Redevelopment Commission
Regular MeetingLafayette, IN · July 22, 2021
Minutes
~
LAFAYETTE
~
MINUTES OF THE
LAFAYETTE REDEVElOPMENT COMMISSION
July 22, 2021
11:00 am
Council Chambers, City Hall
Attendance
Commissioners: Shelly Henriott, Jos Holman, Jim Terry, T.J. Thieme
Absent:
Ex-Officio Members: Dave Moulton, Josh Loggins
Absent:
Staff: Dennis Carson, Economic Development Director; John Collier, Economic Development Assistant Director; David
Huhnke, Marketing Director; Jacque Chosnek, City Attorney; Cindy Murray, City Clerk; Jeremy Diehl, Controller; Jeromy
Grenard, City Engineer; Dave Griffee, Asst. Director of Public Works; Mayor Roswarski
Guests: Alex Gonzalez, Kettelhut Construction, Inc.; Tim Balensiefer, TBIRD Design Services; Margaret Troup, Journal &
Courier
Welcome and Call to Order
Jos Holman welcomed everyone to the Redevelopment Commission meeting, noted that a quorum was present and
opened the meeting of the Lafayette Redevelopment Commission at 11:00am.
Minutes
Shelly Henriott moved to approve the minutes of the June 24, 2021 meeting. T.J. Thieme seconded and the motion
passed unanimously.
New Business
Kettelhut Inc.: Public Safety Building & Parking Garage Change Order #l-Bid Event #2 Core and Shell -Presented by
Alex Gonzalez of Kettelhut, Inc., this is a Change Order to the CMc at risk contract we have with Kettelhut Inc. for
construction of the Public Safety Building and Parking Garage. This represents Bid Package #2 of our three packages
and Guaranteed Maximum Prices {GMP}. This change order/bid event agreement is for the core and shell work such as
masonry, metal louvers, covers, roofing, waterproofing of the amenity deck, framing, exterior curtain wall and doors
and totals $5,939,507. Bid Package #1 was approved for $14,250,933. The project total to date is $20,190,440. One
more final bid package is expected to be released for bid later in August. T.J. Thieme moved to approve. Jim Terry
seconded and the motion passed unanimously.
TBIRD Design Services Corporation: Engineer's Services-S 4th Street Boundary and Topography Survey - The
agreement is for TBIRD Design Services to evaluate the former rail corridor land between 3rd and 5th Streets. With the
overall development climate strong, the City would like to consider uses for this area, but needs good baseline
information. Once the survey is complete, we can better evaluate potential uses for the area and decide on how to
proceed. This contract, presented by Tim Balensiefer, will be in the amount of $27,400 plus up to $600 in reimbursable
expenses. Jim Terry moved to approve. Shelly Henriott seconded and the motion passed unanimously.
Director's Report
Dennis stated that work on the Public Safety Building and Garage is moving along well. We are currently looking over
details of exterior signage, the furniture package and other interior/exterior details. Alex Gonzalez of Kettelhut
Construction, Inc. gave more specific details on the construction aspect ofthe project. Excavation is underway to
accommodate the lower level of the parking garage and overhead utilities in the alley are being moved underground.
The steel is expected to arrive in September. Bids for Package #3 are expected at the end of August and will be
presented for approval in September.
Claims
Jim Terry moved to approve the July 2021 claims in the amount of Four Million, Three Hundred Three Thousand, Five
Hundred Thirty-Eight Dollars and Fifteen Cents ($4,303,538.15). Shelly Henriott seconded and the motion passed
unanimously.
Public Comment
There were no comments received from the public.
Adjournment
Shelly Henriott moved to adjourn the meeting. T.J. Thieme seconded and the motion passed unanimously. The meeting
of the Lafayette Redevelopment Commission was adjourned at l1:13am.
Respectfully submitted
Michelle Conwell, Recording Secretary
AP~
T.J hleme, Secretary
Lafayette Redevelopment Commission
Get email alerts for Lafayette