Board of Works
Regular MeetingLafayette, IN · July 6, 2021
Minutes
BOARD OF PUBLIC WORKS AND SAFETY
MINUTES
July 6, 2021
Regular Session:
The Board of Public Works and Safety met in regular session on Tuesday, July 6, 2021 at 9:00 a.m. in the
Common Council Chambers. Members present were: Gary Henriott, Cindy Murray, Amy Moulton, Norm
Childress and Ron Shriner
Jacque Chosnek, City Attorney, was also present.
President Henriott called the meeting to order.
The Pledge of Allegiance was given to the flag of our Country.
MINUTES
Mrs. Moulton moved for approval of the minutes from the June 29, 2021 regular meeting. Mrs. Murray seconded.
Passed.
NEW BUSINESS
Engineering
Contract-Bonlou Drive Signal Installation Project
Jeromy Grenard, Public Works Director, presented to the Board and recommended approval of a Contract for the
Bonlou Drive Signal Installation Project with Hawk Enterprises. The contract is in the amount of $285,678.19.
Mr. Childress moved for approval. Mr. Shriner seconded. Passed.
Notice to Proceed-Bonlou Drive Signal Installation Project
Mr. Grenard presented to the Board and recommended approval of a Notice to Proceed for the Bonlou Drive
Signal Installation Project. The project is set to start today upon approval. Mrs. Moulton moved for approval. Mrs.
Murray seconded. Passed.
Change Order #1-2021 CDB Curb, Sidewalk, Approach and Ramp Replacement Project
Mr. Grenard presented to the Board and recommended approval of Change Order #1 for the 2021 CDBG Curb,
Sidewalk, Approach and Ramp Replacement Project with Dixon Construction. The change order includes
concrete and gutter, sidewalk and drive approach added for better transition to meet existing and fix drainage
issues. The change order is an addition in the amount of $22,608.50 which brings the revised contract amount to
$146,311.50. Mr. Shriner moved for approval. Mr. Childress seconded. Passed.
Change Order #1-Treece Meadows North Entrance Reconstruction
Mr. Grenard presented to the Board and recommended approval of Change Order #1 for the Treece Meadows
North Entrance Reconstruction with Heartland Contractors. The change order includes addition of handicap
ramps and complete ramps at the intersection. The change order is an addition in the amount of $3,800.00 which
brings the revised contract amount to $66,172.00. Mr. Childress moved for approval. Mrs. Moulton seconded.
Passed.
Board of Public Works and Safety
July 6, 2021
Page 2
CLAIMS
Jenna Karle, Controller’s Office, presented for Board approval, Claims in the amount of $3,958,802.40. President
Henriott asked a question on Page 29 regarding the Gripp Incorporated invoice for Additional Rain Gauge
System. Mrs. Karla stated that those rain gauges are for Lafayette Renew. Brad Talley, Renew Superintendent,
explained how the rain gauges are utilized with the system along with the importance of the data they provide.
Mrs. Murray moved for approval. Mrs. Moulton seconded. Passed.
Mrs. Murray announced that the Common Council meeting will be held tonight at 6:00pm due to Independence
Day Holiday observance yesterday.
Time: 9:09 a.m.
BOARD OF PUBLIC WORKS AND SAFETY
Gary Henriott s/s
President
ATTEST: Mindy Miller s/s
Mindy Miller, 1st Deputy Clerk
Minutes written by Mindy Miller, 1st Deputy Clerk
*A digital audio recording of this meeting is available in the Lafayette City Clerk’s Office or online at
http://www.lafayette.in.gov/agendacenter.
**A list of all permits issued for the preceding week is available at
http://www.lafayette.in.gov/DocumentCenter/Index/375
Get email alerts for Lafayette
A daily email when new agendas and minutes are posted.