Transportation Committee
Regular MeetingMount Pleasant, SC · December 4, 2017
Minutes
TOWN OF MOUNT PLEASANT, SOUTH CAROLINA
TRANSPORTATION COMMITTEE
Monday, December 4, 2017 at 12:15 p.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane
Mount Pleasant, SC 29464
MINUTES
Members Present: Mayor Will Haynie, Chair; Joe Bustos; Bob Brimmer
Staff Present: Eric DeMoura, Brad Morrison, Paul Lykins
Mayor Haynie called the meeting to order at 12:15 p.m.
Mayor Haynie stated several residents were present to address the
Committee on another agenda item and suggested that due to the length of
the agenda and with respect to the residents’ time, agenda item eight (8),
Discussion of cut through traffic on Cottingham Drive, be moved to agenda
item four (4).
Mr. Brimmer moved to amend the agenda by moving agenda item three (3),
Review and evaluation of the Coleman Boulevard Revitalization project, to
item six (6), item four (4), Executive session to receive legal advice on any
issue related to the review and evaluation of the Coleman Boulevard
Revitalization project, if needed to item seven (7) and item five (5), Post
Executive Session for Committee to take action on any item listed on an
executive session agenda or discussed in an executive session during a proper
noticed meeting to agenda item eight (8); motion seconded by Mr. Bustos.
Motion carried unanimously.
Mr. Bustos moved to approve the amended agenda; motion seconded by Mr.
Brimmer. Motion carried unanimously.
1. Approval of Minutes from the October 2, 2017 meeting
Transportation Committee Minutes
December 4, 2017
Page 2 of 12
Mr. Brimmer moved for approval of the October 2, 2017, minutes; motion
seconded by Mr. Bustos. Motion carried unanimously.
2. Public Comments
None
3. Presentation of results of the public meeting regarding the Park West
Boulevard widening project.
Mr. Lykins stated that staff would be presenting Committee a summary of
public input received on the Park West Boulevard widening project with a
typical section to be selected for full design. Mead and Hunt will be designing
the project and improvements include a four (4) lane divided section with
consideration for bike lanes and an improved multi-use path. The project is
divided into two (2) phases with phase one (1) beginning at the entrance of
the Park West Recreation facility and Park West Boulevard extending to the
Grey Marsh Road roundabout. Phase two (2) will encompass the road section
from the Grey Marsh Road roundabout to Bessemer Road. The estimated
cost is six to seven million, five hundred thousand dollars ($600,000-
$7,500,000) with one million, one hundred thousand dollars ($1,100,000)
currently budgeted and the design estimated to be completed by Fall 2018.
Staff is also reviewing additional bike lanes and upgraded lighting for the
remainder of Park West Boulevard that is not included in the section that is
being presented.
Mr. DeMoura stated that the prior Transportation Committee’s desire was
not to phase the project and staff has presented Committee with two (2)
phases as an option should a phased scenario fit within the budget
constraints.
Mr. Morrison stated that two (2) phased sets of plans will be produced with
the option to bid both phases together or separately.
Referring to a graphic, Mr. Lykins, explained the project limits from the
entrance of the Park West Recreation facility to the Bessemer Road
roundabout reflecting the two (2) phases. Staff is seeking direction from
Committee for the desired road cross section selected from the three typical
Transportation Committee Minutes
December 4, 2017
Page 3 of 12
sections presented at the public input meeting. The purpose of the public
input meeting was to present the public with the options and gather input for
the proposed improvements on Park West Boulevard. All material and
information were provided to the Homeowners Association (HOA) to be
distributed to residents.
Mayor Haynie inquired when the public input meeting was conducted.
Mr. Lykins replied that the meeting was conducted on October 26, 2017.
Thirty-eight (38) residents attended the meeting and forty-one (41) residents
provided input on the project. Twenty-three (23) residents or fifty-six percent
(56%) preferred option typical section one (1), one (1) resident preferred
typical section 2, eight (8) residents or twenty percent (20%) preferred typical
section three (3), six (6) residents provided feedback regarding drainage
issues and alternate roadways and three (3) residents were opposed to the
project. Based on the feedback of the public input, typical section one (1) was
recommended by staff for full design.
Mr. Bustos inquired if in typical section two (2), a shared use lane would still
have a cyclist in the roadway with no designated lanes.
