Malvern City Council
Regular MeetingMalvern, AR · August 24, 2021
Minutes
AGENDA
MALVERN CITY COUNCIL
SPECIAL CALLED MEETING
Tuesday, August 24, 2021
Streamed from the Mayor' s Office, 6: 00 PM
I. CALL MEETING TO ORDER
II. INVOCATION
III. ROLL CALL
IV . APPROVE BID - POLICE STATION PROJECT
V. ADJOURNMENT
MINUTES OF THE MALVERN CITY COUNCIL
Tuesday, August 24, 2021
Streamed from the Mayor' s Office
6: 00 P. M.
I' he Malvern City Council met in special session on " I' uesday, August 24,
2021, at 6 00 p. m. via Microsoft Teams and advertised as required by law, due to
the Covid- 19 Pandemic of 2020/ 2021. The meeting was available for viewing live
on YouTube. The opportunities for attending the meeting had been advertised on
the City' s website ( with link provided), the City' s Facebook page, and in the
Malvern Daily Record.
Mayor Weldon called the 1- item special council meeting to order and
announced that the purpose was to accept the bid for construction of the new
police facility. Weldon led the invocation and pledge of allegiance. Answering the
roll call were Council members Mary Fraction, William Wilson, Lynn Davis, Wayne
Reynolds, Peggy Lusinger, Matthew Keenan, David Cross and Larry Stiles. Also
present was City Clerk/ Treasurer Phyllis Dial with City Attorney Cecilia Ashcraft
absent.
Mayor Weldon introduced Severen Girod of Ideal Construction, who
presented the low bid on the project for constructing the new police facility. Mr.
Girod told the Council that his Vice President Hunter Kippert, was also on the call
to answer any questions. He stated that after meeting with the architect, Mayor,
Yolice Chief, and several council members they had been able to modify the plans
and find $ 326, 242 in reductions. Mayor Weldon presented a list of the reductions,
showing the total of the project, including architect' s fees, is now $ 2, 885, 081. 15.
Mayor Weldon presented a spreadsheet showing an availability of $ 1, 050, 683. 40
from county and city sales tax receipts collected over anticipated revenues. She
stated that acceptance of the revised bid should now require only an extra
19, 669. 53 from the general fund to complete the project. A motion was made by
Alderman Cross, seconded by Council Member Davis to accept the bid on the
police facility from Ideal Construction with revisions. Voting for the motion were
Council Members Fraction, Wilson, Davis, Reynolds, Lusinger, Keenan, Cross, and
Stiles.
Council Member Stiles asked about the generator included in the project
costs before revisions, and the mayor advised that it is still in there and will power
the whole facility. She stated that the Council chambers also include extra outlets
so that in the case of a natural disaster, the facility can be used as a " war room";
something that we have never had before.
1
MINUTES OF THE MALVERN CITY COUNCIL
Tuesday, August 24, 2021
Streamed from the Mayor' s Office
6: 00 P. M.
Mr. Kippert told the council that they will issue the letters of intent on the
project and get the notice to proceed prepared. He stated that by the end of next
week they should be able to provide a full construction schedule. He said that
they are technically starting the project now, but it may be a couple of weeks
before they see any physical work going on at the project site.
Chief of Yolice Donnie "I' aber thanked the Mayor and Council for their
support of the project and the new facility. He stated that he was excited to get
started. Mr. Kippert said that he anticipated a great project and has been
impressed with the Council and the architects' willingness to do what was
necessary to make the project a reality.
Upon a motion by Alderman Cross, seconded by Alderman Stiles, the
meeting was adjourned.
ti- t,<<„;,,
l:.!I `'..,
1. .. .
Phyllis Dial, City Clerk/ Treasurer Brenda J. We on, Mayor
i',,,;'
j`,\`
i= 111,`;,`\`:
2
j
o;,[
J GrC9 C. Pumphrey
j V'.
ai.i Tf < rc ie•. ce
f n:.-.
iling ndc! r<••.: r
1 33: s7: n::.. n: d.<:.
j 1•. 1.•., bri{(111•.•.
i I VJ
4
a:.
PyDSiFJPi] REY
i .. n. . , . ....
