Committee Chairman Marc Moonen called the meeting to order at 5:01 p.m.
Roll Call: Present: Trustee Marc Moonen (Chair); Trustee Linda Beal (Vice-Chair); Committee members
Jane Mueller, and Joe Eberle; Utility District Accountant Mike Sargent; Village Engineer Don Neitzel (via
Zoom); DPW Director Nick Wilichowski; Administrator Kathy Nickolaus; and Clerk Elisa Cappozzo Katch to
record the minutes. Committee member Dan Plese was absent and excused.
The Committee and members of the public recited the Pledge of Allegiance.
Citizen Comment: None.
Minutes – 2/21/2024 Public Works & Utility Committee
Motion by Mueller, second by Eberle, to approve the minutes of the February 21, 2024 Public Works &
Utility Committee meeting as presented. Motion carried.
Department Reports
A. Dept. of Public Works
DPW Director Nick Wilichowski gave a brief update on current DPW projects and accomplishments (see
attached). No action was taken.
B. Utility District
Engineer Don Neitzel gave a brief update of current Utility District projects and accomplishments (see
attached). No action was taken.
Trustee Moonen directed Engineer Neitzel and Administrator Nickolaus to research agreement with
Richmond School regarding fees and percentage split, and asked Administrator Nickolaus to follow up
with a letter to the School.
Unfinished Business
A. Discussion and necessary action regarding possible Sewer Rate study
The Committee directed Administrator Nickolaus to check with Ehlers regarding a possible rate study.
No action was taken.
B. Discussion and necessary action regarding Richmond Force Main maintenance or replacement
Motion by Moonen to table the matter until the April meeting to allow time for additional information
gathering. The motion was seconded by Beal, was voted on, and carried unanimously.
New Business
A. Bid Award for 2024 Pavement Resurfacing Program
Motion by Eberle, second by Mueller, to award base bid only to Payne + Dolan for $369,550.00, and
recommendation to Village Board of the same. The motion was voted on and carried unanimously.
Office: (262)246-6100 | Email: villagehall@lisbonwi.gov | Web: www.LisbonWI.gov
Public Works & Utility Committee Minutes
March 20, 2024
Page 2 of 2
Items to be Placed on a Future Agenda
Engineer Neitzel will bring information regarding possible Sewer Service area extension for gravity sewer
to the April meeting.
Adjournment
There being no further business, Beal moved to adjourn. The motion was seconded by Eberle, was voted
on, and carried unanimously. The meeting was adjourned at 5:56p.m.
Respectfully submitted,
Elisa Cappozzo Katch, WCMC
Lisbon Village Clerk
Office: (262)246-6100 | Email: villagehall@lisbonwi.gov | Web: www.LisbonWI.gov
Agenda
VILLAGE OF LISBON
W234 N8676 Woodside Rd.
Lisbon, WI 53089
A.
Join Zoom Meeting Online: https://us06web.zoom.us/j/88319721129?pwd=Rm1tdkgzcW9PMG5HY051MlBpbzR4UT09
Join Zoom by Phone: Dial 1-312-626-6799 Meeting ID: 883 1972 1129 Passcode: 027704
PUBLIC WORKS & UTILITY COMMITTEE MEETING AGENDA
Lisbon Village Hall
Wednesday, March 20, 2024
5:00 P.M.
1. Call to Order and Roll Call
2. Pledge of Allegiance
3. Citizen Comment (Please limit your comments to three minutes)
4. Approval of Meeting Minutes:
• 2/21/2024 Public Works & Utility Committee
5. Department Reports
A. Department of Public Works – Nick Wilichowski
B. Utility District – Don Neitzel
6. Unfinished Business
A. Discussion and necessary action regarding possible sewer rate study, and recommendation to the
Village Board of the same.
B. Discussion and necessary action regarding Richmond Force Main maintenance or replacement, and
recommendation to the Village Board of the same.
7. New Business
A. Discussion and necessary action regarding bid award for 2024 Pavement Resurfacing Program, and
recommendation to the Village Board of the same.
