Conservation Commission
Regular MeetingLowell, MA · December 8, 2021
Minutes
CONSERVATION COMMISSION
LOWELL, MASSACHUSETTS
December 8, 2021
Note: These minutes are not completed verbatim. For further detail, video recordings are available at
the Pollard Library, second floor reference desk or online at www.LTC.org.
Due to the COVID-19 pandemic, this meeting was held both in person and virtually using Zoom.
Members Present: Chairwoman Varnum, Brad Buitenhuys, Weston Standish, Stephen Laput, William
Lovely (Zoom)
Members Absent: Kevin Dillon and Perry Downs
Others Present: Peter Cutrumbes, Assistant Planner
CALL TO ORDER
The meeting was called to order by Chairwoman Varnum at 7:02 PM.
ORDER OF BUSINESS
CONTINUED BUSINESS
Notice of Intent
John Faneros
16 Mount Joy Drive
Tewksbury, MA 01876
DEP #: Pending
Project Location: 19 Clifton Street, 01850
A Notice of Intent has been filed by John Faneros to construct a new single family house within the 100-
year flood plain. This project has not received a filing number from Massachusetts DEP.
On Behalf: Ken Lania, Engineer, presented the project. K. Lania said that the compensation area would
be excavated out in advance of the construction.
Speaking in Favor: None
Speaking in Opposition: Denise Roy, 7 Clifton Street, is an abutter and expressed her opposition. She
says the back area of the lot continually floods.
Discussion: L. Varnum asked if there would be additional staging and fencing in the area, as it has fallen
into disrepair. K. Lania said that they would be happy to meet any conditions the Conservation
Commission asks. L.Varnum said that the backyard during a recent site visit was damp. K. Lania said that
he believes it may be because of a high water table. B. Lovely asked if we could display the Site Plan next
time.
Motion: B. Buitenhuys motioned to continue to 1/12, with W. Standish seconding. The motion passed
unanimously (5-0).
Request for Determination of Applicability
Sovann Kong
1535 Middlesex Street
Lowell, MA 01851
Project Location: 51-57 Shirley Avenue, 01854
A Request for Determination of Applicability has been filed by Sovann Kong to remove brush. The
proposed work will take place in the 100-year floodplain.
On Behalf:
Speaking in Favor:
Speaking in Opposition:
Discussion:
Motion: W. Lovely moved to continue to the 1/26 meeting, and was seconded by B. Buitenhuys. The
vote was unanimous (5-0).
Request for Determination of Applicability
Chantho Mo
138 Martin Street
Lowell, MA 01854
Project Location: 138 Martin Street, 01854
A Request for Determination of Applicability has been filed by Chantho Mo seeking approval to repave
and expand their driveway which was previously expanded in the 100-year floodplain without
Conservation Commission approval. The applicant is also seeking approval to reconstruct and expand a
deck which has fallen into disrepair in the 100-year floodplain.
On Behalf:
Speaking in Favor:
Speaking in Opposition:
Discussion: B. Buitenhuys did feel that the additional paved area did not alter the contour.
Motion: B. Buitenhuys moved to continue to 1/26, and was seconded by W. Standish. The motion
passed unanimously (5-0).
Request for Determination of Applicability
Suelene Caetano
509 Wentworth Avenue
Lowell, MA 01852
Project Location: 509 Wentworth Avenue, 01852
A Request for Determination of Applicability has been filed by Suelene Caetano to construct a three-
season porch within the 100-year floodplain.
On Behalf:
Speaking in Favor:
Speaking in Opposition:
Discussion: No property owner at the meeting.
Motion: B. Buitenhuys motioned to continue to 1/12, and was seconded by W. Standish. The motion
passed unanimously (5-0).
NEW BUSINESS
Request for Determination of Applicability
Lowell Regional Water Utility
815 Pawtucket Boulevard
Lowell, MA 01854
Project Location: Pawtucket Boulevard and Varnum Avenue, 01854
A Request for Determination of Applicability has been filed by the Lowell Regional Water Utility to
connect an existing water main at Dunbar Avenue and Pawtucket Boulevard to a new water main which
will extend and connect to an existing water main at the intersection of Varnum Avenue and Mammoth
Road.
On Behalf: Evan Walsh from the LRWU introduced the project. The project will provide redundancy
across the river, but will have to go under culverts on the brooks in the area.
Speaking in Favor:
Speaking in Opposition:
Discussion: L. Varnum asked about erosion controls. Paul Pyros spoke to the erosion controls they will
be providing on both sides of the roads. He said they are planning on straw waddles, but are happy to
take Commission recommendations. L. Varnum asked when the work would happen. P. Pyros said from
roughly July-November of 2022 for the water main, and final paving restoration will take place in the
spring of 2023. W. Lovely asked if there are any other planned projects in this area. E. Walsh said
because it will be repaved, it will be under a 5 year moratorium.
Motion: B. Buitenhuys moves to make a negative III determination, which was seconded by S. Laput. The
motion was unanimous (5-0).
