HPMPO Transportation Advisory Committee (TAC)
Regular MeetingHigh Point, NC · June 28, 2016
Agenda
HIGH POINT URBAN AREA MPO
TRANSPORTATION ADVISORY COMMITTEE (TAC)
Agenda for the June 28, 2016 TAC Meeting
10:00 AM
High Point Parks and Recreation Department
Administration Building
136 Northpoint Avenue, High Point
Ethics Statement
In accordance with the State Government Ethics Act, it is the duty of every TAC member to avoid
conflicts of interest. Does any TAC member have any known conflict of interest with respect to any
matters coming before the TAC today? If so, please identify the conflict and refrain from any
participation in the particular matter involved.
Public Comment Period
Action Items
1. Consideration of the May 24th TAC meeting minutes. (Neal Grimes) Page 1
2. Recommendation for approval of amendments to the 2016-2025 MTIP. (Greg Venable)
(Greg Venable) Page 6
Information Items
3. Rail SPOT Project R150274 – Purchase of 5 new bi-level passenger cars for future Piedmont service
between Raleigh and Charlotte. (Greg Venable) Page 11
4. Discussion of HPMPO bylaws relating to public comment period. (Greg Venable) Page 15
Agency Reports
5. NCDOT Board of Transportation Report (Cheryl McQueary – NCDOT Division 7 Board Member)
6. Division Engineer’s Reports
a. Division 7 (Mike Mills) Page 17
b. Division 8 (Darius Sturdivant) Page 22
c. Division 9 (Pat Ivey) Page 23
7. Triad Air Awareness Report (Lorelei Elkins)
8. NCDOT Transportation Planning Branch Report (Keith Dixon)
9. Hi tran Report (Angela Wynes)
10. PART Report (Scott Rhine) Page 26
11. Other Business
Next TAC Meeting
August 23, 2016 - 10:00 AM
High Point Parks and Recreation Department
Administration Building
136 Northpoint Avenue, High Point
TAC
Meeting
Meeting Date 6/28/2016 Agenda Item No. 1
Action Requested Approve
Section Tab
Consideration of the May 24th TAC meeting minutes. (Neal Grimes)
Information Summary Attachments Yes No
The complete meeting minutes are in your packet as Attachment 1.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
1
MINUTES
TRANSPORTATION ADVISORY COMMITTEE
May 24, 2016
TAC MEMBERS PRESENT:
Alan Perdue – Guilford County
Cheryl McQueary – NCDOT Board
Neal Grimes – Thomasville
Jim Myers – Lexington
Keith Volz – Jamestown
Larry Ward – Denton
Bill Bencini – High Point
Larry Warlick – Archdale
Fred McClure – Davidson County
Darrell Frye – Randolph County
TCC MEMBERS PRESENT: Greg Venable, Pat Ivey, Mike Mills, Chuck Smith,
Diane Hampton, Guy Cornman, Bryan Fulbright, Wayne Davis, Keith Dixon, Jen Britt,
John Gray, Mark McDonald, Jason Miller, and Carrie Spencer
OTHERS PRESENT: John Hanes (Transportation Planning), Gwen Ford (COHP),
Marcie Kennedy (COHP), LG Cashion (Davidson County Airport), Karel Van Der
Linden (Davidson County Airport), Angela Wynes (HiTran), Jesse Day (PTRC) and
Suzana Hatta (NCDOT).
CITIZENS
Lee Gill
RECORDING SECRETARY: John Hanes, City of High Point
Item 1: Reading of the Ethics Statement.
Neal Grimes read the Ethics Awareness and Conflict of Interest Reminder.
Item 2: Public Comment Period
Neal opened up the public comment period.
Lee Gill spoke in opposition and presented information regarding the NC 109 project.
Neal closed the public comment period.
ACTION ITEMS
Item 3: Consideration of the March 22, 2016 TAC meeting minutes.
2
There were no corrections to the minutes.
Motion by: Jim Myers
Seconded: Cheryl McQueary
Vote:
For: Unanimous
Against: None
Item 4: Public Hearing for the SPOT 4.0 HPMPO prioritization process
priority list of projects.
Greg explained the process and discuss the project list. No one spoke.
Item 5: Consideration of SPOT 4.0 HPMPO prioritization process priority list
of projects.
Greg discussed the ranking process and scoring of highway, bike and pedestrian, rail,
transit, and aviation projects.
Motion by: Bill Bencini
Seconded: Jim Myers
Vote:
For: Unanimous
Against: None
Item 6: Consideration to amendments to the 2016-2025 Metropolitan
Transportation Improvement Program.
There were several STIP additions and STIP modifications to rail projects that are being
recommended for TAC approval. One was for the piedmont corridor (train 74/75 operations)
and the remaining additions/modifications were for statewide improvements. There was also
a resolution for the HPMPO prioritization and priority list of projects.
Motion by: Jim Myers
Seconded: Cheryl McQueary
Vote:
For: Unanimous
Against: None
3
INFORMATION ITEMS
There were no information items.
AGENCY REPORTS
Item 7: NCDOT Board of Transportation Report.
Cheryl McQueary stated modifications to the right-of-way process to shorten the length
of the process. She reported that there would be an education session on this in June and
session on voting on the process in July.
Item 8: Division Engineer’s Reports.
Division 7
Mike Mills reported on several pedestrian improvement projects that will be let this
summer in the High Point area. Division 7 will be holding a public meeting for the SPOT
4.0 on June 20th from 5-7 p.m. at the Division 7 office in Greensboro.
Division 8
Jen Britt reported on active and upcoming projects in the HPMPO area. Active projects
include asphalt surface treatment, resurfacing, and pavement rehabilitation. Division 8
will hold a SPOT 4.0 public meeting on June 27th from 5-7 p.m. at their office in
Carthage.
Division 9
Diane Hampton reported on centrally and division managed construction projects. These
included bridge replacements, asphalt resurfacing, and design build projects. Pat Ivey
mentioned that I-285 designation request had been sent to FHWA. He address questions
relating to NC 109 and guidance from the attorney general on how to proceed. Division
9 will hold a SPOT 4.0 public meeting at their office in Winston-Salem on July 12th from
5-7 p.m.
Item 9: Triad Air Awareness.
No one was present. Jesse Day mentioned that particulate matter had been reduced by
12% in the Thomasville area.
Item 10: NCDOT Transportation Planning Branch Report.
Keith Dixon introduced himself and will be serving as HPMPO’s representative from the
NCDOT Transportation Planning Branch. Keith discussed forecasts in the Archdale area
that he is working on.
Item 11: Hi tran Report
Angela Wynes discussed new bus delivery is to occur in October or November. She also
addressed rebranding and potential of expanding service.
Item 12: PART Report
4
No one was present.