8. Items to be Placed on a Future Agenda
9. Adjournment
NOTE: It is possible that members of and possibly a quorum of members of other governmental bodies of the municipality may attend the above
meeting(s) to gather information. No action will be taken by any governmental body other than that specifically noticed above. Requests from persons
with disabilities who need assistance to participate in this meeting or hearing should be made to the Village Clerk’s office at 262-246-6100 at least 72
hours in advance of the meeting.
Village of Lisbon | W234N8676 Woodside Road, Lisbon WI 53089-1545 | (262)246-6100 | www.LisbonWI.gov
VILLAGE OF LISBON
Public Works & Utility Committee Minutes
February 21, 2024
DRAFT
PUBLIC WORKS & UTILITY COMMITTEE MINUTES
The regular meeting of the Lisbon Public Works & Utility Committee was held on Wednesday, February
21, 2024, at the Lisbon Village Hall, W234 N8676 Woodside Road, Lisbon, WI.
Committee Chairman Marc Moonen called the meeting to order at 5:00 p.m.
Roll Call:
Present: Trustee Marc Moonen (Chair); Trustee Linda Beal (Vice-Chair); Committee members Jane Mueller,
Joe Eberle, and Dan Plese; Utility District Accountant Mike Sargent; Village Engineer Don Neitzel; DPW
Director Joe DeStefano; and Administrator Kathy Nickolaus. Clerk Elisa Cappozzo Katch was absent and
excused.
Pledge of Allegiance
The Committee and members of the public recited the Pledge of Allegiance.
Citizen Comment
None.
Minutes – 1/17/2024 Public Works & Utility Committee
Motion by Mueller, second by Eberle, to approve the minutes of the January 17, 2024 Public Works &
Utility Committee meeting as presented. Motion carried 4:0, with Beal abstaining.
Department Reports
A. Dept. of Public Works
DPW Director Joe DeStefano gave a brief update on current DPW projects and accomplishments (see
attached). No action was taken.
B. Utility District
Utility Administrator Mike Sargent reported on flows for the Utility District (attached). Engineer Don
Neitzel gave a brief update of current Utility District projects and accomplishments (see attached). No
action was taken.
Unfinished Business
A. Consideration of possible sewer rate study
Don will bring additional information to the next meeting. No action was taken.
B. Consideration of Richmond Force Main maintenance or replacement
Don will bring additional information to the next meeting. No action was taken.
New Business
A. Approve purchase of UTV for Parks Division
Motion by Moonen to approve purchase of a UTV from Proven Power, Inc., in an amount not to exceed
$45,393.40, and recommendation to Village Board of the same. The motion was seconded by Beal,
was voted on, and carried unanimously.
Office: (262)246-6100 | Email: villagehall@lisbonwi.gov | Web: www.LisbonWI.gov
Public Works & Utility Committee Minutes
February 21, 2024
Page 2 of 2
B. Approve purchase of body/plow package for 2025 Western Star 47X
Motion by Eberle to approve purchase of a complete body and plow package from Burke Truck, in an
amount not to exceed $135,086.60, and recommendation to Village Board of the same. The motion
was seconded by Plese, was voted on, and carried unanimously.
C. Discussion and necessary action re: 2025 Water Pollution Control Facility (WPCF) project
No action was taken.
D. Discussion and necessary action re: possible water service to Willow Springs
No action was taken.
E. Discussion and necessary action re: increase in Sussex billing for system in-flow & infiltration
No action was taken.
There being no further business, Trustee Beal took her leave.
Items to be included on a future Agenda
None.
Adjournment
There being no further business, Eberle moved to adjourn. The motion was seconded by Mueller, was
voted on, and carried unanimously. The meeting was adjourned at 7:15p.m.
Respectfully submitted,
Kathy Nickolaus
Lisbon Administrator
Office: (262)246-6100 | Email: villagehall@lisbonwi.gov | Web: www.LisbonWI.gov
February 2024
DPW Monthly
Report
Highway Division
• Staff went out for 4 winter weather events in February.
• Staff brined roads ahead of weather events in February.
• Staff had salt delivered and pushed up into the salt shed.
• Staff washed plow trucks when able in between events.
