon Jones as the new Division 8 Engineer.
Division 9
Diane Hampton reported that the US52/NC 8 replacement bridge over US 29/64/70/I 85
Bus. Loop in Lexington will be available April 1, 2016. The landscaping project on I-85
4
from Hargrave Rd. in Davidson Co. to Long Ferry Rd. in Rowan Co. began on November
3. The I-85 Bus. Upgrade and the bridge replacement over Swearing Creek should be
finished by the end of this month with the roadwork portion being finished mid-
December. There are several other bridge and projects under development. The Winston
Rd. widening project which will tie into the new 3159 project will be let in 2019.
Item 10: Triad Air Awareness.
Lorelei Elkins was not present.
Item 13: NCDOT Transportation Planning Branch Report.
We had a telecom call with Hemal. She stated that Information Planning Branch is
moving up the date of the draft UPWP to January 21, 2016 to align with the Public
Transportation Division deadline. A draft will be presented at the January 26 TAC
meeting and a request will be made to put the document out for a 30 day public review
period. Approval will be requested at the March TAC meeting.
Item 14: Hi tran Report
Angela Wynes was not present.
Item 15: PART Report
Mark Kirstner reported that additional stops were added to route 4 and connected with
Triangle Transit in Mebane. The ridership on this route has more than doubled. PART is
conducting interviews with consulting teams for phase two of the freight study. He
thanked Davidson County and the MPO for their partnership in making revisions to
Route 9. The PART board approved those revisions. Route 9 will no longer travel to
Greensboro but passengers can transfer in High Point. All data showed that more people
were traveling to High Point and the airport area from Davidson County for their jobs.
This route will also travel to the Thomasville hub.
Item 16: Other Business
The next meeting will be Tuesday, January 26, 2016.
There was no other business. The meeting was adjourned.
5
TAC
Meeting
Meeting Date 1/26/2016 Agenda Item No. 2
Action Requested Approve
Section Tab
Consideration to release the Draft 2016-2017 Unified Planning Work Program (UPWP)
for a minimum 30 public review and comment period. (Greg Venable)
Information Summary Attachments Yes No
The Draft 2016-2017 UPWP is the work plan for the MPO for the upcoming fiscal year.
As part of the Public Participation Policy for the MPO the Draft UPWP must be available
for a minimum 30 day public review and comment period. At the conclusion of the
comment period a public hearing will be held at a regularly scheduled TAC meeting. The
public comment period provides time for the TAC and the general public to review the
document and make comments to MPO staff. Information will be provided at the TAC
meeting.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
6
TAC
Meeting
Meeting Date 1/26/2016 Agenda Item No. 3
Action Requested Approve
Section Tab
Consideration of amendments to the 2016-2025 Metropolitan Transportation
Improvement Program. (Greg Venable)
Information Summary Attachments Yes No
The amendments and resolution are included in your packet for review.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
7
High Point RESOLUTION
AMENDING THE 2016-2025 HIGH POINT METROPOLITAN
TRANSPORTATION IMPROVEMENT PROGRAM
Archdale WHEREAS, the Transportation Advisory Committee has reviewed the current
2016-2025 Metropolitan Transportation Improvement Program and found an
amendment is necessary; and
Denton
WHEREAS, the following amendments have been proposed:
Jamestown
ADDITIONS
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
Randolph
County
8
MODIFICATIONS
High Point
Archdale
Denton
Jamestown
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
9
High Point
Archdale
NOW THEREFORE, be it resolved by the Transportation Advisory Committee
for the High Point Metropolitan Planning Organization that the 2016-2025
Denton Metropolitan Transportation Improvement Program be amended as listed above
on this the 26th day of January 2016.
Jamestown A motion was made by TAC Member ______________and seconded by TAC
member _______________ and approved this the 26th day of January 2016.
_________________________
Lexington
Neil Grimes
Chairman, Transportation Advisory Committee
Thomasville
Subscribed and sworn to me this the 26th day of January 2016.
Trinity ______________________________________
Notary Public
Wallburg My commission expires ______________________
Davidson
County
10
TAC
Meeting
Meeting Date 1/26/2016 Agenda Item No. 4
Action Requested Information
Section Tab
Update of NCDOT Project Prioritization 4.0 (SPOT 4.0). (Greg Venable)
Information Summary Attachments Yes No
Update on SPOT 4.0 projects.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
11
TAC
Meeting
Meeting Date 1/26/2015 Agenda Item No. 5-10
Action Requested Information
Section Tab
Agency Reports
Information Items Attachments Yes No
Agenda Item 5
NCDOT Board of Transportation Report (Cheryl McQueary – NCDOT Division 7 Board
Member)
Agenda Item 6
Division 7 – (Mike Mills)
Division 8 – (Darius Sturdivant)
Division 9 – (Pat Ivey)
Agenda Item 7
Triad Air Awareness (Lorelei Elkins)
Agenda Item 8
Transportation Planning Branch Report (Wayne Davis)
