Board of Works
Regular MeetingLafayette, IN · July 2, 2013
Minutes
BOARD OF PUBLIC WORKS AND SAFETY
MINUTES
July 2, 2013
Regular Session:
The Board of Public Works and Safety met in regular session on Tuesday, July 2, 2013 at 9:00 a.m. in the
Common Council Chambers. Members present were: Gary Henriott, Cindy Murray, Ron Shriner, Norm
Childress and Dawn Ross.
Jacque Chosnek, 1st Deputy City Attorney, was also present.
President Henriott called the meeting to order.
The Pledge of Allegiance was given to the flag of our Country.
MINUTES
Mr. Childress moved for approval of the minutes from the June 25, 2013 regular meeting. Mrs. Murray
seconded. Passed.
BIDS UNDER ADVISEMENT
All Structure Demolition located at 1329 Central Street
President Henriott stated that this item will remain under advisement.
NEW BUSINESS
Engineering
Guaranteed Energy Savings Performance Contract-Durkees Run Interceptor & Earl Ave. Reconstruction
Phase 2B
Jenny Leshney, Public Works Director, presented to the Board and recommended approval of the
Guaranteed Energy Savings Performance Contract for Durkees Run Interceptor & Earl Ave
Reconstruction Phase 2B with Bowen Engineering in the amount of $7,044,700.00. Mrs. Leshney stated
that Phase 2B is from the intersection of Main Street and Earl Avenue to South Street for the installation
of the 84” diameter storm sewer and structure along with relocation of water main and overall road
reconstruction. The intersection of Main Street and Earl Avenue will be closed starting July 8th, 2013 for
approximately three weeks. Mark Chmeliwskyj, Butler, Fairman & Seufert Representative, stated that
Phase 2B encompasses stormwater pipe improvements from the intersection of Main Street and Earl
Avenue up to the intersection of Kossuth Street and Earl Avenue along with water main relocation to
allow the storm sewer to be constructed. Mr. Chmeliwskyj stated also that there will be temporary
patching over the storm sewer pipe, temporary curbing and permanent trail on the west side of the street
between Main Street and Kossuth Street. Discussion ensued. Ted Deahl, Bowen Engineering
Representative, stated that the calculations for the $9 million estimated savings for the City of Lafayette is
a stipulated savings that Butler, Fairman & Seufert, Bowen Engineering and the City of Lafayette
collectively worked on together to come up with. President Henriott stated that the estimated savings are
the best estimates at this point in time on how this infrastructure improvement will lower costs,
maintenance and improve results. Mrs. Leshney stated that the city will be evaluating how much flow will
Board of Public Works and Safety
July 2, 2013
Page 2
not be treated at the wastewater plant due to the new sewer system installation having a separate system,
not a combined system. Mr. Childress moved for approval. Mrs. Ross seconded. Passed.
Notice to Proceed- Guaranteed Energy Savings Performance Contract-Durkees Run Interceptor & Earl
Ave. Reconstruction Phase 2B
Mrs. Leshney presented to the Board and recommended approval of a Notice to Proceed Guaranteed
Energy Savings Performance Contract-Durkees Run Interceptor & Earl Ave. Reconstruction Phase 2B.
Construction will begin on July 8, 2013. Mr. Shriner moved for approval. Mrs. Ross seconded. Passed.
Change Order #2-Veterans Memorial Parkway Phase 2
Bob Foley, Engineering, presented to the Board and recommended approval of Change Order #2 for
Veterans Memorial Parkway Phase 2 in the amount of $37,800.00. Mr. Foley stated that the change order
is to remediate the failed subgrade on the trail and includes an additional 9 contract working days to
complete the subgrade treatment. Mr. Childress moved for approval. Mrs. Ross seconded. Passed.
CLAIMS
Mike Jones, Controller, presented for Board approval, Claims in the amount of $9,543,452.27. President
Henriott asked if there were any further questions other than the ones that were asked and answered in
caucus, there were none. Mr. Childress moved for approval. Mrs. Ross seconded. Passed.
Time: 9:16 a.m.
BOARD OF PUBLIC WORKS AND SAFETY
Gary Henriott s/s
President
ATTEST: Mindy Miller s/s
Mindy Miller, 1st Deputy Clerk
Minutes written by Mindy Miller, 1st Deputy Clerk
*A digital audio recording of this meeting is available in the Lafayette City Clerk’s Office.
Ordinance Violations Bureau
From the Office of the Engineer: 1st Letter Summary (95 issued) 2nd Letter Summary (1 issued) and
Ticket Summary (40 issued) from the Ordinance Violations Bureau for the month of June 2013
Board of Public Works and Safety
July 2, 2013
Page 3