PROJECT: MALVERN POLICE DEPARTMENT
20-Aug-21
j VALUE ENGINEERING OPTIONS)
ITEM ; TRADE
DESCRIPTION AMOUNT
As ro osed on 8- 4- 21
All canstruction materials testin
Testing 9 to be P aid for b Y the owner soil com p acdon g2,a.50)
testing
and concrete compressive strenght testing
2
Landscaping Not accepted
Delete seeding 8 top soil along east and south side of the building.( No landscaping)
3 Delete portion of sidwalk on south side of
oncrete building from Door 102A to sallyport door 109 ( 9, 932)
C
4 Millwork In Break 107, chan e Stainless steel counter to to lastic laminate. Not Acce ted
5 Millwork In Shower 151, chan e solid surtace vani to in to lasdc laminate. Not Acce ted
6
Millwork
n
City Council 174, change all solid surface wall caps and council desk top to plastic Not Accepted
laminate includes half wall& council desk
7
Delete the haff wall with the PLAM pp and caf doors Not Accepted-
i entirely in City Council 174.( The
council desk will remain as bfrch panels with plam See item# 36
topsj
below
EIFS Reduce the thicfiness of the EIFS from 2" to 1- 1/ 2"( reveals still in project) 5950)
9
Doors Frames, Hdw Change door hinges to from 5 2
McKlnney TA2714 to MPB79, 260( see spec sheet)
Change all LVT to VCT( Armstrong Excelon). This will be in the Corridors,
looring Lobby Not Accepted
areas, Foyer, Storage and Shate Police room.( See finish schedule)
Change all Sheet Vinyl to alternate Sheet Vnyl(
Artnstrong Timberline). This will be in Not Accepted
the toilets, Armory, PaVol Room, PFR Officer, Copy/Rec, Offlces, Storage areas,
Detective rooms, Records room. See finish schedule. ("
Flooring Cannot be taken with item
131,# 32 or Ki3 below. This changes the CURRENT floor plan, not the revised
floor plan with the sallyport inside. See items# 11 and# 12 below for options wtth
sali ort inslde the exiskn bulldin .
12
Not Accepted
Change all altemate Sheet Vinyl to VCT( Artnstrong Excelon). This will be in the toilefs,
Armory, Patroi Room, PFR Officer, Copy/Rec, Offices, Storage areas, Delective rooms,
Flooring Records room. ('"
Cannot be take wlth Item#f31,# 32 or i33 below. This changes
tha CURRENT floor ptan, not tho revsied floor plen with sally port inside.See
items# 11 and# 12 below far options wlth sallyport inslde the exisUng building.)
13
Flooring Chan e Mondo
Rubber Floor Tile to Ro e Recoil Rubber Tile. See s ec sheet 3 825)
14
Change all new roof panels( ON IXSITING BUILDING ONLY) from the Not Accepted-
specified roof
PEMB
panels to Standing Seam( 24" trapezoidiai snaplock), 24 ga., galvalume frnlsh.( We do see item# 37 for
not reccomned an exposed fastener panel system).
Sallyport& North entrance canopy Ait raof below
to remain as specified( colored 24 ga. standing seam) No elechic seamer. Lock into
lace.
15
pEMg Delete the weatheriigheness 1, 008)
warranty for the main building roof
16
PEMB/ General educt all work at the Sallyport as designed( would Not aceepted-
need to add back frnishes 8
Sallyport) overfiead door if relocated inside see item# 31
building)- PENDING RE- DESIGN.
below
17 S rinkler If owner can fumish ori inal s rinkler drawin s
Not acce
18 Plumbin Altemate fi ctura acka e for WGi, WG2, L- 1, L- 2, SK- 1, WH- 1, HB- 1 and
RPZ. 5, 778
19 Plumbin Value of Lift Station for se arate fundfn
20 z8 4 7
HVAC Chan e s uare duct to round duc2. PENDING ENGINEERS REVIEW c s ypp
21 Electrical
22 Use Altemate li ht fi cture acka e b same manufacturer. 29, 205
Delete ower com
Electrical an char es if the
existing CT/ Meter and service disconnect do not
have t be relocated.( Reference y o)
23
Key Note 4/ ED. 01)
General Delete or defer generator
including concrete pad, generator,conduit and wire to the
Not accepted
24
ATS. ATS shall remain for future connection.
General
Delete Pergola System
remain in and type" C" lights under the Pergola. CE fixtures at exits to
Sidewalk
ro' ect. under ero al s tem to remain.
n
Not accepted
25 General
26 General
6cistin 6" and 3" water service to remain in iPs resent loca6on.
