HPMPO Transportation Advisory Committee (TAC)
Regular MeetingHigh Point, NC · February 23, 2016
Minutes
Attachment 1
MINUTES
TRANSPORTATION ADVISORY COMMITTEE
February 23, 2016
TAC MEMBERS PRESENT:
Jim Myers –Lexington
Neal Grimes – Thomasville
Keith Volz – Jamestown
Bill Bencini – High Point
Larry Ward – Denton
Clyde Lynn Reece - Wallburg
Larry Warlick – Archdale
Steve Shell – Davidson County
TCC MEMBERS PRESENT: Greg Venable, Guy Cornman, Bryan Fulbright, Ed
Lewis, Chuck Smith, Mark McDonald, Jason Miller, Mark Kirstner, John Gray, Kelly
Larkins, Jen Britt, Diane Hampton, Marty Tillman, and Carrie Spencer.
OTHERS PRESENT: John Hanes (Transportation Planning), Gwen Ford (COHP),
Randy McCaslin (COHP), L.G. Cashion (Davidson County Airport), Karel Ban Der
Linden (Davidson County Airport), Lee Gill (Citizen, Wallburg), and Eddie
MacEldowney (Citizen)
RECORDING SECRETARY: Marianne Janiszewski, City of High Point
Item 1: Reading of the Ethics Statement.
Neal Grimes read the Ethics Awareness and Conflict of Interest Reminder. No one had
any conflicts.
Item 2: Public Comment Period
Neal opened up the public comment period.
Lee Gill, 580 Oaklawn Rd., spoke in opposition to the NC 109 project. H provided
several maps and diagrams to support his position.
Neal closed the public comment period.
ACTION ITEMS
Item 3: Consideration of the January 26, 2016 TAC meeting minutes.
There were no corrections to the minutes.
Motion by: Jim Myers
1
Attachment 1
Seconded: Bill Bencini
Vote:
For: Unanimous
Against: None
Item 4: Consideration to amendments to the 2016-2025 Metropolitan
Transportation Improvement Program.
There are four STIP additions and one STIP modification that are being recommended for
TAC approval. PART has some projects that he would like to include in the amendment to
the TAC. There are two projects on the list for replacement buses that are using funding
from NCDOT not the MPO. The first projects funding originated from FTA section 5339
funding which will be transferred into the 5307 program for FTA grant purposes. Funding
for the second project will go directly through NCDOT which will go through partner direct.
These grant funds need to be recorded in the local TIP. There are also two projects on the list
that are being funded through CMAQ funds which came through the HP MPO “Call for
Projects” and have already been approved by HP MPO. The first project is to implement a
new Palladium circulator in North High Point beginning in 2017. The funds will be an 80/20
split. The second project is for a replacement bus. Hi tran is also requesting replacement
busses.
Motion by: Larry Warlick
Seconded: Jim Myers
Vote:
For: Unanimous
Against: None
INFORMATION ITEMS
Item 5: SPOT 4.0 Update.
Greg reported that NCDOT has to approve all prioritization processes throughout the
State. Greg handed out a draft version that will be submitted to NCDOT. It spells out
how we are going to vote and rank projects and the criteria that will be used. This year
highway, bicycle and ped, rail, aviation and transit projects will be included. The ranking
criteria that we will use is spelled out individually for these projects and modes. The data
that is determined at the State level is taken to rank these projects. We have 36 highway
projects and whatever project is ranked number 1 will be given 100 points which will
count as 40%. This will be added to the 60% from part one of the ranking process which
2
Attachment 1
will give the overall total ranking for our priority list for SPOT 4.0. The DOT voting will
take place at the March 22 TAC meeting. The ranking criteria along with the DOT vote
will be released on March 23rd for public review and comment period. The State already
has this list and is looking it over and we are not anticipating any major changes. Each
member gets 10 dots for each mode with a maximum of 5 dots that can be placed on one
project.
Item 6: Davidson County airport Project Information.
L.G. Cashion and Karel Van Der Linden gave a presentation.
AGENCY REPORTS
Item 7: NCDOT Board of Transportation Report.
No one was present.
Item 8: Division Engineer’s Reports.
Division 7
Ed Lewis reported that the bids on the Lexington Ave. Bridge Project were rejected. The
project will be re-let next month. The Pavement Rehabilitation Project on I-74/US-311
came in 12% under the engineer’s estimate. The date of availability for this project will
be in April. Ed was asked if there has been any movement on the public meeting for the
bridge project over NC 68 and I-74. Ed reported that this project is going to be a
combination of updating everyone that lives in this area about the project and along with
that there is going to be a noise wall presentation. They hope to combine the public
involvement process for the noise wall with the public meeting.
Division 8
Jen Britt reported that Prospect St. bridge replacement project is about 34% complete.
There are two SPOT safety projects where they are upgrading the traffic signal to
flashing yellow. There is also an I-73 pavement rehabilitation project underway.
Division 9
Diane Hampton reported that the interchange project in Lexington over US 29 – I-85
Business has been let and utility work is underway. The milling and resurfacing of US
64 will start next month. The interchange project at Davidson County Community
College will be let in FY 21. The bid opening for the turn lane project on Hickory Tree
Rd. is tomorrow. The Winston Rd. Project is will let in FY 19. The rest of the projects
are bridge and resurfacing projects.
Item 9: Triad Air Awareness.
No one was present
Item 10: NCDOT Transportation Planning Branch Report.
No one was present. .
3
Attachment 1
Item 11: Hi tran Report
Angela Wynes reported that staff is continuing to work on service changes and expansion
for the short range transit plan. Hi tran has 14 new busses ordered and are hoping for
delivery in late Fall. The fare boxes will no longer take the magnetic strip cards. Only
smart cards and cash will be able to be used.
Item 15: PART Report
Mark Kirstner reported that Business 40 through Winston Salem will be closed in about
1.5 years for a period of about 2 years. This year’s MPO Conference will take place in
Greensboro. Registration for the conference is open.
Item 16: Other Business
The next meeting will be Tuesday, March 22, 2016 at 9:00 am.
There was no other business. The meeting was adjourned.
4
Agenda
HIGH POINT URBAN AREA MPO
TRANSPORTATION ADVISORY COMMITTEE (TAC)
Agenda for the February 23, 2016 TAC Meeting
10:00 AM
High Point Parks and Recreation Department
Administration Building
136 Northpoint Avenue, High Point
Ethics Statement
In accordance with the State Government Ethics Act, it is the duty of every TAC member to avoid
conflicts of interest. Does any TAC member have any known conflict of interest with respect to any
matters coming before the TAC today? If so, please identify the conflict and refrain from any
participation in the particular matter involved.
