Board of Public Works
Regular MeetingKaukauna, WI · February 2, 2026
Minutes
BOARD OF PUBLIC WORKS
A meeting of the Board of Public Works was called to order by Chair Thiele on Monday, February 2,
2026, at 6:00 P.M.
Alders present: Antoine (Zoom), DeCoster, Eggleston, Kilgas, Moore, Schell, Schumacher, and
Thiele.
Also present: Mayor Penterman, Attorney Greenwood, DPW/Eng. Neumeier, Payroll Coordinator Ault,
Project Engineer Conger, Associate Planner Nelson, Fin. Dir. Van Rossum, Street Superintendent Van
Gompel, Senior Accountant Roehl (Zoom), Mark. and Com. Manager Fencl (Zoom), and interested
citizens.
1. Correspondence – none.
2. Discussion Topics.
a. Recommendation to Award Project 2-26: Wisconsin Avenue Area Utility Relay - Phase 1.
The Engineering Department has reviewed and analyzed ten bids received on January 28, 2026, at
4:00pm for Project 2-26 Wisconsin Avenue Area Utility Relay – Phase 1 and compared said bids
against the Engineer’s estimate that was put together prior to bid opening. The Engineer’s
estimate is compiled utilizing previous years’ prices and adjusted for inflation and changes in
work descriptions, while also anticipating where hidden costs may be. The lowest bidder was
$290,190.46 lower than the Engineer estimate, and was $75,626.71 lower than the second lowest
bidder, which shows that the city is getting a great price to complete this work. Nine of the ten
bidders were within $295,000 which shows that the bids were competitive, and that the city is
getting amazing pricing for this work.
Motion made by Moore, seconded by Schell to award Project #2-26 Wisconsin Avenue Area Utility
Relay – Phase 1 to Carl Bowers & Sons, Kaukauna, WI for Base Bid Units A thru C, a total amount
of $961,191.54.
All Ald. voted aye.
Motion carried.
b. Authorization to seek bids for Project 3-26 2026 Alley Paving Project.
The Engineering Department has completed survey and is finalizing design for the reconstruction
of the following alleys: Dixon/East Seventh Street Alley- Quinney Avenue to West terminus, East
Seventh/Eighth Street Alley- Crooks Avenue to Metoxen Avenue, West Fourth/Fifth Street Alley –
Miner Street to Main Avenue, and West Thirteenth/Fourteenth Street Alley – Hendricks Avenue to
Main Avenue. The alley reconstruction and paving work will include removal of existing pavements
and any existing base, installation of storm sewer in two of the alleys, installation stone base,
asphalt pavement, driveway aprons, and restoration.
Alders discussed concerns about how residents already paid for the street in front of their house
and now must pay for the alley behind their house. It was also discussed how the alleys are in
rough shape which makes it challenging for snow plowing and general access.
Alder Eggleston stated that it is unsustainable to have residents pay for two streets, especially in
older neighborhoods where the property values are not as high. While those assessments can be
placed on the tax roll for 10 years, it is still a large dollar amount. Alder Eggleston expressed how
financially challenging it could be to keep stacking assessments on residents.
Department of Public Works Engineer Neumeier, stated that some of these older neighborhoods
have never been repaved, had alleys repaved, or had any utilities redone, which is why these
assessments are all happening at once. Neumeier stated they could space the assessments out
but that would cost more money in maintenance, which is the trade off associated with holding off
on some assessments.
Motion made by Kilgas, seconded by Antoine to authorize the Engineering Department to seek
bids for Project #3-26, 2026 Alley Paving.
All Ald. voted aye.
Motion carried.
c. Authorization to seek bids for Project 8-26 2026 Sidewalk Rehabilitation Project.
The city completes a sidewalk replacement project every other year. A sidewalk replacement
project is scheduled for 2026. The purpose of the project is to identify sidewalks that are in the
right-of-way and are defective. In addition to rehabilitating sidewalks, the program will also inspect
crosswalk safety and make needed upgrades to existing crosswalks. Homeowners are given
notice of defective sidewalk abutting their property and are given an opportunity to complete the
work themselves or by a privately hired contractor. The City hired contractor will replace the
sidewalk if the homeowner fails to do so and the cost is then assessed back to the abutting
property owner.
Motion made by Moore, seconded by Eggleston to authorize the Engineering Department to seek
bids for Project 8-26: 2026 Sidewalk Replacement Program.
All Ald. Voted aye.
Motion carried.
d. Authorization to seek Proposals for LaFollette Park Pavilion and Site Design.