Agenda Item 9
Hitran (Angela Wynes)
Agenda Item 10
PART Report (Scott Rhine)
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
12
January 7, 2016
Project Update – Division 7
Cheryl McQueary, Board Member
Mike Mills, PE, Division Engineer
Division 7 Team
13
Division 7 - Stats
• Employees - 540 Permanent
• Road Miles - 5,417
• Bridges - 1,032
• Airports - 3
• Rail Stations - 3
• Interstates - 4
• Welcome Centers -1
• Population - 893,348
14
Transportation
Division 7 2012-2025 STIP Summary
• Highway 117 projects $ 973 million
• Aviation 8 projects $ 64 million
• Bike/Ped 9 projects $ 28 million
• Rail 2 projects $ 8 million
• Transit 72 projects $ 508 million
• Total: 208 projects $1.580 billion
• Programmed amounts include all sources
15
Transportation
Aviation
• Piedmont International (PTI)
• Cessna
• Federal Express
• HAECO
• Honda Aircraft
• Burlington-Alamance
• GE Honda Aero Engines
• Rockingham
16
Transportation
PTI Airport
17
Transportation
Honda Aircraft
18
Transportation
HAECO America
Airframe Service
• Global MRO
• 600,000 sq ft facility
• 3 wide-body hangers
1 narrow-body hanger
• 1600 employees in
Triad
• Adding 200 employees
in High Point facility
• Adding 177,000 sq ft
facility at PTI with
400 employees
19
Transportation
Greensboro
Highway Projects
• 4 projects shown on map
- Widening of US-220
- Western Loop
- Reroute of Bryan Blvd
- Connecting NC 68 and
US 220
• Eastern Loop
20
Transportation
PTI Airport
• Rerouting Bryan
Blvd connecting to
NC 68
• Beginning of NC
68 to US 220
Connector
21
Transportation
Greensboro
Urban Loop
• Lower half of the
Loop is completed
(black line)
• Western end is under
construction (blue
line)
• Eastern end is under
construction (green
line)
• Northern end in two
parts (orange and red
lines)
22
Transportation
Greensboro Loop -
Western End
• 5 miles in length,
• 6 bridges
• $123 Million investment
• Began Construction in
October 2013
• Open to Traffic
September 2017
• One of the longest bridge
spans over a wetland in
NC
• Span is approx. 0.8 miles
in length
23
Transportation
Greensboro Loop
- Eastern End
• 5 miles in length
• 14 bridges
• $112 Million
investment
• Began Construction
July 2014
• Open to Traffic July
2018
24
Transportation
NC 220 North
Widening
• 13 miles, 11 bridges
• $96 Million investment
• Began Construction
April 2012
• Open to Traffic
December 2016
25
Transportation
Caswell County –
Intersection at NC 86
& Walter’s Mill Road
• $243,000 investment
• Begin Construction
June 2016
• Operational August
2016
26
Transportation
NC 119 Bypass
A and B Sections
• 4.2 miles in length
• $ 106 investment
• Began Section A ROW in 2014
• Begin B Section in 2020
• Ready for traffic Section A in
2020
• Ready for traffic Section B 2024
27
Transportation
NC 119 Bypass,
Mebane
• North Carolina Industrial
Center
• 600 Acres in Park
• 250 Acres Developed
• Economic Impact:
• 1,000 Jobs
• $ 150 million tax value
28
Transportation
Widening of I-40,
Orange County
• Approximately 11 miles
• $88 Million investment
• Begin ROW in 2021 for
interchanges
• Construction in 2023
• Completion expected
2026
• This goes from I-85 in
Orange County to US
15-501 in Durham
County.
29
Transportation
Piedmont Improvement Projects
30
Transportation
McLeansville Road
Grade Rail Project
• Grade Separation
and Highway
Improvements
• $7.4 Million
investment
• Began construction
November 2014
• Completion
February 2017
31
Transportation
Bike and Ped
• #1 Bike and Ped
Statewide project
• 4 mile path
• P3 project between
City of Greensboro
and Action
Greensboro
• $171.4 M planned,
underway and
completed economic
development
32
Transportation
Downtown Greensboro Greenway
33
Transportation
Downtown Greensboro Greenway
34
Transportation
Honda Aircraft Type Certification Event
• http://cfvod.kaltura.com/p/970021/sp/97002100/thumbnail/entry_id/0_6zzy
3tk9/version/100012/acv/422/width/903/height/516
35
Transportation
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO
TIP/WBS # Description Let Date Completion Date Status Cost Comments
Design and bid
Small Construction.
document
Install pedestrian improvements on SR 1009 (N. Main Street) at M.A. w/ City, Signal
preparation in
43250 Lexington Avenue (WCR, pedestrian signal heads, traffic Mar. 2016 Spring 2016 $140,000 plans submitted for
progress by City,
islands) Division Traffic
City addressing
review and approval.
signal comments
U-2412A R/W plans
SR 1486 (Greensboro Road) / SR 4121 (High Point Road),
34802.2.2 complete, STIP, Programmed
Widening (part on new location) from SR 4228 (Vickrey Chapel FY 2019 FY 2022 $51,900,000
34802.2.6 Acquisition -% due to HB97
Road) to I-74/US 311 Bypass
34802.3.3 complete?
Planning and
U-4758 Design activities
Improvements to Johnson Street/Sandy Ridge Road from Skeet
40251.2.1 7/16/19 FY2022 underway, R/W $18,300,000 STIP
Club Road to I-40
40251.3.1 plans complete
7/21/2017
Central Design in
progress, Public
U-5169
I-74/US 311 and NC 68 (Eastchester Drive) interchange workshop early
45220.2.1 6/19/18 FY 2019 $15,775,000 STIP
improvements 2016, R/W
45220.3.1
plans complete
6/17/16
Utility Relocation System
17BP.7.R.22 Bridge #895 on SR 1486 (Lexington Ave.) over Bouldin Branch Spring 2016 Summer 2016 in progress, R/W $577,000 Preservation, M.A.