Item 13: Other Business
No further business the meeting was adjourned.
Motion by: Fred McClure
Seconded: Jim Myers
Vote:
For: Unanimous
Against: None
5
TAC
Meeting
Meeting Date 6/28/2016 Agenda Item No. 2
Action Requested Approve
Section Tab
Consideration of amendments to the 2016-2025 MTIP. (Greg Venable)
Information Summary Attachments Yes No
The proposed amendments to the 2016-2025 MTIP for the High Point MPO are included
in you packet. Staff is requesting approval of the amendments to the 2016-2025 MTIP.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
6
High Point
RESOLUTION
AMENDING THE 2016-2025 HIGH POINT METROPOLITAN
Archdale TRANSPORTATION IMPROVEMENT PROGRAM
WHEREAS, the Transportation Advisory Committee has reviewed the current 2016-
2025 Metropolitan Transportation Improvement Program and found an amendment is
Denton necessary; and
WHEREAS, the following amendments have been proposed:
Jamestown
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
7
High Point
Archdale
Denton
Jamestown
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
8
High Point
Archdale
Denton
Jamestown
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
9
High Point
Archdale
Denton
Jamestown
NOW THEREFORE, be it resolved by the Transportation Advisory Committee for the
Lexington High Point Metropolitan Planning Organization that the 2016-2025 Metropolitan
Transportation Improvement Program be amended as listed above on this the 28th day of
June 2016.
Thomasville
A motion was made by TAC Member ______________and seconded by TAC
member _______________ and approved this the 28th day of June 2016.
Trinity _________________________
Neil Grimes
Chairman, Transportation Advisory Committee
Wallburg
Subscribed and sworn to me this the 28th day of June 2016.
Davidson ______________________________________
County Notary Public
My commission expires ______________________
Forsyth
County
Guilford
County
10
TAC
Meeting
Meeting Date 6/28/2016 Agenda Item No. 3
Action Requested Information
Section Tab
Rail SPOT 4.0 Project (R150274) (Greg Venable)
Information Summary Attachments Yes No
The NCDOT Rail Division has requested the High Point MPO consider placing some of
our local input points on this rail project. This project was originally submitted by the
Capital Area MPO, Charlotte MPO and Greensboro MPO and was only listed in their list
of projects. However, the Rail Division is asking all the MPOs, Divisions, and RPOs in
which the rail line runs from Raleigh to Charlotte to share in the point Assignment. For
the HPMPO the amount of points we can assign to the project is 21 points because 21
percent of this project is in the HPMPO. The project is the purchase of 5 new bi-level
passenger cars for future Piedmont service between Raleigh and Charlotte. Additional
information is included in the packet.
11
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
12
Purpose
NCDOT would like to purchase 5 bi-level rail coach cars to assist in providing additional
passenger capacity. This project provides one bi-level rail car for each Piedmont frequency
including upcoming 4th and 5th frequencies. The lower deck also allows for easier access for
customers with disabilities.
Cost
The cost of the project is $18,000,000.
Point Allocation
This project was submitted into SPOT P4.0 by Capital Area Metropolitan Planning
Organization (CAMPO). Because this project spans multiple regions, it was determined that
multiple MPOs would have the ability to contribute a portion of the maximum 100 points.
The portion of points awarded by each MPO is based on the percentage of the track mileage
of the Piedmont corridor within each MPO. Greensboro Urban Area Metropolitan Planning
Organization (GUAMPO) has committed the maximum number of points to the project.
Point Allocation Point Allocation
6% 9%
CAMPO
22% DCHCMPO Division 5
18% 16% 19%
BGMPO Division 7
GUAMPO 26% Division 8
12% 0% 39%
HPUAMPO Division 9
21% CRMPO Division 10
12%
CRTPO
13
14
TAC
Meeting
Meeting Date 6/28/2016 Agenda Item No. 4
Action Requested Information
Section Tab
Discussion of Public Comment Period Bylaws (Greg Venable)
Information Summary Attachments Yes No
Discussion of HPMPO bylaws relating to public comment period.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
15
TAC
Meeting
Meeting Date 5/24/2016 Agenda Item No. 5-10
Action Requested Information
Section Tab
Agency Reports
Information Items Attachments Yes No
Agenda Item 5
NCDOT Board of Transportation Report (Cheryl McQueary – NCDOT Division 7 Board
Member)
Agenda Item 6
Division 7 – (Mike Mills)
Division 8 – (Darius Sturdivant)
Division 9 – (Pat Ivey)
Agenda Item 7
Triad Air Awareness (Lorelei Elkins)
Agenda Item 8
Transportation Planning Branch Report (Wayne Davis)
Agenda Item 9
Hitran (Angela Wynes)
Agenda Item 10
PART Report (Scott Rhine)
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
16
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO
TIP/WBS # Description Let Date Completion Date Status Cost Comments
Design and bid
document being
Small Construction.
Install pedestrian improvements on SR 1009 (N. Main Street) at reviewed by
M.A. w/ City, Signal
43250 Lexington Avenue (WCR, pedestrian signal heads, traffic Summer 2016 Fall 2016 Department, $140,000
plans approved,
islands) waiting for City to
LAP
resubmit plans
and bid package
B-5358
R/W plans
46072.1.1 STP funds, LAP,
Replace Bridge #428 on Model Farm Rd over Richland Creek 9/30/16 Summer 2017 complete; R/W $1,050,000
46072.2.FD1 City match
certified
46072.3.FD1
I-5821 Design and bid
50464.3.1 package
I-5789 Pavement Rehabilitation: I-85 from 0.4 miles South of I-85 submittal to NHPP - Interstate
6/21/16 Summer 2017 $16,900,000
53029.3.1 Business to South of SR 1009 (S. Main St.) in Archdale Raleigh-100% Maintenance
I-5738 Complete, let
52020.3.1 pending
Design and bid
package
I-5734
submitted to
52010.3.1 Pavement Rehabilitation: I-40 from 1.1 miles East of SR 1556 NHPP - Interstate
6/21/16 Summer 2017 Raleigh - 100% $9,664,000
I-5762 Gallimore Dairy Rd to Forsyth County Line Maintenance
complete, bids
53005.3.1
rejected-
readvertised
Design activities
I-5734A NHPP - Interstate
Bridge Preservation (Bridge 384) on I-40 over NC 68 Sept. 2016 Spring 2017 underway -75% $1,300,000
52010.3.2 Maintenance
complete
Planning and
I-5712 Design activities STIP, P3.0,
Interchange improvements at I-40/US 421 and SR 1850 (Sandy
50126.2.1 1/19/21 FY 2023 underway, R/W $7,800,000 Coordinate w/
Ridge Road)
50126.3.1 plans complete U-4758
1/18/19
17
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO
TIP/WBS # Description Let Date Completion Date Status Cost Comments
Planning and
U-4758 Design activities
Improvements to Johnson Street/Sandy Ridge Road from Skeet STIP, Coordinate w/
40251.2.1 7/16/19 FY2022 underway, R/W $18,300,000
Club Road to I-40 I-5712
40251.3.1 plans complete
7/21/2017
R/W plans being
U-2412A
SR 1486 (Greensboro Road) / SR 4121 (High Point Road), revised - April
34802.2.2 STIP, Programmed
Widening (part on new location) from SR 4228 (Vickrey Chapel FY 2019 FY 2022 2017 completion, $51,900,000
34802.2.6 due to HB97
Road) to I-74/US 311 Bypass R/W Acquisition -
34802.3.3
10% complete
Central Design in
progress, Public
U-5169
I-74/US 311 and NC 68 (Eastchester Drive) interchange workshop Mid
45220.2.1 6/19/18 FY 2020 $15,775,000 STIP
improvements 2016, R/W
45220.3.1
plans complete
6/17/16
W-5601GI Safety improvements on SR 1546 (Guilford College Road) at SR Design activities
HSIP, Construction
50138.2.192 1558 (Hickory Grove Road) and SR1546 (Guilford College Road) Jan. 2017 5/1/17 underway -10% $133,000
by State Forces
50138.3.192 at ramps to Wendover Ave.) complete
18
Page 1 of 3
06/08/2016
North Carolina Department of Transportation
Active Projects Under Construction - Guilford Co.
