Firing Range Building Committee
Regular MeetingMiddletown, CT · July 18, 2023
Minutes
FIRING RANGE BUILDING COMMITTEE
MINUTES
July 18, 2023
1. Meeting Called to Order
Chairman Vinnie Loffredo called Meeting to Order.
Members Present: Councilman Vinnie Loffredo, Chairman
Chief Erik M. Costa – Police Dept.
Chief Jay Woron – Fire Dept.
Councilman Phil Pessina
Maryann Serra
Barbara McAuliffe
Joe Bibisi
Staff Absent: Councilman Darnell Ford
Christopher Holden, Public Works
Staff Present: Captain John Lozefski – Police Dept.
Howard Weisberg, Deputy Director – Public Works
Guests Present: Bullets Campbell, F.B.I.
1. Approval of Minutes
Chairman Loffredo made a motion for approval of minutes from June 20, 2023 meeting with the
correction of member Joe Bibisi NOT being present –All were in favor and there being no
discussion or objection, motion passed.
2. Public Comment Opens
***None***
3. Old Business
***None***
4. New Business
Project Update;
Continuing on the berm
Capping the berm at 90% payment to allow 10% for stabilization and seeding which will
be done later
Working on finalizing the wall and sound proofing approval
Once approved, pouring of concrete slab for walls will begin and walls will be delivered
Beginning the layout to get things ready for the target system
Bullets has been down in Florida and Alabama – Field offices for the Targeting System
The system that Bullets saw was essentially a mockup of what would be provided for us
Potentially adds an element of training that does not exist on any other law enforcement
range, which would make the range an absolute state of the art range
Bullets reported that the system is simple to use, and easy to swap parts, and the software
program is simple and works well
TRS is working with TPS as the subcontractor – so the cost estimate would be between the
two companies
Councilman Pessina asked if it is possible to have documentation before the August meeting.
Bullets agreed that he would get something written up with all of the main key points and law
enforcement enhancements.
Councilman Loffredo suggested having the Police Department’s IT dept. also take a look at the
documents.
Looking to complete phase one by the end of October. In addition, plan to complete phase two by
May.
Invoice number four – Invoice total is $122,931.87 with the 5% retainage taken out.
Continuing construction to the backstop and side berm
Completed the berm
Drainage
Site grading
Councilman Loffredo asked where the balance was left at this point. Howard responded – 1.321
million dollars, which would include the ballistic walls, bullet trap and target system.
Councilman Loffredo then made a motion to approve the invoice. All were in favor, so the motion
was passed unanimously.
Communication details-
Howard began by say that if there are questions from the contractor, he will provide his opinion.
However, if they ask for the opinion of the committee, he will then instruct them to create a request
for information to bring to the committee for weigh in.
The contractors are looking to begin components of Phase Two, prior to completion of Phase One.
Concrete pad pouring is the beginning of Phase two and if completion of Phase one needs to
happen before Phase Two, pouring can’t happen until October. In that case the crew can’t begin
because of the colder weather. This would cause a 3-4 month delay in the project.
Option One – Shift work focus off of Phase One completion and begin site work and concrete
prep for Phase Two.
Option Two – See if there is engineering evidence to support as assertion that concrete can be
poured into November – December as long as winter is not horrible.
Councilman Lofreddo made reference to the City’s agreement of having 1.5 million for the
completion of Phase One.
Bullets stated that his strong preference would be option two, which would not alter written
agreements. Howard Weissberg also gave more details about what a cold weather plan would look
like. The council then continued pros and cons back and forth of both options.
Bullets did state that his understanding is that funds are sitting at the field office and would be
available for the project if needed.
Councilman Lofreddo stated that he will have a meeting with Public Works and the finance dept.
to make sure that they have the necessary funding. He suggested tabling the matter to the next
meeting and at that point, the committee will come to a new agreement.
1. Meeting Adjourned
Before adjournment, it was suggested that the next Firing Range Meeting take place at the
actual site of construction. All agreed to the idea.
Chairman Loffredo made a Motion to adjourn. First by Barabra McAuliffe, seconded by Marann
Serra. All were in favor and there being no discussion or objection, motion passed.
Next Firing Range Building Committee Meeting is Tuesday, August 15, 2023, 4:00 P.M.
TO LISTEN TO THIS MEETING IN ITS ENTIRETY, PLEASE VISIT THE
FOLLOWING WEBSITE:
www.cityofmiddletown.com
Respectfully Submitted,
Stacey Scarrozzo
Recording Secretary
Agenda
FIRING RANGE BUILDING COMMITTEE
SPECIAL MEETING
AGENDA
July 18, 2023
4:00 P.M
Hybrid
Police Conference Room
And Webex
Join from the meeting link
https://middletownct.webex.com/middletownct/j.php?MTID=m33c284580a46e40
39bae7115426a81ef
Join by meeting number
Meeting number (access code): 2331 949 7374
Meeting password: m9R9yKXnyW5
Tap to join from a mobile device (attendees only)
+1-408-418-9388,,23319497374## United States Toll
Join by phone
+1-408-418-9388 United States Toll
Global call-in numbers
Join from a video system or application
Dial 23319497374@middletownct.webex.com
You can also dial 173.243.2.68 and enter your meeting number.
1. Meeting Called to Order
2. Public Comment
3. Old Business
4. New Business
Project Update
Invoices
5. Meeting Adjourned