Mr. Lykins replied in the affirmative explaining that a cyclist would have full
use of the lane, sharing the lane with the vehicle.
Mr. Bustos asked if there was an option for a bike lane or an amount of asphalt
to be added to the walking path for cyclist.
Mr. Lykins replied in the affirmative stating that all three (3) options include
improvements to the multi-use path.
Mr. Bustos inquired if improvements to the path would be wide enough for
pedestrians and cyclists.
Mr. Lykins replied in the affirmative stating that currently the path is
approximately six (6) ft. wide. Staff would like to widen the multi-use path to
eight (8) or ten (10) ft. wide, if possible. Option one (1) includes a marked
bike lane explaining that bike lanes are very popular for avid cyclists and
commuters. An experienced cyclist will opt to ride in traffic so providing a
lane is beneficial. There are marked bike lanes on Dunes West Boulevard and
Transportation Committee Minutes
December 4, 2017
Page 4 of 12
in the future, it would be desirable to have bike lanes along Dunes West and
Park West Boulevards between SC-41 and US -17.
Mr. Brimmer commented that the multi-use path will continue to be used by
children and residents that are riding for recreation and competitive riders
will use the roadway.
Mayor Haynie stated that with regards to the South Carolina Department of
Transportation (SCDOT) and the Ben Sawyer Boulevard, it is his understanding
that once a bike lane is striped, cyclists must use it and asked Mr. Morrison if
his understanding is correct.
Mr. Morrison replied in the negative stating that rule does not apply to the
Park West Boulevard widening project since, in addition to the marked bike
lane in the roadway, a multi-use path is proposed, which would allow both
bicyclists and pedestrians and it would be designed as such. The current
multi-use path in Park West is six (6) ft. wide and does not meet the minimum
standards. Although the path has historically been utilized as a multi-use
path, it should actually be designated as a sidewalk because the minimum
width of a multi-use path is eight (8) ft. and when a multi-use path has heavier
usage, the width should be ten to twelve (10-12) ft. wide, which allows for
options of marking for bike and pedestrian user. Because the path is in an
easement, staff will need to investigate the option to widen it to
approximately ten to twelve (10-12) ft. to ensure there are no conflicts with
utilities or other issues. Currently, staff is proposing to widen the multi-use
path to minimum of eight (8) ft.
Mayor Haynie inquired if option one (1) would include a striped bike lane on
the roadway and noted that to comply with the law, a cyclist is required to
stay within the designated lane and further inquired if the striped bike lane
precludes the cyclists from using the multi-use path.
Mr. Morrison replied that bikes would be permitted on the multi-use path
and the only thing that would be prohibited would be golf carts or any other
type of motorized vehicle.
Mayor Haynie commented that the experienced commuter or competitive
cyclist will be gaining a bike lane as an alternative to the multi-use path.
Transportation Committee Minutes
December 4, 2017
Page 5 of 12
Mr. Morrison replied in the affirmative stating cyclists have expressed a
preference to a designated bike lane on the roadway to eliminate any conflict
between competitive cyclists and pedestrians or casual cyclists due to high
speed differentials. It is best to have pedestrians and casual cyclists on the
multi-use path.
Mr. Brimmer stated the issue is a safety issue since the sidewalk path is
currently offset from the road and causes cars exiting subdivisions to stop at
the path and again at the intersection creating a safer ride for the competitive
cyclist.
Mayor Haynie asked DeMoura what staff needed the Committee to do to
proceed with the improvements.
Mr. DeMoura replied staff is asking Committee to choose the cross section
that will dictate the design.
Mr. Haynie stated that after a motion has been made, the floor will open for
discussion.
Mr. Bustos asked if the motion would be a recommendation to full Council.
Mr. DeMoura replied that this type of decision is usually left to Committee.
4. Selection of road cross section for Park West Boulevard
Mr. Brimmer moved to recommend option number one for the Park West
Boulevard widening roadway; motion seconded by Mr. Bustos.
Pat Sullivan, 1002 Plantation Court, asked how wide the bike lane will be.
Mr. Lykins answered the bike lane will be four (4) ft. wide.
Motion carried unanimously.