Public Comment Period
Action Items
1. Consideration of the January 26th TAC meeting minutes. (Neal Grimes) Pages 1-6
2. Consideration of amendments to the 2016-2025 Metropolitan Transportation
Improvement Program. (Greg Venable) Pages 7-14
Information Items
3. SPOT 4.0 update. (Greg Venable) Page 15
4. Davidson County Airport Project Information (L.G. Cashion) Page 16
Agency Reports
5. NCDOT Board of Transportation Report (Cheryl McQueary – NCDOT Division 7 Board Member)
6. Division Engineer’s Reports
a. Division 7 Pages 18-22
b. Division 8 Page 23
c. Division 9 Pages 24-26
7. Triad Air Awareness Report (Lorelei Elkins) Pages 27-28
8. NCDOT Transportation Planning Branch Report (Wayne Davis)
9. Hi tran Report (Angela Wynes)
10. PART Report (Scott Rhine) Pages 29-30
11. Other Business
TAC
Meeting
Meeting Date 2/23/2016 Agenda Item No. 1
Action Requested Approve
Section Tab
Consideration of the January 26th TAC meeting minutes. (Neal Grimes)
Information Summary Attachments Yes No
The complete meeting minutes are in your packet as Attachment 1.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
1
MINUTES
TRANSPORTATION ADVISORY COMMITTEE
January 26, 2016
TAC MEMBERS PRESENT:
Jim Myers –Lexington
Neal Grimes – Thomasville
Keith Volz – Jamestown
Cheryl McQueary – NCDOT Board
Bill Bencini – High Point
Larry Ward – Denton
Joe Geigle – FHWA
Larry Warlick - Archdale
TCC MEMBERS PRESENT: Greg Venable, Guy Cornman, Bryan Fulbright, Ed
Lewis, Heidi Galanti, Chuck George, Mark McDonald, Pat Ivey, Jason Miller, Mark
Kirstner, Darius Sturdivant, John Gray, Wayne Davis, Kelly Larkins, Chuck Smith, Mike
Mills, Brandon Jones, and Carrie Spencer.
OTHERS PRESENT: John Hanes (Transportation Planning), Vickie Embry(COHP
Transportation), Gwen Ford (COHP), Randy McCaslin (COHP), Gary Kennedy (Citizen,
Wallburg), Beth Kennedy (Citizen, Wallburg), Lee Gill (Citizen, Wallburg)
RECORDING SECRETARY: Marianne Janiszewski, City of High Point
Item 1: Reading of the Ethics Statement.
Neal Grimes read the Ethics Awareness and Conflict of Interest Reminder. No one had
any conflicts.
Item 2: Public Comment Period
Neal opened up the public comment period.
Lee Gill spoke in opposition to the NC 109 project and its financial impact on the
homeowners in the area.
Neal closed the public comment period.
Item 3: Report from the Nominating Committee and Election of TAC Chair
and Vice Chair.
Neal Grimes was nominated as Chair and Keith Volz was nominated as Vice-Chair.
They were voted in with no opposition.
Motion by: Jim Myers
2
Seconded: Cheryl McQueary
Vote:
For: Unanimous
Against: None
ACTION ITEMS
Item 4: Consideration of the November 17, 2015 TAC meeting minutes.
There were no corrections to the minutes.
Motion by: Jim Myers
Seconded: Keith Volz
Vote:
For: Unanimous
Against: None
Cheryl McQueary abstained from the vote since she was not present at the November
meeting.
Item 5: Consideration to release the 2016-1017 Unified Planning Work
Program for public review and comment.
The Draft 2016-2017 UPWP is the work plan for the MPO for the upcoming fiscal year. As
part of the Public Participation Policy for the MPO the Draft UPWP must be available for a
minimum 30 day public review and comment period. The draft document will be released to
for public review and comment on February 8 and close on March 11. It will come back to
the TAC for approval at the March meeting. NCDOT put out a new format this year. The
draft document will be sent out to all TAC and TCC members this afternoon. A public
notice will go out stated that the document will be available for public review at all
jurisdictions. Greg handed out the local match which is based on population from the 2010
census numbers. The budget this year is $580,000 which is an increase over last year’s
budget. Money will be taken out of the new budget for a new position that will be opening
up. Some additional funding has also been included for special studies. There is a bike plan
the MPO would like to do and there has been some requests for some small feasibility studies
to be done.
Motion by: Cheryl McQueary
Seconded: Jim Myers
3
Vote:
For: Unanimous
Against: None
Item 6: Consideration to amend the 2016-2025 Metropolitan Transportation
Improvement Program.
These amendments are due to additional funding of approximately $1.6 million from the
State for a ten year period. The Jamestown bypass has been moved up from 2025 to 2019
for construction with completion expected in 2022. ROW plans on this project are
complete and funding is available to start purchasing ROW.
Motion by: Keith Volz
Seconded: Cheryl McQueary
Vote:
For: Unanimous
Against: None
INFORMATION ITEMS
Item 7: SPOT 4.0 Update.
Greg reported that NCDOT has to approve all prioritization processes throughout the
State. Greg handed out a draft version that will be submitted to NCDOT. The ranking
criteria along with the DOT vote will be released on March 23rd for public review and
comment period. The regional impact/local input points window opens on April 1 and
runs until May 31. Review of public comments and final ranking criteria will take place
at the April TAC meeting. The division needs window opens August 1st and runs through
September 30. Unlike last year this year we will know ahead of time which projects will
be funded regionally and what projects will fall to the division level. The dates of the
public information sessions will be released at the March meeting. Greg will send an
email with the dates as soon as he gets them. Staff has considered changing the number
of DOT votes from 12 to 10. Members can vote on as many projects as they want but the
maximum number of votes that can be put on one project is five. This change is up for
discussion. This year bike and ped projects will be included in the ranking. A project
spreadsheet was handed out dividing projects into highway, bicycle and ped, rail, aviation
and transit. In the past a maximum of 100 points was given to the highest ranking
projects. This is how it is written currently but there will be a discussion before it is sent
to NCDOT as to if it is going to be kept like this. Greg also presented a map of the SPOT
projects.
4
AGENCY REPORTS
Item 8: NCDOT Board of Transportation Report.
Cheryl McQueary gave a presentation on division 7 projects and showed a slide show on
the Honda Aircraft Type Certification Event.
Item 10: Division Engineer’s Reports.
Division 7
Mike Mills reported that they are working with the COHP on some pedestrian projects.
The High Point Rd. Project has a let date of 2019. The ROW plans are complete. The
Johnson St./Sandy Ridge Rd. project has a let date of July 2019. Planning and Design is
underway and the ROW plans will be complete in 2017. There will be a public workshop
sometime in early spring for the I-74/US 311 and NC 68 interchange improvement
project. The let date for this project is June, 2018. There are a couple of bridge projects
currently in progress. There are three pavement rehab projects. The pavement project on
I-74 to the Guilford/Forsyth County Line has a let date of February, 16, 2016 with a
completion date of Summer 2017. The project on I-85 from I-85 Business past the
Randolph County Line has a let date of April 19, 2016 with a completion date of Summer
2017. The project on I-40 from Gallimore Dairy Rd. to the Forsyth County Line has a let
date of March 15, 2016 with a completion date of Summer 2017.
Division 8
Darius Sturdivant reported that the Pedestrian Crosswalk project at the Main St./Balfour
Dr. intersection in Archdale is complete. The asphalt project is expected to resume in
April, 2016 with a completion Spring, 2016. The Prospect St. Bridge Project is 33%
complete with an estimated completion date of March, 2017. There are two SPOT Safety
Projects, one is the upgrade of traffic signals at the intersections of NC 62 and Finch
Farm Rd., and at Trinity Rd. and Archdale Rd. A flashing yellow arrow will be added.