Certificate of Compliance
Riverbank Properties, LLC
908-966 Lawrence Street
Lowell, MA 01852
DEP #: 206-0800
Project Location: 908-966 Lawrence Street, 01852
A Request for a Certificate of Compliance has been filed by Cornerstone Land Associates, on behalf of
Riverbank Properties, LLC, for their parking expansion project at 908-966 Lawrence Street.
On Behalf: K. Lania spoke on behalf of the project. He said that obtaining the required materials was
delayed during the pandemic, but all the conditions and stabilization required by the Commission have
been met.
Speaking in Favor:
Speaking in Opposition:
Discussion: L. Varnum asked about the slope leading up to the water between the granite curbing and
the river. K. Lania said the landscaping and loam has been installed. L. Varnum asked about revisiting
this in the spring to see if it is stabilized. In particular, she expressed concern about erosion around the
tree trunks. B. Buitenhuys expressed a desire for a 2 year monitoring period and for the mulch to be
pulled back and replaced with grass.
Motion: B. Buitenhuys motioned to grant with the condition of a 2 year monitoring period and the
removal of mulch from the slope on the northeast corner of the site and plant some mixed grasses. The
motion was seconded by S. Laput. The motion passed unanimously (5-0).
Notice of Intent
Aravind Srinivasan
Anka Homes, LLC
34 Arcola Street
Lexington, MA 02420
DEP #: 206-0809
Project Location: 87 Lafayette Street, 01854
A Notice of Intent has been filed by Anka Homes, LLC to construct a single-family home and driveway
within the 100-year floodplain.
On Behalf:
Speaking in Favor:
Speaking in Opposition: Paul Belley, 65 Alma Street, spoke in opposition due to 2 flood events in the last
20 years. Jason Perry, 99 Rosemont Street, spoke strongly in opposition. Sharon Janda 84 Lafayette
Street, expressed similar concerns, and noted that the runoff from this property runs into her driveway.
Janet Callan (104 Elm Street) and Stephen Laderoute (78-80 Alma Street) expressed similar concerns.
Discussion: L. Varnum asked if there would be testing of the soil on the site. Representative for the
applicant, Michel El-Ashkar, said they would be doing this. M. El-Ashkar said the first floor would be
above the flood line. L. Varnum said the Commission’s concern is anything taking up space in the flood
plain area that would prevent water retention. M. El-Ashkar said he has been making changes after
speaking to City Engineer and Wastewater staff. B. Buitenhuys asked how they will account for
additional volume in the flood zone, which are is attributable to the supports. W. Lovely said that there
is not sufficient information to take a vote. He also said that the size of the footings could change based
on storm conditions. He said he is in favor of continuing with the feeling that there is not enough
information. L. Varnum said she wants to see the results of the test pits, the slab details, and the volume
replacement. B. Buitenhuys suggested that perhaps approval could be dependent on the results of the
test pit. W. Standish said that flood plain compensation should be the main concern. W. Lovely said they
must confirm that there is no lost flood storage within each contour, and that more clarity is required
around onsite stormwater management. B. Buitenhuys said he will not approve the project if there is
not compensation for any flood storage lost.
Motion: L. Varnum moved to continue to 1/26, which was seconded by S. Laput. The motion passed
unanimously, (5-0).
Request for Determination of Applicability
Hardik Patel
11 Perron Way
Lowell, MA 01854
Project Location: 11 Perron Way, 01854
A Request for Determination of Applicability has been filed by Marcos de Oliveira, on behalf of Hardik
Patel, to construct an addition to the single family home at 11 Perron Way within the 100-ft buffer zone
to the Bordering Vegetated Wetlands (BVW).
On Behalf:
Speaking in Favor:
Speaking in Opposition:
Discussion: L. Varnum said it is outside the buffer but that the Commission is concerned about loose soil
or debris rolling down the hill, and asked if they can put up a silt fence. J. Silva agreed.
Motion: W. Standish motioned to issue a negative 3 determination, and B. Buitenhuys seconded. Motion
passed unanimously.
OTHER BUSINESS
Election of Officers
W. Standish motioned to continue to 1/12, and was seconded by B. Buitenhuys. This motion passed
unanimously (5-0).
Public Hearing on National Grid’s Updated Proposal for the Lowell Area Gas Modernization Project
L. Varnum discussed some of the conditions for the agreement, including a donation for conservation in
the City and the preservation of some large trees along the construction. W. Lovely discussed the
various conditions of the MASSDEP superseding order of conditions. W. Standish asked what the
minimum diameter was to preserve the trees. National Grid answered 16-24 inches.
M. Jorgenson said they are voting to accept the amended NOI pursuant to the WPA and issue the
superseding order of conditions under the local wetlands bylaw. W. Lovely motioned to issue an
approval of the amended Notice of Intent pursuant to the City of Lowell wetlands ordinance, and issue a
City OOC with the following 3 conditions 1) save the trees outlined in the amended plan following the
site visit, 2) accept the $14,000 donation to offset the lost trees, 3) ensure that the natural regeneration
of the area takes place by incorporating the specific conditions from the DEP superseding order of
conditions, and was seconded by W. Standish. The vote was 4-0-1 (B. Buitenhuys abstaining).