Mr. Brimmer thanked Mr. Morrison for including a discussion on the issue of
lighting on Park West Boulevard. Park West Boulevard is very dark and as
traffic increases, the issue of how to best to light that road should be
discussed during the Council Retreat to include discussion of traffic flow at
the intersections of the schools in the area and the options of a signalized
intersection or a roundabout at Stockdale Street. There is concern in the
neighborhood that a roundabout or another option there would be worth
Transportation Committee Minutes
December 4, 2017
Page 6 of 12
examining due to the absence of signals in Park West. The Town has invested
a lot of money to keep traffic flowing through the neighborhood and
signalizing the intersection may hamper that effort. Discussion should occur
for consideration of installing a roundabout or another option to maintain
continuous movement along Park West Boulevard in addition to keeping the
aesthetics of the neighborhood.
Mayor Haynie inquired if the issue of lighting is being addressed.
Mr. Lykins stated that the project design will most likely include lighting and
there is consideration for the remainder of Park West Boulevard to US-17 and
back to Wando Planation Way that would be include bike lanes and lighting
for both roadway sections. The design may not be constructed as part of the
project being discussed, but would be designed so that as funding becomes
available the improvements can be completed.
Mr. Morrison explained that South Carolina Electric and Gas (SCE&G) utilizes
a cost recovery formula and if it is not met in three and half or four years, the
Town will pay an aid to construction cost. With recent projects, there has not
been a significant cost to aid in construction because the cost to recovery
ratio is being met. Mr. Lykins explained that the project will be included in
our design to include conduit and all other necessary components to
complete lighting later. Particularly with increased pedestrian activities and
crossing that will be delineated, lighting should be considered in a
comprehensive plan.
Mr. Brimmer inquired if the crosswalks would be marked.
Mr. Morrison answered in the affirmative stating that the proper treatment
type for a four (4) lane roadway will be taken into consideration.
5. Discussion of cut through traffic on Cottingham Drive
Mayor Haynie recognized Paul Thompson stating that Mr. Thompson will be
addressing Committee on the issue of cut through traffic on Cottingham
Drive.
Paul Thompson, 1077 Cottingham Drive, introduced Bryce Westcott stating
that the issue of cut through traffic on Cottingham Drive has been ongoing
Transportation Committee Minutes
December 4, 2017
Page 7 of 12
and that he has been involved in resolving the issue since 2007. Concerns
were expressed to Councilmember Santos on February 23rd and a recent
incident involving a visitor and another vehicle that could have potentially
resulted in an accident prompted his letter to Committee. Multiple studies
have been conducted with Stantec Consulting being the most recent. As a
result of the study, a speed hump was relocated, and an additional stop sign
was installed at the intersection of Pelzer Drive and Cottingham Drive. While
the efforts of the Town are appreciated, driving conditions have not
improved. The additional stop sign is an improvement, but a waste of
taxpayers’ money due to driver’s disregard of the sign with the assumption
that other drivers will stop. With the addition of popular businesses within
the area and the construction of Shem Creek Park, cut through traffic has
increased. Cooper Estates is an older neighborhood and residents would like
to retain the characteristics of the neighborhood regarding the density of
building types and quiet streets. Concerns were expressed after the most
recent study conducted by Stantec Consulting that residents were not
included in an open discussion relating to the issue. Previous Council
members have asked residents what the preference is for a solution. Traffic
calming in the realm of landscaping could be beneficial. Mr. Westcott has
researched landscaping options that have been presented to the
Transportation Department and Council members. Additionally, research
indicates that various municipalities have granted drive through restrictions
in selected areas and Dorchester County has an ordinance that prohibits cut
through traffic. Deputy Chief Kinard has stated that signage and message
boards have been installed to address cut through issues citing that issues
have been reduced by sixty to eighty percent (60-80%) based on data
collected by stealth traffic counters. The Town previously informed residents
that funds were not available to accomplish this option. Cut through traffic is
an issue and residents are pleading for the Town to address their concerns.
Mayor Haynie stated that the Town does not allow construction of new
roadways without sidewalks being incorporated in the design. When Cooper
Estates was developed, construction of sidewalks was not a concern. When
newly elected as a Council Member, one of the first motions he made was
Transportation Committee Minutes
December 4, 2017
Page 8 of 12
with regard to traffic calming in the Groves subdivision. A lot of traffic calming
measures were implemented the Groves perhaps creating more cut through
traffic on Cottingham Drive.