Plans have been completed and the materials have been ordered for the upgrade. There
are some pavement rehab and bridge resurfacing projects coming up.
Division 9
Pat Ivey reported that new bridge project on Winston Rd. over 2970. Utility relocation is
underway and will be available to start construction on April 1, 2016. The 2970/ Bus 85
rehabilitation project on the southern end has a revised completion date of February 1,
2016. There is currently traffic on both new bridges. All lanes are anticipated to be open
on February 1. Division 9 has a consultant onboard for the new interchange project on
2970 at DCCC. The planning, environmental work and design are anticipated to start
later this year.
Item 10: Triad Air Awareness.
Lorelei Elkins was not present. Greg stated that there will be a lunch and learn
tomorrow, January 27.
5
Item 13: NCDOT Transportation Planning Branch Report.
No one was present. Hemal Shah was promoted and is now with the Fayetteville MPO.
Item 14: Hi tran Report
Angela Wynes was not present.
Item 15: PART Report
Mark Kirstner referred to the report in the TAC packet.
Item 16: Other Business
The next meeting will be Tuesday, February 23, 2016.
There was no other business. The meeting was adjourned.
6
TAC
Meeting
Meeting Date 2/23/2016 Agenda Item No. 2
Action Requested Approve
Section Tab
Consideration of amendments to the 2016-2025 MTIP. (Greg Venable)
Information Summary Attachments Yes No
The proposed amendments to the 2016-2025 MTIP for the High Point MPO are included
in you packet. Staff is requesting approval of the amendments to the 2016-2025 MTIP.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
7
High Point RESOLUTION
AMENDING THE 2016-2025 HIGH POINT METROPOLITAN
TRANSPORTATION IMPROVEMENT PROGRAM
Archdale WHEREAS, the Transportation Advisory Committee has reviewed the current
2016-2025 Metropolitan Transportation Improvement Program and found an
amendment is necessary; and
Denton
WHEREAS, the following amendments have been proposed:
Jamestown
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
Randolph
County
8
NOW THEREFORE, be it resolved by the Transportation Advisory Committee
for the High Point Metropolitan Planning Organization that the 2016-2025
Metropolitan Transportation Improvement Program be amended as listed above
on this the 23rd day of February 2016.
A motion was made by TAC Member ______________and seconded by TAC
member _______________ and approved this the 23rd day of February 2016.
_________________________
Neil Grimes
Chairman, Transportation Advisory Committee
Subscribed and sworn to me this the 23rd day of February 2016.
______________________________________
Notary Public
My commission expires ______________________
9
ADDITIONS to the Transit 2016-2025 MTIP/STIP
FY16 FY17 FY18 FY19 FY20 FY21 FY22
STIP # Transit Partner DESCRIPTION match FUND (000) (000) (000) (000) (000) (000) (000)
Piedmont
Authority for
Regional Purchase One Replacement
TA-5194 Transportation Vehicle FUZ 5307 400
Local L 100
Piedmont
Authority for
Regional Purchase One Replacement
TA-5196 Transportation Vehicle JARC 5316 400
Local L 100
NOTES:
TA-5194 – Project funding originated from FTA Section 5339 funding administered by NCDOT. PART applied under
a competitive grant and received funding award. These funds will be transferred to FTA Section 5307 for FTA grant
purposes. MTIP action is to have vehicle included in local MPO TIP so funding can be identified in an upcoming FTA Capital
grant. STIP action has already been approved by NCDOT-BOT.
TA-5196 – Project funding originated from FTA Section 5316 funding administered by NCDOT. PART applied under
a competitive grant and received funding award. These funds will be administred under a grant between NCDOT and FTA.
MTIP action is to have vehicle included in local MPO TIP so funding can be identified in an upcoming FTA Capital grant.
STIP action has already been approved by NCDOT-BOT.
ADDITIONS to the Transit 2016-2025 MTIP/STIP
FY16 FY17 FY18 FY19 FY20 FY21 FY22
STIP # Transit Partner DESCRIPTION match FUND (000) (000) (000) (000) (000) (000) (000)
Piedmont
Authority for
Regional
Transportation –
High Point Urban
TO-5212 Area Operating 5307 CMAQ 459
Local L 115
Piedmont
Authority for
Regional
Transportation –
High Point
TA-5197A Urban Area Bus Replacement 5307 CMAQ 380
Local L 95
NOTES:
TO-5212 – Project funding originated from HP MPO “Call for Projects.” Project funding was approved by HP MPO,
and also received funding award from NCDOT. These funds will be transferred to FTA Section 5307 for FTA grant purposes.
MTIP action is to have operating funds included in local MPO TIP so funding can be programmed in the STIP. Funding is
established to impement a new Palladium Circulator in North High Point beginning in FY2017, and will be utilized for a three
year period at an eligible 80/20 operating ratio for new service in Air Quality maintenance area.
TA-5197A – Project funding originated from HP MPO “Call for Projects.” Project funding was approved by HP MPO,
and also received funding award from NCDOT. These funds will be transferred to FTA Section 5307 for FTA grant purposes.
MTIP action is to have capital funds included in local MPO TIP so funding can be programmed in the STIP. Funding is
established for replacement bus in the PART fleet that is operated in North High Point.
10
High Point
RESOLUTION
Archdale AMENDING THE 2016-2025 HIGH POINT METROPOLITAN
TRANSPORTATION IMPROVEMENT PROGRAM
WHEREAS, the Transportation Advisory Committee has reviewed the current
Denton 2016-2025 Metropolitan Transportation Improvement Program and found an
amendment is necessary; and
Jamestown WHEREAS, the following amendments have been proposed:
ADDITIONS to the Transit 2016-2025 MTIP/STIP
Lexington FY16 FY17 FY18 FY19 FY20 FY21 FY22
STIP # Transit Partner DESCRIPTION match FUND (000) (000) (000) (000) (000) (000) (000)
Piedmont
Authority for
Regional Purchase One Replacement
Thomasville TA-5194 Transportation Vehicle FUZ 5307 400
Local L 100
Piedmont
Trinity Authority for
Regional Purchase One Replacement
TA-5196 Transportation Vehicle JARC 5316 400
Local L 100
Wallburg
ADDITIONS to the Transit 2016-2025 MTIP/STIP
Davidson matc FY16 FY17 FY18 FY19 FY20 FY21 FY22
STIP # Transit Partner DESCRIPTION h FUND (000) (000) (000) (000) (000) (000) (000)
County
Piedmont
Authority for
Regional
Forsyth Transportation –
County High Point
TO-5212 Urban Area Operating 5307 CMAQ 459
Local L 115
Piedmont
Guilford Authority for
County Regional
Transportation –
TA- High Point
5197A Urban Area Bus Replacement 5307 CMAQ 380
Local L 95
Randolph
County
11
NOW THEREFORE, be it resolved by the Transportation Advisory Committee
for the High Point Metropolitan Planning Organization that the 2016-2025
Metropolitan Transportation Improvement Program be amended as listed above
on this the 23rd day of February 2016.