Delete( 2) holding cells
entirely without re- finishing the abandoned space.
27
General MEP
Not ac eped
Chan 9 e HVAC s tem to RTU' s( PENDING
ENGINEERS RE- DESIGN). Not accepted
28
Delete Panel ML( If all ODU units are
deleted and RTU' s are 480 volt fed
General( MEP) from the Not accepted
distribution panel- DP)- PENDING HVAC RE-DESIGN, can only be taken if HVAC
system is changed.
29 New Entry Gable$
Parapet Allourance Reduce the allowance amount at your
discretion.($ 80, 000) Pending
30
Cantignency
Allowance Reduce the allowance amount at your
discretion.($ 50, 000) Pending
Added after Meeting on
8- 13- 21
General
Move Sallyport
Cannot be take
insideifems#
with
the exsiting
11,# 12
building16and re-work floor plan to accommodate.
or#
a"80,A22)
above)
32
BASED ON NEW FLOOR PLAN
WITH SALLYPORT INSIDE BUILDING: 2 050)
Change all
Flooring Sheet Vinyl to altemate Sheet Vinyl( Armstrong Timberline). This will be in the toilets,
Armory, Patrol Room, PFR Officer, Copy/Rec, Offices, Storage areas, Detective rooms,
Records room.( See finish schedule)
33
BASED ON NEW FLOOR PLAN WITH
SALLYPORT INSIDE BUILDING: Change all 6, 396)
Flooring
altemate Sheet Vinyl to VCT( Armstrong Excelon). This will be in the toilets, Armory,
Patrol Room, PFR Officer, Copy/Rec, Offices, Storage areas, Detective rooms,
Records room.( See finish schedule)
BASED ON NEW FLOOR PLAN WITH
SALLYPORT INSIDE EXSITING BUILDING:
Wood Framed 512, 60oj
Change re-configured floor plan( with Sally Port inside existing building) from metal stud
framing to wood framing.
35
Drywall Change exterior sheathing from 1/ 2" apa
plywood to 1/ 2" densglass I34$ 00)
sheathing.
s
Millwork Delete pony wall in city council 174. Council
solid surface tops and birch Desk will remain as orin ali s eoified with
Cannot take this item
panels.(
510, 977)
with items# 6# 7 listed
above)
37
Change ail new roof panels( ON
Metal Roof EXSITING BUILDING ONLY) from the specified 3, 536)
roof
panels to Standing Seam( 24" trapezoidial snaplock), 24 ga., Painted finish. Sallyport&
38 North entrance canopy to remain as s ecified colored 24 ga. standing seam.
Plumbing
Change showers from fiberglass to epoxy paint. WASH
39
Electrical
40
Delete smoke detectors inside the building.( Pending engineers review) 3, 195
General Delete restroom 131 from the project.
52, 369)
S ecial Condifion for review
Bond Expenses 2021
Fire Department
Building 3, 143, 575. 00
Architect
42, 016. 48
Total
3, 185, 591. 48
Street Repair
1, 190, 770.07
Police Station
3, 082, 000.00
Architect
129, 323. 15
Reductions . '
326, 242. 00
I
Tota I I 2, 885, 081. 15
Actual extra carry over $
1, 050, 683. 40
Bond Amount
6, 191, 089. 77 starting in 2021
Expenses
7, 261,442.70
General
19, 669. 53)
Carry over County tax
Actua I
1, 945, 483. 84
p rojected 1, 106, 500. 00
838, 983. 84
Carry over City tax
Acuta I
454, 147. 56
projected
242, 448. 00
211, 699. 56
County tax 838, 983. 84
City tax 211, 699.56
Actual extra Carry over $ 1, 050, 683. 40
BID SUMMARY
Malvern Police Department Facility
the The City
building of Malvern held a bid opening
that will house the renovated
on Tuesday, July 27, 2021 at 2:31 p.m. in
Police Depaztrnent
Facility. Present for the
opening were Mayor Weldon, City Clerk/ Treasurer Dial, Fire Marshall Chris Brewster,
Architect for the Project Greg Pumphrey, and a representative from each of the three
firms
submitting a bid for the project.
Three bids were received with the results as follows:
Bell Construction
3,352,025. 00
Bid Bond Included
Ideal Construction * 3, 082, 000. 00
Bid Bond Included
Shields and Associates
3,492,000. 00
Bid Bond Included
Apparent Low Bid