Certified executed
Design in
B-5358
progress, R/W
46072.1.1 STP funds, LAP,
Replace Bridge #428 on Model Farm Rd over Richland Creek 9/30/16 Summer 2017 plans complete; $1,050,000
46072.2.FD1 City match
City acquiring
46072.3.FD1
R/W
36
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO
TIP/WBS # Description Let Date Completion Date Status Cost Comments
Design and bid
I-5767
Pavement Rehabilitation: I-74/US-311 from 0.7 miles East of I- package
53010.3.1/ NHPP - Interstate
40 to the Guilford /Forsyth County Line to SR1300 (E. Green 2/16/16 Summer 2017 submitted to $20,600,000
I-5736 Maintenance
Drive) Raleigh - 100%
52018.3.1
complete
Design and bid
I-5821
package
50464.3.1/ Pavement Rehabilitation: I-85 from 0.4 miles South of I-85 NHPP - Interstate
4/19/16 Summer 2017 submittal to $9,900,000
I-5789 Business to Randolph County Line Maintenance
Raleigh-25%
53029.3.1
Complete
Design and bid
I-5734
package
52010.3.1/ Pavement Rehabilitation: I-40 from 1.1 miles East of SR 1556 NHPP - Interstate
3/15/16 Summer 2017 submitted to $9,664,000
I-5762 Gallimore Dairy Rd to Forsyth County Line Maintenance
Raleigh - 100%
53005.3.1
complete
37
Contract Number: C202881 Route: SR-4121
Physical Division: 7 County: Guilford
TIP Number: U-2412B, U-2524AE
Length: 4.836 miles Federal Aid Number: NHS-124-1(17)
Resident Engineer: Paul Ingram, PE RE Phone Number: (336)487-0150
Location Description: SR-4228 (VICKERY CHAPEL RD) TO SR-1424 (HILLTOP RD); GREENSBORO
WESTERN LOOP INTERCHANGE AT HIGH POINT RD.
Type of Work: GRADING, DRAINAGE, PAVING, SIGNALS, AND STRUCTURES.
Contractor Name: APAC - ATLANTIC, INC. THOMPSON ARTHUR DIVISION
Contract Amount: $40,094,959.99 Cost Overrun/Underrun: 0%
Availability Date: 10/01/2012 Letting Date: 08/21/2012
Completion Date: 05/13/2016 Work Began: 10/05/2012
Estimated Completion: 07/27/2016
Scheduled Progress: 99.5%
Actual Progress: 82.92%
Contract Number: C203237 Route: US-70
Physical Division: 7 County: Guilford
Length: 0 miles Federal Aid Number:
Resident Engineer: Kris Lorenz, PE RE Phone Number: (336)487-7080
Location Description: BRIDGE #217, 259 & 274 ON US-220 AND #1, 136 & 470 ON SR-2254 (WENDOVER AVE).
Type of Work: CLEANING & PAINTING OF BRIDGE STRUCTURES.
Contractor Name: ASTRON GENERAL CONTRACTING COMPANY INC
Contract Amount: $1,274,112.00 Cost Overrun/Underrun: 0%
Availability Date: 06/01/2013 Letting Date: 02/19/2013
Completion Date: 09/28/2013 Work Began: 06/14/2013
Estimated Completion: 04/30/2014
Scheduled Progress: 100%
Actual Progress: 82.31%
Contract Number: C203256 Route: SR-1820
Physical Division: 7 County: Guilford
TIP Number: U-3615B
Length: 3.388 miles Federal Aid Number: STP-1820(5)
Resident Engineer: Paul Ingram, PE RE Phone Number: (336)487-0150
Location Description: SR-1820 (SKEET CLUB RD) FROM EAST OF SR-1818 (JOHNSON ST) TO WEST OF NC-
68 (EASTCHESTER DR) IN HIGH POINT.
Type of Work: GRADING, DRAINAGE, PAVING, SIGNALS & STRUCTURES.
Contractor Name: APAC - ATLANTIC, INC. THOMPSON ARTHUR DIVISION
Contract Amount: $30,898,017.15 Cost Overrun/Underrun: 0%
Availability Date: 03/02/2015 Letting Date: 01/20/2015
Completion Date: 03/29/2019 Work Began: 05/20/2015
Scheduled Progress: 0%
Actual Progress: 0.33%
Contract Number: C203433 Route: I-73
Physical Division: 7 County: Guilford
TIP Number: I-5110, I-5110A, R-2413A, R-2413B
Length: 9.4 miles Federal Aid Number:
Resident Engineer: Brian V. Smith RE Phone Number: (336)375-1774
Location Description: FUTURE I-73 FROM EXISTING SR-2085 (JOSEPH M BRYAN BLVD) / AIRPORT PKWY
INTERCHANGE TO SOUTH OF US-220 NEAR HAW RIVER.
Type of Work: DESIGN BUILD.
Contractor Name: FLATIRON CONSTRUCTORS, INC. BLYTHE DEVELOPMENT CO JOINT VENT
Contract Amount: $176,550,000.00 Cost Overrun/Underrun: 0%
Availability Date: 05/07/2014 Letting Date: 04/03/2014
Completion Date: 04/25/2017 Work Began: 05/07/2014
Scheduled Progress: 44.13%
Actual Progress: 45.38%
38
Contract Number: C203640 Route: -
Physical Division: 7 County: Guilford
Length: 0.431 miles Federal Aid Number:
Resident Engineer: Kris Lorenz, PE RE Phone Number: (336)487-7080
Location Description: REPLACEMENT OF 4 BRIDGES IN GUILFORD COUNTY AND 3 BRIDGES IN
ORANGE COUNTY.
Type of Work: DESIGN BUILD.
Contractor Name: HAYMES BROTHERS, INC.
Availability Date: 06/01/2015 Letting Date: 04/21/2015
Completion Date: 11/01/2017 Work Began:
Scheduled Progress: 0%
Actual Progress: No work at this time
Contract Number: C203641 Route: SR-2719
Physical Division: 7 County: Guilford
Length: 0.685 miles Federal Aid Number:
Resident Engineer: Chris Kirkman RE Phone Number: (336)570-6830
Location Description: REPLACEMENT OF 5 BRIDGES IN GUILFORD COUNTY AND 5 BRIDGES IN
ORANGE COUNTY.
Type of Work: DESIGN BUILD.
Contractor Name: R.E. BURNS & SONS CO., INC.