Contract TIP Location Description Contractor Name Resident Engineer Contract Bid Availability Work Start Completion Progress Completion
Number Number Amount Date Date Date Schedule Percent
C200800 R-2309AB US-220 FROM SR-2182 (HORSEPEN CREEK TETRA TECH Lorenz, PE, Kris $96,195,464.51 04/02/2012 05/09/2012 Percent
12/27/2016 85.00 57.60
RD) TO EXISTING NC-68 & US-220 CONSTRUCTION INC
INTERSECTION.
C200800 R-2413C US-220 FROM SR-2182 (HORSEPEN CREEK TETRA TECH Lorenz, PE, Kris $96,195,464.51 04/02/2012 05/09/2012 12/27/2016 85.00 57.60
RD) TO EXISTING NC-68 & US-220 CONSTRUCTION INC
INTERSECTION.
C202881 U-2412B SR-4228 (VICKERY CHAPEL RD) TO APAC - ATLANTIC, INC. Ingram, PE, J. Paul $40,094,959.99 10/01/2012 10/05/2012 05/13/2016 99.95 93.82
SR-1424 (HILLTOP RD); GREENS- BORO THOMPSON ARTHUR
WESTERN LOOP INTERCHANGE AT HIGH DIVISION
POINT RD.
C202881 U-2524AE SR-4228 (VICKERY CHAPEL RD) TO APAC - ATLANTIC, INC. Ingram, PE, J. Paul $40,094,959.99 10/01/2012 10/05/2012 05/13/2016 99.95 93.82
SR-1424 (HILLTOP RD); GREENS- BORO THOMPSON ARTHUR
WESTERN LOOP INTERCHANGE AT HIGH DIVISION
POINT RD.
C202923 REPLACEMENT OF 1 BRIDGE IN CASWELL SMITH-ROWE, LLC Ingram, PE, J. Paul $7,292,875.26 04/02/2012 05/01/2012 11/01/2015 100.00 99.34
COUNTY, 3 IN GUILFORD COUNTY, 2 IN
ORANGE COUNTY, & 6 IN ROCKINGHAM
COUNTY.
C203197 U-2524C GREENSBORO-WESTERN LOOP FROM VECELLIO & GROGAN INC Smith, Brian V $122,804,388.50 10/28/2013 10/30/2013 03/14/2018 67.70 46.50
SOUTH OF SR-2137 (OLD OAK RIDGE RD)
TO NORTH OF US-220 (BATTLEGROUND
AVE).
C203237 BRIDGE #217, 259 & 274 ON US-220 AND ASTRON GENERAL Lorenz, PE, Kris $1,274,112.00 06/01/2013 06/14/2013 09/28/2013 100.00 82.31
#1, 136 & 470 ON SR-2254 (WENDOVER CONTRACTING COMPANY
AVE). INC
C203256 U-3615B SR-1820 (SKEET CLUB RD) FROM EAST OF APAC - ATLANTIC, INC. Ingram, PE, J. Paul $30,898,017.15 03/02/2015 05/20/2015 03/29/2019 16.00 6.33
SR-1818 (JOHNSON ST) TO WEST OF THOMPSON ARTHUR
NC-68 (EASTCHESTER DR) IN HIGH POINT. DIVISION
C203290 U-2524BC GREENSBORO W LOOP FROM I-73/I-840 FLATIRON Smith, Brian V $4,955,491.02 07/27/2015 09/08/2015 03/01/2017 67.10 56.92
TO SR-2085 (JOSEPH BRYAN BLVD) CONSTRUCTORS, INC.
INTERCHANGE. BLYTHE DEVELOPMENT
CO JOINT VENT
C203399 U-2525B GREENSBORO EASTERN LOOP FROM FLATIRON Smith, Brian V $111,683,421.13 07/28/2014 08/08/2014 12/28/2018 51.30 61.65
NORTH OF US-70 TO US-29 NORTH OF CONSTRUCTORS, INC.
GREENSBORO. BLYTHE DEVELOPMENT
CO JOINT VENT
C203412 R-2612B US-421 AT SR-3418 (NEELLEY RD) SOUTH BRANCH HIGHWAYS, INC. Lorenz, PE, Kris $13,528,497.85 07/28/2014 08/07/2014 12/28/2016 91.90 80.20
OF GREENSBORO.
C203415 W-5114 NC-68 FROM SOUTH OF SR-2111 (E YATES CONSTRUCTION Ingram, PE, J. Paul $1,819,807.14 06/30/2014 07/01/2014 05/14/2015 100.00 90.76
HARRELL RD) TO SR-4831 (BARTONSHIRE CO., INC.
DR).
C203433 I-5110 FUTURE I-73 FROM EXISTING SR-2085 FLATIRON Smith, Brian V $176,550,000.00 05/07/2014 05/07/2014 04/25/2017 58.49 60.02
(JOSEPH M BRYAN BLVD) / AIRPORT CONSTRUCTORS, INC.
PKWY INTERCHANGE TO SOUTH OF BLYTHE DEVELOPMENT
US-220 NEAR HAW RIVER. CO JOINT VENT
C203433 I-5110A FUTURE I-73 FROM EXISTING SR-2085 FLATIRON Smith, Brian V $176,550,000.00 05/07/2014 05/07/2014 04/25/2017 58.49 60.02
(JOSEPH M BRYAN BLVD) / AIRPORT CONSTRUCTORS, INC.