LaFollette Park is great local park with playground equipment, pickleball courts, basketball courts,
restrooms, a rental pavilion, along with other amenities and great views. This park is located along
Kenneth Avenue at Park Street and has close ties to the downtown, bus routes, the Nelson trail,
and future bike lanes, giving us an opportunity to make it a destination for local and regional
users. The park has aging restroom facilities, basketball surface, parking lot, and walking trails
that all need updates to bring the park back up to safe and accessible conditions.
Neumeier stated how they will involve the neighborhood and community in the design process by
sending out notices to people in the neighborhood and having public input meetings. Neumeier
also stated how they are not looking for bids at this time. They are looking for design services to
help lay out what the park should look like. Once they have a final design, it will come back for
permission to bid out the actual project.
Motion made by Schumacher, seconded by DeCoster to authorize the Engineering Department to
seek proposals for LaFollette Park Pavilion and Site Design.
All Ald. Voted aye.
Motion carried.
e. Authorization to seek Proposals for Design of Kenneth Avenue - W 10th Street to Reaume
Ave.
The City of Kaukauna has applied for and has been awarded a Surface Transportation Program
(STP) Urban project grant through Wisconsin Department of Transportation (WisDOT) for Kenneth
Avenue Reconstruction. The project design may start in fiscal year 2026 and construction has been
tentatively scheduled for 2029. The grant includes up to 80% funding for design, construction, and
oversight of participating costs.
Motion made by Kilgas, seconded by Moore to authorize the Director of Public Works to seek
Proposals for Design of Kenneth Avenue - W 10th Street to Reaume Ave.
All Ald. Voted aye.
Motion carried.
f. Safe Streets and Roads for All (SS4A) Transportation Grant for the County Highway KK
Corridor Study Project.
East Central Wisconsin Regional Planning Commission (ECWRPC), as the designated Appleton (Fox
Cities) Metropolitan Planning Organization (MPO), has been awarded a Safe Streets and Roads for
All grant of $842,876 from the U.S. Department of Transportation. The grant will be used for two
safety study projects in the Fox Cities area: completion of a County Highway KK Corridor study
spanning 4.5 miles between John Street and State Highway 55, and completion of a City of Appleton
Bicycle and Pedestrian Master Plan.
3. Adjourn.
Motion made by Eggleston, seconded by Schell to adjourn.
All Ald. voted aye.
Motion carried.
Meeting adjourned at 6:34 pm.
Kayla Nessmann, Clerk
Agenda
BOARD OF PUBLIC WORKS
City of Kaukauna
Council Chambers
Municipal Services Building
144 W. Second Street, Kaukauna
Monday, February 02, 2026 at 6:00 PM
AGENDA
In-Person and Remote Teleconference via ZOOM
1. Correspondence.
2. Discussion Topics.
a. Recommendation to Award Project 2-26: Wisconsin Avenue Area Utility Relay - Phase 1.
b. Authorization to seek bids for Project 3-26 2026 Alley Paving Project.
c. Authorization to seek bids for Project 8-26 2026 Sidewalk Rehabilitation Project.
d. Authorization to seek Proposals for LaFollette Park Pavilion and Site Design.
e. Authorization to seek Proposals for Design of Kenneth Avenue - W 10th Street to Reaume
Ave.
f. Safe Streets and Roads for All (SS4A) Transportation Grant for the County Highway KK
Corridor Study Project.
3. Adjourn.
NOTICES
Board of Public Works - Notice is hereby given this is a public meeting of the Board of Public Works.
As such, all members or a majority of the City’s Common Council and Standing Committees will
likely be in attendance. While members of the Common Council or any Standing Committees may
participate in discussions, only the Board of Public Works will take formal action.
IF REQUESTED THREE (3) DAYS PRIOR TO THE MEETING, A SIGN LANGUAGE INTERPRETER WILL
BE MADE AVAILABLE AT NO CHARGE.
MEETING ACCESS INFORMATION:
You can access this meeting by one of three methods: from your telephone, computer, or by an app.
Instructions are below.
To access the meeting by telephone:
1. Dial 1-312-626-6799
2. When prompted, enter Meeting ID 234 605 4161 followed by #
3. When prompted, enter Password 54130 followed by #
To access the meeting by computer:
1. Go to http://www.zoom.us
2. Click the blue link in the upper right hand side that says Join a Meeting
3. Enter Meeting ID 234 605 4161
4. Enter Password 54130
5. Allow Zoom to access your microphone or camera if you wish to speak during the meeting
To access the meeting by smartphone or tablet:
1. Download the free Zoom app to your device
2. Click the blue button that says Join a Meeting
3. Enter Meeting ID 234 605 4161
4. Enter Password 54130
5. Allow the app to access your microphone or camera if you wish to speak during the meeting
*Members of the public will be muted unless there is an agenda item that allows for public
comment or if a motion is made to open the floor to public comment.*
Get email alerts for Kaukauna
A daily email when new agendas and minutes are posted.