Contract Amount: $5,940,323.00 Cost Overrun/Underrun: 0%
Availability Date: 06/01/2015 Letting Date: 04/21/2015
Completion Date: 11/01/2018 Work Began: 06/01/2015
Scheduled Progress: 9%
Actual Progress: 13.91%
Contract Number: DG00219 Route: SR-2509
Physical Division: 7 County: Guilford
Length: 10.993 miles Federal Aid Number:
Resident Engineer: Paul Ingram, PE RE Phone Number: (336)487-0150
Location Description: Resurface SR 3093, SR 3029, SR 2826,SR 2732 AND SR 2509
Type of Work: WIDEN AND RESURFACE
Contractor Name: BLYTHE CONSTRUCTION, INC.
Contract Amount: $1,065,598.39 Cost Overrun/Underrun: 0%
Availability Date: 03/30/2015 Letting Date: 10/16/2014
Completion Date: 11/20/2015 Work Began: 07/20/2015
Scheduled Progress: 0%
Actual Progress: 80.37%
Contract Number: DG00260 Route: NC-22
Physical Division: 7 County: Guilford
Length: 12.856 miles Federal Aid Number:
Resident Engineer: Kris Lorenz, PE RE Phone Number: (336)487-7080
Location Description: NC 22 FROM THE RANDOLPH COUNTY LINE TO NC 62 TO JOINT NORTH OF SR
1486 (LEXINGTON AVENUE)
Type of Work: MILLING AND RESURFACING
Contractor Name: SHARPE BROTHERS A DIV OF VECELLIO & GROGAN, INC.
Availability Date: 04/15/2016 Letting Date: 07/16/2015
Completion Date: 11/15/2016 Work Began:
Scheduled Progress: 0%
Actual Progress: No work at this time
39
Contract Number: DG00261 Route: NC-22
Physical Division: 7 County: Guilford
Length: 5.217 miles Federal Aid Number:
Resident Engineer: Paul Ingram, PE RE Phone Number: (336)487-0150
Location Description: A PORTION OF SR 1001, SR 1008, SR 3163 AND SR 2851
Type of Work: MILLING AND RESURFACING
Contractor Name: APAC - ATLANTIC, INC. THOMPSON ARTHUR DIVISION
Availability Date: 04/15/2016 Letting Date: 07/16/2015
Completion Date: 11/15/2016 Work Began:
Scheduled Progress: 0%
Actual Progress: No work at this time
Contract Number: DG00262 Route: -
Physical Division: 7 County: Guilford
Length: 0.098 miles Federal Aid Number:
Resident Engineer: Kris Lorenz, PE RE Phone Number: (336)487-7080
Location Description: REPLACE BRIDGE NUMBER 338 ON SR 1859 (BOYLSTON ROAD) OVER WEST
FORK OF DEEP RIVER (TRIBUTARY 1)
Type of Work: REPLACE BRIDGE NUMBER 338 IN GUILFORD COUNTY
Contractor Name: SMITH-ROWE, LLC
Availability Date: 02/01/2016 Letting Date: 08/06/2015
Completion Date: 03/01/2017 Work Began:
Scheduled Progress: 0%
Actual Progress: No work at this time
Contract Number: DG00265 Route: -
Physical Division: 7 County: Guilford
Length: 31.1 miles Federal Aid Number:
Resident Engineer: Jason Julian RE Phone Number: (336)634-5635
Location Description: 39 SECONDARY ROADS IN GUILFORD COUNTY AND ONE SECONDARY ROAD IN
ROCKINGHAM COUNTY
Type of Work: AST RETREATMENT
Contractor Name: WHITEHURST PAVING CO INC
Availability Date: 04/15/2016 Letting Date: 10/15/2015
Completion Date: 08/31/2016 Work Began:
Scheduled Progress: 0%
Actual Progress: No work at this time
40
DIVISION 8 - ACTIVE PROJECTS (HIGH POINT MPO)
TIP/WBS/ Completion
Description Let Date Status Cost Contractor Comments
Contract # Date
SR 1009 Main Street at SR 1681 Balfour Drive/SR 1911
APAC-
Ashland Street in Archdale. Construct high visibility Contract also includes ER-
Atlantic, INC.
crosswalks and install pedestrian signals. Construct 36% 2971H, Sidewalk project in
DH00175 7/30/15 6/24/16 $1,398,521 Thompson
sidewalk from Ashland Street to Pinecrest Drive. Includes Complete Mt. Gilead - Montgomery
Arthur
resurfacing SR 1567, SR 1545, SR 1597, SR 1794, SR County. Work began 10/7/15
Division
1850 and SR 1864
Replace culverts #97 and # 31 on US 311 Business.
Culvert #97 over Sycamore Creek south of SR 1930 73% Country Boy
DH00171 6/9/15 5/11/16 $707,777 Work began 7/7/15
Bronzie Lawson Road and culvert #31 over Bob's Branch Complete Landscaping
north of SR 1527 Marlboro Church Road.
Asphalt Surface Treatment: SR 1916, SR 2039, SR 1697, 51% Riley Paving
DH00172 6/9/15 $867,269 Work began 9/18/15
SR 1685 and SR 1536 Complete INC
SR 1619 Prospect Street - Replace Bridge #136 over US 33% Lee
B-5114 6/16/15 3/15/17 $4,714,965 Work began 8/7/15
29/70/I-85 Business. Complete Construction
DIVISION 8 - ACTIVE SPOT SAFETY PROJECTS (HIGH POINT MPO)
Project Description Board Approval Date Cost Status
NC 62 at SR 1547 Finch Farm Rd - Upgrade the traffic signal to Flashing
Yellow Arrow (FYA) and restripe the northbound left turn lane to improve the 9/3/2015 $75,000 Signal plans are complete
offset.