A motion was made by TAC Member ______________and seconded by TAC
member _______________ and approved this the 23rd day of February 2016.
_________________________
Neil Grimes
Chairman, Transportation Advisory Committee
Subscribed and sworn to me this the 23rd day of February 2016.
______________________________________
Notary Public
My commission expires ______________________
12
CITY OF HIGH POINT
NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION PUBLIC TRANSPORTATION DIVISION
To: Greg Venable, Transportation Planning Administrator
From: Angela W. Wynes, Transit Manager
Date: February 16, 2016
Subject: FY2016 - 2025 MTIP Amendment
High Point Transit System would like to request the attached amendment to project TA-5170 in
the FY2016 – FY2025 MTIP for the purchase of one (1) 35 foot low floor.
We are requesting TCC/TAC approval of the amendment as soon as possible to allow the MTIP
and STIP reflect these projects in order to secure Federal Transit Administration funding.
If you need more information, please advise.
c: Cassandre’ Haynesworth, NCDOT Public Transportation Division
Tamra Shaw, NCDOT Public Transportation Division
13
High Point RESOLUTION
AMENDING THE 2016-2025 HIGH POINT METROPOLITAN
TRANSPORTATION IMPROVEMENT PROGRAM
Archdale WHEREAS, the Transportation Advisory Committee has reviewed the current
2016-2025 Metropolitan Transportation Improvement Program and found an
amendment is necessary; and
Denton
WHEREAS, the following amendments have been proposed:
Jamestown
Lexington
Thomasville
Trinity
NOW THEREFORE, be it resolved by the Transportation Advisory Committee
for the High Point Metropolitan Planning Organization that the 2016-2025
Wallburg
Metropolitan Transportation Improvement Program be amended as listed above
on this the 23rd day of February 2016.
A motion was made by TAC Member ______________and seconded by TAC
Davidson member _______________ and approved this the 23rd day of February 2016.
County
_________________________
Neil Grimes
Forsyth Chairman, Transportation Advisory Committee
County
Subscribed and sworn to me this the 23rd day of February 2016.
Guilford
County ______________________________________
Notary Public
Randolph My commission expires ______________________
County
14
TAC
Meeting
Meeting Date 2/23/2016 Agenda Item No. 3
Action Requested Information
Section Tab
Update of NCDOT Project Prioritization 4.0 (SPOT 4.0). (Greg Venable)
Information Summary Attachments Yes No
Update on SPOT 4.0 projects.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
15
TAC
Meeting
Meeting Date 2/23/2016 Agenda Item No. 4
Action Requested Information
Section Tab
Davidson County Airport Projects. (L.G. Cashion)
Information Summary Attachments Yes No
Update on projects at the Davidson County Airport.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
16
TAC
Meeting
Meeting Date 2/23/2015 Agenda Item No. 5-10
Action Requested Information
Section Tab
Agency Reports
Information Items Attachments Yes No
Agenda Item 5
NCDOT Board of Transportation Report (Cheryl McQueary – NCDOT Division 7 Board
Member)
Agenda Item 6
Division 7 – (Mike Mills)
Division 8 – (Darius Sturdivant)
Division 9 – (Pat Ivey)
Agenda Item 7
Triad Air Awareness (Lorelei Elkins)
Agenda Item 8
Transportation Planning Branch Report (Wayne Davis)
Agenda Item 9
Hitran (Angela Wynes)
Agenda Item 10
PART Report (Scott Rhine)
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
17
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO
TIP/WBS # Description Let Date Completion Date Status Cost Comments
Design and bid
Small Construction.
document
Install pedestrian improvements on SR 1009 (N. Main Street) at M.A. w/ City, Signal
preparation in
43250 Lexington Avenue (WCR, pedestrian signal heads, traffic Mar. 2016 Spring 2016 $140,000 plans submitted for
progress by City,
islands) Division Traffic
City addressing
review and approval.
signal comments
Planning and
I-5712 Design activiities
Interchange improvements at I-40/US 421 and SR 1850 (Sandy
50126.2.1 1/19/21 FY 2023 underway, R/W $7,800,000 STIP, P3.0
Ridge Road)
50126.3.1 plans complete
1/18/19
R/W plans being
U-2412A
SR 1486 (Greensboro Road) / SR 4121 (High Point Road), revised - Fall
34802.2.2 STIP, Programmed
Widening (part on new location) from SR 4228 (Vickrey Chapel FY 2019 FY 2022 2016 completion, $51,900,000
34802.2.6 due to HB97
Road) to I-74/US 311 Bypass R/W Acquisition -
34802.3.3
10% complete
Planning and
U-4758 Design activities
Improvements to Johnson Street/Sandy Ridge Road from Skeet
40251.2.1 7/16/19 FY2022 underway, R/W $18,300,000 STIP
Club Road to I-40
40251.3.1 plans complete
7/21/2017
Central Design in
progress, Public
U-5169
I-74/US 311 and NC 68 (Eastchester Drive) interchange workshop early
45220.2.1 6/19/18 FY 2020 $15,775,000 STIP
improvements 2016, R/W
45220.3.1
plans complete
6/17/16
R/W Certified, System
17BP.7.R.22 Bridge #895 on SR 1486 (Lexington Ave.) over Bouldin Branch 2/18/16 Summer 2016 Project let $577,000 Preservation, M.A.
pending executed
18
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO
TIP/WBS # Description Let Date Completion Date Status Cost Comments
Design in
B-5358
progress, R/W
46072.1.1 STP funds, LAP,
Replace Bridge #428 on Model Farm Rd over Richland Creek 9/30/16 Summer 2017 plans complete; $1,050,000
46072.2.FD1 City match
City acquiring
46072.3.FD1
R/W
I-5767
Pavement Rehabilitation: I-74/US-311 from 0.7 miles East of I-
53010.3.1/ Project let NHPP - Interstate
40 to the Guilford /Forsyth County Line to SR1300 (E. Green 2/16/16 Summer 2017 $20,600,000
I-5736 pending Maintenance
Drive)
52018.3.1
I-5821
Design and bid
50464.3.1
package
I-5789 Pavement Rehabilitation: I-85 from 0.4 miles South of I-85 NHPP - Interstate
4/19/16 Summer 2017 submittal to $9,900,000
53029.3.1 Business to South of SR 1009 (S. Main St.) in Archdale Maintenance
Raleigh-75%
I-5738
Complete
52020.3.1
Design and bid
I-5734
package
52010.3.1 Pavement Rehabilitation: I-40 from 1.1 miles East of SR 1556 NHPP - Interstate
5/17/16 Summer 2017 submitted to $9,664,000
I-5762 Gallimore Dairy Rd to Forsyth County Line Maintenance
Raleigh - 100%
53005.3.1
complete
19
Contract Number: C202881 Route: SR-4121
Division: 7 County: Guilford
TIP Number: U-2412B, U-2524AE
Length: 4.836 miles Federal Aid Number: NHS-124-1(17)
NCDOT Contact: J. Paul Ingram, PE NCDOT Contact No: (336)487-0150
Location Description: SR-4228 (VICKERY CHAPEL RD) TO SR-1424 (HILLTOP RD); GREENSBORO
WESTERN LOOP INTERCHANGE AT HIGH POINT RD.