PKWY INTERCHANGE TO SOUTH OF BLYTHE DEVELOPMENT
US-220 NEAR HAW RIVER. CO JOINT VENT
19
Page 2 of 3
06/08/2016
North Carolina Department of Transportation
Active Projects Under Construction - Guilford Co.
Contract TIP Location Description Contractor Name Resident Engineer Contract Bid Availability Work Start Completion Progress Completion
Number Number Amount Date Date Date Schedule Percent
C203433 R-2413A FUTURE I-73 FROM EXISTING SR-2085 FLATIRON Smith, Brian V $176,550,000.00 05/07/2014 05/07/2014 Percent
04/25/2017 58.49 60.02
(JOSEPH M BRYAN BLVD) / AIRPORT CONSTRUCTORS, INC.
PKWY INTERCHANGE TO SOUTH OF BLYTHE DEVELOPMENT
US-220 NEAR HAW RIVER. CO JOINT VENT
C203489 P-5204 SR-2819 (MCLEANSVILLE RD) GRADE TRIANGLE GRADING & Ingram, PE, J. Paul $7,078,936.15 10/27/2014 10/29/2014 02/28/2017 52.20 58.05
SEPARATION OVER NS/NCRR RAILROAD PAVING INC
FROM SR-2826 TO NORTH OF SR-2746.
C203518 B-5119 BRIDGES #349 & #291 OVER US-29/70/220 APAC - ATLANTIC, INC. Julian, Jason R $5,973,735.98 03/02/2015 03/16/2015 02/28/2018 39.00 42.33
ON I-40/85. THOMPSON ARTHUR
DIVISION
C203625 B-4959 BRIDGE #193 OVER BUFFALO CREEK ON R.E. BURNS & SONS CO., Smith, Brian V $957,388.91 03/01/2016 12/07/2015 03/06/2017 7.30 99.87
SR-2719 (HIGH ROCK RD). INC.
C203627 C-5558 CITY OF HIGH POINT. MB HAYNES Lorenz, PE, Kris $7,099,452.53 11/30/2015 05/09/2016 02/15/2019
CORPORATION DBA
HAYNES ELECTRIC UTILITY
C203640 REPLACEMENT OF 4 BRIDGES IN HAYMES BROTHERS, INC. Lorenz, PE, Kris $3,124,500.00 06/01/2015 09/02/2015 11/01/2017 14.60 11.63
GUILFORD COUNTY AND 3 BRIDGES IN
ORANGE COUNTY.
C203641 REPLACEMENT OF 5 BRIDGES IN R.E. BURNS & SONS CO., Kirkman, PE, $5,940,323.00 06/01/2015 06/01/2015 11/01/2018 13.75 36.27
GUILFORD COUNTY AND 5 BRIDGES IN INC. Christopher D
ORANGE COUNTY.
C203715 NC-150 FROM NC-68 TO US-220, AND 20 BLYTHE CONSTRUCTION, Ingram, PE, J. Paul $2,068,055.18 04/15/2016 05/23/2016 11/18/2016 0 13.00
SECTIONS OF SECONDARY ROADS. INC.
C203779 I-74/US-311 FROM I-40 IN FORSYTH SHARPE BROTHERS A DIV Ingram, PE, J. Paul $14,950,678.73 04/04/2016 04/04/2016 10/29/2017 9.00 33.42
COUNTY TO BUSINESS I-85 IN HIGH OF VECELLIO & GROGAN,
POINT. INC.
C203779 I-5736 I-74/US-311 FROM I-40 IN FORSYTH SHARPE BROTHERS A DIV Ingram, PE, J. Paul $14,950,678.73 04/04/2016 04/04/2016 10/29/2017 9.00 33.42
COUNTY TO BUSINESS I-85 IN HIGH OF VECELLIO & GROGAN,
POINT. INC.
C203785 I-5790 I-85 FROM SOUTH ELM EUGENE STREET PENHALL COMPANY Smith, Brian V $10,358,599.85 05/02/2016 06/03/2016 09/15/2017
TO I-40 IN GREENSBORO.
C203785 I-5855 I-85 FROM SOUTH ELM EUGENE STREET PENHALL COMPANY Smith, Brian V $10,358,599.85 05/02/2016 06/03/2016 09/15/2017
TO I-40 IN GREENSBORO.
DG00218 RESURFACE 5.041 MILES OF US 220 APAC - ATLANTIC, INC. Lorenz, PE, Kris $1,376,734.85 04/27/2015 07/09/2015 11/20/2015 100.00 100.00
(WENDOVER AVE.) THOMPSON ARTHUR
DIVISION
DG00220 BD-5107AB REPLACE BRIDGE #145 ON SR 1340 SMITH-ROWE, LLC Smith, Brian V $347,976.83 03/04/2015 03/04/2015 02/01/2016 99.90 100.00
(HOPKINS ROAD) OVER CANDY CREEK
DG00226 ER-2973 US 421 AND WOODY MILL ROAD MOTS LANDSCAPING & Ingram, PE, J. Paul $81,384.00 02/21/2015 03/09/2015 05/15/2017 100.00 100.00
LAWNS LLC
DG00226 R-2612A(L) US 421 AND WOODY MILL ROAD MOTS LANDSCAPING & Ingram, PE, J. Paul $81,384.00 02/21/2015 03/09/2015 05/15/2017 100.00 100.00
LAWNS LLC
DG00231 REPLACE BRIDGE #238 ON SR 1005 SMITH-ROWE, LLC Kirkman, PE, $1,396,792.10 06/25/2015 06/25/2015 06/15/2017 34.00 48.57
(ALAMANCE CHURCH ROAD) OVER LITTLE Christopher D
ALAMANCE CREEK
DG00235 ER-2973 SR 2085 (BRYAN BLVD) AND I-73 IN STANIEL KEY Ingram, PE, J. Paul $187,000.80 04/09/2015 05/04/2015 10/30/2016 0 76.12
GUILFORD COUNTY AND US 220 IN LANDSCAPING
20
ROCKINGHAM COUNTY
Page 3 of 3
06/08/2016
North Carolina Department of Transportation
Active Projects Under Construction - Guilford Co.
Contract TIP Location Description Contractor Name Resident Engineer Contract Bid Availability Work Start Completion Progress Completion
Number Number Amount Date Date Date Schedule Percent
DG00238 SS-4907AV US 29/70/220 BETWEEN SR 3000 TRAFFIC CONTROL Lorenz, PE, Kris $56,000.00 06/21/2015 03/23/2016 06/20/2016 Percent
(MCCONNELL ROAD) AND EAST SIDE SAFETY SERVICES, INC.