SR 1004 Trinity Rd at SR 1577 Archdale Rd - Upgrade the traffic signal to
9/3/2015 $10,000 Signal plans are complete
Flashing Yellow Arrow (FYA)
DIVISION 8 - UPCOMING PROJECTS (HIGH POINT MPO)
TIP/WBS/ Completion
Description Let Date Status Cost Contractor Comments
Contract # Date
I-73 Pavement Rehabilitation from US 311 to 0.6 mi North
of SR 1938 Hockett Dairy Road; 7.7 miles - Combined with I- No ROW needed; No utilities
5737: I-73 from 1.3 miles north of SR 1504 Spero Road to to be relocated. NCDOT-BOT
I-5763 Jan-16 TBD TBD $8,978,000 TBD
US 311, 2.2 miles) and Combined with W-5601AJ: I- approved funds January
73/74/US 220 from south of SR 2269 Vision Drive to south 2016.
of SR 1712 Pineview Road.
I-85 South of SR 1009 to North of SR 1912 Lunar Drive in
Archdale. Pavement Rehabilitation. Scope of work should
No ROW needed; No utilities
I-5738 include milling and filling of deteriorating asphalt paved Mar-16 TBD TBD $7,000,000 TBD
to be relocated.
shouders, rehabilitation of ramps and rehabilitation of
concrete aprons around drainage structures.
SR 1404 Fuller Mill Road - Replace Bridge # 58 over an All Environmental permits
B-5128 Mar-16 TBD TBD $733,000 TBD
unnamed Tributary of the Little Uwharrie River. have been received
ROW has been recorded.
SR 1603 School Rd - Replace Bridge #84 over Muddy
17BP.8.R.79 Jan-18 TBD TBD Not Available TBD Power and cable utilities have
Creek
been relocated.
ROW is being acquired;
Utilities to be relocated;
SR 1911 Ashland Street (Archdale) - Replace Bridge #416
17BP.8.R.76 Jun-18 TBD TBD Not Available TBD Power is authorized to move;
over Dale Creek.
Relocation of water lines to
be determined.
41 High_Point_Urban_Area_MPO Div 8 Project Report January 2016
High Point Urban Area MPO/Piedmont Triad RPO
NCDOT Transportation Update
(Davidson County)
Tuesday, January 19, 2016
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects under Construction
Replace Bridge #27 on US 52/NC 8 over US 29/64/70/I- May 1, 2018 Availability date
B-3159 Oct. 20, 2015 (Oct. 28, 2019 $10,164,621 J.T. Russell & Sons, Inc. Utility relocation work is underway
85 Bus. Loop in Lexington perm. vegetation established)
April 1, 2016
June 15, 2016 Work start date April 6, 2015. Traffic is now on new structure in
Replace Bridge #38 on SR 1493 (Frye Bridge Rd) over (Perm. vegetation 85% Complete
B-4741 Dec. 16, 2014 $2,333,794 Dane Construction, Inc. final traffic pattern. Road to remain open during
Muddy Creek in Davidson County established (20% ahead of schedule)
Dec. 12, 2016) construction,with new bridge being built next to existing.
June 15, 2016
(Perm. vegetation 98% Complete Work is ongoing on new bridge - roadway to stay open.
C-4901A NCRR/NS Mainline Bowers to Lake Railroad Roadbed June, 2013 $15,738,016 Blythe Construction, Inc.
established (12% ahead of schedule) Minimal to no impact to vehicular traffic.
Oct. 28, 2016)
Contract Landscaping on I-85 from (SR 1224)
Approx. 17% Contractor began work on Nov. 3, 2015. Currently planting
I-2304AC/AD (L) Hardgrave Rd in Davidson Co. to (SR2120) Long Ferry Sept. 23, 2015 May 6, 2018 $1,281,336 Staniel Key Landscaping
Complete trees.
Rd in Rowan Co.
DDRL Project -Traffic shifted NB outside lane, north of Green
Pavement Rehabilitation, Bridge Preservation, and February 1, 2016 Needles Rd, on 1/6/16. Median crossover will be removed and
Upgrade to Interstate Standards - US 29/52/70/I-85 Bus. (revised) 89.7% Complete inside NB/SB lanes will be paved and Marco Blvd (weather
R-4750 From I-85 to south of SR 1147 (Salisbury Rd) and September, 2013 (Perm. vegetation (schedule has been $7,571,155 J. T. Russell & Sons, Inc.
revised)
permitting). Prime contractor will be complete by end of
Bridges #43 & #225 over Swearing Creek on US established
June 4, 2016) January, except pavement markings and rumble strips (mid-
29/52/70.
March 2016).
Replace Bridge #361 on SR 1837 (Bud Sink Rd) over Leonard 110 days Availability date Completion of project to be 110 calendar days (May 8 - June
(perm. vegetation
BD-5109L Creek in Davidson County. Includes Grading, Drainage, Dec. 9, 2015 Jan. 19 - Feb. 29, $378,498 TCB Builders, LLC 18, 2016) from established availability date (Jan. 19 - Feb. 29,
established by
Widening, Structure, Paving, and Pavement Markings. 2016 2016).
Dec. 31, 2016)
June 23, 2016
Replace Bridge #40 on SR 1298 / I-85 Service Rd (perm. vegetation 10.6% Complete Work began December 7, 2015. Road is closed with off-site
17.BP.9.R.3 October 28, 2015 $830,623 Smith-Rowe LLC
(Grimes Blvd) over Swearing Creek in Davidson County. established (on schedule) detour.
Dec. 9, 2016)
Design Build Project - (Dvdsn Co) Bridge #235 (Hedrick Mill)
Rehabilitation and bridge beam painting of (4) bridges in
complete; #303 (Ball Rd) complete; #431 (Old 64) complete;
17BP.9.R.34 Davidson Co., (1) in Forsyth Co., (3) in Rowan Co., and April, 2012 Oct. 20, 2016 91.5% Complete $12,585,775 Crowder Construction Co.