• Staff cut and trimmed trees with Sussex’s bucket truck in Thousand Oaks Subdivision,
Plainview Road, Hillside Road, Oakwood Road, and Good Hope Road.
• Staff picked up Christmas trees as time permitted.
• Staff performed repairs and preventive maintenance on HWY and FD trucks and equipment
as needed and able.
Parks Division
• Staff plowed in 3 events with the Highway Division.
• Staff has been working on the demo and renovation of the Park Maintenance building
lunchroom, office, and bathroom. It is coming together nicely.
• Staff monitored garbage and bathrooms at all Parks.
• Staff performed repairs and preventive maintenance on Parks trucks and equipment as
needed.
DPW Director
• I attended and conducted the Feb. 7th WCPWA meeting.
• I attended the Feb. 21st PW and U Meeting.
• I plowed/salted in 3 weather events .
• I continued to get all Capital items squared away before I leave.
• I have been prepping as good as I can for the next Director.
• I continued to take care of invoices, r/w permits, capital projects, all clerical tasks
needed and helped around the shop or in the field as needed.
Regards,
Joe DeStefano Jr.
DPW Director
MEMORANDUM
March 15, 2024
To: Village of Lisbon Utility Committee
From: Don Neitzel
Re: Monthly Report
The monthly engineer’s report for the Village of Lisbon Utility Committee is as follows:
February 2024 Flows – Flows remained up to start the month, which was the
case at the end of January due to the warmer weather and rain. Flows were
trending back down toward the end of February. Average flows for the month
were 35 GPM for Jeanine Lift Station, 32 GPM for Plainview, and 31 GPM
for Willow Springs. (see attached graphs for historical flows and current
month).
Richmond School Lift Station - Richmond School Lift Station continued to
operate on the new Pump #1 to start the month. The new Pump #2 was
installed on February 12th. The total run time in hours for the month of
January was 33 hours. Please refer to graph for historical flow data and
current month.
Business Park East – Awaiting final payment request.
Manhole and Sewer Repairs – I spoke with Visu-Sewer today and the are
currently hoping for late April/ early May to get at this work. This is weather
dependent however.
Sewer System Maps (GIS) – No update
2024 Sanitary Sewer Cleaning/Televising – Received email from The
Expediters stating they would like to begin work in early April, if not
sooner. I told them I would confirm that the contract has been
approved by the Village and would get back to them next week.
March 11, 2024
Kathy Nickolaus, Town Administrator
Village of Lisbon
W234N8676 Woodside Road
Lisbon, Wisconsin 53089
107 PARALLEL STREET Re: 2024 Pavement Resurfacing Program
BEAVER DAM, WI 53916
Construction Contract Award Recommendation
1115 S MAIN STREET
WEST BEND, WI 53095
Dear Ms. Nickolaus:
920-356-9447
FAX 920-356-9454
KUNKELENGINEERING.COM
Please find accompanying this transmittal the Bid Tabulation for the 2024 Pavement
Resurfacing Program that was bid on Friday, March 8, 2024. As is evident, Payne & Dolan,
from Waukesha, Wisconsin submitted the low base bid (Thousand Oaks Area) in the amount
of $369,550.00. Three competitive bids were received.
In addition to the base bid, two alternate bids were received. Below are Payne & Dolan’s
bidding results for said alternates:
• Alternate 1 – High Road: $65,563.00
• Alternate 2 – Cordell Drive: $62,342.50.
Based upon the Village’s budgetary requirements, and our analysis and our understanding of
the Contractor’s past work efforts, we heretofore recommend that the Village of Lisbon award
a construction contract to Payne & Dolan, from Waukesha, Wisconsin, in the amount of
$431,892.50 (Base Bid + Alternate 2) with the project schedule to begin in Spring 2024.
Kathy, should either you or the Village Board have any questions or comments regarding this
transmittal, please contact me at your convenience.
Sincerely,
KUNKEL ENGINEERING GROUP
Mitchell Leisses
Office/Project Manager
Enclosure
cc: Elisa Cappozzo, Clerk
BID TABULATION
Village of Lisbon
2024 Pavement Resurfacing Program
Friday, March 8, 2024 10:00 a.m.