Contractor Name: APAC - ATLANTIC, INC. THOMPSON ARTHUR DIVISION
Contract Amount: $40,094,959.99 Cost Overrun/Underrun: 0%
Work Began: 10/05/2012 Letting Date: 08/21/2012
Original Completion Date: 05/13/2016
Revised Completion Date: 08/03/2016
Scheduled Progress: 99.6%
Actual Progress: 83.79%
Contract Number: C203237 Route: US-70
Division: 7 County: Guilford
Length: 0 miles Federal Aid Number:
NCDOT Contact: Kris Lorenz, PE NCDOT Contact No: (336)487-7080
Location Description: REHAB BRIDGE #217, 259 & 274 ON US-220 AND #1, 136 & 470 ON SR-2254
(WENDOVER AVE).
Contractor Name: ASTRON GENERAL CONTRACTING COMPANY INC
Contract Amount: $1,274,112.00 Cost Overrun/Underrun: 0%
Work Began: 06/14/2013 Letting Date: 02/19/2013
Original Completion Date: 09/28/2013
Scheduled Progress: 100%
Actual Progress: 82.31%
Contract Number: C203256 Route: SR-1820
Division: 7 County: Guilford
TIP Number: U-3615B
Length: 3.388 miles Federal Aid Number: STP-1820(5)
NCDOT Contact: J. Paul Ingram, PE NCDOT Contact No: (336)487-0150
Location Description: SR-1820 (SKEET CLUB RD) FROM EAST OF SR-1818 (JOHNSON ST) TO WEST OF NC-
68 (EASTCHESTER DR) IN HIGH POINT.
Contractor Name: APAC - ATLANTIC, INC. THOMPSON ARTHUR DIVISION
Contract Amount: $30,898,017.15 Cost Overrun/Underrun: 0%
Work Began: 05/20/2015 Letting Date: 01/20/2015
Original Completion Date: 03/29/2019
Revised Completion Date: 03/28/2020
Scheduled Progress: 0%
Actual Progress: 0.33%
Contract Number: C203433 Route: I-73
Division: 7 County: Guilford
TIP Number: I-5110, I-5110A, R-2413A
R-2413B
Length: 9.4 miles Federal Aid Number:
NCDOT Contact: Brian V. Smith NCDOT Contact No: (336)375-1774
Location Description: FUTURE I-73 FROM EXISTING SR-2085 (JOSEPH M BRYAN BLVD) / AIRPORT PKWY
INTERCHANGE TO SOUTH OF US-220 NEAR HAW RIVER.
Contractor Name: FLATIRON CONSTRUCTORS, INC. BLYTHE DEVELOPMENT CO JOINT VENT
Contract Amount: $176,550,000.00 Cost Overrun/Underrun: 0%
Work Began: 05/07/2014 Letting Date: 04/03/2014
Original Completion Date: 04/25/2017
Revised Completion Date: 10/18/2017
Scheduled Progress: 45.86%
Actual Progress: 47.38%
20
Contract Number: C203627 Route: -
Division: 7 County: Guilford
TIP Number: C-5558
Length: 80 miles Federal Aid Number: CMS-0710(29)
NCDOT Contact: Kris Lorenz, PE NCDOT Contact No: (336)487-7080
Location Description: CITY OF HIGH POINT SIGNAL SYSTEM
Contractor Name: HAYNES ELECTRIC UTILITY CORP.
Contract Amount: $0.00 Cost Overrun/Underrun: 0%
Work Began: Letting Date: 10/20/2015
Original Completion Date: 02/15/2019
Scheduled Progress: 0%
Actual Progress: No work at this time
Contract Number: C203640 Route: -
Division: 7 County: Guilford
Length: 0.431 miles Federal Aid Number:
NCDOT Contact: Kris Lorenz, PE NCDOT Contact No: (336)487-7080
Location Description: REPLACE 4 BRIDGES IN GUILFORD COUNTY AND 3 BRIDGES IN ORANGE
COUNTY.
Contractor Name: HAYMES BROTHERS, INC.
Contract Amount: $0.00 Cost Overrun/Underrun: 0%
Work Began: Letting Date: 04/21/2015
Original Completion Date: 11/01/2017
Scheduled Progress: 0%
Actual Progress: No work at this time
Contract Number: C203641 Route: SR-2719
Division: 7 County: Guilford
Length: 0.685 miles Federal Aid Number:
NCDOT Contact: Christopher D. Kirkman, PE NCDOT Contact No: (336)570-6830
Location Description: REPLACE 5 BRIDGES IN GUILFORD COUNTY AND 5 BRIDGES IN ORANGE
COUNTY.
Contractor Name: R.E. BURNS & SONS CO., INC.
Contract Amount: $5,940,323.00 Cost Overrun/Underrun: 0%
Work Began: 06/01/2015 Letting Date: 04/21/2015
Original Completion Date: 11/01/2018
Scheduled Progress: 5.5%
Actual Progress: 15.89%
Contract Number: DG00219 Route: SR-2509
Division: 7 County: Guilford
Length: 10.993 miles Federal Aid Number:
NCDOT Contact: J. Paul Ingram, PE NCDOT Contact No: (336)487-0150
Location Description: RESURFACE SR 3093, SR 3029, SR 2826, SR 2732 AND SR 2509
Contractor Name: BLYTHE CONSTRUCTION, INC.
Contract Amount: $1,065,598.39 Cost Overrun/Underrun: 0%
Work Began: 07/20/2015 Letting Date: 10/16/2014
Original Completion Date: 11/20/2015
Scheduled Progress: 0%
Actual Progress: 80.37%
21
Contract Number: DG00260 Route: NC-22
Division: 7 County: Guilford
Length: 12.856 miles Federal Aid Number:
NCDOT Contact: Kris Lorenz, PE NCDOT Contact No: (336)487-7080
Location Description: RESURFACE NC 22 FROM THE RANDOLPH COUNTY LINE TO NC 62 TO JOINT
NORTH OF SR 1486 (LEXINGTON AVENUE)
Contractor Name: SHARPE BROTHERS A DIV OF VECELLIO & GROGAN, INC.