DRIVE (NON-SYSTEM)
DG00245 ER-2973 VARIOUS INTERCHANGES ALONG I-40 STANIEL KEY Ingram, PE, J. Paul $282,985.15 06/08/2015 07/23/2015 04/30/2018 100.00 96.66
LANDSCAPING
DG00253 INTERSECTION OF SR 3330 (SOUTHEAST P & S GRADING LLC Lorenz, PE, Kris $585,254.50 07/06/2015 07/10/2015 03/25/2016 99.99 100.00
SCHOOL ROAD) AND SR 3389 (WOODY
MILL ROAD)
DG00256 B-5736 REPLACE BRIDGE #38 ON NC 61 OVER KEYSTONE CONTRACTING Lorenz, PE, Kris $704,800.00 08/03/2015 09/04/2015 05/06/2016 100.00 96.37
BEAVER CREEK CO INC
DG00260 NC 22 FROM THE RANDOLPH COUNTY SHARPE BROTHERS A DIV Lorenz, PE, Kris $1,265,131.67 04/15/2016 04/25/2016 11/15/2016 30.90 24.09
LINE TO NC 62 TO JOINT NORTH OF SR OF VECELLIO & GROGAN,
1486 (LEXINGTON AVENUE) INC.
DG00261 A PORTION OF SR 1001, SR 1008, SR 3163 APAC - ATLANTIC, INC. Ingram, PE, J. Paul $1,423,221.44 04/15/2016 04/25/2016 11/15/2016 17.80 22.60
AND SR 2851 THOMPSON ARTHUR
DIVISION
DG00262 REPLACE BRIDGE NUMBER 338 ON SR SMITH-ROWE, LLC Lorenz, PE, Kris $562,359.38 02/01/2016 02/01/2016 03/01/2017 43.30 75.81
1859 (BOYLSTON ROAD) OVER WEST
FORK OF DEEP RIVER (TRIBUTARY 1)
DG00265 39 SECONDARY ROADS IN GUILFORD WHITEHURST PAVING CO Lorenz, PE, Kris $782,184.98 04/15/2016 08/31/2016
COUNTY AND ONE SECONDARY ROAD IN INC
ROCKINGHAM COUNTY
DG00269 BP-5500N BRIDGE 42 ON SR 1002 (ALTAMAHAW CLECO CORPORATION Kirkman, PE, $892,257.46 04/15/2016 04/11/2016 07/01/2016 38.00 21.77
UNION RIDGE RD) OVER TOMS CR AND Christopher D
BRIDGE 184 ON SR 2711 (TROXLER RIDGE
RD) OVER HAW RIVER
DG00274 ER-2971G NC 100 FROM STEELE ST. TO BETHEL ST. HOLLINS CONSTRUCTION Ingram, PE, J. Paul $122,953.50 04/01/2016 04/13/2016 12/01/2016 0 53.60
AND NC 62 AT BARTLETT YANCEY HIGH SERVICES INC
SCHOOL
DG00275 CONVERT TWO-WAY STOP TO P & S GRADING LLC Ingram, PE, J. Paul $44,050.00 04/01/2016 04/04/2016 12/31/2016
FOUR-WAT STOP AT THE INTERSECTION
OF NC 150 AND SR 2702
(OSCEOLA-OSSIPPEE ROAD)
DG00281 SR 1486 (LEXINGTON AVE) OVER MOUNTAIN CREEK Ingram, PE, J. Paul $638,245.35 04/11/2016 04/11/2016 02/19/2017 31.00 36.67
BOULDING BRANCH CONTRACTORS INC
21
Division 8 Project Report - HPMPO
June 2016
DIVISION 8 - ACTIVE PROJECTS (HIGH POINT MPO)
TIP/WBS/ Completion
Description Let Date Status Cost Contractor Comments
Contract # Date
Asphalt Surface Treatment: SR 1916, SR 2039, SR 1697, 85% Riley Paving
DH00172 6/9/15 Spring 2016 $867,269 Work started 9/18/15
SR 1685 and SR 1536 Complete INC
APAC-
Resurfacing SR 1567, SR 1545, SR 1597, SR 1794, SR 86% Atlantic, INC.
DH00175 7/30/15 6/24/16 $1,398,521 Work started 10/7/15
1850 and SR 1864 Complete Thompson
Arthur Division
Asphalt Surface Treatment on 30 sections of primary and
17% Whitehurst
DH00178 secondary roads: SR 3261 Pineview Avenue from SR 1627 9/8/15 6/24/16 $844,950 Work started 3/21/16
Complete Paving
Old Thomasville Rd to End of Maintenance
Country Boy
SR 1603 School Rd - Replace Bridge #84 over Muddy 14%
DH00191 2/23/16 4/3/17 $728,888 Landscaping Work started 4/15/16
Creek. Complete
INC
SR 1619 Prospect Street - Replace Bridge #136 over US 45% Lee
B-5114 6/16/15 3/15/17 $4,714,965 Work started 8/7/15
29/70/I-85 Business. Complete Construction
I-73 Pavement Rehabilitation from US 311 to 0.6 mi North of
SR 1938 Hockett Dairy Road; 7.7 miles - Combined with I- APAC-
5737: I-73 from 1.3 miles north of SR 1504 Spero Road to Atlantic, INC.
I-5763 1/19/16 10/28/16 8% Complete $ 6,298,145 Work started 4/18/16
US 311, 2.2 miles) and Combined with W-5601AJ: I- Thompson
73/74/US 220 from south of SR 2269 Vision Drive to south Arthur Division
of SR 1712 Pineview Road.
DIVISION 8 - UPCOMING PROJECTS (HIGH POINT MPO)
TIP/WBS/
Description Let Date Comments Cost
Contract #
I-85 South of SR 1009 to North of SR 1912 Lunar Drive in
Archdale. Pavement Rehabilitation. Scope of work should
Project let date 6/21/2016. Project to be $7,000,000
I-5738 include milling and filling of deteriorating asphalt paved Jun-16
combined with I-5821 and I-5789. Total Contract Amt $16,900,000
shouders, rehabilitation of ramps and rehabilitation of
concrete aprons around drainage structures.
SR 1944 Branson Davis Rd from US 311 to SR 2017 Summer
8CR.207611.xxx Randolph 2016 Summer Resurfacing TBD
Walker Mill Rd. 2016
SR 1533 Pliney Farlow Rd, SR 1534 Roy Farlow Rd, SR
Randolph 2016 Summer Resurfacing
8SP.207611.xxx 1858 Old Marlboro Rd, SR 3107 Evergreen Dr, SR 3108 TBD
(Seals)
Gaddy Dr, SR 3123 Wagoner Rd, SR 3179 Longview Ave
ROW is being acquired; Utilities to be
SR 1911 Ashland Street (Archdale) - Replace Bridge #416 relocated; Power is authorized to move;
17BP.8.R.76 Jun-18 TBD
over Dale Creek. Relocation of water lines to be
determined.