Village Hall W234N8676 Woodside Road Lisbon, WI
Payne & Dolan, Waukesha, Stark Pavement Corp,
Thousand Oaks Area (Kettle Cove Lane, Justin's Way, Meadow Wood Lane) WI Brookfield, WI Wolf Paving, Hartland, WI
Item No. Item Description Quantity Unit Unit Price Total Unit Price Total Unit Price Total
1 Mill Asphalt Pavement, Full Depth 12,300 SY $6.10 $75,030.00 $4.30 $52,890.00 $5.50 $67,650.00
2 Undercutting and Base Course Material 1,230 CY $50.00 $61,500.00 $57.65 $70,909.50 $70.00 $86,100.00
3 Hot Mix Asphalt Pavement 3,700 TN $61.30 $226,810.00 $65.55 $242,535.00 $66.00 $244,200.00
4 Shoulder Restoration 110 TN $11.00 $1,210.00 $40.00 $4,400.00 $34.75 $3,822.50
5 Erosion Control 1 LS $1,000.00 $1,000.00 $500.00 $500.00 $350.00 $350.00
6 Traffic Control and Access 1 LS $2,000.00 $2,000.00 $10,500.00 $10,500.00 $2,350.00 $2,350.00
7 Contract Allowance for Materials and Compaction Testing 1 LS $2,000.00 $2,000.00 $2,000.00 $2,000.00 $2,000.00 $2,000.00
Thousand Oaks Totals $369,550.00 $383,734.50 $406,472.50
Alternate 1 - High Road
Item No. Item Description Quantity Unit Unit Price Total Unit Price Total Unit Price Total
8 Mill Asphalt Pavement, Ful Depth 1,750 SY $11.20 $19,600.00 $5.00 $8,750.00 $7.20 $12,600.00
9 Undercutting and Base course Material 175 CY $50.00 $8,750.00 $61.00 $10,675.00 $82.00 $14,350.00
10 Hot Mix Asphalt Pavement 510 TN $61.30 $31,263.00 $72.00 $36,720.00 $74.00 $37,740.00
11 Shoulder Restoration 20 TN $11.00 $220.00 $103.00 $2,060.00 $118.00 $2,360.00
12 Epoxy Pavement Markings, 4-Inch 2,000 LF $1.80 $3,600.00 $1.80 $3,600.00 $1.80 $3,600.00
13 Epoxy Pavement Markings, 18-Inch 35 LF $18.00 $630.00 $18.00 $630.00 $18.00 $630.00
14 Erosion Control 1 LS $500.00 $500.00 $200.00 $200.00 $100.00 $100.00
15 Traffic Control and Access 1 LS $500.00 $500.00 $3,000.00 $3,000.00 $860.00 $860.00
16 Contract Allowance for Materials and Compaction Testing 1 LS $500.00 $500.00 $500.00 $500.00 $500.00 $500.00
High Road Totals $65,563.00 $66,135.00 $72,740.00
Alternate 2 - Cordell Drive
Item No. Item Description Quantity Unit Unit Price Total Unit Price Total Unit Price Total
17 Mill Asphalt Pavement, Full Depth 1,600 SY $11.85 $18,960.00 $6.00 $9,600.00 $7.20 $11,520.00
18 Undercutting and Base Course Material 160 CY $50.00 $8,000.00 $50.50 $8,080.00 $82.00 $13,120.00
19 Hot Mix Asphalt Pavement 475 TN $71.30 $33,867.50 $76.00 $36,100.00 $74.00 $35,150.00
20 Shoulder Restoration 15 TN $11.00 $165.00 $100.00 $1,500.00 $98.00 $1,470.00
21 Erosion Control 1 LS $350.00 $350.00 $700.00 $700.00 $100.00 $100.00
22 Traffic Control and Access 1 LS $500.00 $500.00 $3,200.00 $3,200.00 $820.00 $820.00
23 Contract Allowance for Materials and Compaction Testing 1 LS $500.00 $500.00 $500.00 $500.00 $500.00 $500.00
Cordell Dr Totals $62,342.50 $59,680.00 $62,680.00