Contract Amount: $0.00 Cost Overrun/Underrun: 0%
Work Began: Letting Date: 07/16/2015
Original Completion Date: 11/15/2016
Scheduled Progress: 0%
Actual Progress: No work at this time
Contract Number: DG00261 Route: NC-22
Division: 7 County: Guilford
Length: 5.217 miles Federal Aid Number:
NCDOT Contact: J. Paul Ingram, PE NCDOT Contact No: (336)487-0150
Location Description: RESURFACE A PORTION OF SR 1001, SR 1008, SR 3163 AND SR 2851
Contractor Name: APAC - ATLANTIC, INC. THOMPSON ARTHUR DIVISION
Contract Amount: $0.00 Cost Overrun/Underrun: 0%
Work Began: Letting Date: 07/16/2015
Original Completion Date: 11/15/2016
Scheduled Progress: 0%
Actual Progress: No work at this time
Contract Number: DG00262 Route: -
Division: 7 County: Guilford
Length: 0.098 miles Federal Aid Number:
NCDOT Contact: Kris Lorenz, PE NCDOT Contact No: (336)487-7080
Location Description: REPLACE BRIDGE NUMBER 338 ON SR 1859 (BOYLSTON ROAD) OVER WEST
FORK OF DEEP RIVER (TRIBUTARY 1)
Contractor Name: SMITH-ROWE, LLC
Contract Amount: $0.00 Cost Overrun/Underrun: 0%
Work Began: 02/01/2016 Letting Date: 08/06/2015
Original Completion Date: 03/01/2017
Scheduled Progress: 0%
Actual Progress: No estimate at this time
Contract Number: DG00265 Route: -
Division: 7 County: Guilford
Length: 31.1 miles Federal Aid Number:
NCDOT Contact: Jason Ryan Julian NCDOT Contact No: (336)634-5635
Location Description: RESURFACE 39 SECONDARY ROADS IN GUILFORD COUNTY AND ONE
SECONDARY ROAD IN ROCKINGHAM COUNTY
Contractor Name: WHITEHURST PAVING CO INC
Contract Amount: $0.00 Cost Overrun/Underrun: 0%
Work Began: Letting Date: 10/15/2015
Original Completion Date: 08/31/2016
Scheduled Progress: 0%
Actual Progress: No work at this time
22
23
High Point Urban Area MPO
NCDOT Transportation Update
(Davidson County)
Tuesday, February 16, 2016
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects under Construction
Replace Bridge #27 on US 52/NC 8 over US 29/64/70/I- May 1, 2019 Availability date
B-3159 Oct. 20, 2015 (perm. vegetation established $10,164,621 J.T. Russell & Sons, Inc. Utility relocation work is underway
85 Bus. Loop in Lexington October 28, 2019)
April 1, 2016
June 15, 2016 Work start date April 6, 2015. Traffic is now on new structure in
Replace Bridge #38 on SR 1493 (Frye Bridge Rd) over (Perm. vegetation 88% Complete
B-4741 Dec. 16, 2014 $2,333,794 Dane Construction, Inc. final traffic pattern. Road to remain open during
Muddy Creek in Davidson County established (20% ahead of schedule)
Dec. 12, 2016) construction,with new bridge being built next to existing.
June 15, 2016
(Perm. vegetation 99% Complete Work is ongoing on new bridge - roadway to stay open.
C-4901A NCRR/NS Mainline Bowers to Lake Railroad Roadbed June, 2013 $15,738,016 Blythe Construction, Inc.
established (10% ahead of schedule) Minimal to no impact to vehicular traffic.
Oct. 28, 2016)
Contract Landscaping on I-85 from (SR 1224)
Approx. 20% Contractor began work on Nov. 3, 2015. Currently planting
I-2304AC/AD (L) Hardgrave Rd in Davidson Co. to (SR2120) Long Ferry Sept. 23, 2015 May 6, 2018 $1,281,336 Staniel Key Landscaping
Complete trees.
Rd in Rowan Co.
Pavement Rehabilitation, Bridge Preservation, and March 15, 2016 DDRL Project - Contractor will be paving SB lanes and Marco
Upgrade to Interstate Standards - US 29/52/70/I-85 Bus. (revised) 92.2% Complete St first week of February. Traffic shift on Feb. 1 on SB side
R-4750 From I-85 to south of SR 1147 (Salisbury Rd) and September, 2013 (Perm. vegetation (schedule has been $7,571,155 J. T. Russell & Sons, Inc. from outside lane to inside lane. All work except some
Bridges #43 & #225 over Swearing Creek on US established revised) pavement markings and rumble strips should be complete by
29/52/70. June 4, 2016) mid-March.
110 days Work not yet begun, scheduled to start Feb. 15, 2016.
Replace Bridge #361 on SR 1837 (Bud Sink Rd) over Leonard
(perm. vegetation Availability date Completion of project to be 110 calendar days (May 8 - June
BD-5109L Creek in Davidson County. Includes Grading, Drainage, Dec. 9, 2015 $378,498 TCB Builders, LLC
established by Jan. 25, 2016 18, 2016) from established availability date (Jan. 19 - Feb. 29,
Widening, Structure, Paving, and Pavement Markings.
Dec. 31, 2016) 2016).
June 23, 2016
Replace Bridge #40 on SR 1298 / I-85 Service Rd (perm. vegetation 15.1% Complete Work began December 7, 2015. Road is closed with off-site
17.BP.9.R.3 October 28, 2015 $830,623 Smith-Rowe LLC
(Grimes Blvd) over Swearing Creek in Davidson County. established (on schedule) detour.
Dec. 9, 2016)
Design Build Project - (Dvdsn Co) Bridge #235 (Hedrick Mill)
Rehabilitation and bridge beam painting of (4) bridges in
complete; #303 (Ball Rd) complete; #431 (Old 64) complete;
17BP.9.R.34 Davidson Co., (1) in Forsyth Co., (3) in Rowan Co., and April, 2012 Oct. 20, 2016 97.1% Complete $12,585,775 Crowder Construction Co.
#424 (E Center St) work to start on Oct. 24, 2015 and
(1) in Stokes Co.
projected to complete Oct. 20, 2016.
Permitting and Express Design Build Contract - Br. #258 over Swearing
DESIGN BUILD - Replace two (2) Bridges in Davidson
design work begun Creek on SR 1272, and Br. #410 over Leonard Creek on SR
17BP.9.R.61 Co., one (1) Bridge in Davie Co., three (3) Bridges in May 19, 2015 June 30, 2019 $10,642,621 Smith-Rowe, LLC
(Anticipate construction work 1844 in Davidson; (1) bridge in Davie; (2) bridges in Rowan;
Rowan Co., and four (4) Bridges in Stokes Co. to begin Summer, 2016) and (4) bridges in Stokes Co.
Permitting and Express Design Build Contract - Br. #86 over First Potts Creek
Mountain Creek
DESIGN BUILD - Replace three (3) Bridges in Davidson design work begun on SR 1158, Br. #95 over Leonard Creek on SR 1838, and Br.
17BP.9.R.62 May 19, 2015 September 1, 2018 $4,740,000 Contractors/SEPI
Co. and seven (7) Bridges in Rowan Co. with Culverts (Anticipate construction work #471 over Unnamed Creek on SR 2416 in Davidson Co. and
to begin Spring, 2016)
Engineering
(7) bridges in Rowan Co.
Milling and resurfacing of 3.8 miles of US 64 from RR
2016CP.09.01. Availability date Division Let contract. Continuation of previous resurfacing
crossing near Decker Rd. to the end of concrete island Aug. 12, 2015 May 20, 2016 $1,035,588 J.T. Russel & Sons, Inc.
10291.1 Sept. 21, 2015 map. Work scheduled to begin after March 15, 2016.
near Linda Pl., just W. of I-85.