Mayor Haynie addressed staff and inquired what the first step would be to
address the issue of cut through traffic on Cottingham Drive.
Mr. Morrison provided a brief history stating that an extensive study was
conducted and involved both neighborhoods to examine the impact on traffic
calming measures in one (1) neighborhood affecting the other neighborhood.
This effort was grass-roots driven with the Town engaging the residents with
each neighborhood having a group of residents that advised the process. The
Town provided options that included discussion of roadway closures and
diverters those discussions produced the traffic calming measures that are
currently in place. Addressing cut through traffic is difficult in Cooper Estates
and options are limited, as a road closure is significant and diverters are not
an option. In summary, staff has worked with the neighborhoods and the
Town has addressed the speed control issue as best possible to this point.
While knowing that controlling cut through traffic would be difficult, there
was always question as to how much speed controls would divert motorists
away from Cooper Estates. Stantec Consulting performed a before and after
study approximately five (5) months ago that can be provided to Committee
again to review the volumes and the speeds.
Mayor Haynie asked Mr. Johnson if he was familiar with or had seen the study
being discussed.
Mr. Johnson stated that he is aware of the study, but has not seen it.
Mr. Haynie stated that the pre-study is being discussed and asked when the
traffic calming plan was implemented in the Groves.
Mr. Morrison replied that the traffic calming plan was implemented in fall of
2016 and the before and after study was conducted in the spring of 2017. The
study can be provided again to Committee and Mr. Thompson. If the issue
of diverting cut through traffic and traffic calming is re-visited, the
neighborhood should be fully engaged in the process. While some residents
on Cottingham Drive may be in favor of a road closure, other residents within
Transportation Committee Minutes
December 4, 2017
Page 9 of 12
the community may be opposed. Any type of diverter on Cottingham Drive is
not an option and would be the same as a road closure.
Mr. DeMoura stated that Mr. Morrison’s statements are correct and that
neighborhood representatives were involved in the process and a product
was delivered. The process was contentious and issues have been resolved
for the time being. If there is any movement to re-address the issue, the
process should start at the beginning and involve the full community to allow
all residents to express their opinions.
Mayor Haynie stated that another option is heightened law enforcement. At
times, this can anger residents within the community if they are ticketed as
opposed to ticketing what is perceived as cut through traffic. Mayor Haynie
is seeking direction from Committee and the community on how best to
proceed in this process.
Mr. Thompson suggested performing traffic counts on all streets in Cooper
Estates to evaluate traffic if the entire community is considered stakeholders,
with the intention to find a solution to keep reckless drivers from using
Cottingham Drive as a cut through in order to save time on their commute.
Mr. Haynie asked Mr. Morrison if there was a current traffic count.
Mr. Morrison replied that he thought the latest traffic count was
approximately three thousand, eight hundred (3,800) vehicles per day.
Mr. Bustos stated that other streets contribute to the speed and volume of
traffic on Cottingham Drive. While law enforcement may not decrease the
traffic volumes, it would be the most effective solution to prevent reckless
driving within the community.
Mr. Thompson stated reckless driving is not caused by residents in the
neighborhood. Residents are concerned about the safety of their children,
pets and pedestrians. It is drivers who have no stake in the neighborhood
that are creating the dangerous situation. Traffic has increased with the
addition of new businesses and recreational parks and the amount of litter
has also increased. Increased enforcement is not the solution.
Transportation Committee Minutes
December 4, 2017
Page 10 of 12
Mr. Haynie stated that Committee and staff will continue to examine the
issue.
Bryce Westcott, 1061 Cottingham Drive, stated that he has lived in the area
for approximately nine (9) years and has worked with Mr. Morrison and Mr.
Ponder to resolve the issue. Traffic volumes have exponentially increased,
and distracted drivers are creating a greater danger. Installing sidewalks on
Cottingham Drive has been discussed and are beneficial in certain regards to
particular areas because pedestrians are not on the roadway. Constructing
sidewalks on Cottingham Drive will only increase cut through traffic because
pedestrians will no longer be using the roadway. I am taxed at the same rate
a resident on Pelzer Drive even though the quality of life has decreased on
Cottingham Drive due to cut through traffic. Having the speed humps
resurfaced and installing an additional stop sign is a great start, but more
needs to be done.