#424 (E Center St) work to start on Oct. 24, 2015 and
(1) in Stokes Co.
projected to complete Oct. 20, 2016.
Permitting and Express Design Build Contract - Br. #258 over Swearing
DESIGN BUILD - Replace two (2) Bridges in Davidson
design work begun Creek on SR 1272, and Br. #410 over Leonard Creek on SR
17BP.9.R.61 Co., one (1) Bridge in Davie Co., three (3) Bridges in May 19, 2015 June 30, 2019 $10,642,621 Smith-Rowe, LLC
(Anticipate construction work 1844 in Davidson; (1) bridge in Davie; (2) bridges in Rowan;
Rowan Co., and four (4) Bridges in Stokes Co. to begin Summer, 2016) and (4) bridges in Stokes Co.
Permitting and Express Design Build Contract - Br. #86 over First Potts Creek
Mountain Creek
DESIGN BUILD - Replace three (3) Bridges in Davidson design work begun on SR 1158, Br. #95 over Leonard Creek on SR 1838, and Br.
17BP.9.R.62 May 19, 2015 September 1, 2018 $4,740,000 Contractors/SEPI
Co. and seven (7) Bridges in Rowan Co. with Culverts (Anticipate construction work #471 over Unnamed Creek on SR 2416 in Davidson Co. and
to begin Spring, 2016)
Engineering
(7) bridges in Rowan Co.
Milling and resurfacing of 3.8 miles of US 64 from RR
2016CP.09.01. Availability date Division Let contract. Continuation of previous resurfacing
crossing near Decker Rd. to the end of concrete island Aug. 12, 2015 May 20, 2016 $1,035,588 J.T. Russel & Sons, Inc.
10291.1 Sept. 21, 2015 map. Work scheduled to begin after March 15, 2016.
near Linda Pl., just W. of I-85.
Contract Resurfacing of 2 sections of NC 8, 1 section of
9CR.10291.160, May 25, 2016 Work began August 3, 2015. Work over the next few months
US 64, 1 section of NC 68 and 8 sections of Secondary May 19, 2015 25.6% Complete $3,755,440 J.T. Russell & Sons, Inc.
9CR.20291.160 (revised) will be limited by temperatures.
routes (20.54 miles) in Davidson County.
Davidson County Asphalt Surface Treatment (AST) Preconstruction meeting held Aug. 19, 2015. Work began
9SP.20295.4 Retreatment (58.79 miles) of various Secondary routes June 10, 2015 May 20, 2016 50% Complete $1,455,996 Blythe Construction, Inc. Sept. 22, 2015. Seasonal limitations in force currently, plan to
in Davidson Co. start back in April, 2016.
42
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects under Development
Bridge Preservation project - Plans are currently being
Bridge Preservation – Bridge #31 on NC 8, Bridges #55 revised. Bridge #55 will be dropped from this contract and
41665.6A TBD TBD $1,600,000 TBD
& 82 on NC 47 in Davidson County completed under another project at a later date. Finalizing
structure plans.
Replace Bridge #42 on SR 1485 (Hampton Rd) over ROW
B-5165 FY 2017 TBD $1,800,000 TBD *Schedule based on Approved 2016-2025 STIP
Muddy Creek FY 2016
Replace Bridge #115 on SR 1711 (Gumtree Rd) over ROW
B-5765 FY 2021 TBD $1,700,000 TBD *Schedule based on Approved 2016-2025 STIP
WSSB RR FY 2019
Replace Bridge #25 on SR 3346 (S. Main St) over ROW
B-5773 FY 2025 TBD $3,250,000 TBD *Schedule based on Approved 2016-2025 STIP
WSSB RR in Lexington FY 2023
Replace Bridge #99 on SR 1810 (Clodfelter Rd) over ROW *Schedule based on Approved 2016-2025 STIP - Project
B-5774 FY 2020 TBD $1,200,000 TBD
Brushy Creek FY 2019 accelerated due to additional revenue (HB 97)
Replace Bridge #100 on SR 1810 (Clodfelter Rd) over ROW *Schedule based on Approved 2016-2025 STIP - Project
B-5776 FY 2020 TBD $1,800,000 TBD
Abbott's Creek FY 2019 accelerated due to additional revenue (HB 97)
ROW
B-5777 Replace Bridge #58 on NC 109 over US 64 FY 2022 TBD $1,850,000 TBD *Schedule based on Approved 2016-2025 STIP
FY 2021
Replace Bridge #118 on US 29NB/64EB/70EB/I-85 Bus ROW *Schedule based on Approved 2016-2025 STIP - Coordinate
B-5779 FY 2025 TBD $4,061,000 TBD
NB over SR 3346 (N Main St) in Lexington FY 2024 with B-5785
ROW Acquisition in
B-5780 Replace Bridge #17 on NC 47 over Swearing Creek FY 2017 TBD $1,400,000 TBD
progress
Replace Bridge #164 and Bridge #168 on US 29/70/I-85 ROW
B-5783 FY 2025 TBD $5,778,000 TBD *Schedule based on Approved 2016-2025 STIP
Bus over NSRR FY 2024
Replace Bridge #121 and Bridge #122 on US 29/70/I-85 ROW *Schedule based on Approved 2016-2025 STIP - Coordinate
B-5785 FY 2025 TBD $4,000,000 TBD
Bus over Leonard Creek FY 2024 with B-5779
ROW
B-5787 Replace Bridge #29 on NC 49 over NC 109 FY 2024 TBD $2,000,000 TBD *Schedule based on Approved 2016-2025 STIP
FY 2023
Extend Sidewalks on SR 3346 (S Main St) and provide Planning/Design/
Construction by City of
C-5216 wide paved shoulders on Anna Lewis Dr and Emergency FY 2016 TBD Right of Way in $601,000 *Schedule based on Approved 2016-2025 STIP
Lexington
Dr. in Lexington progress
Provide wide paved shoulders and construct sidewalks Planning/Design/
Construction by City of
C-5217 on Cornelia St and Hillsdie Dr. Bike and Pedestrian FY 2016 TBD Right of Way in $190,000 *Schedule based on Approved 2016-2025 STIP
Lexington
Improvements on Mize and Biesecker Rds. progress
Pavement Rehabilitation of I-85 from SR 2025 (Squire Planning and Design
I-5793 FY 2018 TBD $6,386,000 TBD *Schedule based on Approved 2016-2025 STIP
Bowers Rd) to 0.3 mi N. of NC 109 in Thomasville in Progress
Pavement Rehabilitation of I-85 from 1.7 mi N of SR
I-5740 Feb., 2016 TBD $200,000 TBD *Schedule based on Approved 2016-2025 STIP
2205 (Old US 64) to 0.3 mi N of US 64
NC 109 from SR 1756 (Old Greensboro Rd) in Davidson
R-2568C *Post Year TBD Planning and Design $129,000,000 TBD *Schedule based on Approved 2016-2025 STIP
County to I-40/US 311 in Forsyth County.