Contract Resurfacing of 2 sections of NC 8, 1 section of
9CR.10291.160, May 25, 2016 Work began August 3, 2015. Work over the next few months
US 64, 1 section of NC 68 and 8 sections of Secondary May 19, 2015 26% Complete $3,755,440 J.T. Russell & Sons, Inc.
9CR.20291.160 (revised) will be limited by temperatures.
routes (20.54 miles) in Davidson County.
Davidson County Asphalt Surface Treatment (AST) Preconstruction meeting held Aug. 19, 2015. Work began
9SP.20295.4 Retreatment (58.79 miles) of various Secondary routes June 10, 2015 May 25, 2016 50% Complete $1,455,996 Blythe Construction, Inc. Sept. 22, 2015. Seasonal limitations in force currently, plan to
in Davidson Co. start back in April, 2016.
24
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects under Development
Bridge Preservation project - Plans are currently being
Bridge Preservation – Bridge #31 on NC 8, Bridges #55 revised. Bridge #55 will be dropped from this contract and
41665.6A TBD TBD $1,600,000 TBD
& 82 on NC 47 in Davidson County completed under another project at a later date. Finalizing
structure plans.
Replace Bridge #42 on SR 1485 (Hampton Rd) over ROW
B-5165 FY 2017 TBD $1,800,000 TBD *Schedule based on Approved 2016-2025 STIP
Muddy Creek FY 2016
Replace Bridge #115 on SR 1711 (Gumtree Rd) over ROW
B-5765 FY 2021 TBD $1,700,000 TBD *Schedule based on Approved 2016-2025 STIP
WSSB RR FY 2019
Replace Bridge #25 on SR 3346 (S. Main St) over ROW
B-5773 FY 2025 TBD $3,250,000 TBD *Schedule based on Approved 2016-2025 STIP
WSSB RR in Lexington FY 2023
Replace Bridge #99 on SR 1810 (Clodfelter Rd) over ROW *Schedule based on Approved 2016-2025 STIP - Project
B-5774 FY 2020 TBD $1,200,000 TBD
Brushy Creek FY 2019 accelerated due to additional revenue (HB 97)
Replace Bridge #100 on SR 1810 (Clodfelter Rd) over ROW *Schedule based on Approved 2016-2025 STIP - Project
B-5776 FY 2020 TBD $1,800,000 TBD
Abbott's Creek FY 2019 accelerated due to additional revenue (HB 97)
ROW
B-5777 Replace Bridge #58 on NC 109 over US 64 FY 2022 TBD $1,850,000 TBD *Schedule based on Approved 2016-2025 STIP
FY 2021
Replace Bridge #118 on US 29NB/64EB/70EB/I-85 Bus ROW *Schedule based on Approved 2016-2025 STIP - Coordinate
B-5779 FY 2025 TBD $4,061,000 TBD
NB over SR 3346 (N Main St) in Lexington FY 2024 with B-5785
ROW Acquisition in
B-5780 Replace Bridge #17 on NC 47 over Swearing Creek FY 2017 TBD $1,400,000 TBD Hydraulic Study complete.
progress
Replace Bridge #164 and Bridge #168 on US 29/70/I-85 ROW
B-5783 FY 2025 TBD $5,778,000 TBD *Schedule based on Approved 2016-2025 STIP
Bus over NSRR FY 2024
Replace Bridge #121 and Bridge #122 on US 29/70/I-85 ROW *Schedule based on Approved 2016-2025 STIP - Coordinate
B-5785 FY 2025 TBD $4,000,000 TBD
Bus over Leonard Creek FY 2024 with B-5779
ROW
B-5787 Replace Bridge #29 on NC 49 over NC 109 FY 2024 TBD $2,000,000 TBD *Schedule based on Approved 2016-2025 STIP
FY 2023
Extend Sidewalks on SR 3346 (S Main St) and provide Planning/Design/
Construction by City of
C-5216 wide paved shoulders on Anna Lewis Dr and Emergency FY 2016 TBD Right of Way in $601,000 *Schedule based on Approved 2016-2025 STIP
Lexington
Dr. in Lexington progress
Provide wide paved shoulders and construct sidewalks Planning/Design/
Construction by City of
C-5217 on Cornelia St and Hillsdie Dr. Bike and Pedestrian FY 2016 TBD Right of Way in $190,000 *Schedule based on Approved 2016-2025 STIP
Lexington
Improvements on Mize and Biesecker Rds. progress
Pavement Rehabilitation of I-85 from SR 2025 (Squire Planning and Design
I-5793 FY 2018 TBD $6,386,000 TBD *Schedule based on Approved 2016-2025 STIP
Bowers Rd) to 0.3 mi N. of NC 109 in Thomasville in Progress
Pavement Rehabilitation of I-85 from 1.7 mi N of SR Availability date *Schedule based on Approved 2016-2025 STIP
I-5740 Feb. 24, 2016 August 31, 2016 $200,000 TBD
2205 (Old US 64) to 0.3 mi N of US 64 April 4, 2016 Currently advertised for bid
NC 109 from SR 1756 (Old Greensboro Rd) in Davidson
R-2568C *Post Year TBD Planning and Design $129,000,000 TBD Currently being re-evaluated in STIP - UNFUNDED
County to I-40/US 311 in Forsyth County.
Convert at grade intersection to Interchange on US ROW
R-5737 FY 2021 TBD $15,000,000 TBD *Schedule based on Approved 2016-2025 STIP)
29/70/I-85 Bus at SR 1798 (Old Greensboro Rd) FY 2019
SS-4909AH Install left turn lane on Hickory Tree Rd (SR 1508) near Availability date
Feb. 24, 2016 September 30, 2016 $660,000 TBD Currently advertised for bid
U-4742NC Mendenhall Road in Davidson County. April 4, 2016
Widen NC 8 (Winston Rd) to multi-lanes from 9th St to Planning and Design
U-5757 FY 2019 TBD $1,254,000 TBD *Schedule based on Approved 2016-2025 STIP
SR 1408 (Biesecker Rd) in Lexington in Progress
Widen SR 1508 (Hickory Tree Rd) from US 52/NC ROW
U-5786 FY 2023 TBD $13,794,000 TBD *Schedule based on Approved 2016-2025 STIP
8/Future I-285 to NC 150 FY 2021
Widen NC 150 to multilanes from US 64 (SR 1493, Frye ROW & Utilities *Schedule based on Approved 2016-2025 STIP - New
U-5902B Post Year TBD $33,150,000 TBD
Bridge Rd) to Forsyth County Line FY 2024 project programmed due to additional revenue (HB 97)
Safety Improvements to median crossovers, etc., on I-85
ROW Division Let. Public meeting scheduled for Jan. 14, 2016 at
W-5601CF Business from SR1797 (Evans Rd) to SR 1963 (Moose January , 2017 TBD $600,000 TBD
June 2016 Davidson County Community College.
Lodge Rd) in Davidson Co.
25
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects Under Development
Bridge Painting on Bridges #136, 150 in Davidson;#'s
Funding issues. There will be plan revisions and a new letting
17BP.9.P.3 29,32,85,86 in Davie; #'s 53,54,55,78,115,185,297,322 TBD TBD $5,000,000 TBD
date - to be determined.
in Forsyth; and #94 in Rowan County.