Mayor Haynie asked Mr. Morrison if there are any measures that reduce
traffic volumes or modify driver behavior. The Committee will communicate
with staff and provide an update. The issue can also be placed on the
Transportation Committee agenda because public safety is a priority.
6. Review and evaluation of the Coleman Boulevard Revitalization project.
Mr. DeMoura asked if Committee desired a general review or discussion in an
open session noting that any issues that relate to a contractual matter should
be discussed in Executive Session.
Mayor Haynie asked for questions or comments.
None.
Mr. Haynie expressed his surprise that there were no comments stating that
residents continually voice opinions and concerns relating to the project. The
project has been placed on the agenda to examine options pertaining to the
contractual matter.
Pat Sullivan, 1002 Plantation Court, stated she was present at the meeting
where Mr. DeMoura and Mr. Morrison presented statistics on the value of a
median and that the discussion has not been recognized other than the
Transportation Committee Minutes
December 4, 2017
Page 11 of 12
opinion that the median needs to be removed. Safety standards should be
taken into consideration with regard to the median. With the issue of cut
through traffic on Cottingham, there have been instances where landscaping
has been successful.
Mayor Haynie asked Ms. Sullivan to forward her information on landscaping
to.
Mr. Bustos moved to go into Executive Session to receive legal advice on any
issue related to the review and evaluation of the Coleman Boulevard
Revitalization project;
Mr. Brimmer asked for a background as to why Committee needs an Executive
Session and what Committee is trying to accomplish.
Mr. Bustos stated that business owners and residents constantly express
concern relating to medians being installed on Coleman Boulevard. It is
interesting that medians are being installed on Coleman Boulevard and
removed near the new Lowes on US-17 and this issue has not been thoroughly
thought out. He has been opposed to many things on Coleman Boulevard and
finds it interesting that at a time medians are being installed on Coleman
Boulevard, they are being removed in other areas to improve traffic and that
is why it is important for the issue to be discussed.
Mr. Brimmer asked for clarification that the Executive Session is to discuss the
possibility of removing the medians.
Mr. Bustos stated the Executive Session is to review the overall contract and
the medians are one of the salient points.
Motion seconded by Mr. Brimmer. Motion carried unanimously.
7. Executive session to receive legal advice on any issue related to the
review and evaluation of the Coleman Boulevard Revitalization project,
if needed.
Mayor Haynie adjourned the meeting to Executive Session at 1:01 p.m.
8. Post Executive Session
Transportation Committee Minutes
December 4, 2017
Page 12 of 12
Committee may take action on any item listed on an executive session
agenda or discussed in an executive session during a properly noticed
meeting.
Mayor Haynie reconvened the meeting at 1:50 p.m. and stated that no actions
were taken and no motions were made.
9. Update – ongoing projects
The Administrator stated due to time constraints, the update relating to
ongoing projects would be attached to the minutes.
10. Adjourn
There being no further business, the meeting was adjourned at 1:51p.m.
Respectfully submitted by,
Cathy Godsey
December 7, 2017
• Designer is Mead and Hunt.
• Improvements include a four lane divided roadway.
• Bicycle and pedestrian path improvements.
• Phase 1 - Recreation area to Grey Marsh Road.
• Phase 2 – Grey Marsh Road to Bessemer Road.
• Estimated Cost - $7.5 M Budgeted Amount $ 1.1M
• Design complete in Fall 2018.
• Consideration for bike lanes for remainder of Park West Boulevard.
• Meeting Purpose: Present to the public and gather input
for the proposed improvements to Park West Boulevard.
• 38 attendees and 41 comments received.
• 23 (56%) preferred Typical Section 1 (Marked Bike Lane).
• 1 (2%) preferred Typical Section 2 (Shared Use Lane).
• 8 (20%) preferred Typical Section 3 (No Bike Lane).
• 6 (15%) preferred other configurations.
• 3 (7%) opposed the project.