High_Point_Urban_Area_MPO Div 8 Project Report June 2016
22
High Point Urban Area MPO
Piedmont Triad RPO
NCDOT Transportation Update
Thursday, June 16, 2016
Completion Construction Project
T.I.P. No. Description Let Date Status Contractor Comments
Date Cost Administrator
Centrally Managed Projects under Construction
May 1, 2019 Contractor began work on project on April 4, 2016. Project is
B-3159 Replace Bridge #27 on US 52/NC 8 over US 29/64/70/I-85 (perm. vegetation J.T. Russell & Sons, Dale Swicegood, PE currently on schedule. Road to remain open during construction,
Oct. 20, 2015 10% Complete $10,164,621
38331.3.FR1 Bus. Loop in Lexington established Inc. (336)249-6255 with periodic lane closures on NC 8 and nighttime stoppages on
October 28, 2019) I-85 Bus.
Anticipate DDRL Project - J.T Russell had completed all work except the
Pavement Rehabilitation, Bridge Preservation, and Upgrade
June 10, 2016 polyurea pavement markings and snowplowable markers. A-1
R-4750 to Interstate Standards - US 29/52/70/I-85 Bus. From I-85 J. T. Russell & Sons, Kelly Seitz, PE
Sept. 17, 2013 (Perm. vegetation 98.8% Complete $7,571,155 Pavement Marking is in the process placing pavement markings.
39889.3.FS1 to south of SR 1147 (Salisbury Rd) and Bridges #43 & Inc. (704)630-3220
established Awaiting 80% vegetation establishment for final acceptance.
#225 over Swearing Creek on US 29/52/70. June 16, 2016) Anticipate completion by June 10, 2016.
2016CPT.09.18. Contract Resurfacing of Primary routes including (1) section
10291.1 Availability J.T. Russell & Sons, Dale Swicegood, PE Signs scheduled to be installed on June 6, and asphalt
2016CPT.09.19.
of US 64, (2) sections of NC 8, and (8) sections of April 19, 2016 May 19, 2017 $2,847,876
June 6, 2016 Inc. (336)249-6255 placement to begin June 13.
20291.1 Secondary routes for 18.729 miles in Davidson Co.
Division Managed Projects under Construction
Contract Landscaping on I-85 from (SR 1224) Hardgrave Contractor completed supplemental seeding and fertilizer
I-2304AC/AD (L) Staniel Key Thomas Gammons
Rd in Davidson Co. to (SR2120) Long Ferry Rd in Rowan Sept. 23, 2015 May 6, 2018 31.5% Complete $1,281,336 topdressing.Contractor is planting containerized grasses
34156.3.12 Landscaping (336)896-2380
Co. throughout project.
Pavement Rehabilitation of 5.17 miles of I-85 from the
Contractor plans to start work the end of June, 2016. Will be all
I-5740 ramps N. of Old Hwy 64 to the concrete pavement south of Availability date Chris Corriher, PE
Feb. 24, 2016 August 31, 2016 $1,069,294 Blythe Construction, Inc. nighttime work. Preconstruction meeting scheduled for May 25,
52021.3.1 SR 2010 (E. Holly Grove Rd), which includes milling, April 4, 2016 (704)630-3200
2016.
paving, and pavement markings.
U-4742NC Grading, drainage, widening, paving, and pavement Contractor began work on April 25, 2016. Project is slightly
39746.3.24 markings on SR 1508 (Hickory Tree Rd) and SR 1601 Thunder Contracting, Wright Archer, III, PE ahead of schedule. One side of the roadway has been widened.
Feb. 24, 2016 Sept. 30, 2016 23.8% Complete $366,513
SS-4909AH (Mendenhall Rd) in Davidson Co. Install left turn lane on SR Inc (336)747-7900 Storm drainage is being installed on the other side in preparation
43399.3.1 1508 (Hickory Tree Rd) near SR 1601 (Mendenhall Rd). for widening. Anticipate some lane closures during construction.
Replace Bridge #361 on SR 1837 (Bud Sink Rd) over June 3, 2016
17BP.9.R.63
Leonard Creek in Davidson County. Includes Grading, (perm. vegetation 90% Complete Dale Swicegood, PE Work began Feb. 16, 2016, using an off-site detour. Work on
45355.2.12 Dec. 9, 2015 $378,498 TCB Builders, LLC
Drainage, Widening, Structure, Paving, and Pavement established (on schedule) (336)249-6255 replacing the bridge has begun
BD-5109L Dec. 31, 2016)
Markings.
June 23, 2016
Replace Bridge #40 on SR 1298 / I-85 Service Rd (Grimes (perm. vegetation 100% Complete Dale Swicegood, PE Work began December 7, 2015. Road was re-opened to traffic
17BP.9.R.3 October 28, 2015 $830,623 Smith-Rowe LLC
Blvd) over Swearing Creek in Davidson County. established (ahead of schedule) (336)249-6255 on May 2, 2016 - approx. 2 months ahead of schedule.
Dec. 9, 2016)
Design Build Project - Bridge #424 (E Center St) work began
on December 7, 2015 and projected will be completed by August
Replace (4) bridges in Davidson Co., (1) in Forsyth Co., (3) Crowder Construction Jeremy Guy, PE 23, 2016. Contractor has completed work on installing girders
17BP.9.R.34 April, 2012 Oct. 20, 2016 98% Complete $12,585,775
in Rowan Co., and (1) in Stokes Co. Co. (336)747-7950 and Darr Branch Channel excavation, as well as removal of
existing culvert. Contractor will be working on bridge deck in
upcoming weeks.
Permitting and design in Express Design Build Contract - Br. #258 over Swearing
DESIGN BUILD - Replace two (2) Bridges in Davidson Co.,
progress Dale Swicegood, PE Creek on SR 1272, and Br. #410 over Leonard Creek on SR
17BP.9.R.61 one (1) Bridge in Davie Co., three (3) Bridges in Rowan May 19, 2015 June 30, 2019 $10,642,621 Smith-Rowe, LLC
(Anticipate construction work to (336)249-6255 1844 in Davidson; (1) bridge in Davie; (2) bridges in Rowan; and
Co., and four (4) Bridges in Stokes Co. begin Fall, 2016) (4) bridges in Stokes Co.
Permitting and design in Express Design Build Contract - Br. #86 over First Potts
Mountain Creek
DESIGN BUILD - Replace three (3) Bridges in Davidson progress Dale Swicegood, PE Creek on SR 1158, Br. #95 over Leonard Creek on SR 1838,
17BP.9.R.62 May 19, 2015 Sept. 1, 2018 $4,740,000 Contractors/SEPI
Co. and seven (7) Bridges in Rowan Co. with Culverts (Anticipate construction work to (336)249-6255 and Br. #471 over Unnamed Creek on SR 2416 in Davidson Co.
begin Fall, 2016)
Engineering
and (7) bridges in Rowan Co.