Letting date delayed due to funding and other priorities.
Replace Bridge #271 on SR 2501 (S. Main St. Ext./ Lick ROW Acquisition
17.BP.9.R.10 June, 2016 TBD $1,000,000 TBD Coordinating with ALCOA to begin construction. Utility
Creek Ch. Rd) over Lick Creek in Davidson County. in progress.
relocation in progress
Replace Bridge #221 on SR 2324 (Harris Rd) over Lick Plan Preparation 75% Complete; Let date is funding
17.BP.9.R.15 TBD TBD $525,000 TBD
Creek in Davidson County. dependent
Replace Bridge #459 on SR 2160 (Smith Rd) over an
17BP.9.R.33 Nov., 2016 TBD $250,000 TBD Letting date delayed due to funding and other priorities.
unnamed creek in Davidson County.
Replace Bridge #63 on SR 1481 (Welcome-Arcadia Rd) This project will not be pursued at this time. Will be deleted
17BP.9.R.57 TBD TBD $443,000 TBD
over Reedy Creek in Davidson County. from program due to funding rules and bridge condition.
9CR.10291.161 Contract Resurfacing of various sections of Primary and
April, 2016 TBD $3,100,000 TBD Centrally let
9CR.20291.161 Secondary routes in Davidson County
Completed Projects
Davidson County Asphalt Surface Treatment (Chip Seal)
9SP.20295.3 April 8, 2015 August 28, 2015 100% Complete $1,555,785 APAC Atlantic, Inc. One year warranty in effect.
Contract
March 15, 2015
Landscaping at Bridge #39 on US 64 over US 29/70/I-85 (Perm. Vegetation Country Boy Landscaping
B-4497L Dec. 10, 2014 100% Complete $14,999
Bus in Davidson Co. established Inc.
Nov. 20, 2015)
Aug. 15, 2015
Replace Bridge #11 on SR 1155 (Swicegood Rd) over (perm. vegetation
BD-5109V Mar. 11, 2015 100% Complete $572,994 Dane Construction, Inc.
First Potts Creek in Davidson County. established
Dec. 30, 2015)
April 30, 2015
Grade separation on SR 2024 (Upper Lake Rd) over (perm. vegetation DH Griffin Construction
C-4901B March, 2013 100% Complete $4,203,035 ARRA Rail Project - Complete and accepted
Hamby Creek / NCRR established Co., LLC
Nov. 11, 2015)
26
Triad Air Awareness January, 2016
Air Quality Notes:
Clean Fuels Advanced Technologies Grant (CFAT)
o The CFAT grant request for proposals is open until March 1st. The CFAT project
is funded by the N.C. DOT and administered by the NC Clean Energy Technology
Center.
o More information can be found here: https://nccleantech.ncsu.edu/clean-
transportation/clean-transportation-projects/clean-fuel-advanced-technology-
project/
Interim I/M Study Bill report
o State legislature did not act on House bill; expect legislature to pick up bill in
2016 short session.
o DAQ will be preparing a final I/M study report for the NC General Assembly by
the end of March 2016 now that the EPA has finalized revisions to the 2015
8-hour ozone
FHWA Webinar Series: Advancing a Sustainable Highway System
o The Sustainable Transport and Climate Change Team within FHWA’s Office of
Natural Environment recently posted webinar recordings related to the FHWA
report Advancing a Sustainable Highway System: Highlights of FHWA
Sustainability Activities.
o Report illustrates how sustainability has been incorporated into a wide variety
of FHWA programs, projects, policies, processes, and partnerships.
o Webinar recordings and transcripts are available at:
https://www.sustainablehighways.dot.gov/FHWA_Sustainability_Activities_We
binars.aspx
o If you have any questions regarding the webinar series or the report, please
contact Connie Hill: Connie.Hill@dot.gov or (804) 775-3378.
Registration for the NC Breathe Conference is now open.
o April 8, 2016 Bridging Research on Economics and Air Quality for the Health of
Everyone
o http://ncbreatheconference.org/
27
Air Quality Report:
Historic AQI results
AQI Results (Ozone and PM2.5)
ORANGE or
GREEN YELLOW higher
2005 181 175 9
2006 186 171 8
2007 201 156 8
2008 217 133 16
2009 270 94 1
2010 230 123 12
2011 247 110 8
2012 273 85 7
2013 252 112 1
2014 222 143 0
2015 271 93 1
Air quality outreach & education programs available for school, civic group and businesses.
Contact Triad Air Awareness at (336) 703-2449 or ElkinsLT@forsyth.cc, Lorelei Elkins
28
Piedmont Authority for Regional Transportation Updates
for the High Point MPO TCC/TAC
February 2016
PART Express Updates
Amtrak Thruway Tickets: On January 1, 2016 PART
Express started accepting the Amtrak Thruway
Tickets. The Amtrak Thruway ticket will be a
convenient and seamless transaction for Amtrak
passengers to ride Route 5.
Route Adjustment Implemented 1/11/16: Route 9
Business 85 Express was adjusted 1/11/16 providing
more service & frequency between Davidson County
and High Point. The route is picking up more
Shown Above: PART Express ridership was 37,778 for December passengers and growing every day. Route 3 High
2015 with an annual projection of 489,780 for FY 2016. Point Express is now serving the Palladium Shopping
Center with more access for passengers.
Planning Department Updates
Route Analysis
• Route 10 Evaluation Underway
• Working with NCDOT Modeling group to use
Piedmont Triad as pilot project for the evaluation of
TBEST Ridership Forecast Model
• Developed draft bus transit mitigation plan for
Business 40 closure
Regional Travel Demand Model
• Selected Contractor and prepared contract for Freight
Model Work
Regional Activities To learn more about PART’s programs and projects, please
• Working on Joint Bus Advertising Contract with visit www.partnc.org
partner transit agencies
• Regional Smart Card & Pay by phone Fare Collection Stay Connected with PART on Social Media!
being studied
Page 1 of 2
29
Page 2 of 2
PART Board Officers for 2016 New Vanpool Fares
Chairperson: Dan Besse, Winston-Salem City Council Now is a great time to join a Vanpool! New
Vice Chairperson: Leonard Williams, Burlington- Vanpool Fares have been posted on the PART
Graham TAC Website.
Treasurer: Carolyn Coleman, Guilford County Board of
Commissioners
Secretary: Ronda Jones, Stokes County Board of
Commissioners
Piedmont Transit Resources Call Center Celebrates 6 Months of Operation
On August 2, 2015 the Piedmont Authority for Regional Transportation (PART) launched the Piedmont Transit
Resources Call Center. This Call Center is a regional transportation information center representing the public transit
services offered by Hi tran, Davidson County Transportation, and PART. Staff is available to answer questions
regarding: Bus route schedules & fares, Real-time bus status, Transit trip planning, Carpool & Vanpool
information, Airport Area Shuttle Request, Pass sales, Emergency Ride Home, and More!
The Piedmont Transit Resources Call Center employs 5 staff members and is open Monday-Friday 6:00AM – 7:00PM.
You can reach the call center at 1-800-588-7787.