Convert at grade intersection to Interchange on US ROW Acquisition
R-5737 FY 2021 TBD $15,000,000 TBD *Schedule based on Approved 2016-2025 STIP)
29/70/I-85 Bus at SR 1798 (Old Greensboro Rd) FY 2019
SS-4909AH Install left turn lane on Hickory Tree Rd (SR 1508) near
Jan., 2017 TBD $660,000 TBD To be advertised Feb. 3, 2016, expected to let in Feb., 2016.
U-4742NC Mendenhall Road in Davidson County.
Widen NC 8 (Winston Rd) to multi-lanes from 9th St to Planning and Design
U-5757 FY 2019 TBD $1,254,000 TBD *Schedule based on Approved 2016-2025 STIP
SR 1408 (Biesecker Rd) in Lexington in Progress
Widen SR 1508 (Hickory Tree Rd) from US 52/NC ROW
U-5786 FY 2023 TBD $13,794,000 TBD *Schedule based on Approved 2016-2025 STIP
8/Future I-285 to NC 150 FY 2021
U-5902 / Widen NC 150 to multilanes from US 64 (SR 1493, Frye ROW & Utilities *Schedule based on Approved 2016-2025 STIP - New
Post Year TBD $33,150,000 TBD
U-5902B Bridge Rd) to Forsyth County Line FY 2024 project programmed due to additional revenue (HB 97)
Safety Improvements to median crossovers, etc., on I-85
ROW Division Let. Public meeting scheduled for Jan. 14, 2016 at
W-5601CF Business from SR1797 (Evans Rd) to SR 1963 (Moose January , 2017 TBD $600,000 TBD
June 2016 Davidson County Community College.
Lodge Rd) in Davidson Co.
43
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects Under Development
Bridge Painting on Bridges #136, 150 in Davidson;# s
Funding issues. There will be plan revisions and a new letting
17BP.9.P.3 29,32,85,86 in Davie; #'s 53,54,55,78,115,185,297,322 TBD TBD $5,000,000 TBD
date - to be determined.
in Forsyth; and #94 in Rowan County
Letting date delayed due to funding and other priorities.
Replace Bridge #271 on SR 2501 (S. Main St. Ext./ Lick ROW Acquisition
17.BP.9.R.10 FY 2016 TBD $1,000,000 TBD Coordinating with ALCOA to begin construction. Utility
Creek Ch. Rd) over Lick Creek in Davidson County. in progress.
relocation in progress
Replace Bridge #221 on SR 2324 (Harris Rd) over Lick Plan Preparation 75% Complete; Let date is funding
17.BP.9.R.15 TBD TBD $525,000 TBD
Creek in Davidson County. dependent
Replace Bridge #459 on SR 2160 (Smith Rd) over an
17BP.9.R.33 FY 2016 TBD $250,000 TBD Letting date delayed due to funding and other priorities.
unnamed creek in Davidson County.
Replace Bridge #504 on SR 2522 (Handy Rd) over Project will be dropped due to funding changes and Division re-
17BP.9.R.53 TBD TBD $400,000 TBD
Branch Cabin Creek in Davidson County. prioritization.
Replace Bridge #555 on SR 2185 (Julian Ave) over N. Project will be dropped due to funding changes and Division re-
17BP.9.R.54 TBD TBD $500,000 TBD
Hamby's Creek in Davidson County. prioritization.
Replace Bridge #63 on SR 1481 (Welcome-Arcadia Rd)
17BP.9.R.57 TBD TBD $443,000 TBD
over Reedy Creek in Davidson County.
9CR.10291.161 Contract Resurfacing of various sections of Primary and
April, 2016 TBD $2,600,000 TBD Centrally let
9CR.20291.161 Secondary routes in Davidson County
Completed Projects
Replace Bridge #195 on SR 2263 (John Black Rd) over April 6, 2015
17.BP.9.R.31 June 11, 2014 (Perm. vegetation 100% Complete $421,170 Smith-Rowe, LLC
Flat Swamp Creek in Davidson County. established
Davidson County Asphalt Surface Treatment (Chip Seal)
9SP.20295.3 April 8, 2015 August 28, 2015 100% Complete $1,555,785 APAC Atlantic, Inc. One year warranty in effect.
Contract
March 15, 2015
Landscaping at Bridge #39 on US 64 over US 29/70/I-85 (Perm. Vegetation Country Boy Landscaping
B-4497L Dec. 10, 2014 100% Complete $14,999
Bus in Davidson Co. established Inc.