Milling and resurfacing of 3.8 miles of US 64 from RR
2016CPT.09.01. Anticipate J.T. Russell & Sons, Dale Swicegood, PE Division Let contract. Continuation of previous resurfacing map.
crossing near Decker Road to the end of concrete island Aug. 12, 2015 80% Complete $1,035,588
10291.1 mid-June, 2016 Inc. (336)249-6255 Anticipate completion in mid-June, 2016
near Linda Place, just West of I-85.
2017CPT.09.11. Asphalt Surface Treatment (AST) of 69.33 miles of Asphalt Maintenance Chris Corriher, PE
March 23, 2016 Oct. 14, 2016 22% Complete $1,782,681 Work began May 9, 2016.
20292.1 Secondary routes in Davidson Co. Solutions, LLC (704)630-3200
Contract Resurfacing of 2 sections of NC 8, 1 section of US
9CR.10291.160, Anticipate J.T. Russell & Sons, Dale Swicegood, PE Work began August 3, 2015. Work resumed March 15, 2016.
64, 1 section of NC 68 and 8 sections of Secondary routes May 19, 2015 95% Complete $3,755,440
9CR.20291.160 mid-June, 2016 Inc. (336)249-6255 Anticipate completion by mid-June.
(20.54 miles) in Davidson County.
23
Completion Construction Project
T.I.P. No. Description Let Date Status Contractor Comments
Date Cost Administrator
Centrally Managed Projects under Development
Replace Bridge #271 on SR 2501 (S. Main St. Ext./ Lick ROW Acquisition Dale Swicegood, PE
17BP.9.R.10 Nov. 23, 2016 TBD $1,000,000 TBD Coordinating with ALCOA to begin construction.
Creek Ch. Rd) over Lick Creek in Davidson County. in progress. (336)249-6255
Replace Bridge #221 on SR 2324 (Harris Rd) over Lick Dale Swicegood, PE
17BP.9.R.15 TBD TBD $525,000 TBD Plan Preparation 75% Complete; Let date is funding dependent
Creek in Davidson County. (336)249-6255
Replace Bridge #459 on SR 2160 (Smith Rd) over an Dale Swicegood, PE
17BP.9.R.33 Nov. 23, 2016 TBD $250,000 TBD Letting date delayed due to funding and other priorities.
unnamed creek in Davidson County. (336)249-6255
Bridge Preservation project - At this time, project will not be
Bridge Preservation – Bridge #31 on NC 8 and Bridge #82 Matt Jones, PE
41665.6A TBD TBD TBD $1,600,000 TBD pursued as designed. Looking at other avenues to replace or
on NC 47 in Davidson County (336)747-7800
rehab these bridges along with Bridge #55.
B-5165 Replace Bridge #46 on SR 1485 (Hampton Rd) over Muddy ROW Acquisition Dale Swicegood, PE
June 20, 2017 TBD $1,850,000 TBD *Schedule based on Approved 2016-2025 STIP
42341.3.1 Creek June 17, 2016 (336)249-6255
B-5765 Replace Bridge #115 on SR 1711 (Gumtree Rd) over ROW Acquisition Dale Swicegood, PE
Nov. 17, 2020 TBD $1,700,000 TBD *Schedule based on Approved 2016-2025 STIP
45721.3.1 WSSB RR Nov. 16, 2018 (336)249-6255
B-5773 Replace Bridge #25 on SR 3346 (S. Main St) over WSSB ROW Acquisition Dale Swicegood, PE
Dec. 17, 2024 TBD $3,250,000 TBD *Schedule based on Approved 2016-2025 STIP
45729.3.1 RR in Lexington July 15, 2022 (336)249-6255
B-5774 Replace Bridge #99 on SR 1810 (Clodfelter Rd) over ROW Acquisition Dale Swicegood, PE *Schedule based on Approved 2016-2025 STIP - Field
Feb. 26, 2020 TBD $1,200,000 TBD
45730.3.1 Brushy Creek March 31, 2019 (336)249-6255 scoping meeting held May 31, 2016
B-5776 Replace Bridge #100 on SR 1810 (Clodfelter Rd) over ROW Acquisition Dale Swicegood, PE *Schedule based on Approved 2016-2025 STIP - Field
Feb. 26, 2020 TBD $1,800,000 TBD
45732.3.1 Abbott's Creek March 31, 2019 (336)249-6255 scoping meeting held May 31, 2016
B-5777 ROW Acquisition Dale Swicegood, PE
Replace Bridge #58 on NC 109 over US 64 Feb. 15, 2022 TBD $1,850,000 TBD *Schedule based on Approved 2016-2025 STIP
45733.3.1 Feb. 19, 2021 (336)249-6255
B-5779 Replace Bridge #118 on US 29NB/64EB/70EB/I-85 Bus NB ROW Acquisition Dale Swicegood, PE *Schedule based on Approved 2016-2025 STIP - Coordinate
April 15, 2025 TBD $4,061,000 TBD
45735.3.1 over SR 3346 (N Main St) in Lexington April 19, 2024 (336)249-6255 with B-5785
B-5780 ROW Acquisition Dale Swicegood, PE
Replace Bridge #17 on NC 47 over Swearing Creek Dec. 14, 2016 TBD $1,400,000 TBD Structure and Geotech design in progress
45736.3.1 Acquisition in progress (336)249-6255
ROW Acquisition
B-5783 Replace Bridge #164 and Bridge #168 on US 29/70/I-85 Dale Swicegood, PE
April 15, 2025 TBD Acquisition $5,778,000 TBD *Schedule based on Approved 2016-2025 STIP
45738.3.1 Bus over NSRR (336)249-6255
April 19, 2024
B-5785 Replace Bridge #121 and Bridge #122 on US 29/70/I-85 ROW Acquisition Dale Swicegood, PE *Schedule based on Approved 2016-2025 STIP - Coordinate
Feb. 18, 2025 TBD $4,000,000 TBD
45740.3.1 Bus over Leonard Creek Feb. 16, 2024 (336)249-6255 with B-5779
B-5787 ROW Acquisition Dale Swicegood, PE
Replace Bridge #29 on NC 49 over NC 109 Sept. 19, 2023 TBD $2,000,000 TBD *Schedule based on Approved 2016-2025 STIP
45741.3.1 Sept. 16, 2022 (336)249-6255
I-5793 Pavement Rehabilitation of I-85 from SR 2025 (Squire Planning and Design in Chris Corriher, PE
Jan. 16, 2018 TBD $6,386,000 TBD DDRL - *Schedule based on Approved 2016-2025 STIP
53032.3.1 Bowers Rd) to 0.3 mi N. of NC 109 in Thomasville Progress (704)630-3200
24
Completion Construction Project
T.I.P. No. Description Let Date Status Contractor Comments
Date Cost Administrator
Centrally Managed Projects Under Development
R-5737 Convert at grade intersection to Interchange on US 29/70/I- ROW Acquisition Dale Swicegood, PE
March 16, 2021 TBD $15,000,000 TBD *Schedule based on Approved 2016-2025 STIP
50195.3.1 85 Bus at SR 1798 (Old Greensboro Rd) March 15, 2019 (336)249-6255