ADJOURNMENT
B. Buitenhuys motioned to adjourn, and W. Standish seconded. The vote was unanimous, (5-0).
Adjourned at 8:38 PM.
Agenda
The City of Lowell • Dept. of Planning and Development • Division of Development Services
Lowell City Hall • 375 Merrimack Street • Lowell, MA 01852
P: 978.674.4144 • F: 978.446.7103
www.LowellMA.gov
Christine McCall
Assistant City Manager/DPD Director
R. Eric Slagle
Director of Development Services
December 3, 2021
In accordance with the Massachusetts General Laws Chapter 131, Section 40, and the City of Lowell
Wetland Ordinance Section 280.1-13, the Lowell Conservation Commission will hold a meeting on
Wednesday, December 8, 2021 at 7:00 PM.
This meeting will occur in-person with the option to join remotely. You can choose to attend in-person
in the City Council Chambers, City Hall, 375 Merrimack Street, Lowell MA 01852; or you can choose to
attend remotely by using one of the following four options to access the meeting:
1. Join using your computer, tablet, or smartphone: https://lowellma.zoom.us/j/9410770919
2. Call (646) 558 8656 and enter the MEETING ID: 941 077 0919
3. Watch LTC channel 99
4. Watch LTC online at: https://www.ltc.org/watch/channel-99/
Review the project materials online at: https://lowellma.gov/1100/Conservation-Commission
AGENDA
CALL TO ORDER
ORDER OF BUSINESS
CONTINUED BUSINESS
Notice of Intent
John Faneros
16 Mount Joy Drive
Tewksbury, MA 01876
DEP #: Pending
Project Location: 19 Clifton Street, 01850
A Notice of Intent has been filed by John Faneros to construct a new single family house within the 100-
year flood plain. This project has not received a filing number from Massachusetts DEP.
Request for Determination of Applicability
Sovann Kong
1535 Middlesex Street
Lowell, MA 01851
Project Location: 51-57 Shirley Avenue, 01854
A Request for Determination of Applicability has been filed by Sovann Kong to remove brush. The
proposed work will take place in the 100-year floodplain.
Request for Determination of Applicability
Chantho Mo
138 Martin Street
Lowell, MA 01854
Project Location: 138 Martin Street, 01854
A Request for Determination of Applicability has been filed by Chantho Mo seeking approval to repave
and expand their driveway which was previously expanded in the 100-year floodplain without
Conservation Commission approval. The applicant is also seeking approval to reconstruct and expand a
deck which has fallen into disrepair in the 100-year floodplain.
Request for Determination of Applicability
Suelene Caetano
509 Wentworth Avenue
Lowell, MA 01852
Project Location: 509 Wentworth Avenue, 01852
A Request for Determination of Applicability has been filed by Suelene Caetano to construct a three-
season porch within the 100-year floodplain.
NEW BUSINESS
Request for Determination of Applicability
Lowell Regional Water Utility
815 Pawtucket Boulevard
Lowell, MA 01854
Project Location: Pawtucket Boulevard and Varnum Avenue, 01854
A Request for Determination of Applicability has been filed by the Lowell Regional Water Utility to
connect an existing water main at Dunbar Avenue and Pawtucket Boulevard to a new water main which
will extend and connect to an existing water main at the intersection of Varnum Avenue and Mammoth
Road.
Certificate of Compliance
Riverbank Properties, LLC
908-966 Lawrence Street
Lowell, MA 01852
DEP #: 206-0800
Project Location: 908-966 Lawrence Street, 01852
A Request for a Certificate of Compliance has been filed by Cornerstone Land Associates, on behalf of
Riverbank Properties, LLC, for their parking expansion project at 908-966 Lawrence Street.
Notice of Intent
Aravind Srinivasan
Anka Homes, LLC
34 Arcola Street
Lexington, MA 02420
DEP #: 206-0809
Project Location: 87 Lafayette Street, 01854
A Notice of Intent has been filed by Anka Homes, LLC to construct a single-family home and driveway
within the 100-year floodplain.
Request for Determination of Applicability
Hardik Patel
11 Perron Way
Lowell, MA 01854
Project Location: 11 Perron Way, 01854
A Request for Determination of Applicability has been filed by Marcos de Oliveira, on behalf of Hardik
Patel, to construct an addition to the single family home at 11 Perron Way within the 100-ft buffer zone
to the Bordering Vegetated Wetlands (BVW).
OTHER BUSINESS
Election of Officers
Vote on National Grid’s Updated Proposal for the Lowell Area Gas Modernization Project
Minutes
November 10, 2021 Meeting Minutes
ADJOURNMENT
Get email alerts for Lowell