Nov. 20, 2015)
Aug. 15, 2015
Replace Bridge #11 on SR 1155 (Swicegood Rd) over (perm. vegetation
BD-5109V Mar. 11, 2015 100% Complete $572,994 Dane Construction, Inc.
First Potts Creek in Davidson County. established
Dec. 30, 2015)
April 30, 2015
Grade separation on SR 2024 (Upper Lake Rd) over (perm. vegetation DH Griffin Construction
C-4901B March, 2013 100% Complete $4,203,035 ARRA Rail Project - Complete and accepted
Hamby Creek / NCRR established Co., LLC
Nov. 11, 2015)
44
Triad Air Awareness January, 2016
Air Quality Notes:
CMAQ 101 Training
o FHWA has released a 27 minute YouTube video on the Congestion Mitigation
and Air Quality Improvement (CMAQ) program. The video provides a basic
introduction to the program, how CMAQ funds are distributed to states, and the
types of projects eligible for the CMAQ program. The training is available at
https://www.youtube.com/watch?v=XKXcs0WtNHA&feature=youtu.be.
o For more information about the CMAQ program contact Emily Biondi at
emily.biondi@dot.gov or (202) 366-9482.
Toolkit for Electric Vehicle (EV) Infrastructure Corridor Development
o Oregon Department of Transportation initiated a pooled-fund study to assist
state and local transportation agencies interested in promoting the use of
alternative vehicle and fuel technologies
o The Deployment of Alternative Vehicle and Fuel Technologies initiative utilizes
a series of workshops around the country to develop a web-based “toolkit” for
state and local transportation agencies. It provides resources and information to
support plug-in electric vehicle (EV) adoption through EV charging
infrastructure development along travel corridors.
o The toolkit is comprised of two components: Resource Library and Workshop
Materials. Additional toolkits will be developed for future workshops conducted
for this initiative. It can be found at: http://altfueltoolkit.org/ev-infrastructure-
corridor-development-toolkit/.
Commuter Dash
o Saturday April 16th Triad Air Awareness & PART will hold the Commuter Dash
fun run/walk to raise awareness about the link between transportation and air
quality. The free race will be held at Triad Park. For questions or if you’re
interested in sponsoring the event, please contacted Lorelei Elkins at
elkinslt@forsyth.cc
Transportation Resources Lunch & Learn
o Wednesday January 27th from 11:30 to 1:00 PM (Lunch included, registration
required.) Register here:
http://events.r20.constantcontact.com/register/event?oeidk=a07ebwzpyhie3db41
1a&llr=iudiftcab
45
AQI
10 20 30 40 50 60 70 80 90 100 110
1/1
1/15
1/29
2/12
2/26
3/12
Air Quality Report:
3/26
4/9
4/23
5/7
5/21
6/4
46 6/18
Ozone
7/2
7/16
PM2.5
7/30
8/13
2015 Ozone and PM2.5
8/27
9/10
9/24
10/8
10/22
11/5
11/19
12/3
12/17
12/31
Piedmont Authority for Regional Transportation Updates
for the High Point MPO TCC/TAC
January 2016
PART Express Updates
Route Adjustments Planned for 1/11/16
Route 3 Adjustment: Effective 1/11/16 High Point
Express will begin serving Palladium Shopping Center
on Samet Drive by the movie theater entrance. High
Point Express will no longer serve the Oak Hollow
Mall. Riders can still access the Oak Hollow Mall area
by departing the bus at Eastchester & Centennial.
Route 9 Route Adjustment: Route 9 Business 85
Express will be adjusted 1/11/16 providing more
service & frequency between Davidson County and
High Point. The route will no longer serve
Greensboro.
Shown Above: PART Express ridership was 38,405 for November
2015 with an annual projection of 500,304 for FY 2016.
To learn more about PART’s programs and projects, please
visit www.partnc.org, piedmonttogether.org &
sharetheridenc.org.
Stay Connected with PART on Social Media!
You're Invited to
Transportation Lunch & Learn
PART is hosting a FREE Transportation Resources Lunch &
Learn on Wednesday, January 27, 2016 11:30am-1:00pm.
Learn about the commuter resources for employees.
Register at www.partnc.org
Page 1 of 2
47
Page 2 of 2
PART Audit Report Reflects Coble Intermodal Center is Under
Continued Improvement Construction
Finally coming to fruition is the Howard Coble
PART has received a superior financial audit
Intermodal Transportation Center which has been
report for the third consecutive year. The PART
in the planning phase since 2005. This facility has
Financial Report, which was presented at the Nov.
been named after Congressman Howard Coble, who
11 monthly Board Meeting, showed a clean
secured the federal earmark back in 2005 and
opinion with no findings of deficiency or internal
supported the project over the years.
control findings.
Construction is underway and will take
View the full report at www.partnc.org.
approximately 12-14 months to complete, with
hopes of completing by December 2016.
New Vanpool Fleet Vehicles 6 MONTH SNAPSHOT (NOVEMBER 2015 – MAY 2016)
12 Ford Transit XLT Vanpool Vehicles have been • Construction Activity Begins
delivered to supplement increased need. PART • Site Grading & Stabilization
Vanpool now has 83 vans in the fleet.
• Foundation Poured
• Structural Steel Installation for Passenger Facility & Canopy
• Interior Framing of Passenger Facility
NEXT UP… (JUNE 2016 – NOVEMBER 2016)
• Roadwork & Widening
• Installation of Roof
• Exterior Improvements Including Landscaping, Fencing,
• and Sidewalks
• Exterior Concrete & Asphalt Work
• Final Building Construction
• GRAND OPENING!
Track your Bus LIVE! VanPOOL Corner
Join the POOL Party!