U-5757 Widen NC 8 (Winston Rd) to multi-lanes from 9th St to SR Planning and Design in Dale Swicegood, PE
June 26, 2019 TBD $1,254,000 TBD *Schedule based on Approved 2016-2025 STIP
54035.3.1 1408 (Biesecker Rd) in Lexington Progress (336)249-6255
U-5786 Widen SR 1508 (Hickory Tree Rd) from US 52/NC 8/Future ROW Acquisition Dale Swicegood, PE
Feb. 21, 2023 TBD $13,794,000 TBD *Schedule based on Approved 2016-2025 STIP
44358.3.1 I-285 to NC 150 Feb. 22, 2021 (336)249-6255
U-5902B Widen NC 150 to multilanes from SR 1493 (Frye Bridge Rd) ROW & Utilities Dale Swicegood, PE *Schedule based on Approved 2016-2025 STIP - New project
TBD TBD $33,150,000 TBD
44725.3.2 to Forsyth County Line TBD (336)249-6255 programmed due to additional revenue (HB 97)
Division Managed Projects under Development
Safety Improvements to median crossovers, etc., on I-85
W-5601CF Chris Corriher, PE Division Let. Public meeting held Jan. 14, 2016 at Davidson
Business from SR1797 (Evans Rd) to SR 1963 (Moose Jan. 25, 2017 TBD $600,000 TBD
50138.3.85 (704)630-3200 County Community College. No ROW required.
Lodge Rd) in Davidson Co.
Locally Administered Projects Under Development
Extend Sidewalks on SR 3346 (S Main St) and provide
C-5216 Planning/Design/ Right Chris Corriher, PE *Schedule based on Approved 2016-2025 STIP - Non-
wide paved shoulders on Anna Lewis Dr and Emergency Sept. 30, 2016 TBD $601,000 TBD
46261.3.1 of Way in progress (704)630-3200 DOT let (City of Lexington)
Dr. in Lexington
Provide wide paved shoulders and construct sidewalks on
C-5217 Planning/Design/ Right Chris Corriher, PE *Schedule based on Approved 2016-2025 STIP -
Cornelia St and Hillside Dr, bike and pedestrian Sept. 30, 2016 TBD $190,000 TBD
46262.3.1 of Way in progress (704)630-3200 Non-DOT let (City of Lexington)
improvements on Mize and Biesecker Rds.
Completed Projects
April 6, 2016 Construction is 100% complete. Awaiting removal of erosion
B-4741 Replace Bridge #38 on SR 1493 (Frye Bridge Rd) over (Perm. vegetation 100% Complete Dale Swicegood, PE
Dec. 16, 2014 $2,333,794 Dane Construction, Inc. control devices prior to final acceptance. Completed 2 months
38514.3.FD1 Muddy Creek in Davidson County established (30% ahead of schedule) (336)249-6255
Dec. 12, 2016) ahead of schedule.
July 1, 2016 Only work on punchlist items remains. Minimal to no impact to
C-4901A (Perm. vegetation 99% Complete Dale Swicegood, PE
NCRR/NS Mainline Bowers to Lake Railroad Roadbed June, 2013 $15,738,016 Blythe Construction, Inc. vehicular traffic. Awaiting permanent vegetation establishment
44001.3.STR01T4A established (5% ahead of schedule) (336)249-6255
Oct. 28, 2016) for final acceptance.
Davidson County Asphalt Surface Treatment (AST)
Chris Corriher, PE
9SP.20295.4 Retreatment (58.79 miles) of various Secondary routes in June 10, 2015 May 23, 2016 100% Complete $1,455,996 Blythe Construction, Inc. Work completed May 23, 2016.
(704)630-3200
Davidson Co.
25
Piedmont Authority for Regional Transportation Updates
for the High Point MPO TCC/TAC
June 2016
PART Express Updates
Mr. Howard Ingram is the Operator of the Month for
April. Mr. Ingram has been with us since May of 2015.
He does an excellent job driving Shuttle 23.
th
On Thursday, June 16 you’re invited to participate in
National Dump the Pump Day. It’s time to save
money, dump the pump and ride public transit.
Celebrate with PART and kick the gas prices to the
th
curb. Ride PART Express, FREE, on June 16 .
Shown Above: PART Express Ridership was 37,406 for April
2016 with a projection of 472,932 for FY 2016.
Alamance Regional Park & Ride Lot
The Alamance Regional Park & Ride Lot is now open. A
st
Ribbon Cutting Event was held on May 31 at the newly
constructed lot.
To learn more about PART’s programs and projects, please
visit www.partnc.org
Stay Connected with PART on Social Media!
“We’ve had a lot of involvement with this project from City of
Burlington, Cone Health, PART Staff, Link Transit, and others.
Planning for this facility has been years in the making and has taken
great leadership to get us to this point. The Alamance Regional Park &
th
Ride Lot is the 29 public use PART parking facility in the region. It is
also a great statistic to mention that there are now 7 Cone health
facilities served by PART Express. This connection in the community
is key and enhances mobility across the region.”
Scott Rhine, PART Executive Director
Page 1 of 2
26
Page 2 of 2
Regional Call Center Activities April PART Receives Safety Awards
Presented Calls: 6,549 Each year the North Carolina Department of Labor presents
Answered Calls: 6,246 Safety Awards in recognition of the outstanding safety and
Avg. % of Calls Answered: 95.4% health efforts for employees. For 2015 PART received three
Speed of Answer: 0:00:07 awards in the Gold category on behalf of PART
Avg. Call Duration: 0:00:52 Administration, PART Operations through National Express
Transit and PART Maintenance/Supervision through National
Express Transit. Congratulations to all PART and National
Express Transit employees for this achievement in safety and
health in the workplace!
Welcome Connie Conklin
Join us in welcoming Mrs. Connie Conklin, CPA to the
PART organization. Connie is our new Director of
Finance and Administration and will be replacing the
position held by Pat Webster, who is retiring later this
year. Connie comes to us with over 26 years' experience
in finance and accounting.
We are happy to have her on the PART team!
27