• Recommendation is to proceed with Typical Section 1
Transportation CIP
Project Updates
DECEMBER , 2017
Ongoing CIP Construction
Coleman Boulevard Revitalization
New 2018 CIP Design
Long Point Road Realignment and Extension
Coleman Boulevard and Patriot’s Point Intersection Improvements
Billy Swails Boulevard Phase 4B
Shem Creek Bridge Bike Lanes
Park West Boulevard Widening
All American Boulevard Extension
Coleman Boulevard Revitalization
CONTRACTOR: Blythe Development
START DATE: September 11, 2017
COMPLETE DATE: August 31, 2019
STATUS: TC Stage 1 – Westbound
Construction community liaison visiting
businesses.
Developed project website.
“What We Get”
• Main Street atmosphere where people gather, live, work and play.
• Enhanced mobility for pedestrians and cyclists as well as motorists.
• Greatly improved drainage facilities that decreases stormwater discharge to adjacent neighborhoods.
• 24.32 acres of runoff cleaned before entering Shem Creek watershed.
• Improved lighting and landscaping for safety and beautification.
• Additional transit facilities with pull-outs and shelters.
Long Point Road Realignment and Extension
CONSTRUCTION COST ESTIMATE (YTD BUDGETED): $16,810,000 ($4,982,249)
DESIGNER: JMT
COMPLETION DATE: Design: September 2019 – Construction: September 2022
STATUS: Design and NEPA process is ongoing.
Coleman Boulevard and Patriot’s Point Road Intersection Improvements
CONSTRUCTION COST ESTIMATE (YTD BUDGETED): $5,100,000 ($5,100,000)
CONSULTANT: STV Incorporated
COMPLETION DATE: Design and Permitting: February 2019 – Construction: December 2020
STATUS: Surveying and preliminary engineering began August 2017. Preliminary designs due this month.
Billy Swails Boulevard 4B
CONSTRUCTION COST ESTIMATE (YTD BUDGETED): $12,568,497 ($2,568,497 TOMP and
$10,000,000 Federal)
DESIGNER: Stantec Consulting Services, Inc.
COMPLETION DATE: Design: August 2020 – Construction: August 2022
STATUS: Preliminary engineering began in August 2017. Public meeting in January. Traffic
analysis and modeling is ongoing.
Shem Creek Bridge Bike Lanes
CONSTRUCTION COST ESTIMATE (YTD BUDGETED): $791,000 ($158,000 TOMP and $633,000 Federal)
CONSULTANT: CDM Smith
COMPLETION DATE: Design: January 2018 – Construction: December 2019
STATUS: Held Public Information Meeting. Currently developing preliminary plans.
Park West Boulevard Widening
CONSTRUCTION COST ESTIMATE (YTD BUDGETED): $6,571,250 ($1,100,000)
CONSULTANT: Mead and Hunt
COMPLETION DATE: Design – December 2018
STATUS: Design contract awarded and notice to proceed issued in August 2017.
• Public Meeting on October 26
• Bike Lanes vs. MUP – Full design to advance after typical section selected.
All American Boulevard Extension
All American
Blvd.
PRELIMINARY COST ESTIMATE (YTD BUDGETED): $5,122,000 ($0)
CONSULTANT: Mead and Hunt
DESIGN: March 2018 – December 2019
CONSTRUCTION: March 2020 – December 2021
STATUS: Currently developing project scope of work.
TRANSPORTATION SALES TAX (TST) & CHARLESTON TRANSPORATION
COMMITTEE (CTC) PROJECTS
TST Projects
• SC-41 Widening – Public Information Meeting Held. NEPA process ongoing.
• Park West Boulevard Left Turn Lane @ Recreation Complex – Complete.
• Park West Boulevard Sidewalk Roundabout to US-17 – Complete.
• Park West Boulevard Sidewalk Stockdale Street to Recreation Complex – Under
Construction.
• Anna Knapp Boulevard Sidewalk Johnnie Dodds to Hibben Ferry – Begin design next year.
• Center Street @ Ben Sawyer Signal Installation – Provided funding.
TRANSPORTATION SALES TAX (TST) & CHARLESTON TRANSPORATION
COMMITTEE (CTC) PROJECTS
CTC Projects
• Pelzer Drive Sidewalk - Bids exceeded budget.
County to rebid as part of larger package.
• Lansing Drive Sidewalk – Currently under design.
• Seacoast Parkway Sidewalk – Funded in 2018. Design
to begin in 2019.
Get email alerts for Mount Pleasant
A daily email when new agendas and minutes are posted.